PUNJAB STATE ELECTRICITY REGULATORY
COMMISSION (ELECTRICITY SUPPLY CODE AND RELATED MATTERS) (11TH AMENDMENT)
REGULATIONS, 2022
PREAMBLE
In
exercise of the powers conferred under Section 181 read with Sections 43, 44,
45, 46, 47, 48, 50, 55, 56, 57, 58, 59, 126, 127, 135, 152, 154 & 163 of
the Electricity Act, 2003 (Central Act 36 of 2003) read with Electricity
(Amendment) Act, 2007 (No. 26 of 2007) and all other powers enabling it in this
behalf, the Punjab State Electricity Regulatory Commission hereby makes
following regulations to further amend the Punjab State Electricity Regulatory
Commission (Electricity Supply Code and Related Matters) Regulations, 2014
including the first to tenth amendments thereof (hereinafter referred to as
"the Principal Regulations"):
Regulation - 1. Short Title, Commencement and Interpretation.
1.1 These Regulations may be called the Punjab
State Electricity Regulatory Commission (Electricity Supply Code and Related
Matters) (11th Amendment) Regulations, 2022.
1.2 These Regulations shall be applicable to all
licensees (including entities exempted under Section 13 of the Act) in their
respective licensed/supply areas and all consumers/persons in the State of
Punjab.
1.3 These Regulations shall come into force from
the date of their publication in the official gazette of the State.
Regulation - 2. Amendment of Regulation 2 of the Principal Regulations.
(i)
The new clauses (aa), (ab), (ca), 2(oa),
(rb), (zla), (ztb), (zva), (zwa),(zyaa), (zzba), (zzbb) & (zzbc) to
Regulation 2 of the Principal Regulations shall be added as under;
(aa)
'Advanced Metering Infrastructure' is an integrated system of smart meters,
communication networks and data management systems that enables two way
communication between the utilities and energy meters, and the functional
blocks of Advanced Metering Infrastructure typically include Head end system,
Wide area network, Neighborhood area network, Data concentrator unit and Home
area network;
(ab)
'Advanced Metering Infrastructure Service Provider' is a person appointed by
the distribution licensee, for owning, operating, and maintaining Advanced
Metering Infrastructure or a part of the Advanced Metering Infrastructure, till
its transfer to the licensee;
(ca)
"Application" means an application form complete in all respects in
the appropriate format, as specified by the Commission, along with documents
and other compliances;
(oa)
'Consumer Meter' means a meter used for accounting and billing of electricity
supplied to or from the consumer but excluding those consumers covered under
Interface Meters;
(rb)
"Disconnection" means the physical separation or remote disconnection
of a consumer from the distribution system of the distribution licensee;
(zla)
"Interface Meter" means a meter used for accounting and billing of
electricity, connected at the point of interconnection between electrical
systems of generating company, licensee and consumers, directly connected to
the Inter-State Transmission System or Intra-State Transmission System or
Distribution System and who have been permitted open access by the Appropriate
Commission;";
(ztb)
"Point of supply" means the point, as may be specified by the State
Commission, at which a consumer is supplied electricity;
(zva)
"Prosumer" means a person who consumes electricity from the grid and
can also inject electricity into the grid for distribution licensee, using same
point of supply;
(zwa)
"Sanctioned Load or Contracted load" means the load in kW (kilo Watt)
or BHP which the Licensee has agreed to supply to a consumer from time to time
as per the applicable terms and conditions indicated in the agreement signed
between the licensee and the consumer The BHP shall be converted to kW by
multiplying it by 0.746;
(zyaa)
'Smart Meter' means a meter as specified in IS 16444 and as amended from time
to time;
(zzba)
'Supply Voltage Interruption' is a condition in which the voltage at the supply
terminals is lower than 5% of the nominal voltage condition. It can be
classified as:
(a)
Planned or Pre-arranged Supply Interruptions
means a supply interruption when network users are informed in advance;
(b)
Forced or Accidental Supply Interruptions,
caused by permanent or transient faults, mostly related to external events,
equipment failures or interference.
An Accidental or forced
supply interruption is classified as:
(1)
Sustained or long interruption means supply
interruption is longer than 3 min;
(2)
Short interruption means supply interruption
is upto & including 3 min.;
(3)
For poly-phase systems, a supply interruption
occurs when the voltage falls below 5% of the nominal voltage on all phases
(otherwise, it is considered to be a dip).
(zzbb)
'System Average Interruption Duration Index' (SAIDI) means the average duration
of sustained interruptions per consumer occurring during the reporting period,
determined by dividing the sum of all sustained consumer interruptions
durations, in minutes, by the total number of consumers;
(zzbc)
'System Average Interruption Frequency Index' (SAIFI) means the average
frequency of sustained interruptions per consumer occurring during the
reporting period, determined by dividing the total number of all sustained
consumer interruption by the total number of consumers;
(ii)
The clause (i) & (zo) to regulation 2 of
the Principal Regulations shall be substituted as under;
(i)
"Billing Cycle or Billing period"
means the period for which regular electricity bills as specified by the
Commission, are issued for different categories of consumers by the
distribution licensee;
(zo)
"Meter" means a device suitable for measuring, indicating and
recording the conveyance of electricity or any other quantity related with
electrical system and shall include, wherever applicable, other equipment such
as Instrument Transformer i.e. 'Current Transformer' (CT) or 'Current
Transformer' (CT) and 'Capacitor Voltage Transformer' (CVT) or 'Current
Transformer' (CT) and 'Inductive Voltage Transformer' (IVT), necessary for the
purpose of measurement;"
Regulation - 3. Amendment of Regulation 4.2 of the Principal Regulations.
The table under Regulation
4.2 regarding the Supply Voltage for different loads/contract demand shall be
substituted as under;
|
Sr. No.
|
Category of Loads/Consumers
|
Supply Voltage
|
|
(i)
|
a) DS/NRS loads not exceeding 7 kW (including motive
load not exceeding 2 BHP).
|
Single phase 230 V (between phase and neutral)
|
|
b) DS loads not exceeding 22.5 kW (including motive
load not exceeding 2 BHP) in Dhera/Dhanis situated outside the phirni of
village through single phase transformer
|
|
c) Industrial demand including general demand not exceeding
7 kVA at consumer's option.
|
|
d) AP load not exceeding 2 BHP.
|
|
e) Street lighting load not exceeding 7 kW.
|
|
(ii)
|
a) DS/NRS loads exceeding 7 kW or motive load exceeding
2 BHP but demand not exceeding 100 kVA.
|
Three phase 400V (between phases)
|
|
b) Industrial demand including general demand (other
than covered under (i) above) not exceeding 100kVA.
|
|
c) Bulk Supply load with contract demand not exceeding
100 kVA.
|
|
d) AP load exceeding 2 BHP/AP high technology loads not
exceeding 100 KW.
|
|
e) Street Light load exceeding 7 kW but not exceeding
100 kW.
Note:-Domestic consumers existing as on 1.8.2012 having
load up to 10 kW shall have the option to have single phase supply or three
phase supply in case their connected load after computing as per Reg.4.5
worked out to be more than 7 kW.
|
|
(iii)
|
a) Arc furnace loads having specified protection system
for suppressing voltage surge and other Large Supply Consumers (General and
Power Intensive Industry) with contract demand not exceeding 4000 kVA.
|
Three phase 11 KV (between phases)
|
|
b) DS/NRS/BS demand exceeding 100 kVA but with contract
demand not exceeding 4000 kVA.
|
|
c) AP High Technology Supply with load exceeding 100
kW.
|
|
(iv)
|
a) Arc furnace loads (other than covered in (iii)
above) with demand not exceeding 20 MVA.
|
Three phase 33/66 kV (between phases) as per
availability of voltage at the nearest feeding S/Stn.
|
|
b) Large Supply Consumers with contract demand
exceeding 4000 kVA but not exceeding 20 MVA.
|
|
c) DS/NRS/BS demand exceeding 4000 kVA but not
exceeding 20 MVA.
|
|
(v)
|
All consumers (except Railway Traction) with contract
demand exceeding 20 MVA but not exceeding 50 MVA.
|
Three phase 66/132 kV (between phases) as per
availability of voltage at the nearest feeding S/Stn.
|
|
(vi)
|
All Consumers (except Railway Traction) with contract
demand exceeding 50 MVA. The applicant can opt for supply at 400 kV subject
to technical feasibility clearance by the licensee.
|
Three phase 132/220/400kV (between phases) as per
availability of voltage at the nearest feeding S/Stn.
|
|
(vii)
|
Railway Traction Supply Consumers
|
Single/two/three phase 132/220 kV (between phases) as
per availability of voltage at the nearest feeding S/Stn.
|
Regulation - 4.Regulation 4.2 A shall be added to the Principal Regulations after sub-regulation 4.2.2 as under:
4.2
A Supply Voltage for connectivity at single point under Regulation 6.6:
The Supply Voltage for the
purpose of release of connectivity at Single Point to colonies/complexes
covered under Regulation 6.6 on the basis of loading norms specified in
Regulation 6.7 shall be as under:
|
Sr. No
|
Estimated Load in kVA
|
Supply Voltage
|
|
(i)
|
estimated load not exceeding 4000 kVA
|
Three phase 11 kV (between phases)
|
|
(ii)
|
estimated load exceeding 4000 kVA but not exceeding 20
MVA
|
Three phase 33/66 kV (between phases) as per
availability of voltage at the nearest feeding S/Stn.
|
|
(iii)
|
estimated load exceeding 20 MVA but not exceeding 50
MVA
|
Three phase 66/132 kV (between phases) as per
availability of voltage at the nearest feeding S/Stn.
|
|
(iv)
|
estimated load exceeding 50 MVA
|
Three phase 132/220 kV (between phases) as per
availability of voltage at the nearest feeding S/Stn.
|
Regulation - 5. Amendment of Regulation 6 of the Principal Regulations.
PROCEDURE FOR RELEASE OF NEW
CONNECTION/ADDITIONAL LOAD/DEMAND
(i)
Regulation 6.1 of the Principal Regulations
shall be substituted as under:
6.1
General Terms
(1)
The distribution licensee shall prominently
display on its website and on the notice board in all its offices, the
following; namely:-
(a)
detailed procedure for grant of new
connection, temporary connection, change of consumer category, enhancement of
load, reduction of load or change in name, transfer of ownership and shifting
of premises etc;
(b)
address and telephone numbers of offices where
filled-up application forms can be submitted;
(c)
address of website for online submission of
application form;
(d)
complete list of copies of the documents
required to be attached with the application;
(e)
all applicable charges to be deposited by the
applicant.
(2)
Application forms for all type of connections
as well as modification in existing connection shall be available at all the
local offices of the distribution licensee free of cost as well as on its
website for free download.
(3)
The distribution licensee shall create a web
portal and a mobile app for submission of online application forms.
(4)
The applicant shall have an option to submit
an application form in hard copy form or an electronic means such as online
through web portal or mobile app of distribution licensee.
(5)
In case hard copy of the application form is
submitted, the same shall be scanned and uploaded on the website as soon as it
is received and acknowledgement with the registration number for that applicant
shall be generated and intimated to the applicant.
(6)
In case of online application form through
web portal or mobile app of distribution licensee, the acknowledgement with the
registration number shall be generated on submission of application.
(7)
An application, complete with all the
required information and applicable charges, shall be deemed to be received on
the date of generation of acknowledgement with registration number. In case of
hard copy submission, the acknowledgement with registration number shall be
generated within twenty four hours, of receipt of the application, complete
with all the required information and charges.
(8)
The application tracking mechanism based on
the unique registration number shall be provided by the distribution licensee
through web-based application or mobile app or through SMS or by any other mode
to monitor the status of processing of the application like receipt of
application, site inspection, issuance of demand note, external connection,
meter installation and electricity flow.
(ii)
Regulation 6.2 of the Principal Regulations
shall be substituted as under:
6.2
APPLICATION FOR LOAD/DEMAND NOT EXCEEDING 500kW/kVA
6.2.1
The owner or occupier of a premises requiring new connection or additional
load/demand having total load/demand including additional load/demand, if any,
not exceeding 50kW/kVA for Domestic, Non-Residential, Industrial, Bulk Supply,
AP High Tech/High Density Farming and Compost plants/solid waste management
plants shall submit an application on the prescribed A&A form along with
requisite documents, processing fee, Security (consumption), Security (meter)
and Service Connection Charges as approved by the Commission. No separate
demand notice shall be issued to such applicant/consumer and connection shall
be released within time period specified in these regulations from the date of
receipt of application complete in all respect.
6.2.2
The owner or occupier of a premises requiring new connection or additional
load/demand having total load/demand including additional load/demand, if any,
exceeding 50kW/kVA but not exceeding 500kVA for Domestic, Non-Residential,
Industrial, Bulk Supply, AP High Tech/High Density Farming and Compost
plants/solid waste management plants and all other categories of
consumers/applicants for load/demand not exceeding 500kVA, shall submit an
application on the prescribed A&A form along with requisite documents,
processing fee, Security (consumption), Security (meter) as specified in
Schedule of General Charges approved by the Commission.
(iii)
Regulation 6.4.1 of the Principal Regulations
shall be deleted.
(iv)
Amendment of Regulation 6.4.3 of the
Principal Regulations:
Following provisos shall be
added to clause (b) of Regulation 6.4.3:
Provided further that in
case the supply is to be provided through a prepayment meter, in the absence of
proof of ownership or occupancy mentioned above, any other address proof (where
connection is to be released through a pre-payment meter) shall be accepted for
release of connection.
Provided also that the
release of electric connection to any premises by the distribution licensee in
accordance with these regulations shall not be construed as a proof of legal
rights of the consumer on the said premises.
(v)
Amendment of Regulation 6.7 of the Principal
Regulations-Regulation 6.7 of the principal Regulations shall be substituted as
under:
6.7 Supply of Electricity to Individual Consumers
in the Residential Colonies/Multi-Storey Residential Complexes, Commercial
complexes/malls, IT parks developed under bye- laws/rules of the State Govt.
In the event of Residential
Colonies/Multi-Storey Residential Complexes, commercial complexes/malls, IT
parks (hereinafter referred as colonies/complexes) developed by
developers/builders/societies/owners/associations of residents/occupiers
(hereinafter referred as promoters) under bye-laws/rules of the State Govt. not
covered under Regulation 6.6 above, the promoter(s) shall provide complete
Local Distribution (LD) system in the colony/complex as per the electric layout
plan approved by the distribution licensee and shall also borne all expenses
for providing electrical connectivity to such colony/complex by the
distribution licensee as specified in this regulation. The promoter includes
any agency whether Govt./Local body or private that develops the
colony/complex. The residents/occupiers of such colonies/complexes shall obtain
individual connections directly from the distribution licensee and the release
of such connections shall be governed by the following terms and conditions:-
6.7.1 a)
For obtaining the NOC from the licensee, the promoter shall submit the complete
lay out plan of the electrical network i.e. Local Distribution (LD) system
proposed to be erected in the colony/complex and other documents prescribed by
the licensee along with the processing fee as per Schedule of General Charges
within 45 days of the issue of licence. In case the promoter withdraw his
request or fails to comply with the conditions within stipulated time, the
processing fee shall be forfeited. In case of the failure of the promoter to
approach distribution licensee for obtaining NOC within stipulated time, the
matter shall be taken up by the distribution licensee with the licensing
authority for taking action as per law and conditions of licence.
b) For planning the L.D
system of such colonies/complexes, the distribution licensee shall follow the
following norms for assessment of estimated connected load of such
colonies/complexes:
|
Sr. no. Name of category
|
Load (kW)
|
|
1. (Residential plots-Area Based)
|
|
|
a. Up to 100 (Sq. Yards)
|
5
|
|
b. Above 100 to 200 (Sq. Yards)
|
8
|
|
c. Above 200 to 250 (Sq. Yards)
|
10
|
|
d. Above 250 to 350 (Sq. Yards)
|
12
|
|
e. Above 350 to 500 (Sq. Yards)
|
20
|
|
f. Above 500(Sq. Yards)
|
30
|
|
2. (Residential flats-Covered area based))
|
|
|
a. upto 350sqft
|
4
|
|
b. Above 350 to 600
|
5
|
|
c. Above 600 to 900
|
7
|
|
d. Above 900 to1200
|
8
|
|
e. Above 1200 to 1600
|
10
|
|
f. Above 1600 to 1900
|
12
|
|
g. Above 1900-2200
|
13
|
|
h. Above 2200-2600
|
15
|
|
i. Above 2600-3000
|
17
|
|
j. Above 3000
|
20
|
|
3. Group Housing (area based in case detailed layout
plan is not available)
|
37 Watt/Sq. yard
|
|
4. IT Parks
|
21 Watt/Sq. yard
|
|
5. Sites for Hotels and Malls (area based, in case
detailed layout plan is not available)
|
290 Watt/Sq yard
|
|
6. Sites for Hotels and Malls (covered area based if
layout plan based on Punjab Govt. norms & FAR etc. )
|
175 Watt/Sq. yard
|
|
7. Shops/Showrooms/office space in colonies or
complexes (upto 50 Sq. yards)
|
10 kW/Shop/Floor
|
|
8. Shops/Showrooms/office space in colonies or
complexes (above 50 Sq. yards) (Area based, in case detailed layout plan is
not available OR covered area based if layout plan as per Pb. Govt. norms
& FAR etc.)
|
175 Watt/Sq. yard/Shop/Floor
|
|
9. Other commercial plot(s) for dispensary, school,
hospital etc. including other common services failing under commercial
category
|
35 Watts per sq. yard
|
|
10. Load for other common services including Electric
Vehicle charging station(s)
|
As per actual
|
Note:
(1)
Forty percentages (40%) of the total
residential load of plots/flats fifty percentages (50%) of the total commercial
load of commercial complexes/Malls and seventy percentages (70%) of the total
load of IT park as calculated above shall be taken as colony load. The load
shall be converted in k VA by using a power factor of 0.90.
The above norms shall be
applicable for calculating estimated load of the colony/complex where NOC is
issued by the licensee on or after the date of notification of (Electricity
Supply Code and Related Matters) (11th Amendment) Regulations, 2022 in the
Government Gazette.
6.7.2
The distribution licensee shall work out the estimated load of the
colony/complex as per the norms specified in clause (b) of regulation 6.7.1
above and approve the electrical layout plan of Local Distribution (LD) system
in accordance with the construction practices of the distribution licensee. The
distribution licensee, while approving the electrical layout plan, shall design
the LD system in such a way as to ensure optimum utililisation of electrical
network. The transformation capacity should commensurate with the estimated
load of the colony/complex. The estimated cost of the LD system shall be worked
out by the distribution licensee. The expenditure of L.D system including
service cable up to the metering point of each consumer and the 11 kV system in
the colony/complex shall include cost of the material, labour plus 16%
establishment charges there on.
The distribution licensee
shall also plan and approve the 11 kV distribution system for providing
connectivity and to feed the estimated load of the colony/complex from its
distribution network. Accordingly, the distribution licensee shall work out the
connectivity charges which shall include expenditure incurred by the
distribution licensee to provide 11 kV connectivity to the colony/complex and
the System Loading Charges, as specified in this regulation. The expenditure
for providing 11 kV connectivity shall include cost likely to be incurred by
the distribution licensee for providing the individual 11kV service line(s) to
the colony/complex (cable or conductor from pole/tower of feeder/distribution
main to the colony premises/metering point) and proportionate cost of common
portion of the distribution main including breaker from nearest feeding grid
sub-station having power transformer of 33-66/11kV or 132-220/11kV, as the case
may be, which is feeding the 11kV line(s) connected to the colony/complex, as
per the Standard Cost Data approved by the Commission. In case the existing
11kV distribution main is required to be augmented/extended/bifurcated or a new
11kV line/plant is to be erected to allow connectivity to any colony then such
work shall be carried out by the distribution licensee at its own cost provided
the promoter pays the full cost of service line and proportionate cost of the
common portion of the augmented/extended/bifurcated/new distribution main
including breaker as per the Standard Cost Data approved by the Commission.
In addition, the promoter
shall also be liable to pay the System Loading Charges for the total estimated
load of the colony/complex as per the Cost data approved by the Commission. It
shall be the responsibility of the distribution licensee to create necessary
capacity at the grid sub-station at its cost to cater the load of the
colony/complex including the erection or augmentation of grid sub-station or
the transmission network, as may be required by the licensee. After the
connectivity charges including system loading charges are deposited by the
promoter with the distribution licensee, the promoter shall not be liable to
erect grid substation or provide land to the licensee for erection of grid
sub-station.
The connectivity charges as
per this regulation shall be recoverable from the developers who deposit the
connectivity charges with the distribution licensee on or after the date of
publication of these regulations in Punjab Government Gazette.
Provided that in case the
cost of grid sub-station and/or HT/EHT line including bay/breaker or the
connectivity charges including System Loading Charges have been deposited by an
authority under the State Act viz. PUDA/GMADA/GLADA etc., with the distribution
licensee, the connectivity charges including System Loading Charges for the
same shall not be recovered from the developer of such colony/complex.
6.7.3
The promoter shall furnish a Bank Guarantee (BG valid for the period of NOC)
from any bank registered and regulated by RBI equivalent to 35% of the
estimated cost of the LD system of the colony along with connectivity charges
as per regulation 6.7.2 before the approval of the electrical layout plan and
issue of NOC by the distribution licensee. The NOC shall be issued by the
licensee within 45 days of the receipt of proposal complete in all respects
along with requisite documents and the BG to the satisfaction of the licensee.
The BG as per this regulation shall be recoverable from the promoters to whom
the NOC or revised NOC is issued by the distribution licensee on or after the
date of publication of these regulations in Punjab Government Gazette. The
distribution licensee shall ensure that conditions of NOC and time lines for
construction of LD system are implemented by the promoter failing which
punitive action shall be taken by the licensee. The NOC shall clearly spell out
the events of default on the part of developer which may result in encashment
of BG by the distribution licensee.
6.7.4
The temporary connection to the colony/complex shall be released in the name of
promoter only after the issue of NOC by the distribution licensee for carrying
out development works and for other temporary needs as permitted by the
distribution licensee. The temporary connection for the colony/complex shall
only be released through a smart meter with pre-payment features. The competent
officer of the distribution licensee shall verify the test report to ensure
that no load, which is not authorized, is connected by the promoter. It shall
be the responsibility of the load sanctioning authority to ensure that the
temporary connection is not misused by the promoter. In case the promoter is
found to be misusing the temporary supply, the distribution licensee without
prejudice to its right to initiate action under section 126 of the Act read
with regulation 36 of these regulations, shall be authorized to take other
punitive action as may be provided in the NOC. The other terms and conditions
for regulating temporary supply shall be as specified in regulation 8.3 of
these regulations.
6.7.5
The promoter may deposit the estimated cost of Local Distribution (LD) system
of the colony as per approved layout sketch along with connectivity charges as
specified in regulation 6.7.2 and get it executed from the distribution
licensee. The BG accepted by the distribution licensee as specified in
Regulation 6.7.3 shall be returned after the promoter deposit all the requisite
charges. The phase wise development of LD system may be carried out by the
licensee as per requirement but any cost escalation over a period of time shall
be borne by the licensee. The distribution licensee shall be responsible to
release individual connections within the time frame specified in Reg. 8.
6.7.6 (a)
The promoter shall have the option to execute the works of internal LD system
of the colony/complex of its own in accordance with the electric layout
plan/sketch approved by the distribution licensee after submission of necessary
documents, BG etc as specified in Regulation 6.7.2 subject to payment of 15%
supervision charges on the labour cost to the licensee.
Provided that the
distribution transformers and other material to be used for the internal LD
System of the colony shall be as per the specifications approved by the
licensee and shall be procured from the vendors approved by the licensee. The
Distribution Transformers (DTs) may be procured by the developer from the
distribution licensee. However, the developer shall be at liberty to procure
the DTs from the approved vendors of the distribution licensee after getting
the same inspected from the distribution licensee at manufacturer's site. A 21
days' notice shall be served on the distribution licensee by the developer to
inspect the DTs. In case DTs are not inspected within 21 days from the date of
receipt of notice by the distribution licensee from the developer, it shall be
deemed to have been inspected and approved by the distribution licensee.
(b) After completion of the
LD system of the colony/complex and inspection/clearance by the Chief
Electrical Inspector to Govt. of Punjab, the distribution licensee will take
over the L.D system which will be connected to its distribution system after
deposit of connectivity charges by the promoter as specified in Regulation
6.7.2. The BG accepted by the distribution licensee as per regulation 6.7.2
shall be returned to the promoter. The distribution licensee shall thereafter
maintain the L.D system at its own cost. It shall be the responsibility of the
licensee to release connections to the residents/occupiers of the
colony/complex according to the time frame specified in Reg. 8.
Provided that the phase wise
development of LD system may be carried out by the promoter as per requirement.
In case the promoter requests for energisation of incomplete/partial LD system,
the same shall be allowed provided the promoter furnish a Bank Guarantee (BG
valid for 3 years) from any bank registered & regulated by RBI equivalent
to the estimated cost of balance works as per the cost of material and labour
prevailing at the time of allowing connectivity for the partial load plus
expected % age increase in the cost of material & labour in the next 3
years as may be approved by the Commission on the basis of increase in the cost
during the preceding 3 years. This BG may be extended for each block of 3 years
by increasing the base value with expected % age increase in the cost of
material & labour as may be approved by the Commission. The amount of Bank
Guarantee shall keep on reducing with the completion of remaining works of the
L.D system. After submission of Bank Guarantee to the satisfaction of the
licensee, the BG accepted at the time of issue of NoC shall be returned to the
developer.
6.7.7
The developer shall also be responsible to lay service cables up to the
metering point of individual occupier's premises/common service connection
points at its cost. In case meter is installed outside the consumer's premises,
the service cable from the meter up to the main switch of the consumer shall
also be provided at its own cost by the developer. Each resident/occupier of
these colonies/complexes shall submit A&A form for supply of electricity to
the distribution licensee in accordance with Regulation 6 of Supply Code, 2014.
The applicant shall have the right to seek connection for load/demand as per
his/her requirements irrespective of the norms fixed in regulation 6.7.1(b).
The distribution licensee shall not recover any Service Connection Charges from
individual consumers. However, the applicant shall deposit Security
(consumption) and Security (meter) as per Schedule of General Charges. The
distribution licensee shall release the connections within time limits
prescribed in regulation 6.8 & 8.
6.7.8
A promoter shall obtain separate connection for common services under relevant
category. Such connections shall be transferred to RWA or the local authority
after the promoter hands over the colony/complex to such RWA/local authority.
(vi)
Amendment of Regulation 6.8 of the Principal
Regulations
6.8 Acceptance of A&A (Application and
Agreement) Form and Issue of Demand Notice;
The first sentence and
heading of Regulation 6.8.3 shall be substituted as under:
6.8.3
Issue of Demand Notice to
applicants/consumers with load/demand exceeding 50 kW/kVA:
In case of
applicants/consumers covered under Regulation 6.2.1 i.e. with load/demand not
exceeding 50 kW/kVA, no demand notice shall be issued and all charges including
Service Connection charges shall be got deposited along with A&A form. The connection
shall be released on the basis of seniority in order of receipt of application
complete in all respects by the licensee. The demand notices to the
applicants/consumers not covered under Regulation 6.2.1 i.e. with load/demand
exceeding 50 kW/kVA, shall be issued by the distribution licensee as per the
seniority list of the applicants maintained by the distribution licensee for
different categories of consumers as per Regulation 6.8.2. The Demand Notice
shall specify:
(a) -----------
(b) -----------
Regulation - 6. Amendment of Regulation 8 of the principal Regulations.
Time limits for release of
new connection/additional load/demand;
The clause (a) and (b) of
Regulation 8.1 of the Principal Regulations shall be substituted as under;
8.1 The distribution licensee shall provide supply
of electricity to the premises pursuant to the application submitted under
Regulation 6 within time limits mentioned hereunder:
(a)
Where no augmentation, erection and extension
of distribution main, erection/augmentation of distribution transformer or
power transformer is required for effecting such supply, the supply shall be
provided within Seven (7) working days for DS/NRS category consumers and
Fifteen (15) working days for other than DS/NRS consumers from the date of
submission of application complete in all respects in case of consumers covered
under regulation 6.2.1 and from the date of compliance of the Demand Notice in
case of consumers not covered under regulation 6.2.1.
(b)
In cases where augmentation/extension of a
distribution main or augmentation of power transformer or erection/augmentation
of distribution transformer is required but there is no requirement of erecting
and commissioning a new HT/EHT line or grid sub-station or power transformer,
the supply shall be provided within the period specified hereunder;
Type of service connection
requested Period from date of application in cases covered under 6.2.1 and from
the compliance of Demand Notice for cases covered under 6.2.2 within which the
distribution licensee shall provide supply
|
Low Tension (LT) supply
|
30 days
|
|
High Tension (HT) supply
|
|
|
-11000 volts
|
45 days
|
|
- 33000 volts
|
75 days
|
|
Extra High Tension (EHT) supply
|
90 days
|
Provided that the
distribution licensee may, at the earliest but not later than fifteen days
before the expiry of the time schedule, seek approval of the Commission, for
extension of period specified above, in cases where the magnitude of work
involved for extension/augmentation of the supply system is such that the
distribution licensee may reasonably require more time.
Regulation - 7. Amendment of Regulation 12 of the Principal Regulations.
Regulation 12 of the
Principal Regulations shall be substituted as under:
12. Consequences of exceeding sanctioned or
contracted load or contract demand
A consumer shall not exceed
his sanctioned load/contracted load or contract demand, as applicable, as per
the agreement signed between the consumer and the distribution licensee. A
consumer exceeding his sanctioned load/contracted load or contract demand, as
applicable, shall be proceeded against as per Condition 23 of the General
Conditions of Tariff.
Regulation - 8. Amendments in Regulation 16.3 of the Principal Regulations.
The Regulation 16.3 of the
Principal Regulations shall be substituted as under:
16.3
The distribution licensee shall not be entitled to demand Security
(consumption) from any applicant/consumer in case electricity is supplied
through a pre-payment meter.
Provided that in the case a
pre-payment meter is installed at the premises of an existing consumer, the
distribution licensee shall refund the Security (consumption) including
interest charges of such consumer by adjustment against any outstanding dues
and balance amount, if any, shall be refunded through cheque to the consumer.
Regulation - 9. Amendment of Regulation 21 of the Principal Regulations.
USE, ETC. of METERS:
(i)
Regulation 21.1 of the Principal Regulations
shall be substituted as under;
21.1
Requirement of Meters
No connection shall be given without a
meter and such meter shall be the smart pre-payment meter or pre-payment meter.
Any exception to the smart meter or prepayment meter shall have to be duly
approved by the Commission. The Commission, while doing so, shall record proper
justification for allowing the deviation from installation of the smart
pre-payment meter or prepayment meter. All meters shall conform to
CEA(Installation and operation of Meters) Regulations 2006, as amended from
time to time. The term meter shall also include, wherever applicable, other
metering equipment such as current transformer, voltage transformer with wiring
& accessories etc. essentially required for measuring/recording conveyance
of electricity and shall hereinafter called "Meter".
Provided that the existing
meters, other than smart meters, shall be replaced with smart meters with
prepayment facility with effect from date as may be notified separately by the
Commission.
(ii)
Regulation 21.2.1 of the Principal
Regulations shall be substituted as under;
21.2.1
The Consumer meter shall generally be owned by the licensee and the consumer
shall pay the monthly rental for such equipment at rates specified in the
Schedule of General Charges approved by the Commission.
Provided that in case the
licensee has engaged the services of Advanced Metering Infrastructure Service
Provider to provide Advanced Metering Infrastructure services for an Advanced
Metering Infrastructure project area, the ownership of meters shall remain with
Advanced Metering Infrastructure Service Provider during the contract period.
(iii)
Regulation 21.2.3 of the Principal
Regulations shall be amended as under:
21.2.3
The words "real time display unit" shall be substituted by words
"at home display unit".
(iv)
Regulation 21.2.4 of the Principal
Regulations shall be amended as under;
(a)
The first sentence shall be substituted as
under;
In case a meter is installed
outside the premises of a consumer, the service cable from the outgoing
terminals of the meter to Miniature Circuit Breaker/main switch installed at
the consumer premises shall be provided and maintained by the distribution licensee
at its own cost.
(b)
In the second sentence, the words "real
time display unit" shall be substituted by words "at home display
unit"
(c)
The third & fourth proviso shall be
substituted as under:
Provided also that the
location of meter and height of meter display from floor shall be as specified
in IS 15707, as amended from time to time.
Provided also that for
outdoor installations, the meters shall be protected by appropriate enclosure
of level of protection as specified in IS 15707, as amended from time to time.
(v)
The sub-regulation 21.2.7 shall be
substituted as under;
21.2.7
The distribution licensee before introducing any new technology in metering or
changing specifications which may affect the billing of the consumers, shall
inform the consumers through public notice in at least three leading Newspapers
of the State indicating salient features of the new meter and necessary
guidelines for its usage.
Provided that the meter
including any metering equipment conforms to the provisions of CEA Metering
Regulations.
In case of pre-payment
meters, it shall be ensured by the licensee that:
(i)
there is arrangement for recharge of the
credit in the meter by the consumer online and offline within area of his
supply.
(ii)
the meter shall set off alarm when the
balance amount in the meter account has reached the threshold amount defined by
the consumer.
(iii)
the electricity supply shall be automatically
cut-off once the credit gets exhausted in the meter and there shall be no
requirement of 15 days notice. This shall not be treated as disconnection and
the supply shall be resumed automatically on recharging. No reconnection fee
shall be recovered.
(iv)
In case of offline recharge for pre-payment
meter, the coupon shall have validity of three months after which the same
shall be required to be revalidated.
(v)
adequate number of vending machines for
facilitating recharge of coupons in addition to the facility of online recharge
shall be provided.
(vi)
there is vending system interoperability so
that consumer shall not have any problem in getting recharge coupon from
anywhere through any mode as per the availability of the service. It shall be
possible to recharge coupon for different make of meters from any vending
station.
Provided that in case of
pre-paid meter, a rebate of 1% shall be allowed on the energy charges.
(vi)
Amendment of Regulation 21.3 of the Principal
Regulations: Testing of Meters:
(i)
The clause (b) and (c) of the Sub-Regulation
21.3.6 shall be substituted as under:
(b) A consumer may also request the distribution
licensee to test the meter, if he doubts its accuracy. The distribution
licensee shall undertake such testing either at site or in the laboratory
within Fifteen (15) working days on receipt of the request from the consumer.
The testing of meters shall be carried out as per CEA (Installation and
Operation of Meters) Regulations, 2006, as amended from time to time. A copy of
the test results indicating the accuracy of the meter shall be provided to the
consumer immediately.
(c) If after testing, the meter is found to be
correct then the consumer shall be charged testing fee in the electricity bill
for the immediately succeeding billing cycle. In case the meter is found to be
inaccurate/defective/inoperative then no testing fee shall be recovered from
the consumer by the distribution licensee.
Provided that in case meter
is found to be damaged or burnt due to the reasons attributed to the consumer
then the consumer shall bear the cost of the meter along with testing fee
through subsequent bills.
(ii)
Clause (f) to Sub-Regulation 21.3.6 of the
principal Regulations shall be added as under:
If a consumer disputes the
results of testing, the meter shall be tested at a third party testing facility
selected by the consumer from the list of third party testing agencies approved
by the Commission. If it is successfully established that the results of this
test are contrary to the results of the test performed by the distribution
licensee, then the cost of undertaking such test shall be borne by the
distribution licensee. However, in case it is established that the results of
this test are same as the results of the test performed by the distribution
licensee as per clause (e) above, then the cost of undertaking such test shall
be borne by the Consumer. The meter test results and the meter data shall be
issued to the consumer after such test has been completed and the said results
are final and binding on both the consumer and the distribution licensee.
Regulation - 10. Amendment of Regulation 25 of the Principal Regulations.
Regulation 25 of the
Principal Regulations shall be substituted as under;
25.
CONSUMER SERVICE & CONSUMER GRIEVANCES REDRESSAL MECHANISM
25.1
Call Centre for Consumer Services.-
(1)
For providing common services like new
connection, disconnection, reconnection, shifting of connection, change in name
and particulars, load change, replacement of meter, no supply, the distribution
licensee shall establish a centralised 24x7 toll-free call centre with effect
from such date as may be specified by the Commission.
(2)
While other modes to provide services like
paper application, email, mobile, website, etc., may continue, the licensees
shall endeavour to provide all services through a common Customer Relation
Manager (CRM) System to get a unified view of all the services requested,
attended and pending, at the backend for better monitoring and analytics.
(3)
The CRM shall have facilities for SMS, email
alerts, notifications to consumers and officers for events like receipt of
application, completion of service, change in status of application, etc;
online status tracking and auto escalation to higher level, if services are not
provided within the specified time period.
(4)
The distribution licensee shall, in addition
to its notified offices and centralized call centre, set up an adequate number
of complaint centres for the registration/redressal of the complaints by
consumers/applicants.
25.2
Consumer Grievances Redressal Forum
The distribution licensee
shall establish Consumer Grievance Redressal Forum (CGRF) under sub-section (5)
of section 42 of the Act read with Electricity (Rights of Consumers) Rules,
2020 and PSERC (Forum & Ombudsman) Regulations, 2016, as amended from time
to time, at different levels to cater the needs of the sub- division, division,
circle, zone and company level. The forum shall be headed by an officer of the
licensee of appropriate seniority. The forum shall consist of officers of the
licensee and have not more than four members as consumer and prosumer
representatives. The Commission shall nominate one independent member who is
familiar with the consumer affairs. The forum may be assigned different types
of grievances depending on the nature of the grievance and the level at which
it can be best resolved.
Any complainant aggrieved by
the non-redressal of his/her grievance by the distribution licensee may
himself/herself or through his/her authorized representative, approach the
Appropriate Forum established by the distribution licensee as per PSERC (Forum
and Ombudsman) Regulations, 2016, as amended from time to time, in writing for
the redressal of his/her grievance.
In case of non-compliance of
the order of the Appropriate Forum within the specified period, the aggrieved
person may approach the appropriate authority as per the provisions of PSERC
(Forum and Ombudsman) Regulations, 2016, as amended from time to time.
25.3
Redressal of Grievances by Ombudsman
25.3.1
A complainant aggrieved by an order of the Corporate Forum or non-redressal of
grievance by the Corporate Forum within the prescribed period shall have the
right to submit an appeal to the Ombudsman as per the provisions of PSERC
(Forum and Ombudsman) Regulations, 2016, as amended from time to time.
25.3.2
In case of non-compliance of award/order of the Ombudsman within the specified
period, the consumer may approach the Ombudsman as per provisions of PSERC
(Forum and Ombudsman) Regulations, 2016, as amended from time to time.]
25.4
Registration of Complaints/Reporting mechanism
25.4.1
Complaints pertaining to failure/interruption of supply listed in para 1 of
Annexure-1 shall be registered by the distribution licensee at the complaint
centres and/or centralized call centre in the format specified in Annexure-3A.
The complainant shall be immediately intimated of the complaint number and the
date and time of its registration.
25.4.2
All other complaints listed in para 2 to 7 of Annexure-1, shall be registered
in the notified offices of the distribution licensee and/or centralized call
centre in the Proforma at Annexure-3B. The complainant shall be immediately
intimated of the complaint number and date & the time of its registration.
25.4.3
All complaints shall be attended to/rectified first by the officer/functionary
in charge of the notified office within the time limits specified by the
Commission. In case the complainant is not satisfied with the response or there
is no response, the complainant shall have the right to approach the
Appropriate Forum as specified in the PSERC (Forum and Ombudsman) Regulations,
2016, as amended from time to time.
25.4.4
The Commission may at any time review the adequacy of the complaint centres set
up by the distribution licensee and functioning of centralized Call Centre. The
Commission may issue such directions to the distribution licensee as deemed
necessary in the interest of consumers.
25.4.5
The distribution licensee shall every month compile data of complaints
registered in format 3A and 3B, in the proforma at Annexure-4 and furnish the
same to the Commission along with the half yearly/annual reports to be submitted
as per Regulation 27.
25.5
The distribution licensee shall be required to maintain standards of
performance for supply to all consumers as specified in Annexure-1. The periods
specified in these standards are the maximum time permissible for services to
be provided to the consumers. It shall, however, be the endeavor of the
distribution licensee to provide the best possible services well before the
time limits specified in these Regulations.
Regulation - 11. Amendment of Regulation 26 of the Principal Regulations.
PAYMENT
OF COMPENSATION-
Regulation 26 of the
Principal Regulations shall be substituted as under:
26.1
In the event of failure to meet the Standards of Performance specified in
Annexure-1, the distribution licensee shall be liable to pay compensation to
the affected consumers as specified in Annexure-5.
Provided that the maximum
limit of compensation payable in case of violation of any Standard of
Performance shall be Rs. 10,000/- except in case of reference no. 1.2(e), (h),
(i) and 4 of Annexure-5 where the maximum limit of compensation shall be Rs.
20,000/-. In case affected consumers are more than one, the amount of
compensation within this limit shall be shared by all the claimant consumers
for each notified office and this amount shall be distributed equally amongst
all the claimant consumers who have been awarded the compensation by the
competent authority.
26.2
The aggrieved consumer(s) may submit the claim for compensation in the format
to the Nodal officer of the Appropriate Forum and as per the procedure
specified in PSERC (Forum and Ombudsman) Regulations, 2016, as amended from
time to time, within one month from the date of cause of action. The amount
shall be paid to the affected consumer(s) by way of adjustment in the
electricity bills of the immediately succeeding months upon the award of
compensation.
Provided that consumer(s)
shall be automatically compensated, as may be specified by the Commission, for
those parameters which can be monitored remotely when it can be successfully established
that there is a default in performance of the distribution licensee. In such
case, the amount shall be paid to affected consumer(s) in the electricity bills
of the immediately succeeding billing cycle.
Provided further that an
aggrieved consumer(s), not satisfied with the orders of the Appropriate Forum,
may approach the Corporate Forum within 2 months from the receipt of the order
as per the provisions of PSERC (Forum and Ombudsman) Regulations, 2016, as
amended from time to time.
Provided also that the
aggrieved consumer(s), not satisfied with the orders of the Corporate Forum,
may approach the Ombudsman within 30 days from the receipt of the order of the
Forum.
26.3
The compensation payable by the distribution licensee under Regulation 26.1 and
attributable to its negligence/inefficiency shall not be allowed as a
pass-through expense in the Aggregate Revenue Requirements of the Licensee.
Regulation - 12. Amendment of Regulation 30.2 of the Principal Regulations.
(i)
The Regulation 30.2.1 of the Principal
Regulations shall be amended as under:
Following provisos to
Regulation 30.2.1 shall be added;
Provided that the
distribution licensee may use handheld instrument, meter reading instrument
(MRI), or wireless equipment for recording of the meter reading and/or for
generation of spot bill;
Provided further that if
bills are prepared on the basis of AMR, MRI downloads etc and consumer requests
for reading data, the same shall be provided by the licensee.
(ii)
The clause (a) & (b) of Sub-Regulation
30.2.3 of the Principal Regulations shall be substituted as under;
(a)
In the event of anticipated long absence, a
consumer may deposit in advance an amount equivalent to Fixed Charges along
with meter rentals and any other applicable charges for the period of absence.
In such cases when a consumer gives prior information in writing about his
continued absence, the distribution licensee shall not send any notice or
provisional bill to the consumer and his supply line shall not be disconnected.
The interest on such advance payment of electricity bills shall be paid as
specified in these regulations.
(b)
In case of post payment meters, if the meter
reading cannot be taken on account of premises being found locked/inaccessible
on two consecutive scheduled meter reading dates such a consumer shall be
served with a notice to get the reading recorded by a representative of the
distribution licensee within 15 days or have option to send the picture of the
meter indicating the meter reading and date of meter reading through registered
mobile or through registered e-mail to the official authorized by the
distribution licensee, failing which the premises shall be disconnected
temporarily. An official authorized by the distribution licensee shall
personally verify the facts at site before effecting temporary disconnection of
supply. In case of continued non-compliance for one month after temporary
disconnection, permanent disconnection shall be effected without any further
notice. However, temporary disconnection of an essential service consumer may
be effected after due notice and prior approval of the officer authorized by
the distribution licensee if the premises are found locked on three consecutive
scheduled meter reading dates."
(iii)
Regulation 30.2.4 shall be added after
Regulation 30.2.3 of the Principal Regulations as under;
30.2.4 In case of smart
meters, the meters shall be read remotely at least once in every month and in
case of other pre-payment meters, the meters shall be read by an authorised
representative of the distribution licensee at least once in every three
months. The data regarding energy consumption shall be made available to the
consumer, through website or mobile App or SMS, etc. Consumers having smart
prepayment meters may also be given the data access for checking their
consumption on real time basis.
Regulation - 13. Amendment of Regulation 30.3 of the Principal Regulations.
Clause (d) shall be added
after clause (c) to Regulation 30.3 of the Principal Regulations as under:
(d) In case of pre-payment metering, the
distribution licensee shall issue the bill, to the consumer, on his or her
request.
Regulation - 14. Insertion of new regulation 30.5 A in the Principal Regulations.
The Regulation 30.5 A shall
be added after Regulation 30.5 of the Principal Regulations as under;
30.5A
The distribution licensee shall not generate more than two provisional bills
for a consumer during one financial year and if the provisional billing
continues for more than two billing cycles except under extraordinary situation
due to force majeure, the consumer may refuse to pay the dues until bill is
raised by the distribution licensee as per actual meter reading and no late
payment surcharge shall be leviable on such provisional bill.
Regulation - 15. Amendment of Regulation 30.8 of the Principal Regulations.
Delivery
of Bills
The regulation 30.8 of the
Principal Regulations shall be substituted as under;
The bill shall be delivered
to the consumer immediately in case of spot billing and in other cases within a
period not exceeding fifteen (15) days from the date of meter reading except in
case of supply through pre-payment meters.
Provided that the
distribution licensee shall intimate the consumer about despatch of bill (other
than spot bills) through SMS or email, or by both, immediately and the
intimation shall consist of the details of bill amount and the due date for
payment.
The distribution licensee
shall also upload the bill on its website on the day of bill generation:
Provided further that the
billing details of last one year for all consumers shall also be made available
on the licensee's website.
Regulation - 16. Amendment of Regulation 30.10 of the Principal Regulations.
Regulation 30.10 of the
Principal Regulations shall be substituted as under;
30.10
Duplicate Bill
The Distribution Licensee's
notified offices shall maintain facilities to provide duplicate bills
immediately on request from a consumer on payment of requisite fee as specified
in Schedule of General Charges. Non-receipt of the bill, however, may not
entitle a consumer to delay payment beyond the due date.
Provided that in case of
non-receipt of bill, the consumer shall have the option to deposit the bill on
self assessment basis before the due date calculated on the basis of the
consumption of corresponding month of the previous year. In case, the
consumption of the corresponding month of the previous year is not available
then average consumption of last six months shall be considered.
Provided further that the
excess or deficit payment, as the case may be, shall be adjusted in the
subsequent bill(s).
Regulation - 17. Amendment in Regulation 30.11 of the Principal Regulations.
The second sentence in first
proviso to Regulation 30.11 shall be substituted as under;
"In case a consumer
does not receive the first bill by the end of the next billing cycle, he may
inform the officer/functionary in charge of notified office of the distribution
licensee who shall arrange for issue of the bill within seven working
days."
Regulation - 18. Amendments in Regulation 30.12 of the principal Regulations.
The Regulation 30.12 of the
Principal Regulations shall be substituted as under:
30.12 Change of
Occupancy/Vacation of premises
It shall be the
responsibility of the owner/occupant of a premises to get a special reading
done by the distribution licensee at the time of change of occupancy or on the
premises falling vacant. The owner or occupier may request the distribution
licensee in writing for a special reading at least 15 days in advance of such a
change. The distribution licensee shall arrange a special reading and deliver
the final bill, including all arrears till the date of billing, within 7 days
of the meter reading. The final bill shall also include payment for the period
between the date of special reading and the proposed vacation of the premises
on a pro rata basis. On receipt of final payment from the consumer, the
distribution licensee shall issue a No-Dues certificate to the consumer within
7 working days from the receipt of final payment.
Regulation - 19. Amendment in Regulation 31 of the Principal Regulations.
Regulation 31.3 of the
principal Regulations shall be substituted as under;
If the due date indicated in
the bill for payment is a Sunday or a Public Holiday declared by the State
Government or if the distribution licensee's office is closed for any other
reason, the succeeding working day shall be treated as the due date.
Provided that in case of
payment to be made by a consumer through RTGS and the due date indicated in the
bill for payment is a bank holiday/RTGS holiday then the succeeding bank
working day shall be treated as the due date.
Regulation - 20. Amendment of Regulation 33 of the Principal Regulations.
Termination of
Agreement-Regulation 33 of the Principal Regulations shall be substituted as
under:
33.1
In case of continued default in payment of any amount due to the distribution
licensee by any consumer for a period of more than six months, the distribution
licensee shall terminate the agreement executed with the consumer and dismantle
the electric line or works connected with the supply of electricity to the
consumer.
Provided that the
distribution licensee may retain the electric line or plant in case it is
likely to used for other consumers or to retain right of way.
33.2
A consumer may also request the distribution licensee for disconnection of
supply and termination of agreement from a future date. On receipt of such a
request, the licensee shall arrange a special meter reading and prepare the
final bill. The supply shall be disconnected by the distribution licensee
immediately after receipt of all outstanding amounts till that date. The
balance amount due to any consumption between the final reading and the
permanent disconnection, if any, may be adjusted against Security (consumption)
and Security (meter) with the licensee. The balance security deposit shall be
refunded to the consumer within a period of 7 working days.
33.3
If a refund due is delayed beyond a period of seven working days of termination
of the agreement as per regulation 33.1 or 33.2 above, the distribution
licensee shall, without prejudice to other rights of the consumer, pay interest
on such refund for such period of delay at Bank Rate (as on 1st April of each
year) as notified by RBI plus 4%
Regulation - 21. Amendment of Regulation 34.2 of the Principal Regulations.
The first paragraph of
Regulation 34.2 of the Principal Regulations shall be substituted as under;
Where a distribution
licensee has disconnected supply of electricity to any premises in consequence
of a default on the part of the consumer and if the consumer seeks reconnection
within 6 months from the date of disconnection then the distribution licensee
shall resume supply of electricity (other than theft cases) within six working
hours from the time the consumer:
(a)
----------------------------------
(b)
-------------------------------------
(c)
-----------------------------------------
Regulation - 22. Amendment of clause 3 of Annexure-1 of the Principal Regulations.
The clause 3 of Annexure-1
of the Principal Regulations shall be substituted as under;
3.
COMPLAINTS ABOUT METERS
3.1 The distribution licensee shall inspect and
check correctness of a meter within three working days of receipt of a complaint
or report by its authorized official/officer/representative. If the meter is
defective (i.e. it is stuck up, running slow, fast or creeping), the
distribution licensee shall replace the meter within 24 hours in urban areas
and 72 hours in rural areas of the confirmation regarding defective meter from
the field officials.
3.2 The distribution licensee shall replace a
burnt out or stolen meter within 24 hours in urban areas and 72 hours in rural
areas of the receipt of a complaint. Supply to the consumer shall, however, be
immediately restored even by bypassing the meter till such time a new meter is
installed.
Regulation - 23. Amendment of Annexure-2.
OVERALL
STANDARDS OF PERFORMANCE
Annexure 2 of the Principal
regulations shall be substituted as under:
(1)
Long or Sustained Supply Voltage
Interruptions
The Distribution Licensee
shall calculate the reliability of its distribution system on the basis of
number and duration of sustained or long supply voltage interruptions (longer
than 3 min) in a reporting period, using the following indices:
(i)
System Average Interruption Frequency Index
(SAIFI);
(ii)
System Average Interruption Duration Index
(SAIDI);
The Indices shall be
computed for the distribution licensees for each month for all the 11kV and
66/33kV feeders in the supply area, and then aggregating the number and
duration of all interruptions in that month for each feeder. The Indices shall
be computed using the following formulae:
Ai = Total
number of sustained interruptions (each longer than 3 min) on ith feeder
for the month;
Bi = Total
duration in minutes of all sustained interruptions (longer than 3 min) on ith feeder
for the month;
Ni = Number
of Customers on ith feeder affected due to each sustained
interruption;
Nt = Total
number of customers served by the Distribution Licensee in the supply area;
n = number of 11kV and
66/33kV feeders in the licensed area of supply;
(2)
The distribution licensee shall maintain the
reliability on monthly basis within the limits specified in table below:
Table
12: Limits for Reliability indices
|
Reliability Indices
|
Limits
|
|
|
|
URBAN
|
RURAL
|
|
SAIDI
|
600 Minutes per customer
|
900 Minutes per customer
|
|
SAIFI
|
15 interruptions per customer
|
25 interruptions per customer
|
While calculating the given
reliability indices, the following types of interruptions shall not be taken
into account:
(i)
Momentary outages of duration less than three
minutes.
(ii)
Outages due to Force Majeure events such as
cyclone, floods, storms , war, mutiny, civil commotion, riots, lightning,
earthquake, lockout, grid failure, fire affecting licensee's installations and
activities;
(iii)
Outages that are initiated by the National
Load Despatch Centre/Regional Load Despatch Centre/State Load Despatch Centre
during the occurrence of failure of their facilities;
While calculating the given
reliability indices, the interruptions due to scheduled or planned outages
shall be taken into account. The distribution licensee shall strive to capture
reliability indices data directly from the feeder monitoring system and there
should not be any manual interventions as far as possible.
The Distribution Licensee
shall maintain data on the reliability indices specified above for each
zone/circle/division on a monthly basis.
The Distribution Licensee
shall put up, at the end of each month, such monthly information on reliability
indices, on website of the Distribution Licensee and shall submit such report
quarterly to the Commission.
Regulation - 24. Amendments of Annexure 5 of the principal Regulations.
(i)
The Ref No. 3 in the table under Annexure-5
of the Principal Regulations shall be substituted as under:
|
|
|
|
|
Ref.
|
Complaint classification
|
Standard
|
Compensation payable for each block of delay for
violation of standard
|
Designated functionary to deliver the service/Mode of
compensation [Manual(M) or Automatic (A)]
|
|
|
|
|
Compensation payable to individual consumer if the
event affects a single consumer
|
Compensation payable to each consumer if the event
affects more than one consumer
|
|
3.
|
Meter complaints
|
|
|
|
|
|
3.1
|
Inspection and replacement of slow, fast/creeping,
stuck up meters
|
Inspection within 3 working days and replacement within
24 working hours in urban areas and 72 working hours in rural areas of
receipt of confirmation
|
Rs. 200/- for each day of default
|
Not applicable
|
JE/Incharge of area (M)
|
|
3.2
|
Replacement of burnt meters
|
Within 24 working hours in urban areas and 72 working
hours in rural areas of the receipt of complaint.
|
Rs. 300/- for each day of default
|
Not applicable
|
JE/Incharge of area (M)
|
|
(ii)
The Ref. No. 8 shall be added in the
table under Annexure-5 of the Principal Regulations as under;
|
|
8.
|
Long Supply Voltage Interruptions
|
|
|
|
|
(a)
|
SAIDI in Minutes per consumer
|
(i) 600 minutes/consumer for urban areas
(ii) 900 minute/consumer for rural areas
|
5 paisa/minute/kW or kVA beyond the specified limit
|
2 paisa/minute/kW or kVA beyond the specified limit
|
Feeder incharge (M)
|
|
(b)
|
SAIFI in interruptions per consumer
|
(i) 15 interruptions/consumer for urban areas
(ii) 25 interruptions/consumer for rural areas
|
Rs. 50 per interruption beyond the specified limit
|
Rs. 20 per interruption beyond the specified limit
|
Feeder incharge (M)
|
(iii)
Following note below the table under Annexure
5 shall be added:
In the event of the failure
of the distribution licensee to meet the Standards of Performance against Ref.
No 1.1, 1.2, 1.3, 1.4 and 4 specified in the table above, the affected
consumer(s) shall be automatically compensated as specified in Regulation 26 of
these regulations.
Regulation - 25. Amendment of Annexure-8; Assessment of Electricity Charges in Case of Unauthorised Use/Theft.
(i)
Sub-clause a(i) of clause (1) of Annexure 8
shall be substituted as under;
The consumption of
electricity in such case will be computed on the basis of the meter reading.
However, in case where electricity is used for the purpose other than for which
the usage of electricity was authorized (U/S 126 (6) (b) (iv) of the Act) then
assessment shall be made in proportion of the load used for other purpose i.e.
unauthorised load to the total load as explained under. In case where
electricity is used for the premises or the areas other than those for which
the supply of electricity was authorized (U/S 126 (6) (b) (v) of the Act) then
assessment shall be made in proportion of the load extended to other premises
or area i.e. unauthorised load to the total load including extended load as
explained under.
Explanation:
Quantum of assessed consumption
of energy (Q) = C x (A/B)
Where C - Total Consumption
recorded by the healthy meter during the period of assessment (in kWh or kVAh,
as applicable)
A = Unauthorised load (kW)
detected at the time of inspection
B = Total Load detected (kW)
at the time of inspection
(ii) Clause (4) of Annexure
8 shall be amended as under;
Unit Assessed= LxDxHxF where
L for consumers covered
under non-contract demand system shall be load found connected during
inspection in kW and
L for consumers covered
under contract demand system shall be the sanctioned contract demand or the
maximum demand recorded during last one year which ever is highest.
D is the number of working
days per month ------------------------------
H is use of supply hours per
day ------------------------------------
F is demand factor
-------------------------------------------------