Tariff
based Competitive-bidding Guidelines for Transmission Service
[Tariff
based Competitive-bidding Guidelines for Transmission Service][1]
[17th April, 2006]
1. Preamble.
Promotion of competition in
the electricity industry in India is one of the key objectives of the
Electricity Act, 2003 (the Act). Development of a transmission system is
essential both for encouraging competition and for creating electricity
markets. These guidelines are aimed at facilitating competition in this sector
through wider participation in providing transmission services and tariff
determination through a process of tariff based bidding.
Section 61 and 62 of the
Act provide for tariff regulation and determination of tariff of generation,
transmission, wheeling and retail sale of electricity by the Appropriate
Commission. Section 63 of the Act states that —
“Notwithstanding anything
contained in section 62, the Appropriate Commission shall adopt the tariff if
such tariff has been determined through transparent process of bidding in
accordance with the guidelines issued by the Central Government.”
[2][Tariff based Competitive
Bidding Guidelines for Transmission Service and Guidelines of Encouraging
Competition in Development of Transmission Projects] have been framed under the
above provisions of section 63 of the Act. The specific objectives of these
guidelines are as follows:
Promote competitive
procurement of transmission services.
Encourage private
investment in transmission lines.
Facilitate transparency and
fairness in procurement processes;
Facilitate reduction of
information asymmetries for various bidders;
Protect consumer interests
by facilitating competitive conditions in procurement of transmission services
of electricity;
Enhance standardization and
reduce ambiguity and hence time for materialization of projects;
Ensure compliance with
standards, norms and codes for transmission lines while allowing flexibility in
operation to the transmission service providers.
2. Scope of the Guidelines
(1) These guidelines are being issued
under the provisions of Section 63 of the Electricity Act, 2003 for procurement
of transmission services for transmission of electricity.
(2) The guidelines shall apply
for procurement of transmission services for transmission of electricity
through tariff based competitive bidding, through the mechanisms described in
this notification and to select transmission service provider for a new
transmission line and to build, own, maintain and operate the specified
transmission system elements.
(3) “Transmission line” has
been defined in para 2(72) of the Electricity Act, 2003 as all high pressure
cables and overhead lines (not being an essential part of the distribution
system of a licensee) transmitting electricity from a generating station to
another generating station or a substation, together with any step up and step
down transformers, switch gear and other works necessary to and used for the
control of such cables or overhead lines, and such buildings or part thereof as
may be required to accommodate such transformers, switch gear and other works.
(4) Procurement of transmission
services would include all activities related to survey, detailed project
report formulation, arranging finance, project management, obtaining
transmission license, obtaining right of way, necessary clearances, site identification, land compensation, design,
engineering, equipment, material, construction, erection, testing and
commissioning, maintenance and operation of transmission lines and/or
substations and/or switching stations and/or HVDC links including terminal
stations and HVDC transmission line. It will be in such a manner that the
required transmission services as specified in the bid document are provided by
execution of the project up to completion and commissioning and its subsequent
maintenance and operation so that the facilities are available as per the
target availability for recovery of full transmission charges fixed by the
appropriate commission. For availability of transmission line below the target,
subject to para 2.5 below, transmission tariff payable to the TSP will be in
accordance with the appropriate regulation of the appropriate commission.
(5) If the availability of the
transmission line is below the norms prescribed by the CERC for six consecutive
months the procurer of transmission service or the billing and accounting agency or the operator of the transmission
system may seek revocation of transmission license as per the procedure laid
down under the Electricity Act, 2003 and in accordance with rule 5 of Electricity
Rules, 2005.
3. Bid Process Coordinator (BPC)
(1) The Bid Process
Coordinator, herein after referred to as BPC, would be responsible for
coordinating the bid process for procurement of required transmission
services [3][for
each inter-State Transmission Project to be implemented under tariff-based
competitive bidding in accordance with these guidelines].
(2) For procurement of
transmission services, required for [4][any]
inter-state transmission [5][project],
the Central Government shall notify any Central Government Organization/Central
Public Sector Undertaking [6][or
its wholly owned subsidiary (Special Purpose Vehicle)] to be the BPC. The BPC
will be notified by the Ministry of Power and nomination of BPC will be for a
period of three years at a time. It will be open for Ministry of Power to
review the nomination of BPC at any time. For immediate implementation of these
guidelines the Empowered Committee constituted as per the provisions of the
“Guidelines for encouraging competition in development of Transmission
Projects” will be the BPC till any other organization is nominated as BPC by
the Ministry of Power.
(3) For procurement of
transmission services required for intra-state transmission, the appropriate
State Government may notify any Organization/State Public Sector Undertaking
especially engaged for this purpose by the appropriate state government or BPC
notified by the Central Government to be the BPC for the state.
(4) All the expenditure
incurred by the BPC in the process of selection of the investor in accordance
with the provisions of these guidelines shall be recovered from the developer
who is finally identified and assigned the task of developing that project. The
amount to be recovered shall be indicated in the RFP document so that bidders
can take that amount into consideration in the tariff to be quoted by them.
4. Preparation for inviting bids
(1) The BPC shall prepare the
bid documentation in accordance with these guidelines and obtain approval of
the Appropriate Commission. Alternatively, the BPC can use the standard bidding
documents notified by Ministry of Power. Standard Bid Documents in accordance
with these guidelines will be notified by Ministry of Power within three months
of the notification of these guidelines. Approval of the Appropriate Commission
would be necessary if any material deviation is proposed to be made from the
Standard Bid Documents.
(2) Intimation shall be sent by
the BPC to the appropriate Commission about initiation of the bidding process.
(3) For location specific
substations, switching stations or HVDC terminal or inverter stations the BPC
or its authorized representative should [7][initiate
the process of acquisition of land]. The BPC or its authorized representative
will also [8][initiate
the process of seeking forest clearance, if required].
5. Transmission Service Provider (TSP)
(1) [9][The successful bidder
shall be designated as the Transmission Service Provider (TSP), herein after
referred to as the TSP, after executing the TSA and acquiring the SPV. The TSP
shall seek transmission license from the appropriate Regulatory Commission, if
it is not a deemed licensee. The TSA shall be effective from the date of grant
of license from the appropriate Regulatory Commission.]
(2) The TSP would take-up
execution of the transmission scheme, [10][project]
so as to complete commission and operationalise the transmission line as per
the specified schedule in the [11][TSA].
6. Recovery of Transmission Charges
(1) Total charges for
transmission of electricity by use of the transmission services provided by the
TSP(s) selected through the bidding process as per these guidelines, payable to
the TSP, shall be determined as specified in paras 7.1, 7.2, 7.3, 7.4 and 7.5
of these guidelines.
(2) Recovery of transmission
charges from the users of the transmission services such as State supply
utilities, distribution companies, generation companies, traders, bulk
consumers, etc., shall be done as provided in the “ Guidelines for encouraging
competition in development of transmission Projects”
7. Transmission Charge Structure
(1) For procurement of
transmission services under these guidelines, transmission charges shall be
paid and settled for each payment period (not exceeding one month). A
transmission charge for providing transmission service and operation and
maintenance required for the various transmission elements shall form the basis
for bidding and evaluation. Tariff structure will have two components — one
scaleable and the other non-scaleable. The scaleable component shall not be
more than 15% of the non-scaleable component.
(2) The BPC shall specify
scheduled month of commercial operationalisation for the transmission line
required for the transmission service and invite bids for the transmission
charge.
(3) [12][At the bid evaluation
stage, ratio of minimum and maximum transmission charge (including both the
non-scaleable component and the scaleable component incorporating escalation as
per index being used for the purpose of evaluation) over the term of the
license shall not be less than 0.7 to avoid excessive front loading or back
loading during the period of contract.]
(4) The bidders shall quote
annual tariff payable after commissioning till expiry of license period and the
monthly tariff payable shall be annual tariff divided by 12.
(5) Tariff shall be designated
in Indian Rupees only. Foreign exchange risks, if any, shall be borne by the
provider of transmission service.
(6) Reasonableness
of Transmission Charges.—Criteria
to assess the reasonableness of transmission charges quoted by any bidder will
be stated in the bid documents. BPC will assess the reasonableness of
transmission charges. No bid will be accepted by the BPC if it finds after
evaluation that none of the quoted transmission charges are reasonable. But
this process of assessing the reasonableness will not limit the rights of the
BPC to reject any or all the bids under any other provision of RFQ or RFP or
combined bid.
8. Payment Security Mechanism
(1) Adequate payment security
shall be made available to the TSP by the user of transmission services being
provided by the TSP. The payment security may constitute:
(i) Letter of Credit (LC).
(ii) Letter of Credit (LC)
backed by credible escrow mechanism.
9. Bidding Process
(1) For the procurement of
transmission services under these guidelines, BPC may at its option either
adopt a two-stage process featuring separate Request for Qualification (RFQ)
and Request for Proposal (RFP) or adopt a single stage two envelope tender
process combining the RFP and RFQ processes. The bid documents shall be
prepared in accordance with para 4.1 of these guidelines.
(2) RFQ or combined RFQ and RFP
notice should be published in at least two national newspapers, website of the
BPC and the appropriate Government and preferably in trade magazines also, so
as to accord it wide publicity. The bidding shall necessarily be by way of
International Competitive Bidding (ICB). For the purpose of issue of RFQ
minimum conditions to be met by the bidder shall be specified in the RFQ
notice.
(3) BPC shall provide only
written interpretation of the tender document to any bidder/participant and the
same shall be made available to all other bidders. All parties shall rely
solely on written communication and acceptances from the bidders.
(4) Standard documentation to
be provided in the RFQ shall include,
(5) [13][Definition of requirements,
including:
Brief description of the
Project;
Commissioning milestones to
be achieved by the bidders;
Qualification requirements
to be met by bidders including, minimum net-worth, internal resource
generation, etc with necessary proof of the same, as outlined in the bid
documents;]
(6) [14][The conditions as
specified by the Appropriate Commission to be complied with by a person for
being eligible to obtain a transmission license shall be necessary conditions
for RFQ and will be incorporated in the RFQ by BPC.]
(7) [15][* * *]
(8) [16][* * *]
(9) [17][* * *]
(10) [18][* * *]
(11) RFP shall be issued to all
bidders who have qualified at the [19][RFP]
stage. BPC may call a pre bid conference with all the developers who have
sought documents for RFQ. In case the bidders seek any deviations and BPC
finds [20][those]
deviations are reasonable, the BPC may agree to deviation. The
clarification/revised-bidding document shall be given to all who had sought
the [21][RFP]
document informing about the deviations and clarifications. Wherever revised
bidding documents are issued, the BPC shall provide bidders at least [22][one
month] after issue of such documents for submission of bids.
(12) Standard documentation to
be provided by the BPC in the RFP shall include,
(13) Specified target
dates/months for commissioning and commercial operations and start of providing
the transmission services.
(14) [23][Proposed Transmission Service Agreement(TSA).—The TSP will enter
into a Transmission Service Agreement (TSA) with the concerned utilities. These
may include the utilities falling in the region where the load is located, any
intervening region and the interregional transmission lines between the
regions.
The bid document for the
concerned project shall provide a draft of proposed TSA.]
(15) [24][Required Period of
validity of offer of bidder.]
(16) [25][TSA proposed to be entered
with the selected bidder. The TSA proposed in the RFP stage may be amended
based on the inputs received from bidders during the pre bid conference and it
will be made available to all RFP bidders. No further amendments shall be
carried out in the TSA.]
(17) [26][Bid evaluation methodology
to be adopted by the BPC. The bids shall be evaluated based on annual
transmission charges for all components covered under the package as quoted by
the bidder.]
(18) [27][The RFP shall also specify
the Discount Factor (DF) that would be used for evaluation of bids.]
(19) [28][The RFP will also specify
the bid bond as well as the Contract Performance Guarantee that the bidders
will have to furnish.]
(20) [29][The proposed
indemnification agreement between the TSP and the utilities will also be
provided along with the RFP. This indemnification will be applicable to both
the TSP and the utilities from the zero date as specified in the RFP.]
(21) [30][The RFP shall also specify
the liquidated damages that would apply in event of delay in start of providing
the transmission services.]
(22) [31][Other technical,
operational and safety criteria to be met by bidder/TSP, including the
provisions of the technical standard specified by CEA, IEGC/State Grid Code,
relevant orders of the Appropriate Commission, etc., as applicable.]
(23) Bid
submission and evaluation.—To
ensure competitiveness, the minimum number of qualified bidders will be two.
(24) [32][Bid evaluation committee.—The Empowered Committee shall constitute
a committee for evaluation of the bids with at least one representative from
CEA and not less than two representatives from the concerned Regional Power
Committees with at least one representative from every concerned RPC and one
independent member. The independent member shall have expertise in financial
matter/bid evaluation.]
(25) The bids shall be opened in
public and representatives of bidders shall be allowed to remain present.
(26) The technical bids shall
be [33][examined]
to ensure that the bids submitted meet minimum eligibility criteria set out in
the [34][bid]
documents on all technical evaluation parameters. Only the bids that meet all
elements of the minimum technical criteria set out in the RFQ shall be
considered for further evaluation on the transmission charges bids.
(27) The transmission charge bid
shall be rejected if it contains any deviation from the [35][bid
documents] for submission of the same.
(28) The bidder who has quoted
lowest [36][levelised]
transmission charge as per evaluation procedure shall be considered for the
award.
10. Arbitration
Regulatory Commission under
the provisions of the Electricity Act, 2003.
11. Time Table for Bid Process
(1) [37][A suggested time-table for
the bid process is indicated below. The BPC may give extended time-frame
indicated herein based on the prevailing circumstances and such alterations
shall not be construed to be deviation from these guidelines.
Event |
Elapsed Time from Zero date |
Publication of RFQ |
Zero date |
Submission of Response to RFQ |
30 days |
Short listing based on responses and issuance of
RFP |
60 days |
Bid clarification, conference, Final
clarification and revision of RFP |
85 days |
Technical and price bid submission |
120 days |
Short listing of bidder and issue of LOI |
135 days |
Signing of Agreements |
145 days] |
(2) A suggested time-table for
the Single stage two envelope bid process is indicated below. The procurer may
give extended time-frame indicated herein based on the prevailing circumstances
and such alterations shall not be construed to be deviation from these
guidelines.
Event |
Elapsed Time from Zero date |
Publication of RFP |
Zero date |
Bid clarification, conferences etc. and revision
of RFP |
60 days |
Technical and price bid submission |
120 days |
Short-listing of bidder and issue of LOI |
150 days |
Signing of Agreements |
180 days |
12. Contract award and conclusion
(1) [38][After selection and issue
of LOI from the BPC, the selected bidder shall acquire the SPV created for the
Project to become TSP and sign the TSA, if not already signed by the SPV, in
accordance with the terms and conditions as finalized in the bid document. The
TSA will be effective only upon grant of transmission license from the
Appropriate Commission.]
(2) [39][The TSP shall make an
application for grant of transmission license to the Appropriate Commission
within [40][ten
days] of issuance of LOI or signing of TSA, whichever is later.]
(3) [41][The BPC shall make the
final result of evaluation of all bids public.]
(4) [42][The TSA along with the
certification by the Empowered Committee shall be forwarded to the Appropriate
Commission for adoption of tariffs in terms of Section 63 of the Act.]
(Gireesh B. Pradhan)
Joint Secretary to the
Government of India
No. 23/23/05-R&R (Col.
II)
Government of India
Ministry of Power
(R&R Cell)
Dated: 6th August, 2007
To,
The CMD, PTC India Ltd.
2nd Floor, NBCC Tower
15, Bhikaji Cama Place
New Delhi — 110 006
Subject:
Regarding provisions of the Electricity Act, 2003
Sir,
I am directed to refer to
your letter dated 7th May, 2007 on the above subject and to convey that:
(i) Section 9(2) of the
Electricity Act, 2003 given the right to open access to a person who has
constructed a captive generating plant and maintains and operates such a plant
(as defined under Electricity Act, 2003 and the Rules made hereunder), for the
purposes of carrying electricity from the captive generating plant to the
destination of his use, subject to availability of adequate transmission
facility. This provision is distinct from the open access which is to be
introduced in phases by the State Electricity Regulatory Commissions (SERCs)
under Section 42 for the consumers other than captive users on payment of cross
subsidy surcharge, if any Therefore, the right to open access for captive
generating plants flows from Section 9(2) and not from Section 42(2) and hence
is no dependent upon introduction of open access by SERCs under Section 42 of
the Act.
(ii) However, supply of surplus
power from a captive generating plant to non captive consumers will be covered
by the provisions of Section 42 of the Act.
Yours faithfully
Director
No. V-1/2007-IPC(Pt.)
Government of India
Ministry of Power
New Delhi, dated 9th
August, 2007
To,
Principal Secretary
(Energy)
All States and Union
Territories
Subject:
Signing of State Support Agreement/MOU for facilitating setting up of Power
Plants including those using imported coal.
Sir,
(1) I am directed to state that
numerous enquiries have been received on the requests by entrepreneurs for
signing State Support Agreement/MOU with States for facilitating setting up
power stations including those to
be set up on imported coal.
(2) Section 7 of the Electricity Act, 2003 provides that a generating station may be
established, operated and maintained without obtaining a license under the Act.
The States could assist the developers through MOUs for securing land, obtaining the requisite
environment and other clearances and in achieving financial closure.
(3) These projects could
thereafter tie up sale of power in accordance with the provisions of the
Electricity Act, 2003 and the Tariff Policy, 2006:
(a) under provisions of Section
63 of the Electricity Act, 2003 i.e. by responding to tariff based bids from
the distribution companies, or
(b) making use of open access
for transmission and operate as merchant power plants selling their power:
(i) directly to a consumer
(u/s. 49 of the Act) or to a distribution licensee for short term sales [under
proviso to Section 62(1)(a) of
the Act], or
(ii) to an electricity trader
u/s 10 of the Act.
(c) functioning as a
captive/group captive power plant wheeling surplus power to open access consumers (u/s.
49) or a distribution company in
short term [under proviso
to Section 62(1)], making use of ‘open access in
transmission’. Surplus power will
be determined as per the Electricity Rules, 2005.
(4) The
power plant can also operate as a captive power plant, and the power can be consumed by the owners in terms of the provisions of
the Electricity Act, 2003 and
the Electricity Rules, 2005.
[1]
Ministry of Power, No. 11/5/2005-PG(i). dated 17-4-2006.
[2]
Subs. for “These guidelines” by Resolution dated 4-7-2007.
[3]
Ins. by Resolution dated 4-7-2007.
[4]
Ins. by Resolution dated 4-7-2007.
[5]
Ins. by Resolution dated 4-7-2007.
[6]
Ins. by Resolution dated 4-7-2007.
[7]
Subs. by Resolution dated 4-7-2007.
[8]
Subs. by Resolution dated 4-7-2007.
[9]
Subs. by Resolution dated 4-7-2007.
[10]
Ins. by Resolution dated 4-7-2007.
[11]
Subs. by Resolution dated 4-7-2007.
[12]
Subs. by Resolution dated 4-7-2007.
[13]
Subs. by Resolution dated 4-7-2007.
[14]
Subs. by Resolution dated 4-7-2007.
[15]
Deleted by Resolution dated 4-7-2007. Prior to deletion it read as:
“9.4.3. Required Period of validity of offer
of bidder;
[16]
Deleted by Resolution dated 4-7-2007. Prior to deletion it read as:
9.4.4. The conditions as specified by the
Appropriate Commission to be complied with by a person for being eligible to
obtain a transmission licence shall be necessary conditions for RFQ and will be
incorporated in the RFQ by BPC.
[17]
Deleted by Resolution dated 4-7-2007. Prior to deletion it read as:
9.4.5. Other technical, operational and
safety criteria to be met by bidder/TSP, including the provisions of the
IEGC/State Grid Code, relevant orders of the Appropriate Commission, etc., as
applicable.
[18]
Deleted by Resolution dated 4-7-2007. Prior to deletion it read as:
9.4.6. The BPC may, at its option, require
demonstration of financial commitments from lenders at the time of submission
of the bids. This would accelerate the process of financial closure and
delivery of transmission services for transmission of electricity;”
[19]
Subs. by Resolution dated 4-7-2007.
[20]
Subs. by Resolution dated 4-7-2007.
[21]
Subs. by Resolution dated 4-7-2007.
[22]
Subs. for “two months” by Resolution dated 9-12-2013.
[23]
Subs. by Resolution dated 4-7-2007.
[24]
Subs. by Resolution dated 4-7-2007.
[25]
Subs. by Resolution dated 4-7-2007.
[26]
Subs. by Resolution dated 4-7-2007.
[27]
Subs. by Resolution dated 4-7-2007.
[28]
Subs. by Resolution dated 4-7-2007.
[29]
Subs. by Resolution dated 4-7-2007.
[30]
Ins. by Resolution dated 4-7-2007.
[31]
Ins. by Resolution dated 4-7-2007.
[32]
Subs. by Resolution dated 4-7-2007.
[33]
Subs. for “scored” by Resolution dated 4-7-2007.
[34]
Subs. for “RFQ” by Resolution dated 4-7-2007.
[35]
Subs. for “tender conditions” by Resolution dated 4-7-2007.
[36]
Ins. by Resolution dated 4-7-2007.
[37]
Subs. by Resolution dated 9-12-2013.
[38]
Subs. by Resolution dated 4-7-2007.
[39]
Subs. by Resolution dated 4-7-2007.
[40]
Subs. for “one month” by Resolution dated 9-12-2013.
[41]
Subs. by Resolution dated 4-7-2007.
[42]
Subs. by Resolution dated 4-7-2007.