Uttar
Pradesh Electricity Regulatory Commission (Modalities Of Tariff Determination)
Regulations, 2023
[28th
February 2023]
In exercise of the powers
conferred under Section 181 read with Section 61, Section 62, Section 63 and
Section 86 of the Electricity Act 2003 and all other powers enabling it in this
behalf, and after previous publication, the Uttar Pradesh Electricity
Regulatory Commission hereby makes the following regulations, namely:
Regulation - 1. Short Title and Commencement
(1)
These regulations may be called the Uttar
Pradesh Electricity Regulatory Commission (Modalities of Tariff Determination)
Regulations, 2023.
(2)
These regulations shall come into force from
the date of their publication in the Official Gazette.
(3)
These regulations shall extend to the whole
of the State of Uttar Pradesh.
Regulation - 2. Definitions
(1)
In these regulations, unless the context
otherwise requires:
(1)
"Act" means the Electricity Act,
2003;
(2)
"Commission" means the Uttar
Pradesh Electricity Regulatory Commission;
(3)
"Existing Project" means a project
which has achieved commercial operation;
(4)
"Intra-State Transmission System"
or "InSTS" in respect of the State shall have the same meaning as
defined in the Act;
(5)
"Ongoing Project" means a project
which has been under implementation but has not achieved commercial operation;
(6)
"Regulated Tariff Mechanism" or
"RTM" means determination of tariff by the Commission in accordance
with the regulations specified by the Commission under Section 62 of the Act;
(7)
"State Transmission Utility" or
"STU" shall have the same meaning as defined in the Act;
(8)
"STU Transmission Plan" means an
updated five-year rolling Intra-State Transmission System Plan for the State as
prepared and issued every year by STU;
(9)
"Tariff Based Competitive Bidding"
or "TBCB" means determination of tariff through transparent process
of bidding in accordance with the guidelines issued by the Central Government
under Section 63 of the Act;
(10)
"Year" means a financial year from
1st April to 31st March.
(2)
Save as aforesaid and unless repugnant to the
context or if the subject matter otherwise requires, words and expressions used
in these regulations and not defined here, but defined in the Act or any other
regulations of this Commission shall have the meaning assigned to them under
the Act, or any other regulations of this Commission. Similarly, words and
expressions used in these regulations and not defined here, but defined in the
guidelines issued by the Central Government under Section 63 of the Act shall
have the meaning as assigned to these in the guidelines.
(3)
Reference to any Acts, Rules and Regulations
shall include amendments or consolidation or re-enactment thereof.
PART 1 MODALITY FOR POWER PURCHASE APPROVAL
FOR THE DISTRIBUTION LICENSEE IN THE STATE
Regulation - 3. Power Procurement under Section 62 of the Act
(1)
All existing power generating projects for
which tariff is currently being determined in accordance with Regulated Tariff
Mechanism (RTM) under Section 62 of the Act, including those whose PPA(s) have
been approved by the Commission for RTM, shall be grandfathered and accordingly
these projects will continue to be covered under RTM framework and their
tariffs will be determined under Section 62 for the remainder of the PPA period
or life of the plant, whichever is earlier.
(2)
Expansion of existing state owned and
controlled power generating projects will be allowed under Section 62 and their
tariffs shall be determined based on norms specified in the UPERC (Terms and
Conditions of Generation Tariff) Regulations, as amended from time to time.
Provided that in case of
expansion of generating capacity by private developers, the tariffs for the
incremental generating capacity would be determined in accordance with RTM
framework under Section 62. However, such expansion under RTM framework would
be restricted up to the quantum of power approved under their existing PPA with
the distribution licensee(s) in the state.
(3)
Power produced from all Waste-to-Energy
plants set up as per approved PPA with the distribution licensee in the State.
(4)
Tariff of all Hydro Power Plants including
Pump Hydro Power Plants, for which PPA has been approved by the Commission,
shall be determined in accordance with RTM framework under Section 62.
Regulation - 4. Power Procurement under Section 63 of the Act
Tariff for all power procurement under long term, medium term not covered in
Regulation 3 and HP-DAM (High Price Day Ahead Market) shall be discovered
through competitive bidding route with prior approval of the Commission for the
requirement of such capacity to be bid in pursuance to Section 86 (1)(b) of the
Act. Further, any deviation from TBCB guidelines shall require prior approval
of the Commission.
PART 2 TRANSMISSION
Regulation - 5. STU Transmission Plan
(1)
The STU shall prepare an updated five-year
Transmission System Plan for the State (identifying specific transmission
projects which are required to be taken up along with others (a) Brief Scope of
Work; (b) Estimated Cost; (c) Estimated COD/implementation timelines) for approval
of the Commission by 28th February on rolling basis every year (or as
stipulated in the State Grid Code) in accordance with the State Grid Code read
with Indian Electricity Grid Code and other guidelines/ regulations of Central
Electricity Authority.
(2)
All intra-State transmission projects shall
be consistent with the STU Transmission Plan. No intra-State transmission
project shall be considered for implementation, unless the project is a part of
the STU Transmission Plan and has been duly approved by the Commission.
Regulation - 6. Tariff Determination for InSTS Projects under Section 63 of the Act
(1)
All new greenfield intra-State transmission
projects of 220 kV & above voltage level, being part of the STU
Transmission Plan, shall be implemented through Tariff Based Competitive
Bidding (TBCB) in accordance with the guidelines issued under Section 63 of the
Act and any deviation from the guidelines should have prior approval of the
Commission. The tariff of such intra-State transmission projects shall be discovered
under Section 63 of the Act.
Provided that following new
greenfield intra-State transmission projects, being part of the STU
Transmission Plan, shall be covered under RTM framework (under Section 62 of
the Act) subject to prior approval of the Commission:
(a)
Intra-State transmission projects of
strategic importance or works required for catering to an urgent situation,
where proposal of such importance or urgency is supported by the recommendation
of the State Government;
(b)
Deposit works, whose funds are accounted for
under consumer contribution;
(c)
Small schemes such as LILO lines, whether for
the purpose of a city bypass or otherwise, and entailing a cost not exceeding
Rs. 100 Crores. However, after completion of project, if it is found that the
capital cost incurred has exceeded the ceiling limit of Rs 100 Crores, then
such excess amount shall not be passed under Regulated Tariff and shall be
borne by the transmission licensee through its own reserve/cost.
Regulation - 7. Tariff Determination for InSTS Projects under Section 62 of the Act
(1)
Tariff for all other intra-State transmission
projects not covered under Regulation 6.1, being part of the STU Transmission
Plan, shall be determined in accordance with RTM framework under Section 62 of
the Act.
(2)
Implementation of augmentation/ strengthening
works (excluding O&M works) at the intra-State transmission substation
and/or line, being part of the STU Transmission Plan, shall be carried out by
the respective developer in accordance with the provisions under Section 62 of
the Act read with UPERC (Multi Year Tariff for Distribution and Transmission)
Regulations 2019, as amended from time to time, for which the STU shall obtain
prior approval of the Commission on case-to-case basis.
PART 3 DISTRIBUTION
Regulation - 8.
Retail Tariff of the consumers shall be determined in accordance with Section
62 of the Electricity Act 2003 along with UPERC (Multi Year Tariff for
Distribution and Transmission) Regulations 2019, as amended from time to time.
PART 4 MISCELLANEOUS
Regulation - 9. Power to Relax
The Commission may by general or special order, for reasons to be recorded in
writing, and after giving an opportunity of hearing to the parties likely to be
affected, may relax any of the provisions of these regulations on its own
motion or on an application made before it by the affected party.
Regulation - 10. Power to Remove Difficulties
If any difficulty arises in giving effect to these regulations, the Commission
may on its own motion or on an application filed by any affected party, issue
such practice directions as may be considered necessary in furtherance of the
objective of these regulations.