TELANGANA STATE ELECTRICITY REGULATORY COMMISSION (TERMS
AND CONDITIONS FOR DETERMINATION OF GENERATION TARIFF) REGULATIONS, 2019
PREAMBLE
Introduction
Section 62 and Section 86(1)(b) of the Electricity Act,
2003, require the Commission to determine the tariff for supply of electricity
by a Generating Entity to a Distribution Licensee and to regulate electricity
purchase and procurement process of Distribution Licensees including the price
at which electricity shall be procured, from the Generating Entities or
Licensees or from other sources through agreements for purchase of power for
distribution and supply within the State. Section 61 of the Act requires the
Commission to specify the terms and conditions for such determination of
tariff. Accordingly, the Commission in exercise of the powers conferred by
section 181(2) (zd) read with section 61 of the Electricity Act, 2003 (36 of
2003) thereof and all other powers enabling it in this behalf, hereby, makes
the following Regulation.
Regulation - 1. Short title, commencement and extent.
1.1. These Regulations shall be called the
Telangana State Electricity Regulatory Commission (Terms and Conditions for
Determination of Generation Tariff) Regulations, 2019;
1.2. These Regulations shall come into force
with effect from the date of its publication in the Telangana State Gazette and
shall remain in force till amended or repealed by the Commission:
Provided that for all purposes, including the review
matters pertaining to the period till FY 2018-19, the issues related to
determination of Aggregate Revenue Requirement shall be governed by the
provisions of the Andhra Pradesh Electricity Regulatory Commission (Terms and
conditions for determination of tariff for supply of electricity by a
generating company to a distribution licensee and purchase of electricity by
distribution licensees) Regulation, 2008, including amendments thereto, as may
be applicable.
1.3 These Regulations shall extend to the
entire state of Telangana.
1.4 These Regulations shall be applicable to
all existing and future Generating Entities and their successors, if any for
determination of Aggregate Revenue Requirement within the state of Telangana in
all matters covered under these Regulations from 1 April, 2019 to 31 March,
2024.
Regulation - 2. Definitions and interpretation.
In these Regulations, unless the context otherwise
requires
2.1. "ABT Mechanism" means
availability based tariff mechanism.
2.2. "Accounting Statement(s)"
means for each Financial Year, the following statements, namely:
2.2.1. balance sheet, prepared in accordance
with the form contained in the Companies Act, 2013 as amended from time to
time, as applicable;
2.2.2. profit and loss account, complying
with the requirements contained in the Companies Act, 2013, as amended from
time to time, as applicable, cash flow statement prepared in accordance with
the applicable Accounting Standards of the Institute of Chartered Accountants
of India
2.2.3. report of the statutory auditors;
2.2.4. cost records prescribed by the Central
Government under the Companies Act, 2013, as applicable together with notes
thereto, and such other supporting statements and information as the Commission
may direct:
Provided that separate Accounting Statements shall be
prepared and submitted to the Commission for each Licensed Business in
accordance with the License conditions, and for each regulated business:
Provided further that, in case separate Accounting
Statements are not submitted for each Licensed Business in accordance with the
License conditions and for each regulated business for the FY 2018-19 onwards,
the petitions filed by the Generating Entity, may be rejected by the Commission
after giving the Petitioner a reasonable opportunity of being heard:
Provided also that the Generating Entity shall submit the
statutory auditor's comments, observations and notes to accounts, along with
the Accounting Statements, and a summary of the key issues highlighted by the
statutory auditor and the steps taken to address them:
2.3. "Act" means the Electricity Act,
2003 (36 of 2003), as amended from time to time.
2.4. "Aggregate Revenue Requirement
(ARR)" means the annual revenue requirement for each financial year
comprising of allowable expenses and return on capital pertaining to the
Generating Entity, for recovery through tariffs and charges, in accordance with
these Regulations;
2.5. "Allocation Statement" means
for each Financial Year, a statement in respect of each of the separate
businesses of the Generating Entity, showing the amounts of any revenue, cost,
asset, liability, reserve or provision etc., which has been either:
2.5.1. determined by apportionment or
allocation between different businesses of the Generating Entity including the
Licensed Business, together with a description of the basis of the apportionment
or allocation; or
2.5.2. charged from or to each such Other
Business together with a description of the basis of that charge
Provided further that, separate Unit-wise and
Station-wise Accounting Statements for Generation Business shall be prepared
and submitted to the Commission wherever possible.
2.6. "Applicant" or
"Petitioner" means a Generating Entity, who has made an application
for determination of tariff in accordance with the Act and these Regulations
and includes a Generating Entity whose tariff is the subject of a review by the
Commission on suo-motu basis or as part of a truing- up exercise.
2.7. "Auxiliary Energy Consumption
(AUX)" in relation to a period, in case of a Generating Station or Unit,
means the quantum of energy consumed by auxiliary equipment of the Generating
Station, such as the equipment being used for the purpose of operating plant
and machinery, including switchyard of the Generating Station and the
transformer losses within the Generating Station, and shall be expressed as a
percentage of the sum of gross energy generated at the generator terminals of
all the Units of the Generating Station:
Provided that the Auxiliary Energy Consumption shall not
include the energy consumed for supply of power to housing colony and other
facilities at the Generating Station and the power consumed for construction
works at the Generating Station;
2.8. "Availability" in relation to
a Thermal Generating Station/Unit for any period means the average of the daily
average declared capacities as certified by the State Load Despatch Centre
(SLDC) for all the Days during that period, expressed as a percentage of the
Installed Capacity of the Generating Station/Unit minus the normative Auxiliary
Consumption in Megawatts (MW), as specified in these Regulations, and shall be
computed in accordance with the following formula
In relation to a Thermal Generating Station/Unit
N
Availability = 100 X ? DCi/{N X IC X (1-AUXn)}
%
i=1 where, N = number of Time Blocks in the given period
DCi = Average Declared Capacity in MW for the ith Time
Block in such period
IC = Installed Capacity of the Generating Station/Unit in
MW
AUXn = Normative Auxiliary Consumption in MW, expressed
as a percentage of gross generation in MW.
2.9. "Bank Rate" shall mean the
"One-year Marginal Cost of Funds-based Lending Rate" (MCLR) declared
by State Bank of India and in effect on April 1st of the Financial Year of the
date of petition/application.
2.10. "Beneficiary or
Beneficiaries" in relation to a Generating Station means the purchaser of
electricity generated at such Station whose tariff is determined under this
Regulation.
2.11. "Block" in relation to a
combined cycle Thermal Generating Station includes combustion
turbine-generators, associated waste heat recovery boiler, connected steam
turbine-generator and auxiliaries;
2.12. "Books of Accounts" includes
records maintained by the Generating Station in respect of all sum of money
received and expended; all sales and purchases of goods and services; the
assets and liabilities; and any other cost/revenue items or financial
transactions;
2.13. "Capital Cost" means the
capital cost of a Project or its Unit or Stage as the case maybe as determined
by the Commission after prudence check in accordance with clause 7 of this
Regulation.
2.14. "Capacity Index" in relation
to a Hydro power generating stations means the average of the daily capacity
indices over one year excluding those days on which Maximum Available capacity
is Zero due to non-availability of water
Capacity Index =
Sum of Capacity indices for all the days of the
year/Number of days in the year when the Maximum Available Capacity is non-zero
2.15. "CEA" means Central
Electricity Authority referred to in Section 70 of the Act.
2.16. "CERC" means the Central
Electricity Regulatory Commission referred to Section 76 of the Act;
2.17. "CERC Regulations" means the
Central Electricity Regulatory Commission (Terms and Conditions of Tariff)
Regulations, 2014 as amended from time to time.
2.18. "Change in Law" means
occurrence of any of the following events :
2.18.1. enactment, bringing into effect or
promulgation of any new Indian law ; or
2.18.2. adoption, amendment, modification,
repeal or re-enactment of any existing Indian law ; or
2.18.3. change in interpretation or
application of any Indian law by a competent court, Tribunal or Indian
Governmental Instrumentality, which is the final authority under law for such
interpretation or application ; or
2.18.4. change of any condition or covenant
by any competent statutory authority in relation to any consent or clearances
or approval or Licence available or obtained for the Project ; or
2.18.5. coming into force or change in any
bilateral or multilateral agreement or treaty between the Government of India
and any other Sovereign Government having implications for the Generating
Station regulated under this Regulation ; or
2.18.6. any change in taxes or duties, or
introduction of any taxes or duties levied by the Central or any State
Government
2.19. Commission means the Telangana State
Electricity Regulatory Commission;
2.20. "Competitive Bidding" means a
transparent process for procurement of equipment, services and works in which
bids are invited by the Project developer through open
advertisement/e-procurement covering the scope and specifications of the
equipment, services and works required for the Project, the terms and
conditions of the proposed contract, the criteria by which the bids shall be
evaluated, and shall include domestic as well as international Competitive
Bidding.
2.21. "Conduct of Business
Regulations" means the Telangana State Electricity Regulatory Commission
(Conduct of Business) Regulations, 2015, as amended from time to time;
2.22. "Control Period" means the
period comprising five Years from April 1st, 2019 to March 31st, 2024, as the
Second control period and as may be extended by the Commission.
2.23. "Cut-off Date" means the 31st
March of the Year ending after two (2) Years of the Year of start of commercial
operation of a Project and, in case a Project is declared to be under
commercial operation in the last quarter of a Year, it shall mean the 31st
March of the Year ending after three Years of the Year of start of such
commercial operation.
2.24. "Date of Commercial
Operation" (or "COD") shall have the meaning as assigned in
clause 5 of this Regulation;
2.25. "Day" means the 24 hour
period starting at 00:00 hour(s)
2.26. "De-capitalisation" means
reduction in gross fixed assets of the Project corresponding to the removal of
assets as admitted by the Commission;
2.27. "Declared Capacity" (or
"DC") in relation to a Generating Station means, the capability to
deliver ex-bus electricity in MW declared by such Generating Station in
relation to any Time-Block of the Day as defined in the Grid Code or whole of
the Day, duly taking into account the availability of fuel or water, and
subject to further qualification in the relevant Regulation
2.28. "Design Energy" means the
quantum of energy which can be generated in a 90% Dependable Year with 95%
Installed Capacity of the hydro Generating Station;
2.29. "Detailed Project Report" (or
"DPR") means a capital expenditure report with projected Capital Cost
exceeding the limits specified in these Regulations, for which the Generating
Entity is required to obtain prior in-principle approval by submitting a
Detailed Project Report (DPR) in accordance with the Guidelines of the
Commission for in-principle Clearance of proposed investment schemes;
2.30. "Distribution Licensee" means
a Licensee authorised to operate and maintain a distribution system for
supplying electricity to consumers in its area of supply.
2.31. "End of Control Period
Review" means a review to be undertaken in accordance with the clause 3.13
of this Regulation;
2.32. "Existing Project" means a
Project which has been declared under commercial operation on a date prior to
commencement of the Control Period;
2.33. "Expected Revenue from Tariff and
Charges" means the revenue estimated to accrue to the Generating Entity
from the regulated business at the prevailing level of tariff and charges.
2.34. "Extended Life" means the
life of a Generating Station or Unit thereof beyond the period of Useful Life,
as may be approved by the Commission on a case to case basis
2.35. "Force Majeure Event" means,
with respect to any party, any event or circumstance, or combination of events
or circumstances, which is not within the reasonable control of, and is not due
to an act of omission or commission of that party and which, by the exercise of
reasonable care and diligence, could not have been prevented ; and, without
limiting the generality of the foregoing, shall include the following events or
circumstances:
2.35.1. acts of God, including but not
limited to lightning, storm, action of the elements, earthquakes, flood,
torrential rains, drought and natural disaster ;
2.35.2. acts of war, invasion, armed conflict
or act of foreign enemy, insurrections, riots, revolution, terrorist or
military action ;
2.35.3. unavoidable accident, including but
not limited to fire, explosion, radioactive contamination and toxic chemical
contamination ;
2.35.4. any shutdown or interruption of the
grid, which is required or directed by the concerned Load Despatch Centre
2.36. "Generation Business" means
the business of production of electricity from a Generating Station for the
purpose of:
2.36.1. giving supply to any premises or
enabling supply to be so given, or
2.36.2. supply of electricity to any
Distribution Licensee in accordance with the Act and the rules and Regulations
made there under, or
2.36.3. subject to the Regulation made under
sub-section (2) of Section 42 of the Act, supply of electricity to any consumer
2.37. "Generating Entity" means any
company or body corporate or association or body of individuals, whether
incorporated or not, or artificial juridical person, which owns or operates or
maintains a Generating Station.
2.38. "Generating Station(s)" (or
"Station(s)") means a Station for generating electricity, including
any building and plant with step-up transformer, switchgear, switch yard, cables
or other appurtenant equipment used for that purpose and the site thereof ; a
site intended to be used for a Generating Station, and any building used for
housing the operating staff of a Generating Station, Further provided that
where electricity is generated by waterpower, includes penstocks, head and tail
works, main and regulating reservoirs, dams and other hydraulic works, but does
not include any sub-station.
2.39. "Generating Unit(s) or
Unit(s)" in relation to a Thermal Generating Station (other than combined
cycle Thermal Generating Station) means steam generator, turbine-generator and
auxiliaries, or in relation to a combined cycle Thermal Generating Station,
means turbine generator and auxiliaries; in relation to a hydro generating
station means turbine generator and its auxiliaries;
2.40. "Grid" means the high voltage
backbone system of inter-connected transmission lines, sub-stations and
Generating Stations;
2.41. "Grid Code" means the Indian
Electricity Grid Code specified by the Central Commission or the Telangana
State Electricity Regulatory Commission (State Grid Code) Regulations whichever
is applicable as amended from time to time or subsequent re-enactment thereof;
2.42. "Gross Calorific Value" (or
"GCV") in relation to a Thermal Generating Station means the heat
produced in kilocalories (kcal) by complete combustion of one kilogram (kg) of
solid fuel or one litre of liquid fuel or one standard cubic meter of gaseous
fuel, as the case may be.
2.43. "Gross Station Heat Rate" (or
"GSHR") means the heat energy input in kcal required to generate one
kilo Watt hour (kWh) of electrical energy at generator terminals of a Thermal
Generating Station.
2.44. "Implementation Agreement"
means the agreement, contract or memorandum of understanding, or any such
covenant, entered into between the Generating Station and transmission licensee
for the execution of associated transmission system in coordinated manner.
2.45. "Infirm Power" means
electricity injected into the Grid prior to the COD of a Unit or Block of the
Generating Station;
2.46. "Installed Capacity" (or
"IC") means the summation of the name plate capacities of all the
Units of the Generating Station or the capacity of the Generating Station
(reckoned at the generator terminals) as may be approved by the Commission from
time to time;
2.47. "Kilowatt-Hour" (or
"kWh") means a unit of electrical energy, measured in one (01)
kilowatt or one thousand watts (1,000) of power produced or consumed over a
period of one (01) hour;
2.48. "License" means license
granted under section 14 of the Act;
2.49. "Licensed Business" means the
functions and activities, which are required to be undertaken by the Licensee,
in terms of the License granted under the Act;
2.50. "Licensee" means a person who
has been granted a License.
2.51. "Maximum Continuous Rating"
(or "MCR") in relation to a Generating Unit of the Thermal Generating
Station means the maximum continuous output at the generator terminals,
guaranteed by the manufacturer at rated parameters, and in relation to a Block
of a combined cycle Thermal Generating Station means the maximum continuous
output at the generator terminals, guaranteed by the manufacturer with water or
steam injection (if applicable) and corrected to 50 Hz Grid frequency and under
specified site conditions;
2.52. "Mid-term Review" means a
review to be undertaken in accordance with the clause 3.12 of this Regulation;
2.53. "New Generating Unit/Station"
means a generating unit/station declared under commercial operation on or after
the date of coming into force of these Regulations.
2.54. "Ninety (90) % Dependable
Year" shall mean the Year in which the annual energy generation has the
probability of being equal to or in excess of 90% of the expected period of
operation of the Station.
2.55. "Non-DPR Scheme" means a
capital expenditure scheme with projected Capital Cost within the limits
specified in these Regulations, for which the Generating Entity is not required
to obtain prior in principle approval of the Commission.
2.56. "Non-Tariff Income" means the
income relating to the regulated business other than from tariff, excluding any
income from Other Business.
2.57. "Normative Annual Plant
Availability Factor" (or "NAPAF"), in relation to a Generating
Station means the availability factor as specified in clause 17.3 and 18.3 of
these Regulations for Thermal Generating Station and hydro Generating Station
respectively.
2.58. "Officer" means an officer of
the Commission.
2.59. "Operation and Maintenance
expense" (or "O&M expense") in respect of a Generating
Entity means the expenditure incurred on operation and maintenance of the
Generating Station or Unit of a Generating Entity, or part thereof, and
includes the expenditure on manpower, repairs, spares, consumables, insurance
and overheads, but excludes fuel expenses and water charges and shall be as
determined in clause 19 of this Regulation.
2.60. "Original Project Cost" means
the capital expenditure incurred by a Generating Entity within the original
scope of the Project, up to the Cut-Off Date as admitted by the Commission.
2.61. "Original Scope of Work"
means the activities to be performed under a contract or sub-contract in the
completion of Project or scheme as approved by the Commission;
2.62. "Other Business" means any
business undertaken by the Generating Entity, other than generation of
electricity;
2.63. "Pit head" refers to the top
of a mining pit or coal shaft that is immediately adjacent to the Generating
Station
2.64. "Plant Availability Factor"
(or "PAF"), in relation to a Generating Station for any period means
the average of the daily Declared Capacities (DCs) for all the Days during the
period expressed as a percentage of the Installed Capacity in MW less the
normative Auxiliary Energy Consumption.
2.65. "Plant Load Factor" (or
"PLF"), in relation to a Thermal Generating Station for a given
period, means the total sent-out energy corresponding to actual generation
during such period, expressed as a percentage of sent-out energy corresponding
to Installed Capacity in that period, and shall be computed in accordance with
the following formula :
2.65.1. In relation to a to a Thermal
Generating Station/Unit
N PLF = 100 X ? SGi/{N X IC X (1-AUXn)} %
i=1 where,
N = number of Time Blocks in the given period;
SGi = Scheduled Generation in MW for the ith Time Block
of the period;
IC = Installed Capacity of the Generating Station/Unit in
MW;
AUXn = Normative Auxiliary Consumption in MW, expressed
as a percentage of gross generation in MW;
N
? = Summation from i = 1 to N; i=1 2.66.
"Primary Energy" in relation to a hydro power generating station
means the quantum of energy generated up to the design energy on per year basis
at the generating station;
2.67. "Project" means a Generating
Station
Provided that in case of a hydro Generating Station
includes all components of generating facility such as dam, intake water
conductor system, power Generating Station and generating units of the scheme,
as apportioned to power generation.
Further provided that in case of Thermal Generating
Stations it does not include mining if it is a Pit Head Project and dedicated
captive coal mine.
2.68. "Prudence Check" means the
scrutiny of reasonableness of expenditure incurred or proposed to be incurred,
financing plan, use of efficient technology, cost and time overrun and such
other factors as may be considered appropriate by the Commission for
determination of Aggregate Revenue Requirement and tariff.
2.69. "Pumped Storage Hydro Generating
Station" means a hydro station which generates power through energy stored
in the form of water energy, pumped from a lower elevation reservoir to a
higher elevation reservoir.
2.70. "Reform Act" means the Andhra
Pradesh Electricity Reform Act, 1998.
2.71. "Run-of-river Generating
Station" means a hydro Generating Station, which does not have upstream
pondage.
2.72. "Run-of-river Generating Station
with pondage" means a hydro Generating Station with sufficient pondage for
meeting the diurnal variation of power demand.
2.73. "Scheduled Commercial Operation
Date or SCOD" shall mean the date(s) of commercial operation of a
Generating Station or Generating Unit or Block thereof as indicated in the
Investment approval or as agreed in power purchase agreement whichever is
earlier.
2.74. "Scheduled energy" means the
quantum of energy scheduled by the concerned load despatch center to be
injected into the grid by a generating station for a given time period.
2.75. "Scheduled generation" at any
time or for a time block or any period means schedule of generation in MW or
MWh ex-bus given by the concerned Load Dispatch Centre;
2.76. "Secondary Energy " in
relation to a hydro power generating station means the quantum of energy
generated in excess of the design energy on per year basis at the generating
station;
2.77. "Small Gas Turbine Generating
Station" means and includes open cycle gas turbine or combined cycle
Generating Stations with gas turbines in the capacity range of 50 MW or below.
2.78. "Start Date or Zero Date"
means the date indicated in the investment approval for commencement of implementation
of the Project and where no date has been indicated, the date of investment
approval shall be deemed to be the Start Date or Zero Date.
2.79. "State" means the state of
Telangana.
2.80. "State Grid Code" means the
Code specified by the Commission under clause (h) of sub-section (1) of section
86 of the Act;
2.81. "Storage-type Power Station"
means a hydro power Generating Station associated with large storage capacity
to enable variation in generation of electricity according to demand.
2.82. "Straight Line Method" means
the method where depreciation results in a constant charge over the Useful Life
if the asset's residual value does not change.
2.83. "Time-Block" means a time
block of fifteen (15) minutes or any such shorter duration as may be notified
by CERC and Commission, for which specified electrical parameters and
quantities are recorded by special energy meter, with first time block starting
at 00.00 hours or such other period as the Commission may stipulate.
2.84. "Terminal Liabilities" means
terminal benefits such as Death-cum-Retirement Gratuity, Pension, Commuted
Pension, Leave Encashment, LTC, Dearness relief, Interim relief, Medical
reimbursement including fixed medical allowance in respect of pensioners.
2.85. "Thermal Generating Station"
means a Generating Station or a Unit thereof that generates electricity using
fossil fuels as its primary source of energy.
2.86. "Trial Run or Trial
Operation" means the successful running of the Generating Station or Unit
thereof at MCR or Installed Capacity for continuous period of 72 hours in case
of Unit of a Thermal Generating Station or Unit thereof and 3 hours in case of
a Unit of a hydro Generating Station or Unit thereof;
Provided that:
2.86.1. The short interruptions, for a
cumulative duration of 4 hours, shall be permissible with a corresponding
increase in the duration of the test. Cumulative Interruptions for more than 4
hours shall call for repeat of Trial Operation or Trial Run.
2.86.2. Partial loading may be allowed with
the condition that average load during the duration of the Trial Run shall not
be less than Maximum Continuous Rating or the Installed Capacity or the Name
Plate Rating excluding period of interruption and partial loading but including
the corresponding extended period.
2.86.3. Units of thermal and hydro Central
Generating Stations and inter-State Generating Stations shall also demonstrate
capability to raise load up to 105% or 110% of this Maximum Continuous Rating
or Installed Capacity or the Name Plate Rating as the case may be.
2.87. "Unit" in relation to a
Thermal Generating Station (other than combined cycle Thermal Generating
Station) means steam generator, turbine-generator and auxiliaries or, in
relation to a combined cycle Thermal Generating Station, means turbine-generator
and auxiliaries; and, in relation to a hydro Generating Station, means turbine-
generator and its auxiliaries.
2.88. "Useful life" means in
relation to a Unit of a Generating Station, from the date of commercial
operation shall mean the following, namely:-
(i)
Coal/Lignite based thermal generating
Station: 25 years;
(ii)
Gas/Liquid fuel based thermal Generating
Station: 25 years;
(iii)
Hydel Generating Station including Pumped
Storage, Hydel Generating Station : 40 years
Provided further that the extension of life of the
projects beyond the completion of their useful life shall be decided by the
Commission.
2.89. "Year" or "Financial
Year (FY)" means a financial year;
2.90. Words and expressions used and not
defined in the Regulation but defined in the Act and Reform Act shall have the
meanings assigned to them in the Act or Reform Act. Expressions used herein but
not specifically defined in the Regulation or in the Act but defined under any
law passed by a competent legislature and applicable to the electricity
industry in the State shall have the meaning assigned to them in such law.
Subject to the above, expressions used herein but not specifically defined in
this Regulation or in the Act or any law passed by a competent legislature
shall have the meaning as is generally assigned in the electricity industry.
In the interpretation of this Regulation, unless the
context otherwise requires:
(i)
words in the singular or plural term, as the
case may be, shall also be deemed to include the plural or the singular term,
respectively;
(ii)
references herein to the 'Regulation' shall
be construed as a reference to this Regulation as amended or modified by the
Commission from time to time in accordance with the applicable laws in force;
(iii)
the headings are inserted for convenience and
may not be taken into account for the purpose of interpretation of this
Regulation;
(iv)
reference to the statutes, Regulations or
guidelines shall be construed as including all provisions consolidating,
amending or replacing such statutes, Regulations or guidelines, as the case may
be, referred to;
Regulation - 3. Applicability and General Principles.
3.1. This Regulation shall apply in all cases
where tariff for a Generating Station or a Unit thereof is required to be
determined by the Commission under section 62 of the Act.
Provided that, Provisions of these Regulations shall not
be applicable for the Determination of Tariff for the Generation of Electricity
from Renewable Energy Sources.
3.2. The Commission shall be guided by the
Regulations contained herein for determining the tariff for supply of
electricity by a Generating Entity to a Distribution Licensee in the following
cases:
3.2.1. where such tariff is pursuant to a
power purchase agreement or arrangement entered into subsequent to the date of
effectiveness of these Regulations; or
3.2.2. where such tariff is pursuant to a
power purchase agreement or arrangement entered into prior to the date of
effectiveness of this Regulation and either the Commission has not previously
approved such agreement/arrangement or the agreement/arrangement envisages that
the tariff shall be based on the this TSERC Generation Tariff Regulations,
2019;
3.3. This Regulation shall not apply for
determination of tariff in case of the following:
3.3.1. Generating Stations whose tariff has
been discovered through tariff based Competitive Bidding in accordance with the
guidelines issued by the Central Government and adopted by the Commission under
Section 63 of the Act;
3.4. This Regulation shall be applicable to
all existing and future Generating Entities and their successors, if any.
3.5. These Regulations supersede the
"APERC Terms and Conditions for Determination of Tariff for Supply of
Electricity by a Generating company to a Distribution Licensee and Purchase of
Electricity by Distribution Licensees Regulation 1 of 2008".
Multi-Year Tariff Framework
3.6. The Commission shall determine the
tariff for supply of electricity by a Generating Entity, except from renewable
sources of energy to a Distribution Licensee under a multi-year tariff
framework with effect from April 1, 2019.
Provided that where the Commission believes that a
shortage of supply of electricity exists, it may fix the minimum and maximum
ceiling of tariff for sale or purchase of electricity in pursuance of an
agreement, entered into between a Generating Entity and a Distribution Licensee
or between Distribution Licensees, for a period not exceeding one year to
ensure reasonable prices of electricity.
Notwithstanding anything contained in this Regulation,
the Commission shall adopt the tariff if such tariff has been determined
through a transparent process of bidding in accordance with the guidelines
issued by the Central Government pursuant to Section 63 of the Act.
3.7. The Multi-Year Tariff framework shall be
based on the following elements, for determination of Aggregate Revenue
Requirement and Expected Revenue from Tariff and Charges for Generating Entity:
3.7.1. The Applicant shall submit a detailed
Multi-Year Tariff application comprising the following for each year of the
Control Period:
(a)
the forecast of Aggregate Revenue Requirement
for the entire Control Period
(b)
expected revenue from existing tariffs
(c)
proposed tariff
(d)
revenue gap
Provided that the performance parameters, whose trajectories
have been specified in this Regulation, shall form the basis for projection of
these performance parameters in the Aggregate Revenue Requirement for the
entire Control Period;
3.7.2. Determination of Aggregate Revenue
Requirement and tariff for the Generating Entity for each Financial Year within
the Control Period by the Commission at the start of the Control Period;
3.7.3. Petition for Mid-term Review of
operational and financial performance vis-a-vis the approved forecast for the
first two years of the Control Period; and revised forecast of Aggregate
Revenue Requirement, expected revenue from existing tariff, expected revenue
gap, for the third, fourth and fifth year of the Control Period, shall be
submitted by the Generating Entity;
3.7.4. True-up for the first year and second
year of the Control Period based on audited accounts and provisional true-up
for the third year of the Control Period of operational and financial
performance vis-a-vis the approved forecast for the respective Years shall be
submitted by the Generating Entity along with its Petition for Mid-term Review;
3.7.5. Determination of the revised Aggregate
Revenue Requirement and tariff for Generating Entity by the Commission for the
fourth and fifth year of the Control Period based on the Mid-term Review;
3.7.6. True-up for the first year and second
year of the Control Period, provisional true-up for the third year of the
Control Period of operational and financial performance vis-a-vis the approved
forecast for the respective years, and categorisation of variation in
performance as those caused by factors within the control of the Petitioner
(controllable factors) and by factors beyond its control (uncontrollable
factors) by the Commission, along with the Midterm Review
3.7.7. The mechanism for pass-through of
approved gains or losses on account of uncontrollable factors as specified by
the Commission in this Regulation;
3.7.8. The mechanism for sharing of approved
gains or losses on account of controllable factors as specified by the
Commission in this Regulation;
3.8. Petitions to be filed during the Second
Control Period-The Petitions to be filed in the Second Control Period under
these Regulations are as under:-
3.8.1. Multi-Year Tariff Petition n shall be
filed by April 1 2019, comprising:
(a)
Truing-up for FY 2014-18 to be carried out
under the Andhra Pradesh Regulation 1 of 2008 - Terms and Conditions for
Determination of Tariff for Supply of Electricity by a Generating Entity to a
Distribution Licensee and Purchase of Electricity by Distribution Licensees or
CERC Regulations as relevant.
(b)
Provisional Truing-up and truing up for FY
2018-19 to be carried out under the Andhra Pradesh Regulation 1 of 2008 - Terms
and Conditions for Determination of Tariff for Supply of Electricity by a
Generating Entity to a Distribution Licensee and Purchase of Electricity By
Distribution Licensees or CERC Regulations as relevant.
Provided that the Commission may, if it considers
appropriate, carry out the truing-up for the year FY 2018-19, along with the
truing up for the first two years of the Control Period FY 2019-24 during the
Mid-Term Review.
(c)
Aggregate Revenue Requirement for each year
of the Control Period under this Regulations;
(d)
Revenue from the sale of power at existing
tariffs and projected revenue gap for each year of the Control Period under
this Regulation;
3.8.2. Mid-term Review Petition
(a)
Truing-up for the first and second year and
provisional truing-up for third year of the Control Period to be carried out
under these Regulations.
(b)
Revised forecast of Aggregate Revenue
Requirement, expected revenue from existing tariff and charges and revenue gap
for the fourth and fifth year of the Control Period.
Provided that a petition may be filed at any time during
the Control Period in case of variation in uncontrollable factors that may
result in sudden, steep, and sustained increase in tariff.
3.9. The
Petitioner shall submit separate audited Accounting Statements along with the
petition for determination of tariff and truing-up under these Regulations.
3.10. Multi-Year Tariff Petition
3.10.1. The Multi-Year Tariff Petition shall
include a forecast of Aggregate Revenue Requirement and expected revenue from
tariff for each Year of the Control Period in the manner specified in these
Regulations, and shall be accompanied by applicable fees.
3.10.2. The forecast of Aggregate Revenue
Requirement may be based on assumptions relating to the behavior of individual
variables during the Control Period, including capital investment plan,
financing plan and physical targets, in accordance with guidelines and formats
as may be prescribed by the Commission.
3.10.3. The capital investment plan shall
show, separately, on-going Projects that will spill over into the Control
Period, and new Projects that will commence in the Control Period but may be
completed within or beyond it, for which relevant technical and commercial
details shall be provided.
3.10.4. The forecast of Expected Revenue from
Tariff and Charges shall be based on the following:
(a)
Estimates of quantum of electricity to be
generated by each Unit/Station for each year of the Control Period.
(b)
Prevailing tariff as on the date of filing of
the petition/application or estimated tariff for the new generating
unit/station
3.10.5. Based on the forecast of Aggregate
Revenue Requirement and expected revenue from tariff the Generating Entity
shall submit the proposed tariff (Unit and Station-wise) for each year of the
Control Period, that would meet the gap, if any, in the Aggregate Revenue
Requirement, including unrecovered revenue gaps of previous years to the extent
proposed to be recovered.
3.10.6. Full details supporting the forecast
shall be provided, including but not limited to details of past performance,
proposed initiatives for achieving efficiency or productivity gains, technical
studies, contractual arrangements and secondary research, to enable the
Commission to assess the reasonableness of the forecast.
3.10.7. On receipt of the petition, the
Commission shall either issue an Order approving the Aggregate Revenue Requirement
and tariff for the Control Period, subject to such modifications and
conditions as it may stipulate; or reject the petition for reasons to be
recorded in writing, after giving the Petitioner a reasonable opportunity of
being heard.
3.11. Specific trajectory for certain
variables. The Commission, while approving the Multi-Year Tariff Petition, may
stipulate a trajectory variables.
3.12. Mid-term Review
3.12.1. The Generating Entity shall file a
petition for Mid-term Review and truing-up of the Aggregate Revenue Requirement
and Revenue for FY 2019-20 and FY 2020-21, and provisional truing-up for the FY
2021-22, by November 30, 2021:
Provided that the Petition shall include information in
such form as may be stipulated by the Commission, together with the Accounting
Statements, extracts of Books of Account and such other details, including cost
accounting reports or extracts thereof, as it may require to assess the reasons
for and extent of any difference in operational and financial performance from
the approved forecast of Aggregate Revenue Requirement and expected revenue
from tariff.
3.12.2. The scope of the Mid-term Performance
Review shall be a comparison of the actual operational and financial
performance vis-a-vis the approved forecast for the first three years of the
Control Period; and revised forecast of Aggregate Revenue Requirement, expected
revenue from existing Tariff, expected revenue gap, for the fourth and fifth
year of the Control Period.
3.12.3. Upon completion of the review under clause
3.12.2 herein, the Commission shall attribute any variations or expected
variations in performance, for variables specified under clause 6.7 &
clause 6.8, to factors within the control of the Petitioner (controllable
factors) or to factors beyond its control (uncontrollable factors).
3.12.4. Any variations or expected variations
in performance, for variables other than those specified under clause 6.7 of
this Regulation, shall not ordinarily be reviewed by the Commission during the
Control Period and shall be attributed entirely to controllable factors:
3.12.5. Where the Petitioner believes, for
any variable not specified under clause 6.7, that there is a material variation
or expected variation in performance for any Year on account of uncontrollable
factors, it may apply to the Commission for inclusion of such variable.
3.12.6. Upon completion of the Mid-term
Review, the Commission shall pass an order recording:
(a)
the approved aggregate gain or loss to the
Generating Entity on account of controllable factors for the first two Years of
the Control Period and provisional Truing-up for the third year of the Control
Period, and the amount of such gains or such losses that may be shared in
accordance with clause 6.10 of this Regulation.
(b)
The approved aggregate gain or loss to the
Generating Entity account of uncontrollable factors for the first two years of
the Control Period and provisional Truing-up for the third year of the Control
Period, and the amount of such gains or such losses that were not recovered
during the respective years and which may be shared in accordance with clause
6.9 of this Regulation.
(c)
The approved modifications to the Aggregate
Revenue Requirement and Tariffs for the remainder of the Control Period.
3.13. End of the Control Period Review
3.13.1. The Generating Entity shall file a
petition for End of the Control Period Review and truing-up of the Aggregate
Revenue Requirement and revenue for FY 2021-22 and FY 2022-23, and provisional
truing-up for the FY 2023-24, by November 30, 2023.
Provided that the Petition shall include information in
such form as may be stipulated by the Commission, together with the Accounting
Statements, extracts of Books of Account and such other details, including cost
accounting reports or extracts thereof, as it may require to assess the reasons
for and extent of any difference in operational and financial performance from
the approved forecast of Aggregate Revenue Requirement and expected revenue
from tariff.
3.13.2. The scope of the End of Control
Period Review shall be a comparison of the actual operational and financial
performance vis-a-vis the approved forecast for the third, fourth and fifth
Year(s) of the Control Period;
3.13.3. Upon completion of the review under
clause 3.13.2 of this Regulation, the Commission shall attribute any variations
or expected variations in performance, for variables specified under clause 6.7
& clause 6.8 of this Regulation, to factors within the control of the
Petitioner (controllable factors) or to factors beyond its control
(uncontrollable factors).
3.13.4. Any variations or expected variations
in performance, for variables other than those specified under clause 6.7 of
this Regulation, shall not ordinarily be reviewed by the Commission during the
Control Period and shall be attributed entirely to controllable factors:
3.13.5. Where the Petitioner believes, for
any variable not specified under clause 6.7, that there is a material variation
or expected variation in performance for any Year on account of uncontrollable
factors, it may apply to the Commission for inclusion of such variable.
3.13.6. Upon completion of the End of Control
Period Review, the Commission shall pass an order recording:
(a)
the approved aggregate gain or loss to the
Generating Entity on account of controllable factors for the third and fourth
year of Control Period and provisional Truing-up for the fifth year of the
Control Period, and the amount of such gains or such losses that may be shared
in accordance with clause 6.10 of this Regulation.
(b)
the approved aggregate gain or loss to the
Generating Entity account of uncontrollable factors for the third and fourth
Year of the Control Period and provisional Truing-up for the fifth year of the
Control Period, and the amount of such gains or such losses that were not
recovered during the respective years and which may be shared in accordance
with clause 6.9 of this Regulation.
3.13.7. Also, the Commission shall review the
achievement of objectives and implementation of the principles of MYT laid down
in these Regulations.
3.13.8. To meet the objectives of the Act,
the National Electricity Policy and Tariff Policy, the Commission may revise
the principles of MYT for the subsequent Control Period(s).
3.13.9. The end of a Control Period shall be
the beginning of the subsequent Control Period. The Applicant shall follow the
same procedure for the next Control Period unless required otherwise by the
Commission.
3.13.10. The Commission shall analyse the
performance with respect to the norms set out at the beginning of the Control
Period in the MYT order and shall determine the base values for the next
Control Period, based on actual performance achieved, expected improvement and
other relevant factors.
Regulation - 4. Procedure for determination of tariff.
4.1. Filing of Petition for determination of
Tariff
4.1.1. Petition for determination of tariff
shall be filed in such form and in such manner as specified in this Regulation,
and be accompanied by applicable fees.
4.1.2. The proceedings for determination of
Tariff shall be undertaken by the Commission in accordance with the Regulations
governing its Conduct of Business.
4.1.3. Notwithstanding anything contained in
this Regulation, the Commission shall have the authority to determine the
tariff, either suo-motu or on a Petition filed by the Generating Entity as per
TSERC terms and conditions of generation tariff regulation.
4.2. Petition for determination of tariff
4.2.1. Tariff in respect of a Generating
Station under this Regulations may be determined Stage-wise, Unit-wise or for
the whole Generating Station.
Provided that the terms and conditions for determination
of tariff for Generating Stations specified herein shall apply in like manner
to Stages or Units, as the case may be, as to Generating Stations.
4.2.2. Where the tariff is being determined
for Stage or Generating Unit of a Generating Station, the Generating Entity
shall adopt a reasonable basis for allocation of Capital Cost relating to
common facilities and allocation of joint and common costs across all Stages or
Generating Units, as the case may be.
Provided that the Generating Entity shall maintain an
Allocation Statement providing the basis for allocation of such costs, which
shall be duly audited and certified by the statutory auditors and submit such
audited and certified statement to the Commission along with the application
for determination of tariff.
4.2.3. The Generating Entity shall file the
application for determination of provisional tariff for new Generating Station,
one hundred and eighty (180) Days prior to the anticipated COD of Generating
Unit or Stage or Generating Station as a whole, as the case may be.
4.2.4. The Generating Entity shall make an
application for determination of tariff based on capital expenditure incurred
or projected to be incurred up to the COD and additional capital expenditure
incurred, duly certified by the statutory auditors.
Provided that the application shall contain details of
underlying assumptions for the projected capital cost and additional capital
cost, wherever applicable.
4.2.5. In the case of new Projects, the
Generating Entity may be allowed provisional tariff by the Commission from the
anticipated COD, based on the projected capital expenditure.
4.2.6. If the COD is delayed the provisional
tariff granted shall be applicable till the determination of tariff by the
Commission. The generating entity shall file for determination of tariff within
180 days from the date of COD.
4.2.7. The Generating Entity shall file the
application for determination of final tariff for new Generating Station within
one hundred and eighty Days (180) from the COD of Generating Unit or Stage or
Generating Station as a whole, as the case may be, based on the audited capital
expenditure and capitalisation as on the COD.
4.3. Determination of Tariff for Exist in
Generating Station
4.3.1. Where the Commission has, at any time
prior to April 1, 2019, approved a power purchase agreement or arrangement
between a Generating Entity and a Distribution Licensee or has adopted the
Tariff contained therein for supply of electricity from an existing generating
Unit/Station, then the Tariff for supply of electricity by such Generating
Entity to the Distribution Licensee shall be in accordance with the Tariff
mentioned in such power purchase agreement or arrangement for such period as so
approved or adopted by the Commission.
4.3.2. Where, as on April 1, 2019, the power
purchase agreement or arrangement between a Generating Entity and a
Distribution Licensee for supply of electricity from an existing Generating
Unit/Station or the tariff therein has not been approved by the Commission, or
where there is no power purchase agreement or arrangement, the supply of
electricity by such Generating Entity to the Distribution Licensee after April
1, 2019 shall be in accordance with a power purchase agreement approved by the
Commission.
Provided that the petition for approval of such power
purchase agreement or arrangement shall be filed by the Distribution Licensee
with the Commission within three months from the date of notification of these
Regulations:
Provided further that the supply of electricity shall be
allowed to continue under the present agreement or arrangement until such time
as the Commission approves such power purchase agreement, and shall be discontinued
forthwith if the Commission rejects it, for reasons to be recorded in writing.
4.4. Determination of Tariff for New
Generating Stations
The Tariff for the supply of electricity by a Generating
Entity to a Distribution Licensee from a New Generating Unit/Station shall be
in accordance with the Tariff determined in accordance with these Regulations.
4.5. Tariff Order
4.5.1. The Commission shall, within one
hundred and twenty (120) Days from receipt of a complete petition, and after
considering all suggestions and objections received from the public :
(a)
Issue a Tariff Order accepting the Petition
with such modifications or conditions as may be stipulated in that Order.
(b)
Reject the petition for reasons to be
recorded in writing if such petition is not in accordance with the provisions
of the Act and the rules and Regulations made thereunder or any other
provisions of law, after giving the Petitioner a reasonable opportunity of
being heard.
4.5.2. The Petitioner shall provide the
approved tariff schedule on its internet website, and make available for sale a
booklet containing such tariff to any person upon payment of reasonable
reproduction charges. The approved tariff shall also be published in at least
two English and two Telugu language daily newspapers having wide circulation in
the area of supply of the Distribution Licensee to whom the electricity is
proposed to be supplied in terms of the Tariff Order.
4.5.3. The Tariff so published shall be in
force from the date stipulated in the Order and shall, unless amended or
revised, continue to be in force for such period as may be stipulated therein.
4.6. Adherence to Tariff Order.
4.6.1. No tariff or part of any tariff may
ordinarily be amended more frequently than once in a Year, except in respect of
any changes expressly permitted under uncontrollable factors as specified in
clause 6.7 of this Regulation.
4.6.2. If any Generating Entity recovers a
price or charge exceeding the tariff determined under Section 62 of the Act and
in accordance with these Regulations, the excess amount shall be payable to the
person who has paid such price or charge, along with interest equivalent to the
Bank Rate as defined in this Regulations, without prejudice to any other
liability to which such Generating Entity may be subject to:
Provided that such interest payable to any party shall
not be allowed to be recovered through the Aggregate Revenue Requirement of the
Generating Entity.
Provided also that the Generating Entity shall maintain
separate details of such interest paid or payable by it, and shall submit them
to the Commission along with its Petition.
4.6.3. The Generating Entity shall submit
periodic returns as may be required by the Commission, containing operational
and cost data to enable it to monitor the implementation of its Order.
Regulation - 5. Date of Commercial Operation (COD ).
5.1. Date of Commercial Operation (COD T): he
date of commercial operation of a Generating Station or Unit or element thereof
shall be determined as detailed in clauses 5.2 & 5.3 below.
5.2. COD for Thermal Generating Station-COD
in case of a Generating Unit or Block of the Thermal Generating Station shall
mean, the date declared by the Generating Entity after demonstrating the
Maximum Continuous Rating (MCR) or the Installed Capacity (IC) through a
successful Trial Run after notice to the Beneficiaries, if any, and in case of
the Generating Station as a whole, the COD of the last Generating Unit or Block
of the Generating Station: Provided that:
5.2.1. Where the Beneficiaries have been tied
up for purchasing power from the Generating Station, the Trial Run shall
commence after seven Day notice by the Generating Entity to the Beneficiaries
and SLDC and scheduling shall commence from 00:00 hour after completion of the
Trial Run.
5.2.2. Where the Beneficiaries have not been
tied up for purchasing power from the Generating Station, the Trial Run or each
repeat of Trial Run shall commence after a notice of not less than seven Days
by the Generating Entity to the SLDC.
5.2.3. The Generating Entity shall certify to
the effect that:
(a)
The Generating Station meets the key
provisions of the technical standards of Central Electricity Authority
(Technical Standards for Construction of Electrical plants and electric lines)
Regulations, 2010 as amended from time to time and Grid Code as amended from
time to time.
(b)
The main plant equipment and auxiliary
systems including Balance of Plant, such as Fuel Oil System, Coal Handling
Plant, DM plant, pre-treatment plant, fire-fighting system, Ash Disposal system
and any other site specific system have been commissioned and are capable of
full load operation of the Units of the Generating Station on sustained basis.
(c)
Permanent electric supply system including
emergency supplies and all necessary instrumentation, control and protection
systems and auto loops for full load operation of unit have been put in
service.
5.2.4. Trial Run shall be in accordance with
clause 2.81 of these Regulations.
5.2.5. The certificate required in clause
5.2.3 above shall be signed by the Chief Executive Officer/Chief Managing
Director/Managing Director or the highest relevant authority of the Generating
Entity and a copy of the certificate shall be submitted to the Member
Secretary, (Southern Regional Power Committee) and SLDC before declaration of
COD. The Generating Entity shall submit to the Commission the approval of Board
of Directors to the certificates as required herein within a period of 3 months
of the COD.
5.2.6. Where on the basis of the Trial Run, a
Unit of the Generating Station fails to demonstrate the Unit capacity
corresponding to Maximum Continuous Rating or Installed Capacity or Name Plate
Rating, the Generating Entity has the option to de-rate the capacity or to go
for repeat Trial Run. Where the Generating Entity decides to de-rate the Unit
capacity, the demonstrated capacity in such cases shall be more or equal to
105% of de-rated capacity.
5.3. The SLDC shall convey clearance to the
Generating Entity for declaration of COD within 7 Days of receiving the
generation data based on the Trial Run as per the procedure laid down in the
Indian Electricity Grid Code 2010 and TSERC State Grid Code. Further, if the
SLDC notices any deficiencies in the Trial Run, it shall be communicated to the
Generating Entity within seven (7) Days of receiving the generation data based
on the Trial Run.
Provided that the communication system and data telemetry
system is put into service after completion of COD certification by SLDC
including test transfer of voice and data to respective control centre as
certified by the State Load Dispatch Centre.
5.4. Hydro
Generating Station :COD in case of a Generating Unit of a hydro Generating
Station, including Pumped Storage Hydro Generating Station, the date declared
by the Generating Station from 00:00 hour(s) after the scheduling process in
accordance with the Indian Electricity Grid ode 2010 and TSERC State Grid Code
is fully implemented, and in relation to the Generating Station as a whole, the
date declared by the Generating Entity after demonstrating peaking capability
corresponding to the Installed Capacity of the Generating Station through a
successful Trial Run and after obtaining clearance from the SLDC, and in
relation to the generating station as a whole, the COD of the last generating
Unit of the Generating Station:
Provided that:
5.4.1. where the Beneficiaries have been tied
up for purchasing power from the Generating Station, scheduling process for a
Generating Unit of the Generating Station or demonstration of peaking
capability corresponding to the Installed Capacity of the Generating Station through
a successful Trial Run or each repeat of Trial Run shall commence after at
least seven(7) Day notice by the Generating Entity to the Beneficiaries and
scheduling shall commence from 00:00 hours after completion of the Trial Run.
5.4.2. Where the Beneficiaries have not been
tied up for purchasing power from the Generating Station, the Trial Run shall
commence after a notice of not less than seven Days by the Generating Entity to
the SLDC.
5.4.3. the Generating Entity shall certify to
the effect that:
(a)
the Generating Station meets the key
provisions of the technical standards of Central Electricity Authority
(Technical Standards for Construction of Electrical plants and electric lines)
Regulations, 2010 as amended from time to time and Grid Code as amended from
time to time.
(b)
The main plant equipment and auxiliary
systems including Drainage Dewatering system, Primary and Secondary cooling
system, LP and HP air compressor, Firefighting system, etc. have been
commissioned and are capable for full load operation of units on sustained
basis.
(c)
Permanent electric supply system including
emergency supplies and all necessary Instrumentations Control and Protection
Systems and auto loops for full load operation of the unit are put into
service.
(i)
The certificate required in clause 5.4.3
above shall be signed by the Chief Executive Officer/Chief Managing
Director/Managing Director or the highest relevant authority of the Generating
Entity and a copy of the certificate shall be submitted to the Member
Secretary, (Southern Regional Power Committee) and SLDC before declaration of
COD. The Generating Entity shall submit to the Commission the approval of Board
of Directors to the certificates as required herein within a period of 3 months
of the COD.
(ii)
Trial Run shall be in accordance with clause
2.81 of this Regulation.
(iii)
in case a hydro Generating Station with
pondage or storage is not able to demonstrate peaking capability corresponding
to the Installed Capacity for the reasons of insufficient reservoir or pond
level, the COD of the last Unit of the Generating Station shall be considered
as the COD of the Generating Station as a whole, and it will be mandatory for
such hydro Generating Station to demonstrate peaking capability equivalent to
Installed Capacity of the Generating Unit or the Generating Station as and when
such reservoir/pond level is achieved.
(iv)
If a run-of-river hydro Generating Station or
a Generating Unit thereof is declared under commercial operation during lean
inflows period when the water inflow is insufficient for such demonstration of
peaking capability, it shall be mandatory for such hydro Generating Station or
Generating Unit to demonstrate peaking capability equivalent to Installed
Capacity as and when sufficient water inflow is available. In case of failure
to demonstrate the peaking capacity, the Unit capacity shall be de-rated to the
capacity demonstrated with effect from the COD.
(v)
Where on the basis of the Trial Run, a unit
of the generating station fails to demonstrate the unit capacity corresponding
to Maximum Continuous Rating or Installed Capacity or Name Plate Rating, the
generating company shall have the option to either de-rate the capacity or to
go for repeat Trial Run. If the generating company decides to de-rate the unit
capacity, the demonstrated capacity in such cases shall be more or equal to
110% of de-rated capacity.
(vi)
The SLDC shall convey clearance to the
Generating Entity for declaration of COD within 7 Days of receiving the
generation data based on the Trial Run. Further, if the SLDC notices any
deficiencies in the Trial Run, it shall be communicated to the Generating
Entity within seven (7) Days of receiving the generation data based on the
Trial Run.
Provided that the communication system and data telemetry
system is put into service after completion of COD certification by SLDC
including test transfer of voice and data to respective control center as
certified by the State Load Dispatch C entre.
Regulation - 6. Financial Principles Framework.
6.1. The Generating Entity shall manage its
finances in an optimum and prudent manner.
6.2. In determining the Aggregate Revenue
Requirement and tariff of the Generating Entity, the Commission shall assess
the financial prudence exercised with regard to the following factors:
6.2.1. revenue ;
6.2.2. revenue expenditure;
6.2.3. capital expenditure;
Provided that the Commission may disallow a part of the
Aggregate Revenue Requirement, as efficiency measure, if it finds the exercise
of such prudence to have been deficient.
6.3. The financial prudence with respect to
revenue shall be assessed in terms of the following parameters
6.3.1. Billing efficiency measured as a
percentage of the units billed by the Generating Entity to the total units
injected into the transmission system.
6.3.2. Collection efficiency measured as a
percentage of the amount collected by the Generating Entity to the total amount
billed.
6.3.3. Reduction in arrears receivable from
Beneficiaries.
6.3.4. Whether revenue collected is in line
with the projections made in the Petition and approved by the Commission.
6.4. The financial prudence with respect to
revenue expenditure shall be assessed in terms of the following parameters :
6.4.1. Monitoring of the revenue expenditure
as against the revenue earned, such that the expenses and payment obligations
of the Generating Entity to other entities are met in a timely manner.
6.4.2. Mechanism put in place for monitoring
adherence to the approved revenue expenditure, including schedule of interest
payments for long-term loans and working capital.
Provided that, in case the excess of revenue expenditure
over the revenue earned exceeds 5%, the Generating Entity shall submit detailed
justification for the mismatch along with its Petition for true-up, including a
comparison of the revenue expenditure and revenue estimated in the petition
with the amounts approved by the Commission and with the actual amount of
revenue expenditure and revenue, under key heads:
Provided further that the Generating Entity shall submit
a detailed cash flow statement for the respective business showing the various
sources of revenue, the actual amount of cash collected against the amount
billed, the comparison of the actual revenue expenditure and capital
expenditure with the projected and approved revenue expenditure and capital
expenditure.
Provided also that, in case its payment obligations to
other entities are not regularly met, the Generating Entity shall provide
justification for such shortfall with reference to its cash flow statement.
6.5. The financial prudence with respect to
capital expenditure shall be assessed in terms of the following parameters:
6.5.1. Mechanism put in place for monitoring
the physical progress of Projects with respect to their original schedule.
6.5.2. Optimum drawal of loans in accordance
with the physical progress of the capital expenditure schemes, and efficient
utilisation of such loans.
6.5.3. In case, the excess of actual capital
expenditure or capitalisation exceeds 10% of that approved by the Commission,
the Generating Entity shall submit detailed justification for such excess along
with its petition for true-up.
6.5.4. In case any Project has not been
commenced during the Year despite the Commission's approval, detailed
justification shall be submitted along with the petition for true-up.
6.6. Uncontrollable factors
The "uncontrollable factors" shall comprise the
following factors, which were beyond the control of, and could not be mitigated
by the Petitioner, as determined by the Commission:
6.6.1. Force Majeure events
6.6.2. Change in law
6.6.3. Variation in fuel cost on account of
variation in price of primary and/or secondary fuel prices
6.6.4. Variation in market interest rates for
long-term loan
6.6.5. Variation in freight rates
6.6.6. Non-Tariff Income
6.7. Controllable factors Variations or
expected variations in the performance of the Petitioner, which may be
attributed by the Commission to controllable factors include, but are not
limited to the following:
6.7.1. Variations in capitalisation on
account of time or cost overruns or inefficiencies in the implementation of a
capital expenditure scheme not attributable to an approved change in its scope,
change in statutory levies or Force Majeure Events;
6.7.2. Variation in interest and finance
charges, return on equity, and depreciation on account of variation in
capitalisation as specified in clause 6.8.1 above;
6.7.3. Variation in performance parameters,
such as Availability, Auxiliary Consumption, Secondary fuel oil consumption,
Gross Station Heat Rate.
6.7.4. Variation in amount of interest on
working capital;
6.7.5. Variation in Operation And Maintenance
Expenses;
6.7.6. Variation in coal transit losses.
6.8. Mechanism for pass-through of gains or
losses on account of uncontrollable factor s
6.8.1 The uncontrollable cost shall be
determined based on a petition filed by the concerned Generating Entity.
6.8.2 The aggregate gain or loss to a
Generating Entity on account of variation in cost of fuel from the sources
considered in the Tariff Order, including blending ratio of coal procured from
different sources, shall be passed through as an adjustment in its energy
charges on a monthly basis, as specified in clause 21.6 of this Regulation.
6.8.3 The consequential impact of decisions
of higher Courts or Tribunals or Review Orders passed by the Commission on the
Generating Entity
(a)
for the first and second Years of the Control
Period shall be addressed in the Mid-term Review Order
(b)
for the third, fourth or fifth Years of the
Control Period shall be addressed in the End of Control Period Review Order
6.9 Mechanism for sharing of gains or losses
on account of controllable factors
6.9.1 The approved aggregate gain to the
Generating Entity on account of controllable factors shall be dealt with in the
following manner:
(a)
Two-third (2/3rd) of the amount of such gain
shall be passed on as a rebate in tariff over such period as may be stipulated
in the Order of the Commission.
(b)
The balance amount of such gain shall be
retained by the Generating Entity.
6.9.2 The approved aggregate loss to the
Generating Entity on account of controllable factors shall be dealt with in the
following manner:
(a)
One-third (1/3rd) of the amount of such loss
may be passed on as an additional charge in tariff over such period as may be
stipulated in the Order of the Commission.
(b)
The balance amount of such loss shall be
absorbed by the Generating Entity.
Regulation - 7. Business Plan and Capital investment plan.
(a)
Business Plan
7.1. The Applicant shall file a business plan
along with capital investment plan for its Generation Business on or before 1st
April of the Year preceding the first Year of the Control Period for a duration
covering at least the entire Control Period.
7.2. The business plan shall cover details
such as Generation Planning and forecasts, Capex Investment Plan, future
performance targets, proposed efficiency improvement measures, Compliance
status of Environmental norms, Saving in operating costs. The Business Plan
shall also include, financial statements such as balance sheet, profit and loss
statement and cash flow statement for the Control Period duration, any other
new measures to be initiated for the Generation Business, e.g. automation, IT
initiatives etc.
(b)
Capital Investment Plan
7.3. The Capital Investment Plan submitted
along with Business Plan shall include the details of purpose of investment,
broad technical specifications of the proposed investment and supporting
details. It shall also include capital structure, capitalization schedule with
milestones for completion, financing plan with sources of investment, physical
targets, Cost-benefit analysis, prioritization of proposed investments etc.
7.4. The capital investment plan during the
Control Period shall be commensurate with the requirement of existing capacity.
7.5. In case, the Commission approves lesser
amount of capital expenditure than filed by the Applicant for approval, the
Commission may allow the respective Applicant to determine the priority of
schemes to be considered within the approved amount.
7.6. The capital investment plan for
Renovation and Modernization shall be submitted with all information/data for
approval of the Commission with a Detailed Project Report (DPR) elaborating the
following elements:
(i)
Complete scope and justification;
(ii)
Estimated life extension of the asset;
(iii)
Improvement in performance parameters;
(iv)
Cost-benefit analysis;
(v)
Phasing of expenditure;
(vi)
Schedule of completion with milestones;
(vii)
Reference price level;
(viii)
Estimated completion cost;
(ix)
Other relevant aspects.
7.7. In the normal course, the Commission
shall not revisit the approved capital investment plan during the Control
Period. However, during the Mid-Term Review, the Commission shall monitor the
Year-wise progress of the actual capital expenditure incurred by the Applicant
vis-a-vis the approved capital expenditure.
Provided that the actual capital expenditure incurred
shall be only as per the approved capital investment plan.
7.8. In case the capital expenditure is
required for emergency work which has not been approved in the capital investment
plan, the respective Applicant shall submit an application (containing all
relevant information along with reasons justifying emergency nature of the
proposed work) seeking approval by the Commission. The Applicant shall take up
the work prior to the approval of the Commission provided that the emergency
nature of the scheme has been approved by its Board of Directors:
Provided that the Applicant shall submit the pending
details required as per clause 7.1 within 10 Days of the submission of the application
for emergency work.
Provided that for the purpose of this clause, such
approved capital expenditure shall be treated as a part of actual capital
expenditure incurred by the Applicant as well as the approved capital
expenditure by the Commission.
7.9. The Commission shall approve the capital
investment plan within 90 Days from the date of its filing or submission of
complete information, whichever is earlier, after considering all suggestions
and objections of all stakeholders.
(C) Computation of Capital Cost
7.10. The capital cost admitted by the
Commission after Prudence Check shall form the basis for determination of
tariff.
Provided that Prudence Check may include scrutiny of the
reasonableness of the capital expenditure, financing plan including the choice
and manner of funding, interest during construction, use of efficient
technology, cost over-run and time over-run, and such other matters as may be
considered appropriate by the Commission for determination of tariff.
7.11. Capital cost for a capital investment
Project shall include:
7.11.1. The expenditure incurred or projected
to be incurred up to the date of commercial operation of the project as
admitted by the Commission after Prudence Check.
7.11.2. Interest during construction and
financing charges, on the loans (i) being equal to 70% of the funds deployed,
in the event of the actual equity in excess of 30% of the funds deployed, by
treating the excess equity as normative loan, or (ii) being equal to the actual
amount of loan in the event of the actual equity less than 30% of the funds
deployed.
7.11.3. The interest during construction and
financing charges, on the loans as admitted by the Commission after Prudence
Check in accordance with clause 7.21 & 7.22 of this Regulation.
7.11.4. Capitalised initial spares subject to
the ceiling rates specified in clause 7.12 this Regulation.
7.11.5. Additional capitalisation determined
under this Regulation clause 7.14
7.11.6. Any gain or loss on account of
foreign exchange rate variation pertaining to the loan amount availed up to
COD, as admitted by the Commission after Prudence Check.
7.11.7. Adjustment of revenue on account of
sale of Infirm Power by Generating Station in excess of fuel cost prior to the
COD as specified under this Regulation at clause 8 of this Regulation.
7.11.8. Increase in cost in contract packages
subject to Prudence Check and approved by the Commission.
Provided that in case the actual capital cost is lower
than the approved capital cost, the actual capital cost, subject to Prudence
Check and in accordance with the conditions and methodology specified herein
for the capital cost of New Generating Unit/Station, shall be considered for
determination of tariff of the Generating Entity
Provided that any gain or loss on account of foreign
exchange rate variation pertaining to the loan amount availed up to COD shall
be adjusted only against the debt component of the capital cost:
Provided further that the capital cost of the assets
forming part of the Project but not put to use or not in use, shall be excluded
from the capital cost:
Provided also that the Generating Entity shall submit
documentary evidence in support of its claim of assets being put to use:
Provided also that any capital expenditure incurred based
on the specific requirement of a Generating Entity shall be substantiated with
necessary documentary evidence of such request and undertaking received.
7.12. The actual capital expenditure as on
COD for the Original Scope of Work based on audited accounts of the Generating
Entity or Project, as the case may be, shall be considered subject to Prudence
Check by the Commission.
7.13. Truing up of the capital cost for the
new Generating Station shall be done by the Commission based on Prudence Check
of the audited capital expenditure and capitalisation as on COD.
7.14. Where the actual capital cost incurred
on Year to Year basis is lesser than the capital cost approved for
determination of tariff by the Commission on the basis of the projected capital
cost as on the COD or on the basis of the projected additional capital cost, by
five percent (5%) or more, the Generating Entity shall refund to the
Beneficiaries as approved by the Commission, the excess tariff realized
corresponding to excess capital cost, along with interest at 1.20 times of the
Bank Rate plus 250 basis points, as prevalent on the first Day of April of the
respective Financial Year.
7.15. Where the actual capital cost incurred
on Year to Year basis is higher than the capital cost approved for
determination of tariff by the Commission on the basis of the projected capital
cost as on the COD or on the basis of the projected additional capital cost, by
five (5%) percent or more, the Generating Entity shall, subject to the approval
of the Commission, be entitled to recover from the Beneficiaries the shortfall
in tariff corresponding to such decrease in capital cost along with interest at
0.80 times of the Bank Rate plus 150 basis points, as prevalent on the first
Day of April of the respective Financial Year.
7.16. In relation to multi-purpose
hydroelectric Projects, with irrigation, flood control and power components,
the capital cost chargeable to the power component of the Project only shall be
considered for determination of tariff.
7.17. The capital cost may include initial
spares capitalised as a percentage of the plant and machinery cost up to the
Cut-Off Date, subject to the following ceiling norms :-
Coal
based Generating Stations |
4.0% |
Gas
turbine/combined cycle Generating Stations |
4.0% |
Hydro
Generating Stations, including Pumped Storage Hydro Generating Stations |
4.0% |
Provided that:
7.17.1. Where the benchmark norms for initial
spares have been published as part of the benchmark norms for capital cost by
the CERC Regulations, such norms shall apply to the exclusion of the norms
specified above.
7.17.2. Where the Generating Station has any
transmission equipment forming part of the Project, the ceiling norms for
initial spares for such equipment shall be as per the ceiling norms specified
for transmission system under CERC Regulations.
7.17.3. For the purpose of computing the cost
of initial spares, plant and machinery cost shall be considered as Project cost
as on Cut-Off Date excluding IDC, IEDC, Land Cost and cost of civil works.
7.18. The impact of revaluation of assets
shall be permitted provided it does not result in increase in tariff of the
Generating Entity.
Provided that any benefit from such revaluation shall be
passed on to persons who share the capacity charge in case of a Generating
Entity at the time of Multi Year Tariff determination or Mid-term Review or End
of the Control Period Review, as the case may be.
7.19. Additional Capitalisation
7.19.1. The capital expenditure actually
incurred or projected to be incurred, on the following counts within the
Original Scope Of Work, after the COD and up to the Cut-Off Date, may be
admitted by the Commission subject to Prudence Check. Any additional
capitalization after COD needs prior approval of the Commission:-
(a)
Un-discharged liabilities recognised to be
payable at a future date;
(b)
Works deferred for execution;
(c)
Procurement of initial capital spares within
the Original Scope of Work in accordance with clause 7.12 of these Regulations;
(d)
Liabilities to meet award of arbitration or
for compliance of the order or decree of a court of law;
(e)
Change in law or compliance of any existing
law;
(f)
Any expenses to be incurred on account of
need for higher security and safety of the Station/Unit as advised or directed
by appropriate Government Agencies of statutory authorities responsible for
national security/internal security;
(g)
Deferred works relating to ash pond or ash
handling system and coal handling in the Original Scope of Work
(h)
Any capital expenditure found justified after
Prudence Check necessitated on account of modifications required or done in
fuel receiving system arising due to non-materialisation of coal supply
corresponding to full coal linkage in respect of Thermal Generating Station as
result of circumstances not within the control of the Generating Station.
(i)
Any liability for works executed prior to the
Cut-Off Date, after Prudence Check of the details of such un-discharged
liability, total estimated cost of package, reasons for such withholding of
payment and release of such payments, etc.
Provided that in case of such liabilities, the details
and relevant Board of Director approvals shall be submitted along with the
Petition for determination of final Tariff after the COD of the Generating
Unit/Station.
(j)
Any liability for works admitted by the
Commission after the Cut-Off Date to the extent of discharge of such
liabilities by actual payments.
(k)
Any additional capital expenditure which has
become necessary for efficient operation.
Provided that the claim shall be substantiated with the
technical justification duly supported by documentary evidence like test
results carried out by an independent agency in case of deterioration of
assets, damage caused by natural calamities, obsolescence of technology, up-
gradation of capacity for the technical reason such as increase in fault level.
(l)
An additional capital expenditure for
complying with statutory norms for Environment in accordance with the
appropriate notifications of Ministry of Environment, Forest and Climate
Change.
Provided that, the Generating Company shall approach to
the Commission for change in operational parameters such as change in normative
Auxiliary Consumption on account of technology changes in the Generating Plant
for e.g. installation of Flue Gas Desulfurization (FGD).
(m)
In case of hydro Generating Stations, any
expenditure, which has become necessary on account of damage caused by natural
calamities (but not due to flooding of power house attributable to the
negligence of the Generating Entity) and due to geological reasons after
adjusting the proceeds from any insurance scheme, and expenditure incurred due
to any additional work which has become necessary for successful and efficient
plant operation.
7.19.2. The details of works included in the
Original Scope of Work along with estimates of expenditure, liabilities
recognized to be payable at a future date and the works deferred for execution
shall be submitted along with the petition for determination of final tariff
after COD of the Generating Unit/Station.
7.19.3. Any expenditure, which has been
claimed under renovation and modernisation (clause 7.16 of this Regulation) or
repairs and maintenance under O&M expenses (clause 19 of these Regulation),
shall not be claimed under this clause.
7.19.4. Impact of additional capitalisation
on tariff, if any, shall be considered during Mid-term Review or tariff
determination for the next Control Period as the case may be.
7.19.5. Any expenditure on miscellaneous
items/assets like normal tools and tackles, personal computers, furniture, air-
conditioners, voltage stabilizers, refrigerators, fans, coolers, TV, washing
machines, heat-convectors, carpets, mattresses etc. brought after the Cut-Off
Date shall not be considered for additional capitalisation for determination of
tariff. The said items are illustrated and may include any other similar items.
7.20. De-Capitalisation
7.20.1. In case of De-Capitalisation of
asset, the original cost of such asset shall be deducted from the value of
gross fixed assets (GFA), on and from the date when that asset has been removed
from GFA block and corresponding loan as well as equity shall be deducted from
outstanding loan and the equity respectively in the year of De-Capitalisation.
7.20.2. Loss or Gain due to De-Capitalisation
of asset based on the directions of the Commission due to technological
obsolescence, wear & tear, etc. or due to change in law or force majeure,
which cannot be re-used, shall be adjusted in the ARR of the Generation Entity
in the relevant Year.
7.20.3. Loss or Gain due to De-Capitalisation
of asset proposed by the Generation Entity itself for the reasons not covered
under clause 6.7 of this Regulation shall be to the account of the Generation
Entity.
7.20.4. Loss or Gain due to De-Capitalisation
of asset after the completion of Useful Life of asset shall be to the account
of the Generation Entity.
7.20.5. Principles for treatment of capital
asset which has been removed from GFA before completion of its Useful Life with
prior approval of the Commission and such removed asset is held in reserve for
a continuous period of more than six months for its reuse later shall be as
follows:
(a)
In case the asset has been depreciated more
than 70% of its book value, depreciation shall not be allowed on such asset
from the date of De-Capitalisation to the date such asset is put to re-use;
(b)
In case the asset has been depreciated less
than 70% of its book value, depreciation shall be allowed up to 70% of the
total value of asset from the date of De-Capitalisation to the date such asset
is put to re-use;
(c)
In case such asset has been put to re-use,
differential of maximum permissible depreciation, as per CERC Regulations, and
actual accumulated depreciation, shall be allowed from the date such asset is
put to re-use;
(d)
The Generating Entity shall be allowed return
on equity, interest on loan on the written down value of the decapitalised
asset from the date such asset is put to re-use.
7.21. Renovation and Modernisation for Life
Extension
7.21.1. The Generating Entity shall file a
petition towards the fag end (5 years before) of the Useful Life before the
Commission for approval of the proposal with a Detailed Project Report (DPR)
detailing the complete scope, justification, cost-benefit analysis, estimated
life extension from a reference date, financial package, phasing of
expenditure, schedule of completion, reference price level, estimated
completion cost including foreign exchange component, if any, and any other
information considered to be relevant by the Generating Entity for meeting the
expenditure on renovation and modernisation (R&M) for the purpose of
extension of life beyond the originally recognised Useful Life as specified in
CERC Regulations.
7.21.2. The Commission may grant approval for
additional capital cost on account of R&M after due consideration of
reasonableness of the cost estimates, financing plan, schedule of completion,
interest during construction, use of efficient technology, cost-benefit
analysis, and such other factors as may be considered relevant by the
Commission. Provided that any expenditure included in the R&M on
consumables and cost of components and spares which is generally covered in the
O&M expenses shall be suitably deducted after due Prudence Check from the
R&M expenditure to be allowed.
7.21.3. Any expenditure on replacement,
renovation and modernisation or extension of life of old fixed assets, as
applicable to Generating Entities, shall be considered after writing off the
net value of such replaced assets from the original capital cost, and shall be
computed as follows:-Net Value of Replaced Assets = OCRA - AD Where, OCRA:
Original Cost of Replaced Assets AD: Accumulated depreciation pertaining to
replaced assets
Provided that, in case the original capital cost of the
replaced asset is not available for any reason, it shall be considered by the
Commission on a case-to-case basis.
Provided further that the amount of insurance proceeds
received, if any, towards damage to any asset requiring its replacement shall
be first adjusted towards outstanding actual or normative loan ; and the
balance amount, if any, shall be utilised to reduce the capital cost of such
replaced asset, and any further balance amount shall be considered as
Non-Tariff Income.
7.21.4. In case of gas/liquid fuel based
open/combined cycle Thermal Generating Station, any expenditure which has
become necessary for renovation of gas turbines/steam turbine after twenty five
(25) years of operation from its COD and an expenditure necessary due to
obsolesce or non-availability of spares for efficient operation of the Stations
shall be allowed.
Provided that any expenditure included in the R&M on
consumables and cost of components and spares which is generally covered in the
O&M expenses during the major overhaul of gas turbine shall be suitably
deducted after due prudence from the R&M expenditure to be allowed.
7.21.5. Any expenditure incurred or projected
to be incurred and admitted by the Commission after Prudence Check based on the
estimates of R&M expenditure and life extension, and after deducting the
accumulated depreciation already recovered from the Original Project Cost,
shall form the basis for determination of tariff.
7.22. Interest During Construction (Idc)
7.22.1. Interest during construction shall be
computed corresponding to the loan as specified in from the date of infusion of
debt fund, and after taking into account the utilisation of funds up to SCOD.
7.22.2. In case of additional costs on
account of IDC due to delay in achieving the SCOD, the Generating Entity, shall
be required to furnish detailed justifications with supporting documents for
such delay including prudent phasing of funds.
7.22.3. IDC shall be allowed during the delay
period only on payment basis and not accrual basis.
7.22.4. The Commission shall be guided by the
following principles for the purpose of determining cost due to time over run:
(a)
The entire cost due to time over run has to
be borne by the Generating Entity in case the causes for over-run are entirely
attributable to the Generating Entity. For example imprudence in selecting the
contractors/suppliers and in executing contractual agreements including terms
and conditions of the contracts, delay in award of contracts, delay in
providing inputs like making land available to the contractors, delay in
payments to contractors/suppliers as per the terms of contract, mismanagement
of finances, slackness in project management like improper coordination between
the various contractors, etc.,
(b)
The Commission shall examine on a case to
case basis of the additional cost incurred due to time over-run on account of
factors beyond the control of the Generating Entity e.g., delay caused due to
Force Majeure like natural calamity. The Generating Entity shall clearly
establish, beyond any doubt that there has been no imprudence on the part of
the Generating Entity in executing the Project.
Provided that the consumers should get full benefit of
the Liquidated Damages (LDs) recovered from the contractors/suppliers of the
Generating Entity and the insurance proceeds, if any, to reduce the capital
cost.
Provided that in case of natural calamities, the Generating
Entity shall provide a certificate of the event and the delay duration (in
Days) due to such calamity within 3 months of the occurring of such calamity.
7.23. Incidental Expenditure During
Construction (Ied C)
7.23.1. Incidental expenditure during construction
shall be computed from the Zero Date and after taking into account the
following:
(a)
Pre-operative expenses and additional
expenditure when IDC is admissible necessary to be incurred upto COD as set out
herein;
(b)
Adjustment for any revenue earned during
construction period up to COD on account of interest on deposits or advances;
(c)
Adjustment for any other receipts during
construction.
7.23.2. In case of additional costs on
account of IEDC due to delay in achieving the COD, the Generating Entity shall
be required to furnish detailed justification with supporting documents
including necessary Board of Directors approvals for such delay including the
details of incidental expenditure during the period of delay and liquidated
damages, if any, recovered or recoverable corresponding to the delay.
7.23.3. Any additional cost on account of
IEDC due to delay in achieving the COD shall be examined by the Commission on
case to case basis.
7.23.4. In case the time over-run beyond
scheduled COD is not admissible after due prudence check, the increase of
capital cost on account of cost variation corresponding to the period of time
over-run shall be excluded from capitalisation irrespective of price variation
provisions in the contracts with supplier or contractor of the Generating
Entity.
7.23.5. No additional impact of time over-run
or cost over-run shall be admissible on account of non-commissioning of the
Generating Station by scheduled COD, as the same should be recovered through
Implementation Agreement.
7.23.6. Initial spares shall be capitalised
as a percentage of the plant and machinery cost up to Cut-off Date, subject to
the norms specified at clause 7.12 of this Regulation.
Regulation - 8. Sale of Infirm Power.
Treatment to the inform power shall be in accordance with
the provisions of the TSERC (Deviation Settlement Mechanism and Related
Matters) Regulations as and when specified by the Commission.
Provided that any revenue earned by the Generating Entity
from supply of Infirm Power after accounting for the fuel expenses shall be
adjusted towards reduction in the capital cost based on provisional claims
made.
Provided also that the start-up power drawn by the
Generating Station from the Grid shall be adjusted with ex-bus energy and such
energy shall be billed to its Beneficiaries in the proportion of contracted
capacities.
Regulation - 9. Debt Equity Ratio.
9.1. For determination of Tariff, the
debt-equity ratio for any Project under commercial operation shall be
considered as 70:30 of the amount of capital cost approved by the Commission
under clause 7 of this Regulation, after Prudence Check for determination of
Tariff: Provided that:
9.1.1. Where equity actually deployed is less
than 30% of the capital cost of the capitalised assets, actual equity shall be
considered for determination of Tariff.
9.1.2. Where equity actually deployed is more
than 30% of the capital cost, equity in excess of 30% shall be treated as
notional loan of the Generating Entity.
Provided further that the Generating Entity shall submit
documentary evidence for the actual deployment of equity and explain the source
of funds for the equity.
9.1.3. The equity invested in foreign
currency shall be designated in Indian rupees using the closing exchange rate
at the date of each investment.
9.1.4. Any grant/contribution/deposit
obtained for the execution of the Project shall not be considered as a part of
capital structure for the purpose of debt: equity ratio.
9.2. The premium, if any, raised by the
Generating Entity while issuing share capital and investment of internal
resources created out of its free reserves, shall be reckoned as paid up
capital for the purpose of computing return on equity, provided such premium
amount and internal resources are actually utilised for meeting the capital
expenditure of the Generating Entity, and are within the ceiling of 30% of
capital cost approved by the Commission.
9.3. The debt and equity amount arrived at in
accordance with clause 9.1 above shall be used for calculating interest on
loan, return on equity, and foreign exchange rate variation.
9.4. The Generating Entity shall submit the
audited statement regarding reconciliation of equity required and actually
deployed to meet the capital expenditure of the Project with documentary
evidence approved by relevant authority:
Provided that the reconciliation statement shall indicate
the movement of equity with details of return on equity,
incentive/disincentive, additional equity infused, distribution of dividend,
normative loan etc.
9.5. In case of the Generating Station
declared under commercial operation prior to 1 April, 2019, debt equity ratio
allowed by the Commission for determination of tariff for the period ending 31
March, 2019 shall be considered.
9.6. In case of the Generating Station
declared under commercial operation prior to 1 April, 2019, but where debt:
equity ratio has not been determined by the Commission for determination of
tariff for the period ending 31 March, 2019, the Commission shall approve the
debt-equity ratio based on actual information provided by the Generating
Entity.
9.7. Any expenditure incurred or projected to
be incurred on or after 1 April, 2019 as may be admitted by the Commission as
additional capital expenditure for determination of tariff, and renovation and
modernisation expenditure for life extension shall be serviced in the manner
specified in clause 9.1 of this Regulation.
Regulation - 10. Depreciation.
10.1. Depreciation shall be computed from the
COD of a Generating Station or Unit thereof. In case of the Tariff of all the
Units of a Generating Station for which a single Tariff needs to be determined,
the depreciation shall be computed from the effective COD of the Generating
Station taking into consideration the depreciation of individual Units or
elements thereof.
Provided that effective COD shall be worked out by
considering the actual COD and installed capacity of all the Units of the
Generating Station for which single tariff needs to be determined.
10.2. The value base for the purpose of
depreciation shall be the capital cost of the asset admitted by the Commission.
In case of multiple Units of a Generating Station, weighted average life for
the Generating Station shall be applied. Depreciation shall be chargeable from
the first Year of commercial operation.
10.3. In case of commercial operation of the
asset is for part of the Year, depreciation shall be charged on pro-rata basis.
Provided that, where the Generating Entity does not
furnish sufficient information to compute depreciation on pro-rata basis,
depreciation shall be allowed at the discretion of the Commission.
10.4. Salvage value The salvage value of the
asset shall be considered as 10% and depreciation shall be allowed up to
maximum of 90% of the capital cost of the asset:
Provided that in case of hydro Generating Station, if the
salvage value provided in the agreement signed by the developers with the State
Government for development of the Plant is less than 10%, same shall be
considered:
Provided also that any depreciation disallowed on account
of lower availability of the Generating Station or Generating Unit, shall not
be allowed to be recovered at a later stage during the Useful Life and the
Extended Life.
10.5. Land: Land other than the land held
under lease and the land for reservoir in case of hydro Generating Station
shall not be a depreciable asset and its cost shall be excluded from the
capital cost while computing depreciable value of the asset:
Provided further that the depreciable value of land under
lease shall be the aggregate of lease payments as per the lease agreement.
10.6. Depreciation shall be calculated
annually, based on Straight Line Method and at rates specified in CERC (Terms
and conditions of Tariff) Regulations, 2014, as amended from time to time for
the assets of the Generating Entity.
Provided that the remaining depreciable value as on 31st
March of the Year closing after a period of twelve (12) Years from the
effective COD of the Station shall be spread over the balance Useful Life of
the assets or Extended Useful Life, as provided in this Regulation.
Provided further that in case of repayment of entire loan
is earlier than the period of twelve (12) Years from the effective COD, the
remaining depreciable value as on 31st March of the Year of repayment, shall be
spread over the balance Useful Life of the assets or Extended Useful Life, as
provided in this Regulation.
10.7. In case of the Existing Projects, the
balance depreciable value as on 1 April, 2019 shall be worked out by deducting
the cumulative depreciation as admitted by the Commission up to 31 March, 2019
from the gross depreciable value of the assets.
10.8. The Generating Entity shall submit the details
of proposed capital expenditure during the fag end of the Project (five years
before the end of Useful Life) along with justification and proposed life
extension.
10.9. Depreciation in case of plants that
have been renovated and modernised:
10.9.1. For the existing assets depreciation
shall be allowed on the net asset value over the revised Useful Life of the
plant.
10.9.2. For new assets that have been
installed as part of modernisation and renovation, depreciation shall be
allowed equally over the Extended Life.
10.10. In case of De-Capitalisation of assets
in respect of Generating Entity or Unit there of or any element thereof, the
cumulative depreciation shall be adjusted by taking into account the
depreciation recovered in tariff by the de-capitalised asset during its useful
services.
Depreciation shall be re-computed for assets capitalised
at the time of Truing-up along with the Mid-term Review or at the End of the
Control Period, based on documentary evidence of assets capitalised by the
Petitioner, subject to the Prudence Check of the Commission, such that the
depreciation is allowed proportionately from the date of capitalisation.
Regulation - 11. Return on equity (RoE).
11.1. Return on equity shall be computed in
rupee terms, on the equity base determined in accordance with clause 9 of this
Regulation (Debt equity ratio clause).
11.2. RoE shall be computed at the following
base rates:
11.2.1. Thermal Generating Stations: 15.50%
11.2.2. Run of the river hydro Generating
Station : 15.50%
11.2.3. Storage Type hydro Generating
Stations including Pumped Storage Hydro Generating Stations and Run-of-River
Generating Station with pondage : 16.50%:
11.2.4. Provided that:
(a)
the rate of return of a new Project shall be
reduced by 1% for such period as may be decided by the Commission, if the
Generating Station is found to be declared under commercial operation without
commissioning of any of the Restricted Governor Mode Operation (RGMO)/Free
Governor Mode Operation (FGMO), data telemetry, communication system up to load
dispatch centre or protection system:
(b)
as and when any of the above requirements in
clause 11.2.4 are found lacking in a Generating Station based on the report
submitted by the SLDC, RoE shall be reduced by 1% for the period for which the
deficiency continues:
(c)
The base rates as specified above or as per
Central Electricity Regulatory Commission (Terms and Conditions of Tariff)
Regulations, 2014, including amendments thereto or any superseding Regulations,
whichever is lower shall be used for the computation of RoE.
11.3. Tax on return on equity
11.3.1. The base rate of RoE as allowed by
the Commission under clause 11.2 shall be grossed up with the effective tax
rate of the respective Financial Year.
11.3.2. The effective tax rate shall be
considered on the basis of actual tax paid in the respect of the Financial Year
in line with the provisions of the relevant Finance Acts by the concerned
Generating Entity, as the case may be.
11.3.3. The actual tax income on other income
stream (i.e., income of non-Generation Business) shall not be considered for
the calculation of "effective tax rate".
11.3.4. Rate of return on equity shall be
rounded off to three decimal places and shall be computed as per the formula
given below Rate of pre-tax return on equity = Base rate/(1-t)
Where "t" is the effective tax rate in
accordance with Clause 11.3.1 of this Regulation and shall be calculated at the
beginning of every Financial Year based on the estimated profit and tax to be
paid estimated in line with the provisions of the relevant Finance Act
applicable for that financial Year to the generating entity on pro-rata basis
by excluding the income of non-generation and the corresponding tax thereon.
11.3.5. In case of Generating Entity paying
Minimum Alternate Tax (MAT), "t" shall be considered as MAT rate
including surcharge and cess.
11.3.6. Illustration: -
(a)
In case of the Generating Entity paying
Minimum Alternate Tax (MAT)
@ 20.96% including surcharge and cess:
Rate of return on equity = 15.50/(1-0.2096) = 19.610%
(b)
In case of Generating Entity paying normal
corporate tax including surcharge and cess:
Estimated Gross Income from generation business for FY
2014-15 is Rs. 1,000 Crores.
Estimated Advance Tax for the year on above is Rs. 240
Crores.
Effective Tax Rate for the year 2014-15 = Rs. 240
Crores/Rs. 1,000 Crores = 24%
Rate of return on equity = 15.50/(1-0.24) = 20.395%
11.4. The Generating Entity, shall true up
the grossed up rate of RoE at the end of every Financial Year based on actual
tax paid together with any additional tax demand including interest thereon,
duly adjusted for any refund of tax including interest received from the income
tax authorities pertaining to the tariff MYT period on actual gross income of
any Financial Year. However, penalty, if any, arising on account of delay in
deposit or short deposit of tax amount shall not be claimed by the Generating
Entity. Any under-recovery or over-recovery of grossed up rate on RoE after
truing up, shall be recovered or refunded to Beneficiaries or the long term
transmission customers/DICs as the case may be on Year to Year basis.
Regulation - 12. Interest and finance charges on loan.
12.1. The amount of loans arrived in the
manner as indicated in clause 9 of this Regulation reduced by the corresponding
loan amount of decapitalised asset shall be considered as gross loan for
calculation of interest on loan.
12.2. The loan outstanding as on 1st April of
the respective Year shall be worked out by deducting the cumulative repayment
as admitted by the Commission from the gross loan.
12.3. The repayment for each of the Year of
the Control Period shall be deemed to be equal to the depreciation allowed for
the corresponding Year/period. In case of De-Capitalisation of assets, the
repayment shall be adjusted by taking into account cumulative repayment on a
pro rata basis and the adjustment should not exceed cumulative depreciation
recovered up to the date of De-Capitalisation of such asset.
12.4. The repayment of loan shall be
considered from the first Year of commercial operation of the Project
irrespective of any moratorium period availed by the Generating Entity.
12.5. The rate of interest on loan shall be
based on weighted average rate of interest for actual loan portfolio subject to
the interest rate specified in these Regulations as on the date of filing.
Provided that in no case the rate of interest on loan
shall exceed approved rate of RoE.
Provided further that if there is no actual loan for a
particular Year but normative loan is still outstanding, the last available
weighted average rate of interest shall be considered:
Provided also that if the Generating Entity does not have
actual loan then the rate of interest shall be considered at the interest rate
as specified in these Regulations as on the date of filing, for the notional
loan of the relevant Control Period:
Provided that if such rate on notional loan changes by
more than MCLR during the Control Period and such change subsists for more than
3 continuous quarters in a Year, then the same shall be effected on the
notional loan and adjusted during true-up at the time of Mid-term Review and
End of Control Period Review.
Provided also that the loan availed through open
tendering process (Competitive Bidding) among Scheduled Banks, Financial
Institutions etc., shall be considered at the rate discovered through open
tendering process but limited to interest rate specified in these Regulations.
12.6. Refinancing:
12.6.1. The Generating Entity shall make
every effort to re-finance the loan as long as it results in net savings on
interest and in that event the costs associated with such refinancing shall be
borne by the beneficiaries and the net savings shall be shared between the
Beneficiaries and the Generating Entity in the ratio of 2:1 respectively
subject to Prudence Check by the Commission.
12.6.2. The Generating Entity shall submit
documentary evidence of the costs associated with such re-financing.
12.6.3. The changes to the terms and
conditions of the loans shall be reflected from date of such re-financing.
12.6.4. In case of dispute, any of the
parties may make an application in accordance with TSERC (Conduct of business)
Regulations, 2015 as amended from time to time, including statutory reenactment
thereof for settlement of dispute:
Provided that the Beneficiaries shall not withhold any
payment on account of the interest claimed by the Generating Entity during the
pendency of any dispute arising out of the re-financing of loan.
Regulation - 13. Interest on working capital.
The Commission shall calculate the Working Capital
requirement as follows:
Coal-based
generating station |
|
(a) |
Cost
of coal and lime stone towards stock, if applicable, Lower of : A.
maximum coal stock storage capacity [OR] B.
for generation corresponding to the target availability Pit
head Generating Station - 15 Days coal cost Non
- pit head Generating Station - 30 Days coal cost |
(b)
Cost of coal and limestone for 30 Days of generation corresponding to the
target availability; |
|
(c) |
Cost
of secondary fuel oil for two months of generation corresponding to target
availability; |
(d)
Maintenance spares @ 20% of the O&M expenses specified in clause 19 |
|
(e)
O&M expenses for one (01) month as specified in clause 19 of this
Regulation |
|
(f) |
Receivables
equivalent to two months of capacity charges and energy charges for sale of
electricity calculated on target availability |
(g) |
Minus Payables
for fuel (including oil and secondary fuel oil) to the extent of thirty Days
of the cost of fuel computed at target availability, depending on the
modalities of payment |
Provided that for the purpose of Truing-up, the working
capital shall be computed based on the scheduled generation or target
availability whichever is lower:
Provided further that for the purpose of Truing-up for any
Year, the working capital requirement shall be re-computed on the basis of the
values of components of working capital approved by the Commission in the
Truing-Up before sharing of gains and losses;
Open-cycle
Gas Turbine/Combined Cycle Thermal Generating Stations |
|
(a) |
Fuel
Cost for 30 Days corresponding to the target availability, duly taking into
account mode of operation of the Generating Station on gas fuel and liquid
fuel |
(b) |
Liquid
fuel stock for 15 Days corresponding to the target availability, and in case
of use of more than one liquid fuel, cost of main liquid fuel duly taking
into account mode of operation of the Generating Stations of gas fuel and
liquid fuel |
(c) |
Maintenance
spares @ 30% of Operation And maintenance Expenses specified in clause 19
these Regulations |
(d)
O&M expenses for one month as specified in clause 19 of these Regulations |
|
(e) |
Receivables
equivalent to two months of capacity charge and energy charge for sale of
electricity calculated on target availability, duly taking into account mode
of operation of the Generating Station on gas fuel and liquid fuel |
(f) |
Minus Payables
for fuel (including liquid fuel stock) to the extent of thirty Days of the
cost of fuel computed at target availability, depending on the modalities of
payment: |
Provided that for the purpose of Truing-up, the working
capital shall be computed based on the actual generation or target availability
whichever is lower:
Provided further that for the purpose of Truing-up for
any Year, the working capital requirement shall be re-computed on the basis of
the values of components of working capital approved by the Commission in the
Truing-Up before sharing of gains and losses
Hydro
Generating Station including pumped storahydro-electric Generating Station |
||
(a) |
Maintenance
spares @ 15% of Operation And Maintenance Expenses
specified in Regulation 29 |
|
(b) |
O&M
expenses for one month as specified in these Regulations |
|
(c) |
Receivables
equivalent to two months fixed cost |
|
Provided that for the purpose of Truing-up for any Year,
the working capital requirement shall be re-computed on the basis of the values
of components of working capital approved by the Commission in the Truing-up
before sharing of gains and losses;
13.2. The cost of fuel in cases covered above
shall be based on the landed cost incurred (taking into account normative
transit and handling losses) by the Generating Entity and Gross Calorific Value
of the fuel as per actual for the three months preceding the first month for
which tariff is to be determined and no fuel price escalation shall be provided
during the tariff period.
13.3. Rate of interest on working capital
shall be on normative basis and shall be considered as the Bank Rate plus 150
basis points as on filing date or as on 1st April of the financial Year during
the MYT period in which the Generating Station or Unit thereof is declared
under commercial operation, whichever is later.
Provided that for the purpose of Truing-up for any year,
interest on working capital shall be allowed at a rate equal to the weighted
average Bank Rate prevailing during the concerned Year plus 150 basis points
13.4. Rate of interest on working capital
shall be on normative basis notwithstanding that the Generating Entity has not
taken loan for working capital from any outside agency.
Regulation - 14. Rebates and Delayed Payment Charge.
(a)
Delayed Payment Charges
14.1 In case the payment of bills of
generation Tariff and charges by the Beneficiary is delayed beyond a period of
60 Days from the date of billing, a delayed payment charge at the rate of 1.25%
per month on the billed amount shall be levied for the period of delay by the
Generating Entity, notwithstanding anything to the contrary as may have been
stipulated in the agreement or arrangement with the Beneficiaries.
14.2 Such delayed payment charge and interest
on delayed payment earned by the Generating Entity shall not be considered
under its Non-Tariff Income
(b)
Rebate:14.3 For payment of bills of
generation Tariff and charges within 7 Days of presentation of bills, through
Letter of Credit or through NEFT/RTGS, a rebate of 2% on billed amount,
excluding taxes, cess, duties etc., shall be allowed.
Regulation - 15. Components of Tariff.
15.1 The tariff for sale of electricity from
a thermal Power Generating Station shall comprise of two parts, namely,
15.1.1 The Annual Fixed Charges and
15.1.2 Energy Charges (for recovery of
primary and secondary fuel cost)
15.2 The tariff for sale of electricity from
a Hydro Generating Station shall comprise of two parts, namely, the Capacity
Charge and Energy Charge
15.3 Annual Fixed Charges :
The annual fixed charges shall comprise the following
elements:
15.3.1 Depreciation;
15.3.2 Interest and finance charges on loan;
15.3.3 Interest on Working Capital;
15.3.4 Operation & Maintenance Expenses;
15.3.5 Return on Equity;
Minus
15.3.6 Non-Tariff Income:
Provided that Depreciation, Interest and finance charges
on loan, interest on working capital and Return on Equity for Thermal and Hydro
Generating Stations shall be allowed in accordance with the provisions
specified in these Regulations.
Regulation - 16. Non- Tariff Income & Other Business income.
(a)
Non- Tariff Income
The Generating Entity shall submit forecast of Non-Tariff
Income to the Commission, in such form as may be stipulated by the Commission
from time to time, whose tentative list is as follows:
Income from rent of land or buildings;
Net Income from sale of de-capitalised assets;
Net Income from sale of scrap;
Income from statutory investments;
Interest on advances to suppliers/contractors;
Rental from staff quarters;
Rental from contractors;
Income from investment of consumer security deposit;
Income from hire charges from contactors and others, etc.
Income from the sale of ash/rejected coal The amount of Non-Tariff/other income
relating to the Generation Business as approved by the Commission shall be
deducted from the Annual Fixed Cost in determining the Annual Fixed Charge of
the Generating Entity:
Provided that the Generating Entity shall submit full
details of its forecast of Non-Tariff Income to the Commission in such form as
may be stipulated by the Commission from time to time. Non-Tariff Income shall
also be trued-up based on audited accounts.
(b)
Other Business Income
The net income after tax from Other Business shall be
adjusted in the ARR.
The Generating Entity shall follow segment wise reporting
of Other Business in the audited financial statement and a reasonable basis for
allocation of all joint and common costs between the Licensed Business and the
Other Business and shall submit the Allocation Statement as approved by the
Board of Directors/competent authority to the Commission along with the
application for determination of tariff:
Provided that loss on account of Other Business shall not
be considered in the ARR of the Licensee.
Regulation - 17. Norms of operation for Thermal Generating Stations.
17.1 Recovery of capacity charge, energy
charge, and incentive by the Generating Entity shall be based on the
achievement of the operational norms specified by the Commission.
17.2 Norms of operation for existing
Generating Stations shall be as follows:
Thermal |
|
KTPS
ABC KTPS O&M |
/KTPS
-Stage V |
KTPS
Stage VI |
|
Normative
Annual Plant Availability Factor (Target Availability) |
% |
70.00% |
80.00% |
80.00% |
|
Gross
Station Heat Rate |
kcal/kWh |
3,000 |
2,500 |
2,450 |
|
Secondary
fuel oil consumption |
ml/kWh |
2.00 |
2.00 |
2.00 |
|
Auxiliary
Energy Consumption |
% |
10.00% |
9.00% |
7.50% |
|
Transit
and Handling Losses |
% |
0.80% |
0.80% |
0.80% |
|
Thermal |
|
RTSB |
KTPP-Stage
- I |
KTPP-Stage
- II |
|
Normative
Annual Plant Availability Factor (Target Availability) |
% |
75.00% |
80.00% |
80.00% |
|
Gross
Station Heat Rate |
kcal/kWh |
3,000 |
2,450 |
2,400 |
|
Secondary
fuel oil consumption |
ml/kWh |
2.00 |
2.00 |
2.0 |
|
Auxiliary
Energy Consumption |
% |
10.00% |
7.50% |
7.00% |
|
Transit
and Handling Losses |
% |
0.80% |
0.80% |
0.80% |
Provided that, i. Target Availability for full recovery
of Annual Fixed Charges shall be 85 % for all thermal Generating Stations,
except those covered under Regulation 17.2.
ii. Full Capacity Charges shall be recoverable at
Normative Annual Plant Availability Factor (NAPAF) specified above of these
Regulations. Recovery of Capacity Charges below the level of Normative Annual
Plant Availability Factor (NAPAF) will be on a pro-rata basis. At zero
availability, no Capacity Charges shall be payable.
iii. The Availability certified by SLDC shall also
include Backing Down of the Generating Stations for the purpose of recovery of
capacity charges.
iv. The Normative Annual Plant Load Factor (NAPLF) for
incentive will be the same as the Normative Annual Plant Availability Factor
(NAPAF)
17.3 Norms of operation for new Generating
Stations commissioned during or after the Financial Year 2015 other than those
covered in 17.2 above, shall be as follows:
17.3.1 Normative Annual Plant Availability
Factor (Target Availability): 85%
17.3.2 Normative Annual Plant Load Factor
(NAPLF) for incentive: 85%
17.4 Gross Station Heat Rate
(a)
Coal-based Thermal Generating Station s =
1.045 X Design Heat Rate (kCal/kWh) Where the design heat rate of a Generating
Unit means the Unit heat rate guaranteed by the supplier at conditions of 100%
MCR, zero percent make up, design coal and design cooling water
temperature/back pressure.
Provided that the design heat rate shall not exceed the
following maximum design unit heat rates depending upon the pressure and
temperature ratings of the Units:
MW |
200
to 300 |
>300
&<500 |
>500
&<600 |
>
600 |
Pressure
Rating (Kg/cm2) |
150 |
170 |
170 |
247 |
SHT/RHT
(0C) |
535/535 |
537/537 |
537/565 |
565/593 |
Type
of BFP |
Electrical
Driven |
Turbine
Driven |
Turbine
Driven |
Turbine
Driven |
Max
Turbine Heat Rate (kCal/kWh) |
1,955 |
1,950 |
1,935 |
1,850 |
Min.
BoilerE fficiency |
||||
Sub-Bituminous
Indian Coal |
0.86 |
0.86 |
0.86 |
0.86 |
Bituminous
Imported Coal |
0.89 |
0.89 |
0.89 |
0.89 |
Max
Design Unit Heat Rate (kCal/kW h) |
||||
Sub-Bituminous
Indian Coal |
2,273 |
2,267 |
2,250 |
2,151 |
Bituminous
Imported Coal |
2,197 |
2,191 |
2,174 |
2,078 |
Provided further that in case pressure and temperature
parameters of a Unit are different from above ratings, the maximum design Unit
heat rate of the nearest class shall be taken:
Provided also that where unit heat rate has not been
guaranteed but turbine cycle heat rate and boiler efficiency are guaranteed
separately by the same supplier or different suppliers, the unit design heat
rate shall be arrived at by using guaranteed turbine cycle heat rate and boiler
efficiency.
Provided also that where the boiler efficiency is below
86% for Sub-bituminous Indian coal and 89% for bituminous imported coal, the
same shall be considered as 86% and 89% respectively for Sub-bituminous Indian
coal and bituminous imported coal for computation of station heat rate.
Provided also that maximum turbine cycle heat rate shall
be adjusted for type of dry cooling system.
Provided also that for Generating Stations based on coal
rejects, the Commission will approve the Design Heat Rate on case to case
basis. Note: In respect of Generating Units where the boiler feed pumps are
electrically operated, the maximum design unit heat rate shall be 40 kCal/kWh
lower than the maximum design unit heat rate specified above with turbine
driven BFP.
(b)
Gas-based/Liquid-based thermal Generating
Unit(s)/Block (s= ) 1.05 X Design Heat Rate of the unit/block for Natural Gas
and RLNG (kCal/kWh) = 1.071 X Design Heat Rate of the Unit/Block for Liquid
Fuel (kCal/kWh) Where the Design Heat Rate of a Unit shall mean the guaranteed
heat rate for a Unit at 100% MCR and at site ambient conditions; and the Design
Heat Rate of a block shall mean the guaranteed heat rate for a block at 100%
MCR, site ambient conditions, zero percent make up, design cooling water
temperature/back pressure:
17.5 Secondary fuel oil consumption
Coal-based
generating stations |
0.50
ml/kWh |
17.6 Auxiliary Energy Consumption
(a)
Coal Based Generating Stations
|
With
natural draft cooling tower or without cooling tower |
200
MW series |
8.50% |
300/330/350/500
MW and above series Steam driven boiler feed pumps |
5.25% |
Electrically
driven boiler feed pumps |
7.75% |
Provided further that for thermal generating stations
with induced draft cooling towers, the norms shall be further increased by
0.5%:
Provided also that Additional Auxiliary Energy
Consumption as follows may be allowed for plants with Dry Cooling Systems:
Type
of Dry Cooling System |
(%
of gross generation) |
Direct
cooling air cooled condensers with mechanical draft fans |
1% |
Indirect
cooling system employing jet condensers with pressure recovery turbine and
natural draft tower |
0.5% |
(b)
Gas Turbine/Combined Cycle generating
stations
Combined
Cycle |
2.5% |
Open
Cycle |
1.0% |
17.7 Transit and handling losses:
Transit and handling losses for coal based Generating
Stations, as a percentage of quantity of coal dispatched by the coal supply
company during the month shall be as given below:
17.7.1 Pit head Generating Stations: 0.20%;
17.7.2 Non-pit head Generating Stations:
0.80%;
Provided that in case of Pit Head stations if coal is
procured from sources other than the Pit Head mines which is transported to the
station through rail, transit loss of 0.80% shall be applicable.
Provided further that in case of imported coal, the
transit and handling losses shall be 0.20%, subject to terms of delivery.
17.8 In case a Thermal Generating Station or
Unit is directed by SLDC to operate below normative loading but at or above
technical minimum schedule on account of grid security or due to the lower
schedule given by the Beneficiaries, increase in Gross Station Heat Rate or
penalties imposed by Bureau of Energy Efficiency (BEE) for being non-compliant
arised due to generation backing down/partial loading operation if any or any
such charges incurred by Generating Station or Unit on account of operational
instructions issued by SLDC for grid security purpose, may be considered by the
Commission on case to case basis at time of truing up, subject to prudence
check.
Regulation - 18. Norms of operation for hydro Generating Stations.
18.1. Recovery of capacity charge, energy
charge, and incentive by the Generating Entity shall be based on the
achievement of the operational norms specified by the Commission.
18.2. Normative capacity index for recovery
of annual Capacity charges
|
First
Year of commissioning of the Generating Station |
After
first Year of commissioning of the Generating Station |
Purely
Run-of-river power stations |
85% |
90% |
Storage
type and Run-of- river power stations with pondage |
80% |
85% |
Note: There shall be pro rata recovery of annual Capacity
Charges in case the Generating Station achieves capacity index below the
prescribed normative levels. At Zero capacity index, no fixed charges shall be
payable to the Generating Station.
18.3. Auxiliary Energy Consumption
(a)
Surface hydro-electric power Generating
Stations with rotating exciters mounted on the generator shaft - 0.2% of energy
generated.
(b)
Surface hydroelectric power Generating
Stations with static excitation system - 0.5% of energy generated
(c)
Underground hydroelectric power Generating
Stations with rotating exciters mounted on the generator shaft - 0.4% of energy
generated
(d)
Underground hydroelectric power generating stations
with static excitation system - 0.7% of energy generated
18.4. Transformation losses
From generation voltage to transmission voltage: 0.5% of
energy generated.
Regulation - 19. Operating & maintenance expenses (O&M ).
19.1. The O&M expenses for each year of
the Control Period shall be approved based on the formula shown below
O&Mn = (R&Mn + EMPn+ A&Gn) x 99%
Where,
R&Mn - Repair and Maintenance Costs of the Applicant
for the nth year; EMPn - Employee Cost of the Applicant for the nth year;
A&Gn - Administrative and General Costs of the Applicant for the nth year;
The above components shall be computed in the manner specified in this clause:
19.2. Employee Cost (EMPn)
Employee cost shall be computed as per the approved norm
escalated by CPI, adjusted by provisions for expenses beyond the control of the
Generating Entity and one time expected expenses, such as recovery/adjustment
of Terminal Benefits, implications of pay commission, arrears and interim
relief, governed by the following formula
EMPn = (EMPb X CPI inflation) + Provision
Where:
EMPn: Employee expense for the Year "n"
EMPb: Employee expense as per the preceding Year.
For the first year of Control Period, expense shall be
the average of the trued-up employee expenses after adding/deducting the share
of efficiency gains/losses, for the immediately preceding Control Period,
excluding abnormal, if any, subject to Prudence Check by the Commission.
CPI inflation is the point to point change in the
Consumer Price Index for Industrial Workers (all India) as per Labour Bureau,
Government of India, as reduced by an efficiency factor of 1% for immediately
preceding Year.
CPI index source for one-month lag: Ministry of
Statistics - GOI provided that in case CPI inflation is a negative number, the
escalation/change shall be 0%.
Provision refers to provision for expenses beyond control
of the Generating Entity and expected one-time expenses as specified above.
19.3. Repairs and Maintenance
Expens(R&Mn)
The expense shall be calculated as percentage (as per the
norm defined) of Opening Gross Fixed Assets for the Year governed by following
formula:
R&Mn = Kn X GFAn X WPI inflation
Where:
R&Mn: Repairs & Maintenance expense for nth Year
GFAn: Opening Gross Fixed Assets for nth Year
Kn: 'K' is the immediate preceding Control Period average
(expressed in %) governing the relationship between R&M and Gross Fixed
Assets (GFA).
WPI inflation: point to point change in Wholesale Price
Index (WPI) for immediately preceding Year.
Provided that in case WPI inflation is a negative number,
the escalation/change shall be 0%. Source for WPI - As published by Office of
Economic Adviser - GOI
19.4. Administrative & General Expense
(A&Gn)
A&G expense shall be computed as per the norm
escalated by the inflation factor and adjusted by provisions for confirmed
initiatives (IT etc. initiatives as proposed by the Generating Entity and
validated by the Commission) or other expected one-time expenses, and shall be
governed by following formula:
A&Gn = (A&Gfo * Inflation Factor) Provision
Where:
A&Gn: A&G expense for the Year "n"
A&Gfo: For the first Year of the Control Period, it
shall be the average of the audited A&G expense of the immediately
preceding 3 Financial Years if available, and for subsequent Years it shall be
the preceding Year escalated by the inflation factor.
Inflation Factor: is the sum of the following
> point to point change in the Wholesale Price Index
(WPI) numbers as per Office of Economic Advisor of Government of India for
immediately preceding Year as reduced by an efficiency factor of 1 % multiplied
by 0.5
> point to point change in Consumer Price Index for
Industrial Workers (all India) as per Labour Bureau, Government of India in the
previous year, as reduced by an efficiency factor of 1% multiplied by 0.5
Provided that in case Inflation Factor is a negative
number, the escalation/change shall be 0%. Provision: Cost for initiatives or
other one-time expenses as proposed by the Generating Entity and validated by
the Commission.
19.5. Normative Operation and Maintenance
Expenses for the first Year of a new Generating Entity shall be as per the
norms approved by the CERC in Central Electricity Regulatory Commission (Terms
and Conditions of Tariff) Regulations, 2014 as amended from time to time, for
respective Year unless specifically approved by the Commission.
19.6. Any expenditure on account of license
fee, initial or renewal, fee for determination of tariff and audit fee shall be
allowed on actual basis, over and above the A&G expenses approved by the
Commission.
19.7. O&M expenses of assets taken on
lease/hire-purchase and those created out of the consumer's contribution shall
be considered in case the Generating Entity has the responsibility for its
operation and maintenance and bears O&M expenses.
19.8. With regard to unfunded past
liabilities of pension and gratuity, the Commission will follow the principle
of "pay as you go". The Commission shall not allow any other amount
towards creating fund for meeting unfunded past liability of pension and
gratuity.
19.9. O&M expenses for gross fixed assets
added during the Year, if not accounted already, shall be considered from the
COD on pro-rata basis.
19.10. The O&M expenses incurred by the
Generating Entity on the housing colonies and related expenses including
medical and other facilities, of its operating staff shall be recorded
separately and excluded from the above
19.11. actual O&M expenses are less than
90% of the normative expenses in respect of New generating stations :
Provided, if actual O&M expenses are less than 90% of
the normative expenses, the Commission shall true-up the O&M expenses
during the Mid-Term Review or End of Control Period Review as the case may be.
19.12. Terminal Liabilities such as
death-cum-retirement gratuity, pension, commuted pension, leave encashment,
LTC, medical reimbursement including fixed medical allowance in respect of
pensioners will be approved as per the actuals paid.
19.13. O&M expenses made on account of
extraordinary situations (if any) shall be submitted to Commission for its
approval. Such expenses shall be filed separately and will not be subjected to
provisions of this clause of the Regulation. The approved amount by the
Commission shall be trued up in the Mid-Term Review and End of Control Period
review, as applicable.
19.14. Any increase in employee cost on
account of pay revision etc. will be considered separately by the Commission.
19.15. Prior period expense
19.15.1. The Applicant shall submit to the
Commission the prior period expenses as a part of the filing for Mid-Term
Review and End of Control Period Review;
19.15.2. The Commission shall allow prior
period expenses for uncontrollable cost items only as per the audited accounts,
during such reviews.
Regulation - 20. Foreign Exchange Rate Variation.
20.1. The Applicant may hedge foreign
exchange exposure in respect of the interest on foreign currency loans and
repayment of foreign loans acquired for the Generating Station in part or full
at the discretion of the Applicant.
20.2. The Applicant shall recover the cost of
hedging of foreign exchange rate variation corresponding to the normative
foreign debt, in the relevant Year on Year-to-Year basis as expense in the
period in which it arises and extra rupee liability corresponding to such
foreign exchange rate variation shall not be allowed against the hedged foreign
debt.
20.3. To the extent the Applicant is not able
to hedge the foreign exchange exposure, the extra rupee liability towards
interest payment and loan repayment corresponding to the normative foreign
currency loan in the relevant Year shall be permissible provided it is not
attributable to the Applicant or its contractors.
20.4. The Applicant shall recover the cost of
hedging and foreign exchange rate variation on Year-to-Year basis as income or
expense in the period in which it arises.
Regulation - 21. Computation & Payment of Capacity Charges & Energy Charges for Thermal Generating Stations.
21.1. The fixed cost of a Thermal Generating
Station shall be computed on annual basis, based on norms specified under these
Regulations, and recovered on monthly basis under capacity charge. The total
capacity charge payable for a Generating Station shall be shared by its
Beneficiaries as per their respective percentage share/allocation in the
capacity of the Generating Station.
21.2. The capacity charge payable to a
Thermal Generating Station for a calendar month shall be calculated in
accordance with the following formulae
CC1= (AFC/12)( PAF1/NAPAF ) subject to ceiling of
(AFC/12)
CC2 = ((AFC/6)( PAF2/NAPAF ) subject to ceiling of
(AFC/6)) - CC1
CC3 = ((AFC/4)(PAF3/NAPAF) subject to ceiling of (AFC/4))
- (CC1+CC2)
CC4 = ((AFC/3) (PAF4/NAPAF) subject to ceiling of
(AFC/3)) -
(CC1+CC2+CC3)
CC5 = ((AFC x 5/12) (PAF5/NAPAF) subject to ceiling of
(AFC x 5/12)) -
(CC1+CC2+CC3+CC4) CC6 = ((AFC/2) (PAF6/NAPAF) subject to
ceiling of (AFC/2)) -
(CC1+CC2+CC3+CC4+CC5) CC7= ((AFC x 7/12) (PAF7/NAPAF)
subject to ceiling of (AFC x 7/12)) -
(CC1+CC2 +CC3 +CC4 + CC5 + CC6) CC8 = ((AFC x 2/3)
(PAF8/NAPAF) subject to ceiling of (AFC x 2/3)) -
(CC1+CC2 +CC3 +CC4 + CC5 + CC6 + CC7) CC9 = ((AFC x 3/4)
(PAF9/NAPAF) subject to ceiling of (AFC x 3/4)) -
(CC1+CC2 +CC3 +CC4 + CC5 + CC6 + CC7+ CC8) CC10= ((AFC x
5/6) (PAF10/NAPAF) subject to ceiling of (AFC x 5/6)) -
(CC1+CC2 +CC3 +CC4 + CC5 + CC6 + CC7 + CC8 + CC9) CC11 =
((AFC x 11/12) (PAF11/NAPAF) subject to ceiling of (AFC x 11/12)) -
(CC1+CC2+CC3 +CC4 + CC5 + CC6 + CC7 + CC8 + CC9 + CC10)
CC12 = ((AFC) (PAFy/NAPAF) subject to ceiling of (AFC)) - (CC1+CC2 +
CC3 +CC4 + CC5 + CC6 + CC7 + CC8 + CC9 + CC10 + CC11)
Provided that in case of Generating Station under
shutdown due to Renovation and Modernisation, the Generating Entity shall be
allowed to recover the O&M expenses and interest on loan only.
Where,
AFC Annual fixed cost specified for the year, in Rupees.
NAPAF = Normative annual Plant Availability Factor in
percentage. PAFn = Percent Plant Availability Factor achieved upto the end of
the nth month.
PAFY = Percent Plant Availability Factor achieved during
the Year CC1, CC2, CC3, CC4, CC5, CC6, CC7, CC8, CC9, CC10, CC11, and CC12 are
the Capacity Charges of 1st, 2nd, 3rd, 4th, 5th, 6th, 7th, 8th, 9th, 10th, 11th
and 12th months respectively
21.3. The PAFn up to the end of a particular
month and PAFY shall be computed in accordance with the following formula:
N PAFn or PAFY = 10000 x (Σ) DCi/{ N x IC x (
100 - AUX ) } %
i=1 Where,
AUX = Normative Auxiliary Energy Consumption in
percentage.
DCi= Average Declared Capacity (in ex-bus MW), for the
ith Day of the period
i.e. the month or the year as the case may be, as
certified by the concerned load dispatch centre after the Day is over.
IC = Installed Capacity (in MW) of the Generating Station
N= Number of Days during the period.
Note: DCi and IC shall exclude the capacity of Generating
Units not declared under commercial operation. In case of a change in IC during
the concerned period, its average value shall be taken
21.4. PLF Incentive to a Generating Station
shall be payable at the rate specified in CERC Regulations, 2014 as applicable
during control period.
21.5. The energy charge shall cover the
primary and secondary fuel cost and shall be payable by every Beneficiary for
the total energy scheduled to be supplied to such Beneficiary during the
calendar month on ex-power plant basis, at the energy charge rate of the month
with fuel and limestone price (wherever applicable) adjustment. Total Energy
charge payable to the Generating Entity for a month shall be:
(Energy charge rate in Rs./kWh) x {Scheduled energy
(ex-bus) for the month in kWh.}
21.6. Energy charge rate (ECR) in Rupees per
kWh on ex-power plant basis shall be determined to three decimal places in
accordance with the following formulae
21.6.1. For coal based stations
ECR = {(GSHR - SFC x CVSF) x LPPF/CVPF + SFC x LPSFi + LC
x LPL} x 100/(100 - AUX)
21.6.2. For gas and liquid fuel based
stations
ECR = GSHR x LPPF x 100/{CVPF x (100 - AUX)} Where,
AUX =Normative Auxiliary Energy Consumption in percentage
CVPF=
Weighted Average Gross calorific Value of coal as received,
in kCal per kg for coal based stations
Weighted Average Gross calorific Value of primary fuel as
fired, in kCal per kg, per litre or per standard cubic meter, as applicable for
gas and liquid fuel based stations.
In case of blending of fuel from different sources, the
weighted average Gross Calorific Value of primary fuel shall be arrived in
proportion to blending ratio.
CVSF =Calorific value of secondary fuel, in kCal per ml.
ECR = Energy charge rate, in Rupees per kWh sent out.
GSHR =Gross Station Heat Rate, in kCal per kWh.
LC = Normative limestone consumption in kg per kWh.
LPL = Weighted average landed price of limestone in
Rupees per kg.
LPPF =Weighted average landed price of primary fuel, in
Rupees per kg, per litre or per standard cubic meter, as applicable, during the
month. (In case of blending of fuel from different sources, the weighted
average landed price of primary fuel shall be arrived in proportion to blending
ratio) SFC = Normative Specific fuel oil consumption, in ml per kWh. LPSFi=Weighted
Average Landed Price of Secondary Fuel in Rs./ml during the month.
Provided that energy charge rate for a gas/liquid fuel
based station shall be adjusted for open cycle operation based on certification
of TSSLDC for the open cycle operation during the month.
21.7. The Generating Entity shall provide to
the Beneficiaries of the Generating Station the details of parameters of GCV
and price of fuel i.e., domestic coal, imported coal, e-auction coal, natural
gas, RLNG, liquid fuel etc., as per the forms prescribed at Annexure I of CERC
Regulations;
Provided that the details of blending ratio of the
imported coal with domestic coal, proportion of e-auction coal and the weighted
average GCV of the fuels as fired shall also be provided separately, along with
the bills of the respective month;
Provided further that the copies of the bills and details
of parameters of GCV and price of fuel i.e. domestic coal, imported coal,
e-auction coal, natural gas, RLNG, liquid fuel etc., details of blending ratio
of the imported coal with domestic coal, proportion of e-auction coal shall
also be displayed on the website of the Generating Entity. The details should
be available on its website on monthly basis for a period of three months
21.8. The landed cost of fuel for the month
shall include price of fuel corresponding to the grade and quality of fuel
inclusive of royalty, taxes and duties as applicable, transportation cost by
rail/road or any other means (all these parameters to be shown separately),
and, for the purpose of computation of energy charge, and in case of coal shall
be arrived at after considering normative transit and handling losses as
percentage of the quantity of coal dispatched by the coal supply company during
the month as notified by the Central Electricity Regulatory Commission, for
respective Year unless specifically approved by the Commission;
Provided that any refund of taxes and duties along with
any amount received on account of penalties from fuel supplier shall be
adjusted in the fuel cost
21.9. In case of part or full use of
alternative source of fuel supply by coal based Thermal Generating Stations
other than as agreed by the Generating Entity and Beneficiaries in their power
purchase agreement for supply of contracted power on account of shortage of
fuel or optimization of economical operation through blending, the use of
alternative source of fuel supply shall be permitted to Generating Station.
Provided that in such case, prior permission from
Beneficiaries shall not be a precondition, unless otherwise agreed specifically
in the power purchase agreement:
Provided further that the weighted average price of use
of alternative source of fuel shall not exceed 30% of base price of fuel,
however the Commission will make a prudent check in approving the price of
alternative fuel, considering the improved GCV and impact of energy rate on
account of increased price of alternative source of fuel Provided also that
where the energy charge rate based on weighted average price of use of fuel
including alternative source of fuel exceeds 30% of base energy charge rate as
approved by the Commission for that year or energy charge rate based on
weighted average price of use of fuel including alternative sources of fuel
exceeds 20% of energy charge rate based on weighted average fuel price for the
previous month, whichever is lower shall be considered and in that event, prior
consultation with Beneficiary shall be made not later than three Days in
advance
21.10. Any variation in fuel prices on
account of change in the Gross Calorific Value (GCV) of coal or gas or liquid
fuel shall be adjusted on a monthly basis on the basis of average GCV of coal
or gas or liquid fuel in stock, as fired and weighted average landed cost
incurred by the Generating Entity for procurement of coal, oil, or gas or
liquid fuel, as the case may be for a Station.
21.11. The Generating Entity shall separately
indicate rate of energy charges in its bills at base price of primary and
secondary fuel specified by the Commission.
Regulation - 22. Computation & Payment of Capacity Charges & Energy Charges for Hydro Generating Stations.
22.1. The fixed cost of a hydro Generating
Station shall be computed on annual basis, based on norms specified under these
Regulations, and shall be recovered one twelfth of Annual fixed charges on
every month which shall be payable by the Beneficiaries in proportion to their
respective allocation in the saleable capacity of the Generating Station.
Provided that during the period between COD of the first
unit of the Generating Station and the COD of the Generating Station, the
annual fixed cost shall provisionally be worked out based on the latest
estimate of the completion cost for the Generating Station, for the purpose of
determining the capacity charge and energy charge payment during such period.
22.2. The capacity charge payable to a hydro
Generating Station for a calendar year shall be:
Annual Capacity Charges = (Annual Fixed Charge - Primary
Energy Charge) Provided that the Primary Energy Charge shall not exceed the
Annual Fixed Charge and there shall be pro rata recovery of annual capacity
charges in case the Generating Station achieves capacity index below the
prescribed normative levels. At Zero capacity index, no capacity charges shall
be payable to the Generating Station.
22.3. Hydel stations Energy Charges
1.
Rate of primary energy for all hydro electric
power generating stations, except for pumped storage generating stations, shall
be equal to average of the lowest variable charges of the Central and State
thermal power generating stations of the State for all months of the previous
year. The primary energy charge shall be computed based on the primary energy
rate and scheduled primary energy of the station:
Provided that in case the primary energy charge
recoverable by applying the above primary energy rate exceeds the Annual fixed
charges of a generating station, the primary energy rate of such generating
station shall be calculated by' the following formula : Primary energy rate =
Annual fixed charge/Primary Energy
2.
Primary Energy Charge= Scheduled Primary
Energy x Primary Energy Rate. Secondary Energy Rate shall be equal to the
Primary Energy Rate. Secondary Energy Charge = Scheduled Secondary Energy x
Secondary Energy Rate
Note: i. Annual fixed charges shall be adjusted at
the end of the financial year
ii. Declared capacity of Hydel stations based on the
instructions of SLDC subjected to the water availability constraints.
Regulation - 23. Computation & Payment of Capacity Charges & Energy Charges for Pumped Hydro Generating Stations.
23.1 The fixed cost of a Pumped Storage Hydro
Generating Station shall be computed on annual basis, based on norms specified
under these regulations, and recovered on monthly basis as capacity charge. The
capacity charge shall be payable by the Beneficiaries in proportion to their
respective allocation in the saleable capacity of the Generating Station.
Provided that during the period between COD of the first
Unit of the Generating Station and the COD of the Generating Station, the
annual fixed cost shall be worked out based on the latest estimate of the
completion cost for the Generating Station, for the purpose of determining the
capacity charge payment during such period
23.2 The capacity charge payable to a Pumped
Storage Hydro Generating Station for a calendar month shall be:
If actual Generation during the month is >= 75 % of
the Pumping Energy consumed by the Station during the month (AFC x NDM/NDY) (in
Rupees) If actual Generation during the month is < 75 % of the Pumping
Energy consumed by the Station during the month.
{(AFC x NDM/NDY) x (Actual Generation during the month
during peak hours/75% of the Pumping Energy consumed by the station during the
month) (in Rupees)} Where,
AFC = Annual fixed cost specified for the year, in Rupees
NDM = Number of Days in the month NDY = Number of Days in the year
Provided that there would be adjustment at the end of the
year based on actual generation and actual pumping energy consumed by the
Station during the Year.
Provided further that, the above norms shall be
applicable to the dedicated Pumped Storage Hydro Generating Station only.
23.3 The energy charge shall be payable by
every Beneficiary for the total energy scheduled to be supplied to the
Beneficiary in excess of the Design Energy plus 75% of the energy utilised in
pumping the water from the lower elevation reservoir to the higher elevation
reservoir, at a flat rate equal to the average energy charge rate of 20 paise
per kWh, excluding free energy, if any, during the calendar month, on ex power
plant basis.
23.4 Energy charge payable to the Generating
Entity for a month shall be = 0.20 x {Scheduled energy (ex-bus) for the month
in kWh - (Design Energy for the month (DEm) + 75% of the energy utilized in
pumping the water from the lower elevation reservoir to the higher elevation
reservoir of the month)}
Where,
DEm = Design energy for the month specified for the hydro
Generating
Station, in MWh
Provided that in case the scheduled energy in a month is
less than the Design Energy for the month plus 75% of the energy utilized in
pumping the water from the lower elevation reservoir to the higher elevation
reservoir of the month, then the energy charges payable by the Beneficiaries
shall be zero.
23.5 The Generating Entity shall maintain the
record of daily inflows of natural water into the upper elevation reservoir and
the reservoir levels of upper elevation reservoir and lower elevation reservoir
on hourly basis. The Station shall be required to maximize the peak hour
supplies with the available water including the natural flow of water. In case
it is established that Generating Entity is deliberately or otherwise without
any valid reason, is not pumping water from lower elevation reservoir to the
higher elevation during off-peak period or not generating power to its
potential or wasting natural flow of water, the capacity charges of the Day
shall not be payable by the Beneficiary. For this purpose, outages of the
Unit(s)/Station including planned outages and the forced outages up to 15% in a
year shall be construed as the valid reason for not pumping water from lower
elevation reservoir to the higher elevation during off-peak period or not
generating power using energy of pumped water or natural flow of water:
Provided that the total capacity charges recovered during
the Year shall be adjusted on pro-rata basis in the following manner in the
event of total machine outages in a Year exceeds 15%:
(ACC) adj = (ACC) R x (100- ATO)/85
Where, (ACC) adj - Adjusted Annual Capacity Charges (ACC)
R - Annual
Capacity Charges recovered
ATO - Total Outages in percentage for the year including
forced and planned outages
Provided further that the Generating Station shall be
required to declare its machine availability daily on Day-ahead basis for all
the Time Blocks of the Day in line with the scheduling procedure of Grid Code;
23.6 The concerned Load Dispatch Centre shall
finalise the schedules for the hydro Generating Stations, in consultation with
the Beneficiaries, for optimal utilization of all the energy declared to be
available, which shall be scheduled for all Beneficiaries in proportion to
their respective allocations in the Generating Station.
Regulation - 24. Deviation Charges.
Variations between actual injection of Energy and
scheduled injection of Energy for the Generating Stations, and variations
between actual drawl of Energy and scheduled drawl of Energy for the
Beneficiaries shall be treated as their respective deviations and charges for
such deviations shall be governed by the deviation settlement mechanism
regulations as notified by the Commission.
Regulation - 25. Scheduling, Accounting and Billing.
25.1 Scheduling:
The methodology for scheduling and dispatch for the
Generating Station shall be as specified in the Grid Code and TSERC's
Regulations for Deviation Settlement Mechanism as and when notified by the
Commission.
25.2 Metering and Accounting :
The provisions of the Grid Code and TSERC's Regulations
for Deviation Settlement Mechanism as and when notified by the Commission shall
be applicable.
25.3 Billing and Payment of charges :
25.3.1 Bills shall be raised for capacity
charge, energy charge on monthly basis by the Generating Entity in accordance
with these Regulations, and payments shall be made by the Beneficiaries.
25.3.1 Payment of the capacity charge for a
Thermal Generating Station shall be shared by the Beneficiaries of the
Generating Station as per their percentage shares for the month (inclusive of
any allocation out of the unallocated capacity) in the Installed Capacity of
the Generating Station. Payment of capacity charge and energy charge for a
hydro Generating Station shall be shared by the Beneficiaries of the Generating
Station in proportion to their shares (inclusive of any allocation out of the
unallocated capacity) in the saleable capacity
25.4 Note 1: Shares/allocations of each
Beneficiary in the total capacity of Central sector Generating Stations shall
be as determined by the Central Government, inclusive of any allocation made
out of the unallocated capacity. The shares shall be applied in percentages of
Installed Capacity and shall normally remain constant during a month. Based on
the decision of the Central Government the changes in allocation shall be
communicated by the Member-Secretary, Regional Power Committee in advance, at
least three Days prior to beginning of a calendar month, except in case of an
emergency calling for an urgent change in allocations out of unallocated
capacity. The total capacity share of a Beneficiary would be sum of its
capacity share plus allocation out of the unallocated portion. In the absence
of any specific allocation of unallocated power by the Central Government, the
unallocated power shall be added to the allocated shares in the same proportion
as the allocated shares.
25.5 Note 2: The Beneficiaries may propose
surrendering part of their allocated firm share to other States within/outside
the region. In such cases, depending upon the technical feasibility of power
transfer and specific agreements reached by the Generating Entity with other
States within/outside the region for such transfers, the shares of the
beneficiaries may be prospectively re-allocated by the Central Government for a
specific period (in complete months) from the beginning of a calendar month.
When such re-allocations are made, the Beneficiaries who surrender the share
shall not be liable to pay capacity charges for the surrendered share. The
capacity charges for the capacity surrendered and reallocated as above shall be
paid by the State(s) to whom the surrendered capacity is allocated. Except for
the period of reallocation of capacity as above, the Beneficiaries of the
Generating Station shall continue to pay the full capacity charges as per
allocated capacity shares. Any such reallocation and its reversion shall be
communicated to all concerned by the Member Secretary, Regional Power Committee
in advance, at least three Days prior to such reallocation or reversion taking
effect.
Regulation - 26. Miscellaneous.
26.1 Dispute resolving mechanism
In the event of any dispute regarding interpretation of
any provision of the Terms and Conditions of Generation Tariff Regulations or
rules and procedures notified under the provisions of the Terms and Conditions
of Generation Tariff Regulations, the matter will be decided by the Commission
according to the Act.
Provided that for this purpose the aggrieved person shall
be entitled to file a proper petition before the Commission by following the
Conduct of Business Regulation, 2015 being regulation No. 2 of 2015 and Levy of
Fee for Rendering Services Rendered by the Commission Regulation, 2016 being
regulation No. 2 of 2016.
Provided that the Commission may initiate such suo moto
proceedings as may be necessary in the event of it having come to the
conclusion based on reports of the TSGENCO that action needs to be taken
against any of the stakeholders in terms of the Act, 2003 by exercising the
powers vested in it thereof and by invoking the Conduct of Business Regulation,
2015 being regulation No. 2 of 2015 and Levy of Fees for Rendering Services
Rendered by the Commission Regulation, 2016 being regulation No. 2 of 2016,
where such fee if required to be levied is to be decided at the end of the
proceeding as to who shall pay the same.
26.2 Issue of orders and practice directions
Subject to the provisions of the Act and this Regulation,
the Commission may, from time to time, issue orders and practice directions in
regard to the implementation of these Regulations and procedure to be followed
on various matters, which the Commission has been empowered by these
Regulations to direct, and matters incidental or ancillary thereto.
26.3 Powers to remove difficulties
If any difficulty arises in giving effect to the
provisions of this regulations, the Commission may, by general or specific
order, make such provisions not inconsistent with the provisions of the Act,
2003, as may appear to it to be necessary and expedient for removing such
difficulty duly following the procedure contemplated under the Act, 2003 and
regulations in vogue.
26.4 Power of relaxation
The Commission may in public interest and for reasons to
be recorded in writing, relax any of the provision of these Regulations.
26.5 Interpretation
If a question arises relating to the interpretation of
any provision of these Regulations, the decision of the Commission shall be
final.
26.6 Saving of inherent powers of the
Commission
1.
Anything done or any action taken or
purported to have been done or taken including any rule, notification,
inspection, order or notice made or issued or any appointment, confirmation or
declaration made or any licence, permission, authorization or exemption granted
or any document or instrument executed or any direction given under the
repealed regulation shall, insofar as it is not inconsistent with the
provisions of this regulation, be deemed to have been done or taken under the
corresponding provisions of this regulation shall be deemed to be not invalid
by virtue of such repeal.
2.
Nothing contained in these Regulations shall
limit or otherwise affect the inherent powers of the Commission from adopting a
procedure, which is at variance with any of the provisions of these
Regulations, if the Commission, in view of the special circumstances of the
matter or class of matters and for reasons to be recorded in writing, deems it
necessary or expedient to depart from the procedure specified in these
Regulations.
26.7 Enquiry and investigation
All enquiries, investigations and adjudications under
these regulations shall be done by the Commission through the proceedings in
accordance with the provisions of the Conduct of Business Regulations, 2015.
26.8 Power to amend
The Commission may, at any time, vary, alter, modify or
amend any provisions of this regulation.
Regulation - 27. Summary of timelines.
Description |
Filing
of the Document (on or before) |
Obtaining
additional information and acceptance by the Commission |
Approval
of the Document |
Capital
Investment Plan (to be filed only at the beginning of the Control Period) |
1st
April of the Year preceding the first Year of Control Period |
Within
45 Days of filing of document |
Within
90 Days of acceptance of the filing |
Business
Plan |
1st
April of the Year preceding the first Year of Control Period |
Within
45 Days of filing of document |
Within
90 Days of acceptance of the filing |
Filing
of MYT Petition (ARR and Tariff Proposal for the Control Period) |
1st
April 2019 |
Within
45 Days of filing of document |
Within
120 Days of acceptance of the filing |
Mid-Term
Review |
30th
November of the fourth Year of the Control Period |
Within
45 Days of filing of document |
Within
120 Days of acceptance of the filing |
End
of Control Period Review |
30th
November of the first Year of the subsequent Control Period |
Within
45 Days of filing of document |
Within
120 Days of acceptance of the filing |