PUNJAB
STATE ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS FOR DETERMINATION
OF GENERATION, TRANSMISSION, WHEELING AND RETAIL SUPPLY TARIFF) REGULATIONS,
2022
PREAMBLE
In
exercise of the power conferred on it by section 181 (2) read with section 61
and 62 of the Electricity Act 2003 (36 of 2003) and all other powers enabling
the Commission in this behalf, the Punjab State Electricity Regulatory
Commission hereby makes the following Regulations, laying down Terms and
Conditions for Determination of Generation, Transmission, Wheeling and Retail
Supply Tariff.
PART
I SCOPE, EXTENT AND
DEFINITIONS
Regulation - 1. Short Title, Commencement and Extent.
1.1.
These Regulations may be called the
"Punjab State Electricity Regulatory Commission (Terms and Conditions for
Determination of Generation, Transmission, Wheeling and Retail Supply Tariff)
Regulations, 2022" (PSERC MYT Regulations 2022).
1.2.
These Regulations shall come into force
from 1st April, 2023 and shall unless otherwise directed by the Commission,
remain in force upto 31st March, 2026 for the duration of the third Control
Period.
1.3.
These Regulations shall extend to the
whole State of Punjab.
Regulation - 2. Scope of Petition.
These Regulations shall
apply where the Commission determines:
(a)
Tariff for supply of electricity from a
generating plant (excluding Renewable Energy Sources) owned by the Distribution
Licensee, under section 62 & 64 of the Act;
(b)
Tariff for supply of electricity by a
Generating Company (excluding Renewable Energy Sources) to a Distribution
Licensee, under section 62 & 64 of the Act;
(c)
Tariff for intra-state transmission of
electricity by a Transmission Licensee to an open access customer (including
Distribution Licensee), under section 62 & 64 of the Act;
(d)
State Load Despatch Centre (SLDC) fees and
charges under section 32(3) of the Act;
(e)
Tariff for wheeling and retail supply of
electricity by a Distribution Licensee, under section 62 & 64 of the Act;
(f)
Surcharge in addition to the charges for
wheeling under the first proviso to sub-section (2) of Section 42 of the
Act, in accordance with the Open Access Regulations.
Regulation - 3. Definitions and Interpretation.
3.1.
"Act" means the Electricity Act, 2003 (36 of 2003) as amended or
modified from time to time;
3.2.
"Additional Capitalization" means the capital expenditure incurred or
projected to be incurred, after the date of commercial operation of the project
and admitted by the Commission after prudence check, subject to provisions of
Regulation 18;
3.3.
"Allocation Statement" means for each year, a statement in respect of
each of the businesses (Generation, Transmission, Load Dispatch, Distribution
comprising Wheeling and Retail Supply, Other Business) of the licensee, showing
the amounts of any revenue, cost, asset, liability, reserve or provision etc.,
which has been either;
(a)
Determined by apportionment or allocation
between different businesses of the licensee, together with a description of
the basis of the apportionment or allocation; or
(b)
Charged from or to each such Other Business
together with a description of the basis of that charge;
Provided that 'Allocation
Statement' shall not be construed as a substitute for maintaining separate
accounting statement for the licensed business and other businesses of the
Licensees.
3.4.
"ARR" in these Regulations means Aggregate Revenue Requirement of the
Petitioner;
3.5.
"Auditor" means an auditor appointed by a Generating Company or a
licensee or the State Load Dispatch Centre in accordance with the provisions of
sections 139 & 148 of the Companies Act, 2013 (18 of 2013), or any other
law for the time being in force;
3.6.
"Auxiliary Energy Consumption" or "AUX" in relation to a
generating plant means the quantum of energy consumed by auxiliary equipment of
the generating plant and transformer losses within the generating plant, and
shall be expressed as a percentage of the sum of gross energy generated at the
generator terminals of all the units of the generating plant; and in relation
to a transmission system means quantum of energy consumed in the AC sub-station
or HVDC sub-station for the purpose of air-conditioning, lighting, etc.;
Provided that auxiliary
energy consumption shall not include energy consumed for supply of power to
housing colony and other facilities at the generating station and the power
consumed for construction works at the generating station;
3.7.
A) "Availability or Availability
Factor" in relation to the transmission system for a given period means
the time in hours during which the transmission system is capable of
transmitting electricity at its rated voltage and shall be expressed in
percentage of total hours in the given period and calculated as per formula
specified by CERC from time to time;
3.8.
"Average Cost of Supply" means ratio of the Aggregate Revenue
Requirement of the Distribution Licensee for the year including unrecovered
revenue gaps of previous years along with carrying cost to the extent proposed
to be recovered through retail tariffs, to the total sales of the Distribution Licensee
for the respective year;
3.9.
"Base Year" means the year immediately preceding the first year of
the Control Period.
3.10.
"Beneficiary" in relation to a
(a)
Transmission Licensee means the person who
has availed the transmission system on payment of transmission charges. This
includes a Distribution Licensee, a Transmission Licensee, a person who has set
up a captive generating plant or a Generating Company including merchant power
plant or a consumer availing open access, utilising the transmission system of
a Transmission Licensee. Medium term and short term open access customers shall
not be treated as beneficiaries;
(b)
Generating plant means the person purchasing
electricity generated at such a generating plant whose tariff is determined
under these Regulations;
3.11.
"Block" in relation to a combined cycle thermal generating plant
includes combustion turbine - generator, associated waste heat recovery
boiler(s), connected steam turbine - generator and auxiliaries;
3.12.
"Captive generating plant" means a power plant set up by any person
to generate electricity primarily for his own use and includes a power plant
set up by any co-operative society or association of persons for generating
electricity primarily for use of members of such cooperative society or
association;
3.13.
"CERC" means the Central Electricity Regulatory Commission;
3.14.
"Change in Law" means occurrence of any of the following events:
(a)
enactment, bringing into effect or
promulgation of any new Indian law; or
(b)
adoption, amendment, modification, repeal or
re-enactment of any existing Indian law; or
(c)
change in interpretation or petition of any
Indian law by a competent court, Tribunal or Indian Governmental
Instrumentality which is the final authority under law for such interpretation
or petition; or
(d)
change by any competent statutory authority
in any condition or covenant of any consent or clearances or approval or
license available or obtained for the project; or
(e)
coming into force or change in any bilateral
or multilateral agreement or treaty between the Government of India and any
other Sovereign Government having implication for the generating station or the
transmission system regulated under these Regulations.
Provided that financial
implication of change in law in relation to a PPA shall be as provided in the
PPA
3.15.
"Commission/PSERC" means the Punjab State Electricity Regulatory
Commission;
3.16.
"Conduct of Business Regulations" means Punjab State Electricity
Regulatory Commission (Conduct of Business) Regulations, 2005, as amended from
time to time;
3.17.
"Control Period" means the period of three (3) Years from April 1st,
2023 to March 31st, 2026 which is the third Control Period;
3.18.
"Cut-off Date" means 31st March of the year closing after two years
of the year of commercial operation of the project, and in case the project is
declared under commercial operation in the last quarter of a year, the cut-off
date shall be 31st March of the year closing after three years of the year of
commercial operation;
3.19.
"De-capitalisation" means the reduction in Gross Fixed Assets
corresponding to the removal of assets as approved by the Commission;
3.20.
"Declared Capacity" in relation to a generating plant means the
capability to deliver ex-bus electricity in MW declared by such generating
plant in relation to any period of the day or whole of the day, duly taking
into account the availability of fuel or water, and subject to further
qualification in the relevant Regulation;
3.21.
"Design Energy" means the quantum of energy which can be generated in
a 90% dependable year with 95% installed capacity of the hydro generating
plant;
3.22.
"Deviation" in a time-block for a seller means its total actual
injection minus its total scheduled generation and for a buyer means its total
actual drawal minus its total scheduled drawal;
3.23.
"Distribution Business" means the business of operating and
maintaining a distribution system for supplying electricity in the area of the
supply of the Distribution Licensee;
3.24.
"Distribution Licensee" means a licensee authorised to operate and
maintain a distribution system for supplying electricity to the consumers in
his area of supply;
3.25.
"Effective Date" means April 1st, 2023 for enforcement of these
Regulations;
3.26.
"Electrical Plant" means any plant, equipment, apparatus or appliance
or any part thereof used for, or connected with, the generation, transmission,
distribution or supply of electricity but does not include-
(a)
an electric line;or
(b)
a meter used for ascertaining the quantity of
electricity supplied to any premises; or
(c)
an electrical equipment, apparatus or
appliance under the control of a consumer;
3.27.
"Electricity Supply Code and Related Matters Regulations" means the
Punjab State Electricity Regulatory Commission(Electricity Supply Code and
Related Matters) Regulations, 2014, as amended from time to time;
3.28.
"Existing Distribution System" means the distribution system declared
under commercial operation from a date prior to the effective date;
3.29.
"Existing Generating Plant" means a generating plant declared under
commercial operation from a date prior to the effective date;
3.30.
"Existing Transmission System" means the transmission system declared
under commercial operation from a date prior to the effective date;
3.31.
"Force Majeure Event" means, with respect to any party, any event or
circumstance which is not within the reasonable control of, or is not due to an
act or omission or commission of, that party and which, by the exercise of
reasonable care and diligence, that party is not able to prevent, including,
without limiting the generality of the foregoing:
(a)
acts of God, including but not limited to
lightning, storm, earthquakes, floods, drought and other natural disasters;
(b)
strikes, lockouts;
(c)
acts of public enemy, wars (declared or
undeclared), blockades, insurrections, riots, revolution, sabotage, vandalism
and civil disturbance;
(d)
unavoidable accident, including but not
limited to fire, explosion, radioactive contamination and toxic dangerous
chemical contamination;
(e)
any shutdown or interruption of the Grid,
which is required or directed by the State or Central Government or by the
Commission or the State/Regional Load Despatch Centre;
(f)
any shut down or interruption, which is
required to avoid serious and immediate risks of a significant plant or
equipment failure;
and
(g)
change in law events;
3.32.
"Generation Business" means the business of production of electricity
from a generating station;
3.33.
"Generating Company" means, any company involved in generation
business in the State and/ or any company whose tariff is determined by the
Commission;
3.34.
"Generation Tariff" means the schedule of charges for generation of
electricity including the terms and conditions applicable thereof;
3.35.
"Gross Calorific Value" or "GCV" in relation to a thermal
power generating plant means the heat produced in kCal by complete
combustion of one kilogram of solid fuel or one litre of liquid fuel or one
standard cubic meter of gaseous fuel, as the case may be;
3.36.
"Infirm Power" means electricity injected into the grid prior to
commercial operation of a unit or block of the generating plant;
3.37.
"Installed Capacity" or "IC" means the summation of the
name plate capacities of all the units of the generating plant or the capacity
of the generating plant (reckoned at the generator terminals) approved by the
Commission from time to time;
3.38.
"Inter-State Transmission System" shall have the same meaning as
assigned in the Punjab State Electricity Regulatory Commission (Grid Code)
Regulations, 2013, as amended from time to time;
3.39.
"Intra-State Transmission System" means any system for transmission
of electricity other than an inter-State transmission system;
3.40.
"Licensee" means a person who has been granted a licence under
section 14 of the Act and includes a person deemed to be a licensee under
section 14 of the Act;
3.41.
"Licensed Business" means the functions and activities, which the
licensee is required to undertake in terms of the licence granted by the
Commission or as a deemed licensee under the Act;
3.42.
"Long-term Open Access Customer" means a person defined as long term
open access customer in the Open Access Regulations;
3.43.
"Maximum Continuous Rating" or "MCR" in relation to a unit
of the thermal power generating plant means the maximum continuous output at
the generator terminals, guaranteed by the manufacturer at rated parameters,
and in relation to a unit or block of a combined cycle thermal power generating
plant means the maximum continuous output at the generator terminals,
guaranteed by the manufacturer with water/steam injection (if applicable) and
corrected to 50 Hertz (Hz) grid frequency and specified site conditions;
3.44.
"MCLR" means One Year Marginal Cost of Funds based Lending Rate;
3.45.
"Medium-term Open Access Customer" means a person defined as
medium-term open access customer in the Open Access Regulations;
3.46.
"New Distribution System" means a distribution system declared under
commercial operation on or after the effective date;
3.47.
"New Generating Plant" means a Generating Plant declared under
commercial operation on or after the effective date;
3.48.
"New Transmission System" means a transmission system declared under
commercial operation on or after the effective date;
3.49.
"Non-Tariff Income" means income relating to the regulated business
other than income from tariff, excluding any income from Other Business and, in
case of the Retail Supply Business of a Distribution Licensee, including
receipts on account of cross-subsidy surcharge and additional surcharge on
charges of wheeling;
3.50.
"Open Access Regulations" means the Punjab State Electricity
Regulatory Commission (Terms and Conditions for Intra-state Open Access)
Regulations, 2011, as amended from time to time;
3.51.
"Operation and Maintenance Expenses" or " O&M Expenses"
means the expenditure incurred on operation and maintenance of the generating
plant or the transmission system or the distribution system, as the case may
be, including part thereof, and includes the following expenditure:
(a)
Repair and Maintenance (R & M) Expenses;
(b)
Administration and General (A & G)
Expenses;
(c)
Employee Cost (EC);
3.52.
"Petitioner" means person who has made a petition for determination
of tariff for generation business or transmission business or distribution
business comprising wheeling business and/or retail supply business or recovery
of charges for Load Dispatch or a petition for True-up or a petition for
Capital Investment Plan and/or Business Plan in accordance with these
Regulations and the Act;
3.53.
"Plant Availability Factor" or "PAF" in relation to a
generating plant for any period means the average of the daily declared
capacities (DCs) for all the days during that period expressed as a percentage
of the installed capacity in MW less the normative auxiliary energy
consumption;
3.54.
"Plant Load Factor" or "PLF" for a given period means the
total sent out energy corresponding to scheduled generation during the period,
expressed as a percentage of sent out energy corresponding to installed
capacity of the generating plant in that period and shall be computed in
accordance with the following formula:
3.55.
"Project"
(a)
In case of a thermal generating station, all
components of the thermal generating station and includes coal handling plant,
biomass pellet handling system, pollution control system, effluent treatment
plan, as may be required;
(b)
In case of a hydro generating station, all
components of the hydro generating station and includes dam, intake water
conductor system, power generating station, as apportioned to power generation;
(c)
In relation to the transmission business
means a transmission system comprising specified transmission lines,
sub-stations and associated equipment including communication system;
(d)
In relation to State Load Despatch Centre means
any project associated with integrated operation of power system in the State;
and
(e)
In relation to distribution business means a
distribution system comprising specified distribution lines, sub-stations and
associated equipment;
3.56.
"Rated Voltage" means the manufacturer 's design voltage at which the
transmission/distribution system is designed to operate and includes such lower
voltage at which the line is charged or for the time being charged in
consultation with the supplier and the receiver of electricity;
3.57.
"Retail Supply Business" means the business of sale of electricity by
a Distribution Licensee to the various categories of consumers within the area
of supply in accordance with the terms of the licence for distribution and
retail supply of electricity;
3.58.
"Retail Supply Tariff" means the schedule of charges for retail
supply business including the terms and conditions applicable thereto;
3.59.
"Scheduled Generation" at any time or for any given period or time
block means the ex-bus quantum of energy scheduled in MW by the State Load
Despatch Centre to be injected into the grid by a generating plant;
3.60.
"Short-term Open Access Customer" means a person defined as
short-term open access customer in the Open Access Regulations;
3.61.
"State" means State of Punjab;
3.62.
"Station Heat Rate" means the heat energy input in kCal required to
generate one kWh of electrical energy at generator terminals of a thermal
generating plant;
3.63.
"State Load Despatch Centre" or "SLDC" means the centre
established under sub-section (1) of section 31 of the Act;
3.64.
"State Transmission Utility" or "STU" means the Board or
the Government company specified as such by the State Government under
sub-section (1) of Section 39 of the Act;
3.65.
"Terminal Liabilities" means terminal benefits such as
Death-cum-Retirement Gratuity, Ex-Gratia, Pension including Family Pension,
Commuted Pension, Leave Encashment, LTC, Dearness relief, Interim relief,
Medical reimbursement including fixed medical allowance in respect of
pensioners;
3.66.
"Transmission Licensee" means a person granted a license for
intra-state transmission of electricity in the State and includes any person
deemed to be a Transmission Licensee for intra-state transmission of
electricity (including dedicated transmission lines though operating in two
States but primarily for the conveyance of power with reference to the State);
3.67.
"Unit" in relation to a thermal power generating plant means steam
generator, turbine-generator and its auxiliaries, or in relation to a combined
cycle thermal power generating plant, means turbine-generator and its
auxiliaries; and in relation to a hydro generating station means
turbine-generator and its auxiliaries;
3.68.
"Wheeling" means the operation whereby the distribution system and
associated facilities of a Transmission Licensee or Distribution Licensee, as
the case may be, are used by another person for the conveyance of electricity
on payment of charges to be determined under section 62 of the Act;
3.69.
"Wheeling Business" means the business of operating and maintaining a
distribution system for conveyance of electricity in the area of supply of a
Distribution Licensee;
3.70.
"Wheeling Charges" means the schedule of charges for wheeling
business including the terms and conditions applicable thereto;
3.71.
"Year" means the financial year ending on 31st March;
(a)
"Current Year" means a year in
which the petition for aggregate revenue requirement or determination of tariff
is to be filed;
(b)
"Ensuing Year" means the year
immediately following the current year; and
(c)
"Previous Year" means the year
immediately preceding the current year.
Save as aforesaid and unless
repugnant to the context or the subject-matter otherwise required, words and
expressions used in these Regulations and not defined, but defined in the Act,
or the Central Commission's Regulations or any other Regulation of this
Commission shall have the meaning assigned to them respectively in the Act or
the Central Commission's Regulations or any other Regulations of this
Commission. Expressions used herein but not specifically defined in the
Regulations or in the Acts or any law passed by a competent legislature shall
have the meaning as is generally assigned in the electricity industry.
PART
II FRAMEWORK AND GUIDING
PRINCIPLES
Regulation - 4. General.
4.1.
The Commission in specifying these
Regulations is also guided by the principles contained in the National
Electricity Policy and the Tariff Policy notified by the Central Government
under Section 3 of the Act.
4.2.
The norms specified under these
Regulations are the ceiling norms and this shall not preclude the generating
company and/or licensee or any other person, as the case may be, from agreeing
to improved norms of operation. In case the improved norms are agreed to, such
norms shall be applicable for determination of tariff.
4.3.
The Distribution Licensee also carrying
out the generation business shall prepare separate Annual Accounts for each of
its businesses, namely, for generation (for each of the generating plant),
wheeling and retail supply, as the case may be:
Provided that till such time
as separate annual accounts are available, allocation statement as provided in
these Regulations 5, 6 and 7 shall be applicable.
4.4.
The implementation of Multi-Year Tariff
framework shall be based on the following:
(a)
Business Plan including Capital Investment
Plan shall be submitted by the Petitioner for its generation, transmission,
SLDC and/or distribution business, as the case may be, in accordance with Regulation
9;
(b)
Forecast for each year of the Control Period,
based on reasonable assumptions, of various financial and operational
parameters of ARR to be filed by the Petitioner for its generation,
transmission, SLDC and/or distribution business, as the case may be, in
accordance with Regulation 56;
(c)
Trajectory for specific variables may be
stipulated by the Commission, where the performance of the Petitioner is sought
to be improved, subject to provisions of Regulation 29;
(d)
Mechanism for sharing approved gains or
losses on account of controllable and uncontrollable items in accordance with
Regulation 29.
4.5.
The Commission shall specify ARR for
each year of the Control Period and tariff for the first year of the Control
Period for each business separately. However, the Commission may specify
indicative tariff for the remaining years of the Control Period in the MYT
order.
4.6.
The tariff applicable to each business
in each such year will be determined taking into consideration the following:
(a)
Specified Performance Targets;
(b)
True Up of Uncontrollable Items.
4.7.
Losses on account of controllable items
or normative parameters will not be passed on to the consumers except where the
Commission otherwise considers appropriate to allow such variations on justification
to be provided by the petitioner or for reasons provided in Regulation 8:
Provided that the performance parameters, whose trajectories have been
specified in these Regulations or as approved by the Commission in the Business
Plan or the Multi Year Tariff Order, shall form the basis for projection of
these performance parameters in the Aggregate Revenue Requirement for the
entire Control Period.
Regulation - 5. Segregation of ARR Of Generation and Distribution Businesses.
5.1.
The Distribution Licensee also carrying
out the generation business shall segregate the accounts of the Company into
generation business (separate for each of the generating plant) and
distribution business. The Distribution Licensee, based on segregated accounts,
shall submit separate ARRs for generation and distribution businesses. The ARR
for generation shall be used to determine generation tariff and the ARR for
distribution business to determine wheeling charges and retail tariffs.
5.2.
Until accounts are segregated, Distribution
Licensee shall prepare an Allocation Statement to apportion costs and revenues
to respective businesses.
5.3.
The Allocation Statement shall be
considered by the Commission only if it is certified by the Statutory
Auditor/Cost Auditor and approved by the Board of Directors of the Distribution
Licensee, and it shall be accompanied with an explanation of the methodology
which shall be consistent over the Control Period.
Regulation - 6. Segregation of ARR of Wheeling and Retail Supply Business.
6.1.
The Distribution Licensee shall
segregate the accounts of the distribution business into wheeling business and
retail supply business. The ARR for wheeling business shall be used to
determine Wheeling Charges and the ARR for retail supply business to determine
Retail Supply Tariffs.
6.2.
Until accounts are segregated, the
Allocation Statement shall be applicable as per Annexure "A".
How ever, the Distribution
Licensee could revise it based on actual data and prepare an Allocation
Statement to apportion costs and revenues to respective businesses.
6.3.
The Allocation Statement, certified by
the Statutory Auditor/Cost Auditor and approved by the Board of Directors of
the Distribution Licensee, shall be accompanied with an explanation of the
methodology which shall be consistent over the Control Period.
Regulation - 7. Segregation of ARR of SLDC and Transmission Business.
7.1.
The STU shall have separate accounts for
SLDC and transmission business. The STU, based on segregated accounts, shall
submit separate ARR for SLDC and transmission businesses. The ARR for SLDC
shall be used to determine SLDC Charges and the ARR for transmission business
shall be used to determine transmission charges.
7.2.
Until accounts are segregated, STU
shall prepare an Allocation Statement to apportion costs and revenues to
respective businesses.
7.3.
The Allocation Statement shall be
considered by the Commission only if it is certified by the Statutory
Auditor/Cost Auditor and approved by the Board of Directors of the STU, and it
shall be accompanied with an explanation of the methodology which shall be
consistent over the Control Period.
Regulation - 8. Mytapproach.
8.1.
Baseline Values
(a)
The baseline values for the Control Period
shall be determined by the Commission and the projections for the Control
Period shall be based on these figures;
(b)
The baseline values shall be inter-alia based
on figures approved by the Commission in the past, last three years'
Audited/Provisional Accounts, estimate of the expected figures for the relevant
year, industry benchmarks/norms and other factors considered appropriate by the
Commission:
Provided further that the
Commission may change the values for Base Year and consequently the trajectory
of parameters for the Control Period, considering the actual figures from
audited accounts.
8.2.
Controllable, Normative and Uncontrollable items of ARR
(a)
For the purpose of this Regulation, the items
of ARR shall be identified as 'controllable', 'normative' and 'uncontrollable'.
The variation on account of uncontrollable items shall be treated as a pass
through subject to validation and approval by the Commission;
(b)
In case of a Force Majeure event, variations
in controllable and normative items shall be allowed to pass-through subject to
validation and approval by the Commission;
(c)
The carrying cost for such variations shall
also be permitted and the applicable interest rate shall be in accordance with
Regulation 24.1;
(d)
The items in the ARR shall be treated as
'controllable', 'normative' and 'uncontrollable' as under:
|
ARR Element
|
'Controllable'/ 'Normative'/'Uncontrollable'
|
|
Rate of Interest on Long Term Loans
|
Uncontrollable
|
|
Quantum of Long-Term Loans
|
Controllable
|
|
Return on Equity
|
Normative
|
|
Depreciation
|
Controllable
|
|
Tax Rate
|
Uncontrollable
|
|
Working Capital Requirement
|
Normative
|
|
Rate of Interest on Working Capital and Carrying Cost
|
Uncontrollable
|
|
O&M Expenses i.e.
Employee cost (excluding terminal liabilities that is
part of employee cost, and exceptional changes in pay scale of employees on
account of pay revision etc.)
Repair and Maintenance costs (excluding expenses made
on account of extraordinary situation etc.)
Administrative and General costs (excluding expenses
made on account of extraordinary situation etc.)
|
Normative*
|
|
Availability
|
Normative
|
|
Plant Load Factor
|
Normative
|
|
Heat Rate
|
Normative
|
|
Auxiliary Consumption
|
Normative
|
|
Secondary Fuel Oil Consumption (SFC)
|
Normative
|
|
Transit Loss of Coal
|
Normative
|
|
Fuel Price
|
Uncontrollable
|
|
GCV of Fuel
|
Uncontrollable
|
|
Distribution Loss
|
Controllable
|
|
Transmission Loss
|
Controllable
|
|
Energy Sales
|
Uncontrollable
(Since this is dependent on the load growth in the
State across various consumer categories)
|
|
Power Purchase (Long-term power purchase/
Medium-term / Short-term quantum)
|
Uncontrollable
|
|
Power Purchase Price
|
Uncontrollable
|
|
Non-Tariff income
|
Uncontrollable
|
*Employee cost, A&G
costs and R&M costs are considered normative as per the formula specified
in Regulation 25 individually. The changes on account of Inflation Index and/or
statutory levies shall be adjusted during the True-up. However, if the actual
expenditure is less than normative, than the allowable expenditure shall be
limited to actual expenditure incurred by the petitioner.
8.3.
Norms
Norms shall be set by the Commission
for the items as mentioned in these Regulations. Besides, trajectory for
specific variables may be stipulated by the Commission where the performance of
the petitioner is sought to be improved subject to provisions of Regulation 29.
8.4.
Forecast of expected Revenue from Tariff
The petitioner shall develop
the forecast of expected revenue from tariff and charges separately for each
business. The petitioner shall provide full details supporting the forecast,
including but not limited to details of past performance, proposed initiatives
for achieving efficiency or productivity gains, technical studies/or secondary
research and contractual arrangements, to enable the Commission to assess the
reasonableness of the forecast.
Regulation - 9. Business Plan Including Capital Investment Plan.
9.1 The Petitioner shall file the Business Plan
including the Capital Investment plan for its Generation, Transmission, SLDC
and/or Distribution businesses, as the case may be for approval of the
Commission on or before 20th August of the year preceding the first year of the
Control Period for a duration covering the entire Control Period.
9.2 The Distribution Licensee carrying out the
Generation Business shall file separate Business Plans for its Generation and
Distribution businesses.
9.3 The Business Plan for Generation Business
shall contain among other things the following:
(a)
Capacity addition / reduction;
(b)
Availability forecasts;
(c)
Future performance targets;
(d)
Proposed efficiency improvement measures;
(e)
R&M of existing generation units/projects
and any other new measures to be initiated for the Generation Business, e.g.;
automation, IT initiatives etc.;
(f)
Capital Investment Plan based on the above;
(g)
Man Power Plan.
9.4 The Business Plan for Transmission Business
shall be based on proposed generation capacity addition, future load forecasts
of the State, planned capacity augmentation by the Central Transmission Utility
(CTU) for the State and shall contain among other things the following:
(a)
Future plans of the company including
efficiency improvement measures proposed to be introduced and technical
requirement such as meeting reactive power requirements;
(b)
Plan for reduction in transmission losses;
(c)
Plan for improvement in quality of
transmission service and reliability, metering arrangements and any other new
measure to be initiated by the Licensee, e.g. automation, IT initiatives etc.;
(d)
Capital Investment Plan based on the above;
(e)
Man Power Plan.
9.5 The Business Plan for Distribution Business
shall be based on load forecast of the State and shall include the following:
(a)
Forecast of category/sub category/slab wise
Sales, Connected Load/Demand and number of consumers;
(b)
Power Procurement Plan in line with Punjab
State Electricity Regulatory Commission (Power Purchase and Procurement Process
of Licensee) Regulations, 2012 as amended from time to time;
(c)
Plan for reduction in Distribution Losses;
(d)
Distribution Transformer burn out rate - base
line value and trajectory for each year of the Control Period;
(e)
Meter burn out rate - base line value and
trajectory for each year of the Control Period;
(f)
Plan / initiatives for energy efficiency,
improvement in quality of supply and reliability, Metering arrangements, New
consumer services, IT initiatives, New scheme for carrying out energy audit,
Improvement in metering and billing including any other new measures to be
initiated by the Licensee, Periodical business satisfaction surveys etc.;
(g)
Capital Investment Plan based on the above;
(h)
Man Power Plan.
9.6 Capital Investment in network expansion in
Transmission and Distribution shall be based on Load Flow studies and in
accordance with the requirements of the State Grid Code.
9.7 The Capital Investment Plan covering the
entire MYT Control Period will be submitted in the following two parts:
(a)
Ongoing schemes/works of the previous MYT
Control Period (i.e. works/schemes which are under construction or where full
payments have not yet been made). All spillover works will be included in this;
(b)
Schemes to be taken up in the order of priority
giving the schedule over the full MYT Control Period. In case it is likely to
take more than 3 years, the likely date of completion should also be given.
This will also include such schemes which were part of the Capital Investment
Plan of the previous MYT Control Period but could not be started and which the
Petitioner considers necessary to take up during the present Control Period.
9.8 The Petitioner shall submit the Detailed
Project Reports (DPRs) for all the schemes as per Part (a) and (b) above which
shall include:
(a)
Purpose of investment;
(b)
Broad Technical Specifications of the
proposed investment and supporting details;
(c)
Capital Structure;
(d)
Capitalization Schedule;
(e)
Financing Plan, including identified sources
of investment;
(f)
Physical targets;
(g)
Cost-benefit analysis;
(h)
Prioritization of proposed Investments:
Provided that DPRs will not
be necessary for schemes under Rs. 10 Crore for Generation and Transmission
Businesses, Rs. 5 Crore for Distribution Business and Rs. 1 Crore for SLDC:
Provided further that the total capital expenditure on non-DPR schemes in any
year should not exceed 20% of that for DPR schemes during that year.
9.9 The capital investment plan shall match with:
(a)
For Generation Business:
(i)
capacity addition during the Control Period;
(ii)
renovation and modernisation of the
generating plant as allowed in CERC Regulations;
(b)
For Transmission Business:
(i)
Nature of investment (evacuation project,
system augmentation, system strengthening, IT related projects etc.);
(ii)
Details of physical parameters of the project
such as circuit-kms, capacity in MVA, location of the project etc.;
(iii)
Break-up of investment in capacitor banks,
reduction in reactive power drawal and transmission losses;
(c)
For Distribution Business:
(i)
Replacement of existing assets;
(ii)
Meeting load growth;
(iii)
Technical loss reduction;
(iv)
Non-technical loss reduction;
(v)
Meeting reactive energy requirements;
(vi)
Customer service improvement;
(vii)
Improvement in quality and reliability of
supply etc.
9.10
In case of existing Generation and Transmission projects, the capital
investment for Renovation and Modernization shall consist of a Detailed Project
Report which will include the following elements:
(a)
Complete scope and justification;
(b)
Estimated life extension;
(c)
Improvement in performance parameters;
(d)
Cost-benefit analysis;
(e)
Phasing of expenditure;
(f)
Schedule of completion;
(g)
Reference price level;
(h)
Estimated completion cost including IDC etc.;
(i)
Other aspects.
9.11
The Capital Investment Plan in case of a new or expansion in an existing
generating station shall also include cost of approved rehabilitation and
resettlement (R&R) plan of the project in conformity with the National
R&R Policy and R&R package.
9.12
In case, the Commission approves lesser amount of capital expenditure than
filed by the Petitioner for approval, the Commission may allow the respective
Petitioner to determine the priority of schemes to be considered within the
approved amount.
9.13
In the normal course, the Commission shall not revisit the approved capital
investment plan during the Control Period. The Licensee shall file details of
the capital expenditure incurred for the preceding financial year by 30th June
of the current financial year to enable the Commission to monitor and review
the progress of the capital expenditure incurred by the Petitioner vis-à-vis
the approved capital expenditure:
Provided that the capital
expenditure incurred shall be only for the schemes as per the approved capital
investment plan.
9.14
In case capital expenditure is required for emergency work which has not been
approved in the capital investment plan, the Petitioner shall submit a petition
(containing all relevant information along with reasons justifying emergency
nature of the proposed work) seeking approval by the Commission. The Petitioner
may take up the work prior to the approval of the Commission provided that the
scheme has been approved by its Board of Directors as being of emergent nature:
Provided that the Petitioner
shall submit the pending details required as per Regulation 9.8 and 9.9 within
10 days of the submission of the petition for emergency work: Provided further
that for the purpose of Regulation 9.11, such approved capital expenditure
shall be treated as a part of actual capital expenditure incurred by the
Petitioner in addition to the capital expenditure already approved by the
Commission.
9.15
In case the capital expenditure incurred for ongoing approved schemes exceeds
the amount as approved in the capital expenditure plan, the balance amount and
the incidental cost shall be trued up by the Commission after prudence check
after the end of Control Period. However, for schemes those are completed shall
be trued up while doing the truing of the respective year. The completed
schemes once trued up shall be considered to attain finality and shall not be
reopened for consideration at the time of true-up of remaining schemes to be
done at end of Control Period
Provided that any additional
capital expenditure incurred on account of time over run and/or unapproved
changes in scope of approved schemes except for reasons beyond the control of
Licensee and duly submitted in writing may not be allowed by the Commission:
Provided that capital expenditure incurred on unapproved schemes and not
covered under Regulation 9.11 shall not be allowed by the Commission.
9.16
The Petitioner shall provide a copy of the proposed Capital Investment Plan for
Generation and/ or Distribution Business, as the case may be, to the State
Transmission Utility (STU) for carrying out planning for network augmentation/ strengthening
at the time of filing of this plan with the Commission. The copy of approved
capital investment plan shall also be sent to the STU by the Petitioner,
immediately after approval by the Commission.
9.17
The petitioner shall extend all cooperation to the STU for providing
data/information required for carrying out the planning activity effectively.
9.18
The STU shall also provide a copy of its capital investment plan to the
Distribution Licensee, at the time of filing of this plan with the Commission.
The copy of approved capital investment plan shall also be sent to the
Distribution Licensee by the STU, immediately after approval by the Commission.
9.19
The Commission shall scrutinize and approve the business plan including capital
investment plan taking into consideration the additional information, if any,
provided by the petitioner and the objections/ suggestions of the key
stakeholders.
Regulation - 10. Multi Year Tariff Petition.
10.1.
The Petitioner shall make a petition for the Multi Year Tariff on or before
30th November of the year preceding the first year of Control Period.
10.2.
The Petitioner shall submit the forecast of Aggregate Revenue Requirement for
each year of the Control Period and tariff proposal for the first Year of the
Control Period, in a manner as provided in these Regulations and in formats
specified by the Commission from time to time. The petition shall be
accompanied by such fee payable, as may be specified by the Commission in the
PSERC (Fee) Regulations 2005 as amended from time to time.
Provided that the petition
shall also be accompanied by the true-up Petition based on the latest available
audited accounts.
10.3.
The Petitioner shall develop the forecast of Aggregate Revenue Requirement
using the assumptions relating to the behaviour of individual variables that
comprise the Aggregate Revenue Requirement during each year of the Control
Period, including inter-alia detailed category-wise sales and demand
projections, power procurement plan, trajectories of parameters specified in
these Regulations and Business Plan, in accordance with guidelines and formats,
as may be specified by the Commission from time to time.
10.4.
The Distribution Licensee shall develop the forecast of Expected Revenue from
existing and proposed Tariff and Charges based on the following:
(a)
Distribution Licensee's estimates of the
quantum of electricity to be supplied to Consumers and to be wheeled on behalf
of distribution system users for the ensuing Financial Year within the Control
Period;
(b)
Prevailing tariff as on the date of making
the petition.
10.5.
Based on the forecast of Aggregate Revenue Requirement for the first Year of
the Control Period and Expected Revenue from Tariff and Charges, the
Distribution Licensee for the Distribution Wires Business and Retail Supply
Business, shall propose the tariff for the first Year of Control Period:
Provided that the tariff
proposed by Distribution Licensee shall be in accordance with Section 62 of the
Electricity Act, 2003 and these Regulations.
10.6.
The Petitioner shall provide full details supporting the forecast, including
but not limited to details of past performance, proposed initiatives for
achieving efficiency or productivity gains, technical studies, contractual
arrangements and/or secondary research, to enable the Commission to assess the
reasonableness of the forecast.
10.7.
The Petitioner shall publish its petition filed for Multi Year Tariff / Annual
Revenue Requirements as required by Conduct of Business Regulations. The
Petitioner shall also display the petition on its official website.
Regulation - 11. Truing-Up and Tariff Determination During the Control Period.
11.1.
The Petitioner shall make a petition for True-up and tariff resetting on or
before 30th November of each year of the Control Period.
11.2.
The Generating Company, Transmission Licensee and Distribution Licensee shall
be subject to truing up of expenses and revenue during the Control Period in
accordance with these Regulations.
11.3.
The Generating Company, Transmission Licensee and Distribution Licensee shall
file a petition for truing up of the previous Year or the Year for which the
audited accounts are available and determination of tariff for the ensuing Year
on or before 30th November of each Year, in formats specified by the Commission
from time to time.
11.4.
The Petitioner shall publish its petition filed for Truing Up and Tariff
Determination as required by Conduct of Business Regulations. The Petitioner
shall also display the petition on its official website.
11.5.
The scope of the truing up and tariff determination shall be a comparison of
the performance of the Generating Company, Transmission Licensee or
Distribution Licensee with the approved forecast of Aggregate Revenue
Requirement and Expected Revenue from Tariff and Charges and shall comprise of
the following:
(a)
True-up: a comparison of the audited
performance of the Petitioner for the Financial Year for which the True-up is
being carried out with the approved forecast for such previous Financial Year,
subject to prudence check in accordance with Regulation 12;
(b)
Tariff determination for the ensuing Year of
the Control Period based on the revised forecast of the Aggregate Revenue
Requirement for the Year;
(c)
Review of compliance with directives issued
by the Commission from time to time;
(d)
Other relevant details, if any.
11.6.
The Petitioner shall provide any other information, as may be asked for by the
Commission with a view to assess the reasons and extent of any variation in the
performance from the approved forecast and the need for tariff resetting.
11.7.
The Commission shall review the petition made under the preceding clauses based
on the same principles as approved in the MYT Order on original petition for
determination of ARR and Tariff and upon completion of such review, either
approve the proposed modification(s) with such changes as it deems appropriate,
or reject the petition for reasons to be recorded in writing.
Regulation - 12. True Up.
12.1.
Truing up of the ARR of the previous year shall be carried out and shall be
adjusted in the ARR of the next year of the Control Period.
12.2.
Truing up of uncontrollable items shall be carried out at the end of each year
of the Control Period based on prudence check.
12.3.
Truing-up exercise will be undertaken only when audited accounts for the
year(s) under consideration have been made available. The approved aggregate
gain or loss for each business on account of controllable items will be subject
to provisions of Regulation 8 and Regulation 29.
12.4.
Capital Expenditure, Capitalisation and associated ARR items shall be normally
trued up at the end of the Control Period in accordance with Regulation 9,
while Distribution Loss and Transmission Loss shall be trued up every year
along with truing up of ARR based on prudence check.
12.5.
In case of any change in the approved amounts (positive or negative) during the
True-up exercise, the Commission shall consider the approved carrying cost as a
separate item of the ARR.
12.6.
The Commission may allow/recover the carrying cost for the trued up amount at
the interest rate mentioned in Regulation 24.1:
Provided that no carrying
cost shall be permitted for the period of delay in filing of True-up on account
of non-submission of audited accounts due to the fault of the utility: Provided
further that if the Commission determines an over recovery by the Licensee
during the True-up, carrying cost for such trued up amount shall be recovered
from the Petitioner.
Regulation - 13. Review at the end of the Control Period.
13.1.
At the end of the Control Period, the Commission shall review the achievement
of objectives and implementation of the principles of MYT laid down in these
Regulations.
13.2.
To meet the objectives of the Act, the National Electricity Policy and Tariff
Policy, the Commission may revise the principles of MYT for the subsequent
Control Period.
13.3.
The end of the third Control Period shall be the beginning of the fourth
Control Period. The Petitioner shall follow the same procedure for the next
Control Period unless required otherwise by the Commission. The Commission
shall analyse the performance with respect to the norms set out at the
beginning of the Control Period in the MYT order and shall determine the base
values for the next Control Period, based on actual performance achieved,
expected improvement and other relevant factors.
PART
III COMPONENTS
OF ARR AND TARIFF FOR GENERATION, TRANSMISSION, SLDC AND DISTRIBUTION
BUSINESSES
Regulation - 14. Components of Tariff for Generation Business.
14.1.
The tariff for sale of electricity from a generating plant (Thermal and Hydel)
shall be as follows:
(a)
Thermal Generating Plant
The tariff for supply of electricity
from a Thermal Power Generating Station shall comprise of two parts, namely,
capacity charge (for recovery of the Annual Fixed Cost) and Energy Charges (for
recovery of primary and secondary fuel cost).
(b)
Hydel Generating Plant
The tariff for supply of
electricity from a Hydro Power Generating Station shall comprise of capacity
charge and energy charge to be derived in the manner specified for recovery of
Annual Fixed Cost.
14.2.
Both the components shall be worked out in the manner provided in Regulations
36 and 37.
14.3.
The Annual Fixed Cost of a generating plant (thermal or hydro) shall include
the following elements:
(a)
Return on Equity;
(b)
Interest and Finance Charges on Loan Capital;
(c)
Interest Charges on Working Capital;
(d)
Depreciation;
(e)
Operation and Maintenance Expenses;
(f)
Statutory levies and taxes, if any. Less:
(g)
Non-Tariff Income
(h)
Income from other business
14.4.
The Energy Charges (or Variable Charges) of a thermal generating station shall
consist of primary fuel cost and secondary fuel cost.
14.5.
The tariff for supply of electricity from a thermal and hydro generating
station shall be derived in the manner specified in Regulations 36 and 37.
14.6.
Approval of provisional tariff for a generating station - A Generating Company
may also file a petition, not more than six months prior to the anticipated
Date of Commercial Operation (COD), for determination of provisional tariff of
the Unit or Stage or Generating Station as a whole, as the case may be, based
on the capital expenditure actually incurred up to the date of making the
petition or a date prior to making of the petition, duly audited and certified
by the statutory auditors and the provisional tariff shall be charged from the
date of commercial operation of such Unit or Stage or Generating Station, as
the case may be:
Provided that the Generating
Company shall file a fresh petition in accordance with these Regulations, for
determination of final tariff based on actual capital expenditure incurred up
to the date of commercial operation of the Generating Station duly certified by
the statutory auditors based on Annual Audited Accounts:
Provided further that any
difference in provisional tariff and the final tariff determined by the
Commission and not attributable to the Generating Company may be adjusted at
the time of determination of final tariff for the following year as directed by
the Commission.
Regulation - 15. Components of ARR and Charges for Transmission and SLDC Business.
15.1.
The ARR of the Transmission business and SLDC business shall comprise of the
following components:
(a)
Return on Equity;
(b)
Interest and Finance Charges on Loan Capital;
(c)
Interest Charges on Working Capital;
(d)
Depreciation;
(e)
Operation and Maintenance Expenses;
(f)
ULDC Charges;
(g)
Statutory levies and taxes, if any. Less:
(h)
Non-Tariff Income
(i)
Income from other business
15.2.
The Intra-state Transmission Charge shall include the following components:
(a)
Transmission Charges or Network Usage Charges
to reflect the cost of owning (Capital Investment), servicing and maintaining
the transmission assets in order to transfer bulk power to and from different
locations. The Network Usage Charges or Transmission Tariff, payable by the
beneficiaries of the Transmission System shall be designed to recover the
Aggregate Revenue Requirement approved by the Commission for each year of the
Control Period;
(b)
Reactive Power Charges to reflect the voltage
related drawal of reactive power. Reactive power charges shall be levied as per
the relevant provisions of Punjab State Electricity Regulatory Commission (Grid
Code) Regulations, 2013, as amended from time to time.
15.3.
The SLDC Charges or System Operation Charge shall consist of the cost of
operating the State Load Dispatch Centre (SLDC) including the cost of owning
& maintaining it. These shall be levied as SLDC charges upon the
beneficiaries/users of the services of SLDC in accordance with the provisions
of these Regulations.
Regulation - 16. Components of Tariff for Distribution Business.
16.1
The ARR of the wheeling and retail supply shall comprise the following
components:
|
For Wheeling Charges
|
For Retail Supply Charges
|
|
A
|
A
|
|
(a) Interest and finance charges including Interest on
security deposits as allocated
|
(a) Interest and finance charges including Interest on
security deposits as allocated
|
|
(b) Depreciation
|
(b) Depreciation
|
|
(c) Operation and Maintenance Expenses
|
(c) Operation and Maintenance Expenses
|
|
(d) Return on Equity
|
(d) Return on Equity
|
|
(e) Interest on Working Capital
|
(e) Interest on Working Capital
|
|
(f) Statutory levies and taxes, if any
|
(f) Cost of Power Purchase
|
|
|
(g)Transmission charges including RLDC/SLDC Charges
|
|
|
(h) Wheeling Charges
|
|
|
(i) Bad and doubtful debts
|
|
|
(j) Statutory levies and taxes, if any
|
|
Total (A)
|
Total (A)
|
|
Less
|
Less
|
|
B
|
B
|
|
(a) Non-Tariff income
|
(a) Non-Tariff income
|
|
(b) Income from other business, to the extent specified
for wheeling tariff
|
(b) Income from other business
|
|
|
|
|
Total (B)
|
Total (B)
|
|
ARR = (A)-(B)
|
ARR = (A)-(B)
|
16.2 The tariff for sale of electricity by Distribution Licensee for its
distribution business shall comprise of two parts, namely,
(a)
Fixed /Demand Charge;
(b)
Energy / Variable Charge.
PART
IV GENERAL PRINCIPLES
FOR DETERMINATION OF COMMON ELEMENTS OF ARR AND TARIFF OF GENERATION,
TRANSMISSION, SLDC AND DISTRIBUTION BUSINESSES
Regulation - 17. Capital Cost.
17.1.
The Capital cost of the generating station or the transmission system, as the
case may be, as determined by the Commission after prudence check in accordance
with these Regulations shall form the basis for determination of tariff for
existing and new projects.
17.2.
The Capital Cost of a new project shall include the following:
(a)
The expenditure incurred or projected to be
incurred up to the date of commercial operation of the project;
(b)
Interest during construction and financing
charges, on the loans (i) being equal to 70% of the funds deployed, in the
event of the actual equity in excess of 30% of the funds deployed, by treating
the excess equity as normative loan, or (ii) being equal to the actual amount
of loan in the event of the actual equity less than 30% of the funds deployed;
(c)
capitalised initial spares subject to the
ceiling rates specified in this Regulation;
(d)
additional capitalisation determined under
Regulation 18;
(e)
Any gain or loss on account of foreign exchange
rate variation pertaining to the loan amount availed during the construction
period; and
(f)
Interest during construction and incidental
expenditure during construction as computed in accordance with these
Regulations.
17.3.
The capital cost may include initial spares capitalised as a percentage of the
Plant and Machinery cost up to the cut-off date subject to the following
ceiling norms:
(a)
In case of a generating plant:
|
Coal-based generating plants:
|
4.0%
|
|
Gas turbine/combined cycle generating plants:
|
4.0%
|
|
Hydro generating plants:
|
4.0%
|
(b)
In case of transmission business:
|
Transmission Line:
|
1.0%
|
|
Transmission Substation:
|
|
|
-Green Field
|
4.0%
|
|
-Brown Field
|
6.0%
|
|
Series compensation device and HVDC Station:
|
4.0%
|
|
Gas Insulated sub-station (GIS)
|
5.0%
|
|
Communication System
|
3.5%
|
|
Static Synchronous Compensator
|
6.0%
|
Provided that where the emission control system is installed, the norms of
initial spares specified in this Regulation for coal or lignite based thermal
generating station as the case may be, shall apply.
Provided that where the
power purchase agreement entered into between the Distribution Licensee and the
Generating Company provides a ceiling of actual expenditure, the capital
expenditure shall not exceed such ceiling for determination of tariff:
Provided further that
Distribution Licensee or a Generating Company including Independent
Power Producers (IPPs) who
intend to establish, operate and maintain a new generating plant may make a
petition before the Commission for 'in principle' acceptance of the project
capital cost and financing plan before taking up a project. The petition shall
contain information regarding salient features of the project including the
capacity, location, site specific features, fuel, beneficiaries, break-up of
the capital cost estimates, financial package, schedule of commissioning,
reference price level, estimated completion cost including foreign exchange
components, if any, consent of beneficiary Licensees to whom the electricity is
proposed to be sold etc.: Provided also that where the Commission has given 'in
principle' acceptance to the estimates of project capital cost and financing
plan, the same shall be the guiding factor for applying prudence check on the
actual capital expenditure:
Provided also that in case
of the existing generating plants/transmission projects/distribution business,
the capital cost admitted by the Commission prior to the effective date and
additional capital expenditure projected to be incurred for respective years of
the Control Period as may be admitted by the Commission, shall form the basis
for determination of capital cost.
17.4.
In relation to multi-purpose hydro schemes, with irrigation, flood control and
power components, the capital cost chargeable to the power component of the scheme
only shall be considered for determination of tariff.
17.5.
The Commission may get the capital cost of hydro-electric projects vetted by an
independent agency or expert and in that event the capital cost as vetted by
such agency or expert may be considered by the Commission while determining the
tariff for the hydro generating station.
17.6.
Capital Cost to be allowed for the purpose of determination of tariff will be
based on the Capital Investment Plan approved by the Commission
17.7.
The revenue earned from sale of infirm power in excess of fuel cost prior to
the COD, shall be adjusted against the Capital Cost as specified under
Regulation 33.
17.8.
The amount of any capital contribution made by consumers in the context of
deposit works, open access customers, Govt. subsidy/grants/aid towards work
received without any obligation to return the same and with no interest costs
attached for release of connections/providing of power system, including
connectivity to the distribution system or to the transmission system, as the
case may be, shall be deducted from the original cost of the project of the
respective Petitioner, for the purpose of calculating the amount under debt and
equity under these Regulations.
Regulation - 18. Additional Capitalization.
18.1.
The Capital Expenditure incurred or projected to be incurred, on the following
counts within the original scope of work, after the Date of Commercial
Operation and up to the cut-off date may be admitted by the Commission, subject
to prudence check:
(a)
Un-discharged/Deferred liabilities;
(b)
Works deferred for execution;
(c)
Liabilities to meet award of arbitration or
for compliance of the order or decree of a court;
(d)
On account of change of law:
Provided that the details
included in the original scope of work along with estimates of expenditure,
deferred liabilities and the works deferred for execution shall be submitted
along with the petition for determination of tariff.
(e)
Procurement of initial capital spares in the
original scope of work, subject to ceiling mentioned in Regulation 17.3:
Provided that the details of
work included in the original scope of work along with estimates of
expenditure, un-discharged liabilities and works deferred for execution shall
be submitted along with the petition for determination of tariff after the date
of commercial operation of the project.
18.2.
The Capital Expenditure of the following nature actually incurred after the
cut-off date may be admitted by the Commission subject to prudence check:
(a)
Un-discharged/Deferred liabilities relating
to works/services within the original scope of work;
(b)
Liabilities to meet award of arbitration or
for compliance of the order or decree of a court;
(c)
On account of change of law;
(d)
Any additional works/services which have
become necessary for efficient and successful operation of the project, but
were not included in the original project cost; and
(e)
In case of hydro generating stations, any
expenditure which has become necessary on account of damage caused by natural
calamities (but not due to flooding of power house attributable to the
negligence of the Generating Company) including due to geological reasons after
adjusting for proceeds from any insurance scheme, and expenditure incurred due
to any additional work which has become necessary for successful and efficient
plant operation: Provided that any expenditure on acquiring the minor items or
the assets like tools and tackles, furniture, air-conditioners, voltage
stabilizers, refrigerators, coolers, fans, washing machines, heat convectors,
mattresses, carpets etc. brought after the cut-off date shall not be considered
for additional capitalisation for determination of tariff w.e.f. the date of
the start of first year of the Control Period.
Provided further that if any
expenditure has been claimed under Renovation and Modernisation (R&M) or
repairs and maintenance under (O&M) expenses, same expenditure cannot be
claimed under this Regulation.
18.3.
Impact of additional capitalization in tariff revision within the approved
project cost shall be considered by the Commission once during a particular
year.
18.4.
In case of transmission business, any additional expenditure on items such as
relays, control and instrumentation, computer system, communication system, DC
batteries, replacement of switchyard equipment due to increase of fault level,
emergency restoration system, insulators cleaning infrastructure, replacement
of damaged equipment not covered by insurance and any other expenditure which
has become necessary for successful and efficient operation of transmission
system may be admitted by the Commission:
Provided that any
expenditure on acquiring the minor items or the assets like tools and tackles,
furniture, air-conditioners, voltage stabilizers, refrigerators, coolers, fans,
washing machines, heat convectors, mattresses, carpets etc. bought after the
cut-off date shall not be considered for additional capitalization for
determination of tariff.
18.5.
Any expenditure admitted on account of committed liabilities within the
original scope of work and the expenditure deferred on techno-economic grounds
but falling within the original scope of work shall be serviced in the
normative debt-equity ratio specified in this Regulation.
18.6.
Any expenditure on replacement of old assets or renovation and modernization or
life extension shall be considered on normative debt-equity ratio specified in
this Regulation after writing off the entire value of the original assets from
the original capital cost of the asset replaced.
18.7.
Any expenditure admitted by the Commission for determination of tariff on
account of new works not in the original scope of work shall be serviced in the
normative debt-equity ratio specified in this Regulation.
Regulation - 19. Debt Equity Ratio.
19.1.
Existing Projects - In case of the capital expenditure projects having
Commercial Operation Date prior to the effective date, the debt-equity ratio
shall be as allowed by the Commission for determination of tariff for the
period prior to the effective date:
Provided that the Commission
shall not consider the increase in equity as a result of revaluation of assets
(including land) for the purpose of computing return on equity.
19.2.
New Projects - For capital expenditure projects declared under commercial
operation on or after the effective date:
(a)
A Normative debt-equity ratio of 70:30 shall
be considered for the purpose of determination of Tariff;
(b)
In case the actual equity employed is in
excess of 30%, the amount of equity for the purpose of tariff determination
shall be limited to 30%, and the balance amount shall be considered as
normative loan;
(c)
In case, the actual equity employed is less
than 30%, the actual debt-equity ratio shall be considered;
(d)
The premium, if any raised by the Petitioner
while issuing share capital and investment of internal accruals created out of
free reserve, shall also be reckoned as paid-up capital for the purpose of
computing return on equity subject to the normative debt-equity ratio of 70:30,
provided such premium amount and internal accruals are actually utilized for
meeting capital expenditure of the Petitioner's business.
19.3.
Renovation and Modernization: Any approved capital expenditure incurred on
Renovation and Modernization including the approval in the Capital Investment
plan shall be considered to be financed at normative debt-equity ratio of
70:30. If the actual equity employed is less than 30% then the actual debt
equity ratio shall be considered.
Regulation - 20. Return on Equity.
Return on equity shall be
computed at the base rate of 15.5% for thermal generating stations,
Transmission Licensee, SLDC
and run of the river hydro generating stations and at the base rate of 16.5%
for the storage type hydro generating stations and run of river generating
stations with pondage and 16% for Distribution Licensee on the paid-up equity
capital determined in accordance with Regulation 19:
Provided that Equity
invested in foreign currency shall be converted to rupee currency based on the
exchange rate prevailing on the date(s) it is subscribed:
Provided further that assets
funded by consumer contributions, capital subsidies/Govt. grants shall not form
part of the capital base for the purpose of calculation of Return on Equity.
Regulation - 21. Depreciation.
For the purpose of tariff
determination, depreciation shall be calculated in the following manner:
21.1.
The value base for the purpose of depreciation shall be the capital cost of the
assets admitted by the Commission: Provided that the depreciation shall be
allowed after reducing the approved original cost of the retired or replaced or
decapitalized assets:
Provided that the land,
other than the land held under lease and land for reservoir in case of hydro
generating station, shall not be a depreciable asset and its cost shall be
excluded from the capital cost while computing depreciable value of the assets:
Provided further that Govt.
grants and consumer contribution shall also be recognized as defined under
Indian Accounting Standard 20 (IND AS 20) notified by the Ministry of Corporate
Affairs.
21.2.
The residual/salvage value of the asset shall be considered as 10% and
depreciation shall be allowed up to maximum of 90% of historical capital cost
of the asset:
Provided that I.T. Equipment
and Software shall be depreciated 100% with zero salvage value.
21.3.
The Cost of the asset shall include additional capitalization.
21.4.
The Generating Company, Transmission and Distribution Licensee shall provide
the list of assets added during each Year of the Control Period and the list of
assets completing 90% of depreciation in the Year along with Petition for,
true-up and tariff determination for ensuing Year.
21.5.
Depreciation for Distribution, generation and transmission assets shall be
calculated annually as per straight line method over the useful life of the
asset at the rate of depreciation specified by the Central Electricity
Regulatory Commission from time to time:
Provided that the remaining
depreciable value as on 31st March of the year closing after a period of 12
years from date of commercial operation/put in use of the asset shall be spread
over the balance useful life of the assets:
Provided further that in
case of hydro generating stations, the salvage value shall be as provided in
the agreement signed by the developers with the State Government for creation
of the asset.
21.6.
Depreciation shall be chargeable from the first year of commercial
operation/asset is put in use. In case of commercial operation of the asset/put
in use of asset for part of the year, depreciation shall be charged on pro rata
basis.
Regulation - 22. Foreign Exchange Rate Variation.
22.1.
The Petitioner may hedge foreign exchange exposure in respect of the interest
on foreign currency loans and repayment of foreign loans acquired for the
generating station, transmission system or distribution system, as the case may
be, in part or full at the discretion of the Petitioner.
22.2.
The Petitioner shall recover the cost of hedging of foreign exchange rate
variation corresponding to the normative foreign debt, in the relevant year on
year-to-year basis as expense in the period in which it arises and extra rupee
liability corresponding to such foreign exchange rate variation shall not be
allowed against the hedged foreign debt.
22.3.
To the extent the Petitioner is not able to hedge the foreign exchange
exposure, the extra rupee liability towards interest payment and loan repayment
corresponding to the normative foreign currency loan in the relevant year shall
be permissible provided it is not attributable to the Petitioner or its
contractors.
22.4.
The Petitioner shall recover the cost of hedging and foreign exchange rate
variation on year-to-year basis as income or expense in the period in which it
arises.
Regulation - 23. Interest on Loan Capital.
23.1.
For existing loan capital, interest and finance charges on loan capital shall
be computed on the outstanding loans, duly taking into account the actual rate
of interest and the schedule of repayment as per the terms and conditions of
relevant agreements. The rate of interest shall be the actual rate of interest
paid/payable (other than working capital loans) on loans by the Licensee.
23.2.
Interest and finance charges on the future loan capital for new investments
shall be computed on the loans, based on one (1) year State Bank of India (SBI)
MCLR / any replacement thereof as notified by RBI as may be applicable as on
1st April of the relevant year, plus a margin determined on the basis of
current actual rate of interest of the capital expenditure loan taken by the
Generating Company, Licensee or SLDC and prevailing SBI MCLR.
23.3.
The repayment for each year of the tariff period shall be deemed to be equal to
the depreciation allowed for the corresponding year. In case of
de-capitalisation of assets, the repayment shall be adjusted by taking into
account cumulative depreciation made to the extent of de-capitalisation.
23.4.
The Commission shall allow obligatory taxes on interest, finance charges
(including guarantee fee payable to the Government) and any exchange rate
difference arising from foreign currency borrowings, as finance cost.
23.5.
The interest on excess equity treated as loan shall be serviced at the weighted
average interest rate of actual loan taken from the lenders.
Provided also that if there
is no actual loan for a particular Year but normative loan is still
outstanding, the last available weighted average rate of interest for the
actual loan shall be considered.
Regulation - 24. Rate of Interest on Working Capital and Security Deposit.
24.1.
The rate of interest on working capital shall be equal to the actual rate of
interest paid on working capital loans by the Licensee/Generating Company/SLDC
or the one (1) Year State Bank of India (SBI) MCLR / any replacement thereof as
notified by RBI as may be applicable as on 1st April of the relevant year plus
250 basis points, whichever is lower. The interest on working capital shall be
payable on normative basis notwithstanding that the Licensee/Generating
Company/ SLDC has not taken working capital loan from any outside agency or has
exceeded the working capital loan amount worked out on the normative figures.
24.2.
Interest on security deposits made by the consumers with a Licensee, if any,
shall be considered at the rate specified by the Commission from time to time
and allowed as an item of expense in the ARR of the Distribution Licensee.
Regulation - 25. Operation and Maintenance (O&M) Expenses.
25.1.
The O&M expenses for the nth year of the Control Period shall be approved
based on the formula shown below:
O&Mn =
(R&Mn + EMPn + A&Gn) x (1-Xn)
Where,
§ R&Mn -Repair
and Maintenance Costs of the Petitioner for the nth year;
§ EMPn -Employee
Cost of the Petitioner for the nth year;
§ A&Gn -Administrative
and General Costs of the Petitioner for the nth year;
It should be ensured that
all such expenses capitalized should not form a part of the O&M expenses
being specified here. The above components shall be computed in the manner
specified below:
(i)
R&Mn= K*GFA*WPIn/WPIn-1
Where,
§ 'K' is a constant (expressed in %) governing the
relationship between R&M costs and Gross Fixed Assets (GFA) for
the nth year. The value of 'K' will be specified by the Commission in the MYT
order.
§ 'GFA' is the average value of the gross fixed
assets of the nth year.
§ WPIn means the average rate (on monthly basis) of
Wholesale
Price Index (all commodities) over the year for the nth year.
(ii)
EMPn+ A&Gn= (EMPn-1
+ A&Gn-1)*(INDEXn/INDEX n-1)
INDEXn - Inflation Factor to
be used for indexing the Employee Cost and Administrative and General Costs for
nth year. This will be a combination of the Consumer Price Index (CPI) and the
Wholesale Price Index (WPI) of nth year and shall be calculated as under:-INDEXn =
0.50*CPIn + 0.50*WPIn
'WPIn' means the average
rate (on monthly basis) of Wholesale Price Index (all commodities) over the
year for the nth year.
'CPIn' means the average
rate (on monthly basis) of Consumer Price Index (Industrial workers) over the
year for the nth year.
Note 1: The O&M expenses
of BBMB for the entire Control Period shall be projected separately based on
the latest actual payout. The Commission shall true-up the O&M expenses of
BBMB based on the actual payout. The O&M expense of BBMB shall be treated
as uncontrollable cost item. However, when CERC determines the tariff in
respect of generating plants/units of BBMB, the Commission shall consider the
same
Note 2: For the purpose of
estimation, the same WPIn and CPIn values shall
be used for all years of the Control Period. However, the Commission will
consider the actual values of the WPIn and CPIn at
the end of each year during the True-up the R&M Expenses, Employee Cost and
A&G Expenses on account of this variation.
Note 3: O&M expense
shall be allowed on normative basis or actual whichever lower and shall be
trued-up only to the account of variation in Wholesale Price Index and Consumer
Price Index.
Note 4: Terminal Liabilities
such as death-cum-retirement gratuity, Ex-Gratia, pension including family
pension, commuted pension, leave encashment, LTC, medical reimbursement
including fixed medical allowance in respect of the State PSU / Government
pensioners will be approved as per the actuals paid by the Petitioner.
Note 5: O&M expenses
made on account of extraordinary situations (if any) shall be submitted to
Commission for its approval. Such expenses shall be filed separately and will
not be subjected to provisions of Regulation 29. The amount approved by the
Commission shall be trued up.
Note 6: Exceptional increase
in employee cost on account of Pay Commission based revision for State PSU /
Government employees will be considered separately by the Commission.
Note 7: Any expenditure on
account of license fee, initial or renewal, fee for determination of tariff and
audit fee shall be allowed on actual basis, over and above the A&G expenses
approved by the Commission.
Note 8: O&M expenses of
assets taken on lease/hire-purchase and those created out of the consumers'
contribution shall be considered in case the Generating Company or the Licensee
has the responsibility for its operation and maintenance and bears O&M
expenses.
Note 9: With regard to
unfunded past liabilities of pension and gratuity, the Commission will follow
the principle of 'pay as you go'. The Commission shall not allow any other
amount towards creating fund for meeting unfunded past liability of pension and
gratuity.
Note 10: O&M expenses
for gross fixed assets added during the year, if not accounted already, shall
be considered from the date of commissioning on pro-rata basis.
(iii)
Xn is an efficiency factor
for nth year
The Value of Xn shall
be determined by the Commission in it MYT order for the Control Period.
Regulation - 26. Prior Period Expenses.
26.1.
The Petitioner shall submit to the Commission the prior period expenses as a
part of the filing for ARR and True Up;
26.2.
The Commission shall allow prior period expenses for uncontrollable cost items
only as per the audited accounts, during the ARR and True Up.
Regulation - 27. Non Tariff Income.
27.1.
The following components of income shall be treated as non-tariff income for
the generation, transmission, SLDC and distribution businesses, as applicable:
(a)
Meter/metering equipment rentals;
(b)
Service line charges;
(c)
Net revenue from late payment surcharge (late
payment surcharge less financing cost of late payment surcharge);
(d)
Interest on advances to
suppliers/contractors;
(e)
Interest on staff loans and advances;
(f)
Income from trading;
(g)
Income from staff welfare activities;
(h)
Excess found on physical verification;
(i)
Interest on investments, fixed and call
deposits and bank balances;
(j)
Net recovery from penalty on coal liaison
agents;
(k)
Prior period income;
(l)
Income from open access charges i.e. petition
fee, cross subsidy surcharge, additional surcharge, transmission and/or
wheeling charges, scheduling charges etc.;
(m)
Miscellaneous receipts and any other income
not included above; The Petitioner shall submit full details of its forecast of
non-tariff income to the Commission as a part of ARR filing. The amount
received by the Petitioner on account of non-tariff Income shall be deducted
from the aggregate revenue requirement for calculating the net revenue
requirement of Petitioner's business.
Regulation - 28. Income of other Business.
The Petitioner may engage in
any other business, with prior intimation to the Commission for optimum
utilization of its generation, transmission or distribution assets, as the case
may be. Such instances and transaction shall be governed in accordance with the
Punjab State Electricity Regulatory Commission (Income of Other Businesses)
Regulations, 2005, as amended from time to time.
Regulation - 29. Sharing of Gains and Losses on Account of Controllable and Uncontrollable Factors.
29.1.
The approved aggregate gain or loss to the Petitioner on account of
uncontrollable factors shall be allowed as an adjustment in the ARR of the
Petitioner over such period as may be specified in the Order of the Commission.
29.2.
Nothing contained in Regulation 29.1 above shall apply in respect of any gain
or loss arising out of variations in the price of fuel, which shall be dealt as
per Punjab State Electricity Regulatory Commission (Conduct of Business)
Regulations, 2005 as amended from time to time.
29.3.
The approved aggregate gain and loss to the Petitioner on account of
controllable factors shall be dealt with in the following manner:
(a)
50% of such gain shall be passed on to
consumer over such period as may be specified in the Order of the Commission;
(b)
The balance amount of such gain shall be
allowed to be retained by the Petitioner;
(c)
Loss, if any, will be borne by the Petitioner.
Regulation - 30. Billing and Payment of Charges and Late Payment Surcharge.
30.1.
All bills for capacity charges, energy charges, transmission charges and other
charges shall be raised on monthly basis and payments shall be made by the
beneficiaries on monthly basis.
30.2.
In case, the payment of any bill for charges payable under these Regulations is
delayed by a beneficiary beyond a period of 60 days from the date of billing, a
late payment surcharge at the rate of 1.00% per month or part thereof on the
unpaid amount shall be levied by the Generating Company or Transmission
Licensee, as the case may be.
Regulation - 31. Regulatory Asset.
In extraordinary
circumstances, the Commission may allow creation of Regulatory Asset in case
the Revenue Gap is very substantial and is on account of factors beyond control
of the Generating Company or the Licensee and its full recovery in a single
year will result in tariff shock for the consumers. The Commission will
endeavour to liquidate the Regulatory Asset so created along with carrying cost
in the maximum 3 year period immediately following the year in which it is
created.
PART
V PRINCIPLES FOR
DETERMINATION OF TARIFF AND NORMS FOR OPERATION FOR GENERATION BUSINESS
Regulation - 32. Interest on Working Capital.
32.1.
Components of Working Capital
(a)
Coal-based Thermal Generating Plants: The
Working Capital shall cover the following:
(i)
Fuel Cost including cost of limestone / other
reagent for 2 months corresponding to the normative annual plant availability
factor;
(ii)
Operation and maintenance (O&M) Expenses
for 1 month;
(iii)
Maintenance spares @ 15% of the O&M
expenses;
(iv)
Receivables equivalent to two (2) months of
fixed and variable charges for sale of electricity calculated on the normative
annual plant availability factor.
(b)
Open-cycle Gas Turbine/Combined Cycle Thermal
Generating Plants: The Working Capital shall cover the following:
(i)
Fuel Cost for one month corresponding to the
normative annual plant availability factor, duly taking into account mode of
operation of the generating station on gas fuel and liquid fuel;
(ii)
Liquid fuel sk for ½ month corresponding to
the normative annual plant availability factor, and in case of use of more than
one liquid fuel, cost of main liquid fuel;
(iii)
Maintenance spares @ 30% of operation and
maintenance expenses;
(iv)
Operation & maintenance expenses for one
month;
(v)
Receivables equivalent to 2 months of
capacity charges and energy charges for sale of electricity, calculated on
normative plant availability factor, duly taking into account mode of operation
of the generating plant on gas fuel and liquid fuel.
(c)
Hydro based generating stations: The Working
Capital shall cover the following:
(i)
Maintenance spares @ 15% of operation and
maintenance expenses;
(ii)
Operation & maintenance expenses for 1
month;
(iii)
Receivables equivalent to 2 months of fixed
cost.
Provided further that for
the purpose of Truing-up, the working capital shall be computed based on the
annual plant load factor or normative availability of the generating Station,
whichever is lower;
Provided also that for the
purpose of Truing-up for any year, the working capital requirement shall be
re-computed on the basis of the trued-up figures of receivables, Operation
& Maintenance expenses and other components of working capital approved by
the Commission in the Truing-up;
For the purpose of Truing up
for each year, the variation between the normative interest on working capital
computed at the time of Truing-up and the actual interest on working capital
incurred by the Petitioner, substantiated by documentary evidence, shall be
considered as 'excess normative' or 'deficit normative', as the case may be.
The treatment of such excess and deficit shall be done in following manner:
(a)
'Excess Normative' shall be passed on to
consumer over such period as may be specified in the Order of the Commission;
(b)
'Deficit Normative', if any, will be borne by
the Petitioner.
32.2.
Rate of Interest
The rate of interest on
working capital shall be as per Regulation 24.1.
Regulation - 33. Sale of Infirm Power.
33.1.
Supply of infirm power by a Generating Company shall be treated as Deviation
and paid as per Central Electricity Regulatory Commission (Deviation Settlement
Mechanism and Related Matters) Regulations, 2022, as amended from time to time
or any subsequent re-enactment thereof.
33.2.
Any revenue earned by the Distribution Licensee or Generating Company from sale
of infirm power after accounting for the Fuel expenses shall be applied for
reduction in capital cost and shall not be treated as revenue.
Regulation - 34. Norms for Performance Parameters.
The norms for performance
parameters for a Generating Company i.e. availability, load factor, station
heat rate, specific oil consumption, auxiliary consumption etc. shall be as per
the CERC norms or as determined by the Commission:
Provided that in the case of
a generating unit which undergoes Renovation and Modernization, the Commission
may specify a separate set of norms to be adopted during the renovation and
modernization period and for the subsequent period. These norms shall be
specified by the Commission on case to case basis as part of the Renovation and
Modernization Capital Investment approval. Consequently, the generation tariff
shall be determined accordingly by the Commission.
Regulation - 35. Energy Charges.
35.1.
Energy charges shall be derived on the basis of the landed fuel cost (LFC) of a
generating station (excluding hydro) and shall consist of the following cost:
(a)
Landed cost of primary fuel;
(b)
Landed cost of secondary fuel; and
(c)
Cost of limestone or any other reagent, as
applicable:
Provided that taxes, duties
and amount received on account of penalties received from fuel supplier shall
have to be adjusted in landed fuel cost.
35.2.
Initially, the LFC of primary fuel, secondary fuel and limestone / other
reagents for tariff determination shall be based on actual weighted average
cost of primary fuel and secondary fuel for the preceding three months, and in
the absence of landed costs for the preceding three months, LFC shall be based
on the latest procurement price of primary fuel, secondary fuel and limestone /
other reagents for the generating station.
Regulation - 36. Recovery Of Annual Fixed (Capacity) Charges.
36.1.
The fixed cost of a thermal generating station shall be computed on annual
basis, based on norms specified under these Regulations, and recovered on
monthly basis under capacity charge. The total capacity charge payable for a
generating station shall be shared by the beneficiaries as per their respective
percentage share/allocation in the capacity of the generating station.
36.2.
The Capacity Charge payable to a thermal generating plant for a calendar month
shall be calculated in accordance with the following formulae:
CC1= (AFC/12)( PAF1 / NAPAF
) subject to ceiling of (AFC/12)
CC2 = ((AFC/6)( PAF2 / NAPAF
) subject to ceiling of (AFC/6)) - CC1
CC3 = ((AFC/4) (PAF3 /
NAPAF) subject to ceiling of (AFC/4)) - (CC1+CC2)
CC4 = ((AFC/3) (PAF4 /
NAPAF) subject to ceiling of (AFC/3)) - (CC1+CC2+CC3)
CC5 = ((AFC x 5/12) (PAF5 /
NAPAF) subject to ceiling of (AFC x 5/12)) -(CC1+CC2 +CC3 +CC4)
CC6 = ((AFC/2) (PAF6 /
NAPAF) subject to ceiling of (AFC/2)) -(CC1+CC2+CC3+CC4 + CC5)
CC7= ((AFC x 7/12) (PAF7 /
NAPAF) subject to ceiling of (AFC x 7/12)) - (CC1+CC2 +CC3 +CC4 + CC5 + CC6)
CC8 = ((AFC x 2/3) (PAF8 /
NAPAF) subject to ceiling of (AFC x 2/3)) - (CC1+CC2 +CC3 +CC4 + CC5 + CC6 +
CC7)
CC9 = ((AFC x 3/4) (PAF9 /
NAPAF) subject to ceiling of (AFC x 3/4)) - (CC1+CC2 +CC3 +CC4 + CC5 + CC6 +
CC7+ CC8)
CC10= ((AFC x 5/6) (PAF10 /
NAPAF) subject to ceiling of (AFC x 5/6)) - (CC1+CC2 +CC3 +CC4 + CC5 + CC6 +
CC7 + CC8 + CC9)
CC11 = ((AFC x 11/12) (PAF11
/ NAPAF) subject to ceiling of (AFC x 11/12)) - (CC1+CC2 +CC3 +CC4 + CC5 + CC6
+ CC7 + CC8 + CC9 + CC10)
CC12 = ((AFC) (PAFY / NAPAF)
subject to ceiling of (AFC)) - (CC1+CC2 +CC3+CC4 + CC5 + CC6 + CC7 + CC8 + CC9
+ CC10 + CC11)
Where,
AFC = Annual fixed cost
specified for the year (in Rupees)
NAPAF = Normative annual
plant availability factor (in percent)
PAFM (M =1, 2, 3 ....... ) =
Plant availability factor (in percent)
PAFY = Plant availability
factor achieved during the year (in percent) CC1, CC2, CC3, CC4, CC5, CC6, CC7,
CC8, CC9, CC10, CC11 and CC12 are the Capacity Charges of 1st, 2nd,
3rd, 4th, 5th, 6th, 7th,
8th, 9th, 10th, 11th and 12th months
respectively.
36.3.
The PAFM up to the end of a particular month and PAFY shall be computed in
accordance with the following formula:
36.4.
Incentive to a generating station or unit thereof shall be payable at a flat
rate of 65 paise/ kWh for ex-bus scheduled energy during Peak Hours and 50
paise/ kWh for ex-bus scheduled energy during Off-Peak Hours corresponding to
scheduled generation in excess of ex-bus energy corresponding to Normative
Annual Plant Load Factor (NAPLF) i.e. 85%.
36.5.
In case of fuel shortage in a thermal generating station, the Generating
Company may propose to deliver a higher MW during peak-load hours by saving
fuel during off-peak hours. The SLDC may then specify a pragmatic day-ahead
schedule for the generating station to optimally utilize its MW and energy
capability, in consultation with the Distribution Licensee and other long-term
open access customers. DCi in such an event shall be taken to be equal to the
maximum peak-hour ex-power plant MW schedule specified by the SLDC, for that
day.
36.6.
The fixed cost of a hydro generating station shall be computed on annual basis,
based on norms specified under these Regulations, and recovered on monthly
basis under capacity charge (inclusive of incentive) and energy charge, which
shall be payable by the beneficiaries in proportion to their respective
allocation in the saleable capacity of the generating station, that is to say,
in the capacity excluding the free power to the home State:
Provided that during the
period between the date of commercial operation of the first unit of the
generating station and the date of commercial operation of the generating
station, the annual fixed cost shall provisionally be worked out based on the
latest estimate of the completion cost for the generating station, for the
purpose of determining the capacity charge and energy charge payment during
such period.
36.7.
The capacity charge (inclusive of incentive) payable to a hydro generating
station for a calendar month shall be:
AFC x 0.5 x (NDM / NDY) x
(PAFM /NAPAF) (in Rupees)
Where,
AFC = Annual fixed cost
specified for the year,(in Rupees).
NAPAF = Normative plant
availability factor in percentage.
NDM = Number of days in the
month.
NDY = Number of days in the
year.
PAFM = Plant availability
factor achieved during the month, in percentage.
The PAFM shall be computed
in accordance with the following formula:
|
Where,
|
|
|
AUX
|
=
|
Normative auxiliary energy consumption in percentage
|
|
DCi
|
=
|
Declared capacity (in ex-bus MW) for the ith day of the
month which the station can deliver for at least three (3) hours, as
certified by the SLDC, after the day is over
|
|
IC
|
=
|
Installed capacity (in MW) of the complete generating
station
|
|
N
|
=
|
Number of days in the month
|
|
|
|
|
Regulation - 37. Recovery of Energy Charges (Variable Charges).
37.1.
The Energy (Variable) Charges for a thermal generating plant shall cover the
primary fuel cost, secondary fuel cost, cost of limestone or any other reagent,
as applicable and, shall be payable by every beneficiary for the total energy
scheduled to be supplied to such beneficiary during the calendar month on
ex-power plant basis, at the energy charge rate of the month (with fuel price
adjustment).
37.2.
The Energy Charge for generating plants of the Distribution Licensee/generating
companies for the month shall be worked out on the basis of scheduled ex-bus
energy to be sent out from the generating plant in accordance with the
following formula:
Energy (Variable) Charge
(Rs.)
= Energy Charge Rate (Rs.
/kWh) x Scheduled Energy (ex-bus) for the month (kWh)
37.3.
Variations between actual net injection and scheduled net injection for the
generating stations, and variations between actual net drawal and scheduled net
drawal for the beneficiaries shall be treated as their respective deviations
and such deviations shall be governed by the Indian Electricity Grid Code and
Central Electricity Regulatory Commission (Deviation Settlement Mechanism and
Related Matters) Regulations, 2022, as amended from time to time or any subsequent
re-enactment thereof.
37.4.
Energy Charge Rate (ECR) in Rupees per kWh on ex-power plant basis for coal
based thermal power plant shall be determined to three decimal places in
accordance with the following formulae: ECR = {(SHR - SFC x CVSF) x (LPPF /
CVPF) + (SFC x LPSF) + (LC x LPL)} x 100 / (100 - AUX)
Where,
AUX = Normative auxiliary
energy consumption in percentage;
CVPF = Weighted Average
Gross calorific value of primary fuel as received, in kCal per kg for coal
based station less 85kCal/Kg on account of variation during storage at
generating station or per litre or per cubic meter as applicable;
CVSF = Weighted Average
Calorific value of secondary fuel, in kCal per ml;
ECR = Energy charge rate, in
Rupees per kWh sent out;
SHR = Station Heat rate, in
kCal per kWh;
SFC = Specific fuel oil
consumption, in ml per kWh;
LC = Normative limestone
consumption in kg per kWh;
LPL = Weighted average
landed cost of limestone in Rupees per kg;
LPPF = Weighted average
landed price of primary fuel, in Rupees per kg or per litre or per cubic meter
as applicable;
LPSF = Weighted Average
Landed Price of Secondary Fuel in Rs./ml.
37.5.
Energy charge rate (ECR) in Rupees per kWh on ex-power plant basis for gas and
liquid fuel based thermal power plant shall be determined to three decimal
places in accordance with the following formulae:
ECR = SHR x LPPF x 100 /
{CVPF x (100 - AUX)}
37.6.
Energy charge rate (ECR) in Rupees per kWh on ex-power plant basis, for a hydro
generating station, shall be determined up to three decimal places based on the
following formula, subject to the provisions of Regulation 37.8:
ECR = AFC x 0.5x10/ {DEx
(100-Aux) x (100-FEHS)} Where,
DE = Annual design energy
specified for the hydro generating station, in MWh, subject to provisions of
Regulation 37.7 FEHS = Free Energy share for Home State, if any, in percent (as
defined in CERC Regulations)
37.7.
In case the saleable scheduled energy (ex-bus) of a hydro generating station
during a year is less than the saleable design energy (ex-bus) for reasons
beyond the control of the generating station, the treatment shall be as per
Regulation 37.8, on an petition filed by the generating company.
37.8.
Shortfall in energy charges in comparison to fifty percent of the annual fixed
cost shall be allowed to be recovered in six equal monthly instalments:
Provided that in case actual
generation from a hydro generating station is less than the design energy for a
continuous period of four years on account of hydrology factor, the generating
station shall approach the Central Electricity Authority with relevant
hydrology data for revision of design energy of the station.
37.9.
Any shortfall in the energy charges on account of saleable scheduled energy
(ex-bus) being less than the saleable design energy (ex-bus) during the Control
Period which was beyond the control of the generating station and which could
not be recovered during the said Control Period shall be recovered in
accordance with Regulation 37.8.
37.10.
In case the energy charge rate (ECR) for a hydro generating station, as
computed in Regulation 37.6 above, exceeds hundred and twenty paise per kWh,
and the actual saleable energy in a year exceeds {DE x (100 - AUX) x
(100-FEHS)/10000} MWh, the Energy charge for the energy in excess of the above
shall be billed at hundred and twenty paise per kWh only.
37.11.
The SLDC shall finalise the schedules for the hydro generating stations for
optimal utilization of all the energy declared to be available, which shall be
scheduled for all beneficiaries in proportion to their respective allocations
in the generating station.
Regulation - 38. Landed Cost of Fuel.
The landed cost of fuel for
the month for the purpose of computation of energy charge shall be as specified
in Central Electricity Regulatory Commission (Terms and Conditions of Tariff)
Regulations, 2019, as amended from time to time:
Provided that in case of any
cap specified in the PPA or in relevant Order(s) of the Commission, the same
shall prevail:
Provided further that no
transit and handling losses shall be permissible in case of coal which is
priced on FOR destination basis.
Regulation - 39. Scheduling.
The methodology for
scheduling and dispatch for the generating plant shall be as specified in the
Punjab State Electricity Regulatory Commission (Grid Code) Regulations, 2013,
as amended from time to time.
Regulation - 40. SLDC and Transmission Charges.
40.1.
SLDC and transmission charges as determined by the Commission shall be
considered as a part of expenditure, if payable by the generating plant.
40.2.
SLDC and transmission charges paid for energy sold outside the State, if any
shall not be allowed as expenses.
Regulation - 41. Metering and Accounting.
For all purposes, the
Standards for Metering and Accounting specified in the Punjab State Electricity
Regulatory Commission (Grid Code) Regulations, 2013 and the Central Electricity
Authority (Installation and Operation of Meters) Regulations 2006, as amended
from time to time, shall be applicable.
PART
VI PRINCIPLES FOR
DETERMINATION OF TARIFF AND NORMS FOR OPERATION FOR DISTRIBUTION BUSINESS
Regulation - 42. Interest on Working Capital.
42.1.
Components of Working Capital for Wheeling of electricity shall cover the
following:
(a)
O&M Expenses for wire business for 1
month;
(b)
Maintenance spares @ 15% of the O&M
expenses for wire business;
(c)
Receivables equivalent to two (2) month of
the expected revenue from charges for use of Distribution Wires at the
prevailing tariffs; minus Amount, if any, held as security deposits from
Distribution System Users
42.2.
Components of Working Capital for Retail Supply business shall cover the following:
(a)
O&M Expenses for retail supply business
for 1 month;
(b)
Maintenance spares @ 15% of the O&M
expenses for retail supply business; and
(c)
Receivables equivalent to 2 months of average
of revenue from sale of energy, approved by the Commission in the ARR;
Less
Consumer Security Deposit
One month of power
procurement cost including associated cost
"Provided also that for
the purpose of Truing-up for any year, the working capital requirement shall be
re-computed on the basis of the trued-up figures of receivables, Operation
& Maintenance expenses and other components of working capital approved by
the Commission in the Truing-up;
For the purpose of Truing up
for each year, the variation between the normative interest on working capital
computed at the time of Truing-up and the actual interest on working capital
incurred by the Petitioner, substantiated by documentary evidence, shall be
considered as 'excess normative' or 'deficit normative', as the case may be.
The treatment of such excess and deficit shall be done in following manner;
(a)
'Excess Normative' shall be passed on to
consumer over such period as may be specified in the Order of the Commission;
(b)
'Deficit Normative', if any, will be borne by
the Petitioner."
42.3.
Rate of Interest -The rate of interest on working capital shall be as per
Regulation 24.1.
Regulation - 43. Distribution Loss.
43.1.
The Distribution Loss shall be equal to the difference between the energy
injected into the distribution system (X) and the sum of energy sold to all its
consumers (Y) within the Licensed area.
43.2.
Energy sold shall be the sum of metered sales and assessed unmetered sales
within the Licensed Area, if any, based on approved methodology/norms. The
percentage Distribution Loss shall be as follows:
Percentage Distribution
Loss= ((X- Y)/X) x 100
43.3.
The Distribution Licensee shall file the Distribution Loss trajectory in the
business plan commensurate with the Capital Investment Plan for distribution
business. The Commission after verification and evaluation of the same shall
approve the Distribution Loss trajectory for each year of the Control Period.
43.4.
The consumption of unmetered consumers shall be assessed on the basis of 11 kV
feeder metering/DT metering/sample consumer metering or such other factor as
per methodology approved by the Commission.
43.5.
In the absence of such energy audit/sample surveys/sample DTR metering/feeding
substation end metering, the Commission shall not accept the claim of the
Distribution Licensee and may proceed to fix the Distribution Loss levels for
unmetered consumption on the basis of the information available with it.
43.6.
The Distribution Licensee shall furnish within a period as specified by the
Commission, computation of voltage-wise technical and commercial losses.
43.7.
Any over-achievement and under-achievement of the Distribution Loss trajectory
specified by the Commission shall be subject to provisions of Regulation29. The
Distribution Licensee shall provide a statement of this in the True-up.
43.8.
Notwithstanding above, the Commission may also monitor the Aggregate Technical
& Commercial (AT&C) Losses.
Regulation - 44.Power Purchase, Procurement Process and Cost.
44.1.
Long-term demand and energy forecasts, short term demand and energy forecasts,
long-term power procurement plans, short-term procurement plans and requirement
of additional power shall be approved by the Commission in accordance with the
PSERC (Power Purchase and Procurement Process of Licensee), Regulations 2012,
as amended from time to time.
44.2.
The Commission shall also approve criteria for power purchase in long-term and
short-term, power purchase arrangements or agreements, and cost incurred in
power purchase in accordance with the PSERC (Power Purchase and Procurement
Process of Licensee), Regulations 2012, as amended from time to time.
44.3.
The Distribution Licensee shall furnish a firm proposal with regard to
source-wise purchase of electricity from various renewable sources of energy
including own generation from renewable sources, for complying with its
'Renewable Purchase Obligation' specified by the Commission in PSERC (Renewable
Purchase Obligation and its compliance) Regulations, 2011, as amended from time
to time.
Regulation - 45. Transmission And SLDC Charges.
45.1.
The transmission charges, wheeling charges and other charges payable by the
Distribution Licensee for intra state transmission or wheeling of power
purchased by it, shall be considered as determined by the Commission.
45.2.
The inter-state transmission charges shall be considered as per the Orders of
the Central Electricity Regulatory Commission.
45.3.
SLDC charges, as determined by the Commission, shall be considered as allowable
expenses.
Regulation - 46. Bad and Doubtful Debts and Other Debits.
46.1.
Bad and doubtful debts shall be allowed to the extent the Distribution Licensee
has identified/ actually written off bad debts, subject to a maximum of 1% of
annual sales revenue excluding subsidy, and according to a transparent policy
approved by the Commission. In case, there is any recovery of bad debts already
written off, the recovered bad debts will be treated as Other Income.
46.2.
Other debits including miscellaneous losses and write offs, sundry debts,
material cost variance, losses on account of flood, cyclone, fire etc. shall be
considered by the Commission.
Regulation - 47. Fuel Cost adjustment (FCA).
Any change in fuel cost from
the level approved by the Commission shall be determined by the Distribution
Licensee in accordance with the FCA formula specified by the Commission in the
Conduct of Business Regulations, along with amendments issued from time to time
and, recovered from the consumers after following the procedure detailed in the
Conduct of Business Regulations.
Regulation - 48. Cross-Subsidy.
48.1.
Cross-subsidy for a consumer category means the difference between the average
realization per unit from that category and the average cost of supply per unit
expressed in percentage terms as a proportion of the average cost of supply.
48.2.
The Commission shall determine the tariff so that it progressively reflects the
average cost of supply and the cross subsidy as defined above remains within ±
20% of the average cost of supply.
Regulation - 49. Maintenance and Operation Charges Payable to State Government.
The Commission shall allow
the Maintenance and Operations Charges Payable to State Government on account
of maintenance as well as charges for remaining capital works of RSD.
PART
VII PRINCIPLES
FOR DETERMINATION OF TARIFF AND NORMS FOR OPERATION FOR TRANSMISSION BUSINESS
AND SLDC BUSINESS
Regulation - 50. Interest on Working Capital.
50.1.
Components of Working Capital
The Working Capital shall
cover the following:
(a)
O&M Expenses for 1 month;
(b)
Maintenance spares @ 15% of the O&M
expenses;
(c)
Receivables equivalent to two (2) months of
fixed cost calculated on normative target availability.
"Provided also that for
the purpose of Truing-up for any year, the working capital requirement shall be
re-computed on the basis of the trued-up figures of receivables. Operation
& Maintenance expenses and other components of working capital approved by
the Commission in the Truing-up;
For the purpose of Truing-up
for each year, the variation between the normative interest on working capital
computed at the time of Truing-up and the actual interest on working capital
incurred by the Petitioner, substantiated by documentary evidence, shall be
considered as 'excess normative' or 'deficit normative', as the case may be.
The treatment of such excess and deficit shall be done in following manner:
(a)
Excess Normative' shall be passed on to
consumer over such period as may be specified in the Order of the Commission;
(b)
'Deficit Normative', if any, will be borne by
the Petitioner."
50.2.
Rate of Interest
The rate of interest on
working capital shall be as per Regulation 24.1.
Regulation - 51. Norms of Operation.
51.1.
Normative Annual Transmission System Availability Factor (NATAF)
(a)
For recovery of Annual Fixed Cost, NATAF
shall be as 98.5% for AC system:
(b)
For Incentive, NATAF shall be more than 99%
for AC system: Provided that no Incentive shall be payable for availability
beyond 99.75%:
Provided further that for AC
system, actual outage hours shall be considered for computation of availability
upto two trappings per year. After two trappings in a year, for every tripping,
additional 12 hours outage shall be considered in addition to the actual outage
hours: Provided also that in case of outage of a transmission element affecting
evacuation of power from a generating station, outage hours shall be multiplied
by a factor of 2.
51.2.
Auxiliary Energy Consumption
The charges for auxiliary
energy consumption in the sub-stations for the purpose of air-conditioning,
lighting and consumption in other equipment shall be borne by the Transmission
Licensee and will be included as part of the normative Administrative and
General expenses.
Regulation - 52. Income from Open Access Customers.
The charges payable by the
medium-term and short-term open access customers shall be as specified in PSERC
Open Access Regulations, 2011 as amended from time to time.
Regulation - 53. Transmission Loss.
53.1.
The energy losses in the transmission system of the Transmission Licensee, as
determined by the State Load Despatch Centre and approved by the Commission,
shall be borne by the Transmission System Users in proportion to their usage of
the intra-State transmission system.
53.2.
The Transmission Licensee shall file the Transmission Loss trajectory in the
Business Plan commensurate with the Capital Investment Plan for transmission
business. The Commission after verification and evaluation of the same shall
fix the Transmission Loss trajectory for each year of the Control Period.
53.3.
The Commission may stipulate a trajectory for Transmission Loss in accordance
with Regulation 4.4(c) as part of the Multi-Year Tariff framework applicable to
the Transmission Licensee: Provided further that any variation between the
actual level of Transmission Loss, as determined by the State Load Despatch
Centre and the approved level, shall be subject to provisions of Regulation 29:
Provided further that any
gain / loss sharing with the Transmission Licensee on account of
over-achievement / under-achievement of the Transmission Loss trajectory
specified by the Commission, shall be capped to the Return on Equity earned by
the Transmission Licensee for the respective year.
Regulation - 54. Recovery of Annual Fixed Charges.
54.1.
Transmission Licensee shall recover full transmission charges at the Normative
Annual Transmission System Availability Factor specified for it by the
Commission.
54.2.
Computation and Payment of Transmission Charges
Annual transmission charges
shall be fully recoverable at the specified level of target availability from
the long term customers. Payment of transmission charges below the specified
target availability shall be on pro-rata basis. The charges for network usage
shall be worked out on the basis of available transmission capacity and would
reflect cost of capital investment and operation and maintenance expenses of
the transmission system to transfer bulk power. The revenue from this component
of transmission tariff will meet the annual revenue requirement of the
transmission entity;
Transmission charges
(inclusive of incentive) for a calendar month shall be calculated in accordance
with the following formula:
(a)
For TAFMn<= 98.50%
AFC x (NDMn/NDY)
x (TAFMn/98.50%)
(b)
For TAFMn: 98.50%<TAFMn<=
99.00%
AFC x (NDMn/NDY)
x (1)
(c)
For TAFMn: 99.00%<TAFMn<=
99.75%
AFC x (NDMn/NDY)
x (TAFM/99.00%)
(d)
For TAFMn> 99.75%
AFC x (NDMn/NDY)
x (99.75%/99.00%)
Where:
AFC means Annual Fixed Cost
determined by the Commission for a Transmission Licensee (in Rupees);
NDMn means
number of days in the nth month;
NDY means number of days in
the year;
TAFMn means
Transmission System availability factor for the nth month (in percent),
computed in accordance with CERC Regulations.
Note: Incentive mechanism
for availability shall be applicable only when the Transmission Licensee
submits detailed computation of the availability figures to the Commission duly
certified by the SLDC and the Commission approves the same. The detailed
computation will include all details of the input data, methods of recording
the data (manual or through electronic modes), formulae used for computation and
all other details required to establish the current level of availability:
Provided that the Commission
may get the annual Transmission system availability factor verified from an
independent third party agency, till SLDC becomes an independent entity.
54.3.
Recovery of SLDC Charges
(a)
The SLDC charges from the generating
companies and sellers (which excludes short term open access customers) shall
be collected in proportion to their installed capacity or contracted capacity,
as the case may be, as on the last day of the month prior to billing of the
month.
(b)
The SLDC charges from the Distribution
Licensees and buyers (which excludes short term open access customers) shall be
collected in proportion to the sum of their allocations and contracted
capacities, as the case may be, as on the last day of the month prior to
billing of the month.
PART
VIII FILING
OF BUSINESS PLAN / MULTI YEAR TARIFF/ TRUE UP/ AGGREGATE REVENUE REQUIREMENT
Regulation - 55. Business Plan Including Capital Investment Plan Filing.
The Petitioner shall file
Business Plan including Capital Investment Plan as per the details specified in
Regulation 9 for the Commission's approval on or before 20th August of the year
preceding the first year of the Control Period.
Regulation - 56. Tariff Filing.
56.1.
The Petitioner shall file a petition for approval of ARR & Tariff, for each
year of the Control Period consistent with the business plan and the capital
investment plan approved by the Commission. The ARR &Tariff filing shall be
filed on or before 30th November of the year preceding the year of start of the
Control Period. The petition shall contain all components of the ARR and tariff
as specified in these Regulations:
Provided where the last day
for ARR & tariff filing falls on a day on which the office of the
Commission is closed and by reason thereof, the act cannot be done on that day,
it may be done on the next following day on which the office is open.
56.2.
The Petitioner shall publish the petition as mentioned in the Conduct of
Business Regulations.
56.3.
The petition shall also contain the revenue gap for various years of the
Control Period and a tariff proposal for meeting the revenue gap for each year.
In the absence of the tariff proposal, the petition shall be considered as
incomplete and shall be liable for rejection.
56.4.
The Distribution Licensee shall also provide a copy of tariff filing to the
Transmission Licensee and vice-versa.
56.5.
Notwithstanding anything contained in these Regulations, the Commission shall
at all times have the authority, either suo-motu or on a petition filed by any
interested or affected party, to determine the tariff, including terms and
conditions thereof, of Distribution Licensee, Transmission Licensee or
Generating Company:
Provided that such
determination of tariff may be pursuant to an agreement or arrangement or
otherwise, whether or not previously approved by the Commission and entered
into at any time before or after the commencement of the Act.
Regulation - 57. True Up and Aggregate Revenue Requirement Filing.
The Petitioner shall file
the True Up, ARR on or before 30th November in each year of the Control Period
as per the details mentioned in Regulation 11 for the Commission's review and
approval.
Regulation - 58. Disposal of Petition.
58.1.
The Commission shall, within one hundred and twenty (120) days from the receipt
of a complete petition and after considering all suggestions and objections received
from the public:
(a)
Issue a Tariff Order accepting the petition
with such modifications or such conditions as may be contained in such Order;
or
(b)
Reject the petition for reasons to be
recorded in writing if such petition is not in accordance with the provisions
of the Act and the rules and Regulations made there under or the provisions of
any other law for the time being in force.
58.2.
The Petitioner shall publish the tariff approved by the Commission in English
and local languages in daily newspapers having circulation in the area of
licensee. The Petitioner shall also host the approved tariff/tariff schedule on
its website and make available for sale, a booklet containing such
tariff/tariff schedule/general conditions of tariff as the case may be, to any
person upon payment of reasonable reproduction charges. 58.3. The tariff so
published shall be in force from the date specified in the said order and
shall, unless amended or revoked, continue to be in force for such period as
may be stipulated therein.
Regulation - 59. Summary of Timelines.
|
Description
|
Filing of the Petition
(on or before)
|
Obtaining additional information and acceptance by the
Commission
|
Approval of the Document
|
|
Business Plan including Capital Investment Plan (to be
filed only at the beginning of Control Period)
|
20th August of the year preceding the first year of
Control Period
|
Within 30 days of filing of Petition
|
Within 90 days of acceptance of the filing
|
|
Filing of MYT Petition (ARR and Tariff Proposal for the
Control Period)
|
30th November of the year preceding the first year of
Control Period
|
Within 30 days of filing of Petition
|
Within 120 days of acceptance of the filing
|
|
Aggregate Revenue Requirement/True-up
|
30th November of each year of the Control Period
|
Within 30 days of filing of Petition
|
Within 120 days of acceptance of the filing
|
PART
IX MISCELLANEOUS
Regulation - 60. Supply of Information and Data.
The Petitioner shall submit
information and data as per the formats separately issued by the Commission
from time to time.
Regulation - 61. Issue of Orders and Practice Directions.
Subject to the provision of
the Act and these Regulations, the Commission may, from time to time, issue
orders and practice directions in regard to the implementation of these
Regulations and procedure to be followed on various matters, which the
Commission has been empowered by these Regulations to direct, and matters
incidental or ancillary thereto.
Regulation - 62. Powers to Remove Difficulties.
If any difficulty arises in
giving effect to any of the provisions of these Regulations, the Commission
may, by a general or special order, not being inconsistent with the provisions
of these Regulations or the Act, do or undertake to do things or direct the
Petitioner to do or undertake such things which appear to be necessary or
expedient for the purpose of removing the difficulties.
Regulation - 63. Power of Relaxation.
The Commission may in public
interest and for reasons to be recorded in writing, relax any of the provision
of these Regulations.
Regulation - 64. Power to Waive.
During the period, the
licensee remains an integrated utility performing the functions of Generation
& Distribution, the Commission may waive and/or relax any of the provisions
of these Regulations in any manner if in the opinion of the Commission, it is
impracticable or inexpedient to proceed as per these Regulations. In such a
situation, after recording its reasons, the Commission may adopt any other
approach which is reasonable and is consistent with the overall approach of these
Regulations.
Regulation - 65. Interpretation.
If a question arises
relating to the interpretation of any provision of these Regulations, the
decision of the Commission shall be final.
Regulation - 66. Saving of Inherent Powers of the Commission.
Nothing contained in these
Regulations shall limit or otherwise affect the inherent powers of the
Commission from adopting a procedure, which is at variance with any of the
provisions of these Regulations, if the Commission, in view of the special
circumstances of the matter or class of matters and for reasons to be recorded
in writing, deems it necessary or expedient to depart from the procedure
specified in these Regulations.
Regulation - 67. Enquiry and Investigation.
All enquiries,
investigations and adjudications under these Regulations shall be done by the
Commission through the proceedings in accordance with the provisions of the
Conduct of Business Regulations.
Regulation - 68. Power to Amend.
The Commission, for reasons
to be recorded in writing, may at any time, vary, alter or modify any of the
provision of these Regulations through specific order.
ANNEXURE A
SEGREGATION OF ARR OF WHEELING AND
RETAIL SUPPLY BUSINESS
|
Particulars
|
Wires
Business (%)
|
Retail Supply
Business (%)
|
|
Power
Purchase Expenses
|
0%
|
100%
|
|
Inter-State
Transmission Charges
|
0%
|
100%
|
|
Intra-State
Transmission Charges
|
0%
|
100%
|
|
Employee
Expenses
|
40%
|
60%
|
|
Administration
& General Expenses
|
50%
|
50%
|
|
Repair &
Maintenance Expenses
|
90%
|
10%
|
|
Capital Cost
|
90%
|
10%
|
|
Depreciation
|
90%
|
10%
|
|
Interest on
Long-term Loan Capital
|
90%
|
10%
|
|
Interest on
working capital and on consumer security deposits
|
10%
|
90%
|
|
Bad Debts
Written off
|
0%
|
100%
|
|
Income Tax
|
90%
|
10%
|
|
Non-Tariff
Income
|
10%
|
90%
|
|
Income from
Other Business
|
50%
|
50%
|