Telangana
State Electricity Regulatory Commission Renewable Power Purchase Obligation
(Compliance By Purchase Of Renewable Energy/Renewable Energy Certificates)
Regulation, 2022
[04th
April 2022]
Preamble: Section 86(1)(e)
of the Electricity Act, 2003 provides for promotion of renewable sources of
energy including cogeneration by providing suitable measures for connecting
with the grid and sale of electricity to any person, as also specify the percentage
of total consumption to be purchased in the area of distribution licensees.
In order to achieve this
objective, the Commission had notified a Regulation setting forth the target
and other requirements in compliance of the above provisions the Regulation
being the Telangana State Electricity Regulatory Commission Renewable Power
Purchase Obligation (Compliance by Purchase of Renewable Energy/ Renewable
Energy Certificates) Regulation, 2018 (Regulation No.2 of 2018).
The above said Regulation
was subsisting for the period of four (4) years which shall end on 31.03.2022.
Therefore, framing of fresh Regulation is necessitated to take further steps in
the matter of providing mechanism as required under Section 86(1)(e) of the
Act, 2003.
In this regard, it may be
relevant to notice the relevant provisions of the Tariff Policy, 2016 as
notified by the Government of India exercising powers under Section 3 of the
Electricity Act, 2003.
"(1) Pursuant to
provisions of Section 86(1)(e) of the Act, the Appropriate Commission shall fix
a minimum percentage of the total consumption of electricity in the area of a
distribution licensee for purchase of energy from renewable energy sources,
taking into account availability of such resources and its impact on retail tariffs.
Cost of purchase of renewable energy shall be taken into account while
determining tariff by SERCs. Long term growth trajectory of Renewable Purchase
Obligations (RPOs) will be prescribed by the Ministry of Power in consultation
with MNRE. Provided that co-generation from sources other than renewable
sources shall not be excluded from the applicability of RPOs.
(1)
Within the percentage so made applicable, to
start with, the SERCs shall also reserve a minimum percentage for purchase of
solar energy from the date of notification of this policy which shall be such
that it reaches 8% of total consumption of energy, excluding Hydro Power, by
March 2022 or as notified by the Central Government from time to time.
(2)
Distribution Licensee(s) shall compulsorily
procure 100% power produced from all the Waste-to-Energy plants in the State,
in the ratio of their procurement of power from all sources including their
own, at the tariff determined by the Appropriate Commission under Section 62 of
the Act.
(3)
It is desirable that purchase of energy from
renewable sources of energy takes place more or less in the same proportion in
different States. To achieve this objective in the current scenario of large
availability of such resources only in certain parts of the country, an appropriate
mechanism such as Renewable Energy Certificate (REC) would need to be promoted.
Through such a mechanism, the renewable energy based generation companies can
sell the electricity to local distribution licensee at the rates for
conventional power and can recover the balance cost by selling certificates to
other distribution companies and obligated entities enabling the latter to meet
their renewable power purchase obligations. The REC mechanism should also have
a solar specific REC.
(4)
Appropriate Commission may also provide for a
suitable regulatory framework for encouraging such other emerging renewable
energy technologies by prescribing separate technology based REC multiplier
(i.e. granting higher or lower number of RECs to such emerging technologies for
the same level of generation). Similarly, considering the change in prices of
renewable energy technologies with passage of time, the Appropriate Commission
may prescribe vintage based REC multiplier (i.e., granting higher or lower
number of RECs for the same level of generation based on year of commissioning
of plant)."
Accordingly, in exercise of
powers conferred on it under Sections 61, 66, 86(1)(e) and 181 of the
Electricity Act, 2003 (Central Act No.36 of 2003) and all other powers enabling
it in this behalf, and after previous publication, the Telangana State
Electricity Regulatory Commission hereby makes the following Regulation for
prescribing the obligation for purchase of Renewable Power and its compliance
by purchase of Renewable Energy/Renewable Energy Certificates, namely: -
Regulation - 1. Short title, Extent and Commencement.
(1)
This Regulation shall be called the Telangana
State Electricity Regulatory Commission Renewable Power Purchase Obligation
(Compliance by Purchase of Renewable Energy/Renewable Energy Certificates)
Regulation, 2022.
(2)
This Regulation shall extend to the entire
Telangana State.
(3)
The Regulation shall come into force from the
effective date i.e., on 1st April 2022.
Regulation - 2. Definitions and interpretation.
(1)
In this Regulation, unless the context
otherwise requires -
(a)
Act, 2003 means the Electricity Act, 2003 (36
of 2003) and subsequent amendments thereof;
(b)
Captive Generating Plant means a power plant
set up by any person to generate electricity primarily for his own use and
includes a power plant set up by any co-operative society or association of
persons for generating electricity primarily for use of members of such
co-operative society or association as per the Electricity Rules notified by
Central Government;
(c)
Captive User means the person or member
within the meaning of Section 2(8) of the Act, 2003 being the end user of the
electricity generated in captive generating plant primarily for his own use and
the term captive use shall be construed accordingly;
(d)
Central Agency means the agency as may be
designated by the Central Commission from time to time under the CERC (Terms
and Conditions for recognition and issuance of Renewable Energy Certificate for
Renewable Generation) Regulations, 2010 as amended from time to time;
(e)
Central Commission or CERC means the Central
Electricity Regulatory Commission referred to in sub-section (1) of Section 76
of the Act, 2003;
(f)
CERC Regulations, 2010 means the Central Electricity
Regulatory Commission (Terms and Conditions for recognition and Issue of
Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010
as amended from time to time;
(g)
Certificate means the Renewable Energy
Certificate (REC) issued by the Central Agency in accordance with the
procedures prescribed by it and under the provisions specified in the CERC
Regulations, 2010;
(h)
Co-generation means a process which
simultaneously produces two or more forms of useful energy (including electricity);
(i)
Commission means the Telangana State
Electricity Regulatory Commission as referred to in sub-section (1) of Section
82 of the Act, 2003;
(j)
Conventional Generating Plant means any power
plant generating electricity by using sources other than Renewable Energy
Sources mentioned in this Regulation;
(k)
Distribution Licensee means a Licensee
authorized to operate and maintain a distribution system for supplying
electricity to the consumers in its area of supply;
(l)
Floor Price means the minimum price as determined
by the Central Commission in accordance with the CERC Regulations, 2010, at and
above which the certificate can be dealt in Power Exchange;
(m)
Forbearance Price means the ceiling price as
determined by the Central Commission in accordance with the CERC Regulations,
2010, within which only the Certificate can be dealt in Power Exchange;
(n)
Large Hydel means Hydro Power projects with a
station capacity more than 25 MW ;
(o)
Renewable Hybrid Source means two or more
Renewable Energy Sources used together to provide increased system efficiency
as well as greater balance in energy supply;
(p)
MNRE means the Ministry of New and Renewable
Energy;
(q)
Non-Solar Sources means Renewable Energy
Sources other than Solar Energy Sources;
(r)
Obligated Entity is an entity that is mandated
to fulfil renewable purchase obligation under this Regulation subject to
fulfilment of conditions outlined under clause 3 hereof and for the purposes of
this Regulation shall be the following:
(i)
Distribution Licensee;
(ii)
Captive User-Any consumer who owns a grid
connected Captive Generating Plant based on conventional fossil fuel with
installed capacity of 1 MW and above, or such other capacity as may be
stipulated by the Commission from time to time, and consumes electricity
generated from such plant for his own use;
(iii)
Open Access Consumer in the State - Any
person having a contracted demand of 1 MW and above and consumes electricity
procured from conventional fossil fuel based generation through open access
including procurement from power exchanges;
Provided that an obligated
entity consuming power in any year to the extent of total RPPO specified under
clause 3 hereof from fossil fuel based co-generation power plant shall be
exempted from RPPO. In case the consumption of an obligated entity from such co-generation
power plant is less than the total RPPO, such obligated entity shall be
required to fulfil the RPPO to the extent of shortfall;
(s)
Open Access Consumer means a consumer
availing open access under sub-section (2) of Section 42 of the Act, 2003;
(t)
Pooled Cost of Power Purchase means the
weighted average pooled price at which the distribution licensee has purchased
electricity including the cost of self-generation, if any, in the previous
Financial Year from all the energy suppliers on long-term and medium-term
basis, but excluding the energy purchased from the renewable energy sources;
(u)
Power Exchange means any exchange operating
as the power exchange for electricity in terms of the orders issued by the
Central Commission or recognised by the Commission;
(v)
Renewable Energy with Storage Project means a
combination of renewable energy project with storage or a combination of
renewable hybrid energy project with storage having a single point of injection
or maximum two points of injection into the grid;
(w)
Renewable Hybrid Energy Project means a
renewable energy project that produces electricity from a combination of
renewable energy sources having a single point of injection or maximum two
points of injection into the grid;
(x)
Renewable Energy Sources (or RES)means
renewable sources of energy such as water (Small Hydel - Hydro Power projects
with a station capacity up to and including 25MW), wind, sunlight, biomass,
bagasse, municipal solid waste and other such sources as approved by the MNRE;
(y)
RPPO means Renewable Power Purchase
Obligation prescribed under clause 3 of this Regulation;
(z)
RESCO means Rural Electricity Supply
Co-operative Society;
(za)
State Agency means the State Load
Despatch Centre of the Telangana State as defined under Section 2(66) of the
Act, 2003 or the agency so designated by the Commission under Clause 6(6) of
this Regulation to act as the agency for accreditation and recommending the
renewable energy projects for registration and to undertake functions under
this Regulation;
(zb)
Year means a Financial Year;
(2)
Words and expressions used and not defined in
the Regulation but defined in the Act or any other Regulations of the
Commission shall have the meanings assigned to them respectively in the Act or
any other Regulation as the case may be.
Regulation - 3. Renewable Power Purchase Obligation (RPPO).
(1)
Every Obligated Entity shall purchase from
Renewable Energy Sources a minimum quantity (in kWh) of electricity expressed
as a percentage of its total consumption of energy, during FY 2022-23 to FY
2026-27 as specified in this table below:
Year/RPPO |
2022-23 |
2023-24 |
2024-25 |
2025-26 |
2026-27
|
Solar |
7.50 |
8.00 |
9.00 |
10.00 |
11.00
|
Non-Solar |
1.00 |
1.25 |
1.50 |
1.75 |
2.00
|
Total |
8.50 |
9.25 |
10.50 |
11.75 |
13.00
|
Provided further that the
obligation will be on total consumption of electricity by an Obligated Entity
excluding consumption met from Renewable Energy Sources and Large Hydel:
Provided that on achievement
of Solar RPPO compliance to the extent of 85% and above, remaining shortfall if
any, can be met by excess Non-Solar Energy purchased beyond specified Non-Solar
RPPO for that particular year:
Provided further that on
achievement of Non-Solar RPPO compliance to the extent of 85% and above,
remaining shortfall if any, can be met by excess Solar Energy purchased beyond
specified Solar RPPO for that particular year;
(2)
Roof-top Solar PV System
(a)
The quantum of electricity generated by the
consumer from the Roof-top Solar PV System under the net metering arrangements
shall, if such consumer is not an Obligated Entity, qualify towards meeting the
Solar RPPO of the Distribution Licensee;
(b)
The Distribution Licensee shall install, at
its own cost and with the consent of the consumer, a solar generation meter conforming
to the applicable CEA Regulations at an appropriate location to measure the
energy generated from the Roof-top Solar PV System if it desires that such
energy be counted towards meeting its RPPO. The solar generation meter shall be
maintained by the Distribution Licensee at its cost;
(c)
The purchases made from solar roof-top
projects (gross metering), the unutilised banked energy deemed to have been
purchased by the Distribution Licensees from renewable energy projects under
open access regulations, purchases made at mutually agreed prices and all such
other transactions for which the generator(s) does not claim RECs shall also be
treated as fulfilment of the RPPO prescribed herein;
(3)
The Distribution Licensees shall purchase
power from renewable energy sources at the tariff determined by the Commission
u/s 62 of the Act or at tariffs discovered through transparent process of
bidding u/s 63 of the Act directly or through traders and adopted by the
Commission.
(4)
The purchase of renewable power by the Distribution
Licensee, from other Distribution Licensees in the Telangana State shall also
be taken into account for computing the fulfilment of RPPO by such a Licensee.
(5)
The purchase of REC issued under the CERC
Regulations, 2010, shall also be treated as fulfilment of the RPPO prescribed
herein.
(6)
In the event of the Obligated Entity
fulfilling the RPPO through self-retention of REC as allowed by the CERC
Regulations, 2010, the application for self-retention shall be towards
fulfilment of RPPO of that financial year only; And the Obligated Entity shall
make an application accordingly.
(7)
Distribution Licensees shall compulsorily
procure 100% power produced from all the Waste-to-Energy plants in the
Telangana State.
(8)
The renewable power procured by the Obligated
Entity from renewable energy generating stations bundled with coal/lignite
based thermal generation shall be considered as fulfilment of RPPO;
(9)
Distribution Licensees RPPO shall include
RESCO for the purpose of this Regulation.
(10)
The power from renewable energy sources being
purchased by the obligated entity(s) under the existing power purchase
agreements shall continue till the validity of the existing agreements, even if
the total purchases under such agreements exceed the percentages specified
hereinabove.
(11)
The Commission may, either on its own motion
or on recommendation of the State Agency or on receipt of an application from
the obligated entity(s)or eligible entity(ies), revise for any year the
percentage targets given herein above or to carry forward to next year as
appropriately deemed fit by the Commission.
Regulation - 4. Certificates under the Regulations of the Central Commission.
(1)
The procurement, by the obligated entity(ies)
of RECs issued under the CERC Regulations, 2010, shall be subject to such
directions as the Commission may issue from time to time.
(2)
The RECs purchased by the obligated entity
from the Power Exchange, or the purchase certificate(s) issued by State Agency
in case of self-retention of RECs, shall be deposited by the obligated entity
with the State Agency.
(3)
Notwithstanding the above, the State Agency
can also independently verify the RECs purchased by the obligated entity from
Power Exchange, through Renewable Energy Certificate Registry of India website,
and consider the same towards fulfilment of their RPPO.
Regulation - 5. Obligated Entity.
(1)
Distribution Licensee
(a)
Every Distribution Licensee shall, on a
yearly basis on or before 15thMarch, submit to the State Agency under
intimation to the Commission, the details of the estimated quantum of purchase
from renewable energy sources for the ensuing year. The estimated quantum of
such purchase shall be in accordance with clause 3 of this Regulation;
(b)
The Distribution Licensee shall also submit a
detailed statement to the State Agency under intimation to the Commission at
the end of each year in respect of compliance of RPPO and also place it on the
website of Distribution Licensee;
(c)
Despite availability of power from renewable
energy sources and certificates, if the Distribution Licensee fails to fulfil
its commitment towards minimum purchase from renewable energy sources, it shall
be liable to deposit amount into a separate fund as provided in clause 8 of
this Regulation;
(2)
Captive User and Open Access Consumer
(a)
Every captive user and open access consumer
shall have to submit in advance necessary details regarding total estimated
consumption of electricity and the quantum of power proposed to be purchased
from renewable energy sources for fulfilling its RPPO. The details shall be
submitted to the State Agency on a yearly basis on or before 15thMarch under
intimation to the Commission;
(b)
The captive user and open access consumer
shall submit quarterly status to the State Agency in respect of compliance of
RPPO;
(c)
The captive user and open access consumer
shall submit under affidavit a detailed statement in respect of compliance of
RPPO to the State Agency at the end of each year under intimation to the
Commission;
(d)
Captive user and open access consumer shall
purchase power from renewable energy sources in accordance with clause 3 of
this Regulation. They may also fulfil their RPPO through purchase of RECs. If
the captive user or open access consumer is unable to fulfil the minimum
purchase criteria, then it shall deposit into a separate fund the amount as per
clause 8 of this Regulation;
Regulation - 6. State Agency.
(1)
The State Agency shall function in accordance
with the directions issued by the Commission and shall act in accordance with
the procedures/rules laid down by the Central Agency for discharge of its
functions under the CERC Regulations, 2010.
(2)
The State Agency shall devise an appropriate
protocol for collection of information from various sources such as renewable
energy generating companies, obligated entity, etc., and compute the compliance
of RPPO target by obligated entity.
(3)
The summary statement of RE procurement and
RPPO compliance by each obligated entity shall be published by the State Agency
on a cumulative basis every month on its website.
(4)
The summary statement shall cover RE
procurement by each obligated entity comprising renewable energy procurement
under preferential tariff route or other modality approved by the State
Commission with regard to RPPO as well as renewable energy procurement through
REC mechanism.
(5)
The State Agency shall submit status to the
Commission in respect of compliance of RPPO by the obligated entity(ies) on
yearly basis and initiate appropriate proceedings before the Commission for
compliance verification of the RPPO by the obligated entity(ies).
(6)
Remuneration and Charges: The Commission may
from time to time based on the proposal in this regard from the State Agency
fix the remuneration and charges payable to the State Agency for discharge of
its functions under this Regulation. The fee and charges paid by the obligated
entities and the renewable energy generating companies shall be collected by
the State Agency and utilised for its operations in respect of furthering
objects of this Regulation.
Explanation:- The words for
its operation would include both technical and administrative action for
carrying out the purpose of this Regulation.
(7)
If the Commission is satisfied that the State
Agency is not able to discharge its functions satisfactorily, it may by general
or special order, and by recording reasons in writing, designate any other
agency to function as the State Agency as it considers appropriate.
(8)
In the event of the State Agency functions
have been withdrawn from the existing agency and notified the new agency, the
entire subsisting apparatus both technical and administrative including
finances held for this purpose by the earlier agency shall be transferred to
the new agency and the decision in this regard of the Commission shall be
final.
Regulation - 7. Eligibility and Registration for Certificates.
(1)
The eligibility and registration of
certificates shall be governed by the CERC Regulations, 2010.
(2)
For the purpose of this clause 7,
determination of pooled cost of power purchase shall be as follows:
(a)
DlSCOMs shall submit a petition for
computation of pooled cost of power purchase to the Commission by 30thApril of
that year. The Commission shall issue an order relating to pooled cost of power
purchase for the particular year as expeditiously as possible after it has been
listed for hearing at least once;
(b)
Till the issue of such order the pooled cost
of power purchase of the previous year shall continue to operate as provisional
pooled cost of power purchase;
(c)
After the issue of order for the pooled cost
of power purchase by the Commission, the difference between the provisional
pooled cost of power purchase and the final pooled cost of power purchase shall
be paid/recovered as the case may be in equal instalments in the subsequent
bills for the next two months or as decided by the Commission in the order
while determining the pooled cost of power purchase for that year;
(d)
Where there is a general PPA and such PPA
involves or extends the situation of payment of pooled cost of power purchase,
then the licensees shall endeavour to prepare a draft amendment to such
agreement on a generic basis and submit the same for approval to the
Commission;
(e)
After thorough examination and after
following the due process under the Conduct of Business Regulation, 2015 as
amended from time to time, the Commission may accord approval to the draft PPA
or amendments to the subsisting PPA(s);
(f)
Each such PPA or amendment PPA shall have to
be submitted to the Commission for consent even if there is no deviation from
model PPA approved by the Commission;
Regulation - 8. Consequences of default.
(1)
If the obligated entity does not fulfil the
RPPO as provided in clause 3 of this Regulation during any year, the Commission
may direct the obligated entity to deposit into a separate fund, to be created
and maintained by the State Agency, such amount on the basis of the shortfall
in units of the RPPO and the Forbearance Price decided by the Central
Commission;
Provided that the fund so
created shall be utilised in the manner as may be specified by the Commission
either through general or special order.
(2)
Where any obligated entity fails to comply
with the obligation prescribed in clause 3 of this Regulation, it shall, in
addition to the compliance of the directions under clause 8(1) above, be liable
for penalty as may be decided by the Commission u/s 142 of the Act.
(3)
For this purpose, the Commission may initiate
proceedings either Suo Moto or on a representation made by any of the affected
parties including but not limited to the State Agency.
(4)
Such proceedings shall be in accordance with
the Conduct of Business Regulation, 2015 of the Commission.
Regulation - 9. Information System.
(1)
The State Agency shall post the following
documents/information on its website in a separate web-page titled
Accreditation of RE Projects:
(a)
This Regulation;
(b)
Procedure as mentioned in this Regulation;
(c)
List of applications along with necessary
details received by the State Agency for accreditation;
(d)
List of accreditations granted, indicating -
(i)
Name of RE generating company/station;
(ii)
Point of injection;
(iii)
Capacity (MW) for which accreditation has
been granted;
(e)
List of applications where approval for
accreditation has not been granted along with reasons thereof;
Regulation - 10. Power to Amend.
(1)
The Commission may, at any time add, vary,
alter, modify or amend any provisions of this Regulation.
Regulation - 11. Power to issue directions.
(1)
The Commission may, from time to time, issue
orders and practice directions in regard to the implementation of this
Regulation and procedures to be followed.
Regulation - 12. Power to relax.
(1)
The Commission may by general or special
order, for reasons to be recorded in writing and after giving an opportunity of
hearing to the parties likely to be affected, may relax any of the provisions
of this Regulation on its own motion or on an application made before it by an
interested person.
Regulation - 13. Power to remove difficulties.
(1)
If any difficulty arises in giving effect to
the provisions of this Regulation, the Commission may, by general or special
order, make such provisions not inconsistent with the provisions of the Act,
2003 as may appear to be necessary for removing the difficulty.
Regulation - 14. Saving.
(1)
Anything done or any action taken or
purported to have been done in pursuance of the provisions of the Regulation
No.2 of 2018 shall in so far as it is not inconsistent with the provisions of
this Regulation, be deemed to have been done or taken under the corresponding
provisions of this Regulation.
(2)
Any rights and liabilities arising out of the
earlier Regulation shall be settled within the applicable provisions as may be
appropriately relevant.
Regulation - 15. Inquiry, investigation and adjudication.
(1)
All inquiries, investigations and
adjudications under this Regulation shall be done by the Commission through the
proceedings in accordance with the provisions of the Conduct of Business
Regulations as amended from time to time.