Petroleum and Natural Gas Regulatory Board
(Technical Standards and Specifications including Safety Standards for
Petroleum Installations) Regulations, 2020
Petroleum and Natural Gas
Regulatory Board (Technical Standards and Specifications including Safety
Standards for Petroleum Installations) Regulations, 2020
[11th
November, 2020]
In exercise of the powers
conferred by Section 61 of the Petroleum and Natural Gas Regulatory Act, 2006
(Act 19 of 2006), the Petroleum and Natural Gas Regulatory Board hereby makes
the following Regulations, namely:—
Regulation - 1. Short title and commencement.
(1) These Regulations may be
called the Petroleum and Natural Gas Regulatory Board (Technical Standards
and Specifications including Safety Standards for Petroleum Installations)
Regulations, 2020.
(2) They shall come into force
on the date of their publication in the Official Gazette.
Regulation - 2. Definitions.
(1) In these regulations,
unless the context otherwise requires,
(a) “Act” means the Petroleum
and Natural Gas Regulatory Board Act, 2006 (Act 19 of 2006);
(b) “Board” means the Petroleum
and Natural Gas Regulatory Board established under sub-section (1) of Section 3
of the Act;
(c) “Bonding” means the process
by which two electrical conducting bodies are connected using a conductor to
maintain electrical continuity to prevent sparking;
(d) “Clean agent” means
electrically nonconductive, volatile or gaseous fire extinguishing medium that
does not leave a residue upon evaporation and meets the requirements given in
the latest NFPA 2001 on clean agent fire extinguishing systems in line with
environmental considerations of Kyoto and Montreal Protocol and latest MOEF
regulations (Government of India, Ministry of Environment, Forest and Climate
Change);
(e) “corrosion” means all forms
of wastage, and includes oxidation, scaling, mechanical abrasion and corrosion;
(f) “design pressure” means the
pressure used in the design of equipment, a container, or a vessel for the
purpose of determining the minimum permissible thickness or physical characteristics
of its different parts and where applicable, static head shall be included in
the design pressure to determine the thickness of any specific part;
(g) “Dyke” means an area that
may be defined through the use of structure or the topography at the site for
the purpose of containing any accidental spill of petroleum products;
(h) “Earthing” means the
provision of a safe path of electrical current to ground, in order to protect
structures, plant and equipment from the effects of stray electrical current,
and electrostatics discharge;
(i) “Effluent Treatment Plant
(ETP)” means a mechanism and process used to treat waters that have been
contaminated due to presence of Oil or sludge or Grease or chemicals or sewage
generated of different activities or operations in petroleum installations;
(j) “Emergency Shutdown System”
means a system that safely and effectively stops whole plant or an individual
unit before unrecoverable incidents occurs;
(k) “Explosive mixture” means a
mixture of combustion agent (oxidising product gas, vapour, liquid or solid)
and a fuel (oxidisable product - gas, liquid or solid) in such proportions that
it could give rise to a very rapid and lively oxidization reaction liberating
more energy than is dissipated through conduction and convection; and—
(i) “Lower explosive Limit
(LEL)” means the minimum concentration of a vapour in air (or other oxidant)
below which propagation of flame does not occur on contact with an ignition
source and such limit is usually expressed as volume percentage of the vapour
in air;
(ii) “Upper Explosive Limit
(UEL)” means the maximum concentration of a vapour in air (or other oxidant)
above which propagation of flame does not occur on contact with an ignition
source and such limit is usually expressed as a volume percentage of vapours in
air;
(l) “Failsafe” means design
features which will maintain or result in safe operating conditions in the
event of a malfunction or failure of power, instrument air, components or
control devices;
(m) “Fixed-Length Dip Tube”
means a pipe that has a fixed open end fitted inside a container at a
designated elevation that is intended to show a liquid level;
(n) “flammability range” means
the difference between the minimum and maximum percentage by volume of the gas
in mixture with air that forms a flammable mixture at atmospheric pressure and
ambient temperature;
(o) “Flash Point” means the lowest
temperature at which the liquid yields vapour in sufficient concentration to
form an ignitable mixture with air and gives a momentary flash on application
of a small pilot flame under specified conditions of test as per IS : 1448
(Part-I);
(p) “Hazardous Fluid” means a
liquid or gas that is flammable or toxic;
(q) “Hazardous Area” means the
locations classified according to Zone System which defines the probability of
the hazardous material, gas or dust, being present in sufficient quantities to
produce explosive or ignitable mixtures which require special precautions for
the construction, installation and use of electrical apparatus as specified
below:
(i)
“Zone
0” means ignitable concentrations of flammable gases or vapours which are
present continuously or for long periods of time;
(ii)
“Zone
1” means ignitable concentrations of flammable gases or vapours which are
likely to occur under normal operating conditions; and
(iii)
“Zone
2” means ignitable concentrations of flammable gases or vapours which are not
likely to occur under normal operating conditions and do so only for a short
period of time;
(r) “Intrinsically Safe” means
a circuit or part of a circuit, which is intrinsically safe when any spark or
thermal effect produced normally (that is, by breaking or closing the circuit)
or accidentally (for example, by short circuit or earth fault) is incapable,
under specific test conditions for such purpose, of causing ignition of a
specific gas or vapour and an intrinsically safe apparatus is one in which all
electrical circuits are intrinsically safe;
(s) “Non-Hazardous area” means
an area in which an explosive gas atmosphere is not expected to be present in
quantities such as to require special precautions for the construction,
installation and use of electrical apparatus;
(t) “Ignition Source” means any
item or substance capable of an energy release of type and magnitude sufficient
to ignite any flammable mixture of gases or vapours that could occur at the
site;
(u) “Maximum Allowable Working
Pressure” means the maximum gauge pressure permissible at the top of equipment,
a container or a pressure vessel while operating at design temperature;
(v) “NDT” means Non-Destructive
Testing methods like Dye Penetration Inspection, Wet Fluorescent Magnetic Particle
Inspection, Ultrasonic thickness checks, Ultrasonic Flaw Detection,
Radiography, Hardness Test and other relevant Inspection procedures carried out
to detect the defects in the welds and parent metal of the pressure vessel;
(w) “Oil water separator (OWS)”
means a system designed to separate gross amount of oil and suspended solids
from the oily water effluent generated due to different activities or
operations in Petroleum Installations;
(x) “onshore” means areas other
than offshore which shall form the scope of these regulations and Feeder lines
from or to jetty or other storage points shall also form a part of the onshore
pipelines;
(y) “petroleum” means any
liquid hydrocarbon or mixture of hydrocarbons and any inflammable mixture
(liquid, viscous or solid) containing any liquid hydrocarbon, including crude
oil and liquefied petroleum gas, and the expression ‘petroleum product’ shall
mean any product manufactured from petroleum and Petroleum products are
classified according to their closed cup flash points as given below; namely:—
(i)
Class-A
Petroleum : Liquids which have flash point below 23 °C;
(ii)
Class-B
Petroleum : Liquids which have flash point of 23 °C above but below 65 °C;
(iii)
Class-C
Petroleum : Liquids which have flash point of 65 °C and above but below 93 °C;
(iv)
Excluded
Petroleum : Liquids which have flash point of 93 °C and above; and
(v)
Liquefied
gases including Liquified Petroleum Gas (LPG) do not fall under this
classification but form separate category;
(z) “Petroleum Installation”
means a depot or terminal having facilities for storing, handling,
distribution, transportation, loading or unloading of petroleum, oil and
lubricants;
(aa)
“pressure vessel” means any closed metal
container of whatever shape, intended for the storage and transport of any
compressed gas which is subjected to internal pressure and whose water capacity
exceeds one thousand liters and includes inter connecting parts and components
thereof up to the first point of connection to the connected piping and
fittings, but does not include containers wherein steam or other vapour is or
is intended to be generated or water or other liquid is or is intended to be
heated by the application of fire or the products of combustion or by
electrical means, heat exchangers, evaporators, air receivers, steam type
digestors, steam type sterilizers, autoclaves, reactors, calorifiers, pressure
piping components such as separators or strainers and vessels containing a
liquid under a blanket of compressed inert gas;
(bb)
“Pumpable Capacity (Net Capacity)” means
the capacity of the tank during operation after subtracting the volume of tank
bottom contents up to the top of pump out nozzle from safe filling capacity of
the tank;
(cc)
“Safe Capacity of a Tank” means the
capacity of the tank up to the maximum safe filling height (safe filling level)
of the tank as per statutory requirements and the safe fill level shall be
established for each specific tank that will depend on the type of tank,
diameter, its internal configuration and condition, rate of filling and the
operating practices;
(dd)
“Safety relief device” means an automatic
pressure relieving device actuated by the pressure upstream of the valve and
characterized by fully opened pop action, intended to prevent the rupture of a
pressure vessel under certain conditions of exposure;
(ee)
“Schedule” means the schedule appended to
these regulations;
(ff)
“Service Building” means building
housing facilities for inspection or maintenance or other supporting services
which are directly required for operation of the installation;
(gg)
“Shall” indicates a mandatory
requirement;
(hh)
“Should” indicates a recommendation or
that which is advised but not mandatory;
(ii)
“Slop” means off-specification products
obtained from market that is to say Retail Outlet and like other outlets,
during any disturbance in operation and draining and like other activities from
various equipment or tanks or pumps containing oil-water mixture, but does not
include interface generated during pipe line transfer operations;
(jj)
“Source of ignition” means naked lights,
fires, exposed incandescent materials, electric welding arcs, lamps, other than
those specially approved for use in flammable atmosphere, or a spark or flame
produced by any means;
(kk)
“Stabling Line” means an additional
railway line or spur reserved for additional rake or stabling;
(ll)
“Utilities” means buildings consisting
of administrative building, QC Laboratory, canteen, parking shed, air
compressors with or without dryers, dryers and like other device which shall be
separated from other POL facilities and located as per the separation distance
as specified in the standard in this regard.
(2) Words and expressions, used
and not defined, in these regulations, but defined in the Act or in the rules
or regulations made there under, shall have the meanings respectively assigned
to them in the Act or in the rules or regulations, as the case may be.
Regulation - 3. Application.
Definitions, layout,
design, standard operating procedures, maintenance, inspection, competence
assurance, fire protection, safety management plan and vehicle management
system of Petroleum Installations shall be in accordance with the requirements
of these regulations. These regulations do not apply to petroleum installations
with aggregate storage capacity less than 1000 KL.
Regulation - 4. Scope.
(1) Requirements of these
regulations shall apply to all existing and new Petroleum Installations.
(2) These regulations cover
safety in design, material and equipment, piping system components and
fabrication, installation and testing, commissioning, corrosion control,
operation and maintenance and safety of Petroleum Installations.
(3) These regulations also
cover engineering considerations in design and installations including fire
protection and safety systems.
(4) These regulations do not
cover the requirements in respect of liquified petroleum gas (LPG)
installations.
Regulation - 5. Objective.
These standards are
intended to ensure uniform application of design principles in layout, material
and equipment selection, construction, operations, maintenance and like other
process, as mentioned in Regulation 3 above for safe operation at the facilities
associated with Petroleum Installations.
Regulation - 6. The standard.
The technical standards and
specifications including safety standards (hereinafter referred to as
standards) for Petroleum Installations are as specified in Schedule which cover
layout, design, standard operating procedures, maintenance, inspection,
competence assurance, fire protection, safety management plan and vehicle
management system.
Regulation - 7. Compliance to these regulations.
(1) The Board shall monitor the
compliance to these regulations either directly or through an accredited third
party as per regulations applicable for such purpose on third party conformity
assessment.
(2) The Board of the concerned
entity, within ninety days of the commencement of these regulations shall
appoint one of its directors, who shall be responsible for ensuring compliance
to these regulations
(3) Any entity intending to set
up a Petroleum installation shall make available its detailed plan including
design consideration conforming to these regulations to Petroleum and
Explosives Safety Organisation (PESO) for their approval.
(4) If an entity before the
commencement of these regulations, has laid, built, constructed, kept under
construction or expanded the Petroleum Installation based on some other standard
or is not meeting the requirements specified in these regulations, the entity
shall carry out a detailed Quantitative Risk Analysis (QRA) of its
infrastructure and the entity shall thereafter take approval from its highest
decision making body or its board for non-conformities and mitigation measures
and the entity's board approval along with the compliance report, mitigation
measures and implementation schedule shall be submitted to Petroleum and
Natural Gas Regulatory Board by such entity within six months from the date of
commencement of these regulations.
Regulation - 8. Default and Consequences.
(1) There shall be a system
maintained by the entity concerned for ensuring compliance to the provision of
these regulations through conduct of technical and safety audits during the
construction, commissioning and operation phase.
(2) In case of any deviation or
shortfall in compliance with the provision of these regulations, the entity
shall be given time limit for rectification of such deviation, shortfall,
default and in case of non-compliance thereafter, the entity shall be liable for
the penal action under the provisions of the Act or termination of operation or
termination of authorization.
Regulation - 9. Requirements under other statutes.
It shall be necessary to
comply with all statutory rules, regulations and Acts in force as applicable
and requisite approvals shall be obtained from the relevant competent
authorities for Petroleum Installations.
Regulation - 10. Miscellaneous.
(1) If any dispute arises with
regard to the interpretation of any of the provisions of these regulations, the
decision of the Board shall be final.
(2) The Board may at any time,
by notification in the Official Gazette, effect appropriate modifications in
these regulations.
(3) The Board may issue
guidelines consistent with the Act to meet the objective of these regulations
as if deems fit.
SCHEDULE — 1
Technical
Standards and Specifications including Safety Standards for Petroleum
Installations
(See
Regulation 6)
—PART-A
(Design
and Layout)
1.0 INSTALLATION LAYOUT:
1.1 LAYOUT PHILOSOPHY.—Following philosophy, which
is fundamental in the implementation of these regulations relating to lay out
of installation, should be adopted in layout of an installation:
(1) Presence of ignition source
shall always be contemplated beyond the boundary wall of installation;
(2) Quantitative Risk Analysis
or Assessment shall be carried out at the layout stage with an objective to
arrive at any specific mitigation measures required for Hazards identified.
Risk reduction or mitigation measures shall be given due credit as below:
(i) Risk assessment shall
include Unconfined Vapour Cloud Explosion (UVCE). The outcome shall guide in
preparation of onsite or off-site emergency plan; and
(ii) Quantitative Risk
Assessment (QRA) shall be done whenever major addition in facilities or major
change in the surrounding areas, operating parameters, product grade takes
place or once in every five years, whichever is earlier;
(3) Approaches from the highway
or major road should be provided for normal or emergency movement with minimum
road width of 3.5 metres for one-way movement;
(4) Roads inside the hazardous
area of Installation shall be restricted to vehicles required for operational,
maintenance and safety or security reasons and allowed only with proper safety
fittings and authorization from location in-charge or designated safety
officer, except tank trucks coming inside for filling or decantation;
(5) Alternative access shall be
provided for each facility so that it can be approached for firefighting in the
event of blockage on one route;
(6) Road widths, gradient and turning
radii at road junctions shall be designed to facilitate movement of the
fire-fighting vehicle envisaged in the event of emergency. Minimum road width
of 3.5 M should be maintained for each way. The turning radius at the gantry
shall be designed to facilitate the smooth movement of the tank trucks
(including trailer mounted);
(7) Rail spur should be located
close to the boundary of the installation to minimise road or pipe crossings
and blockage of roads during shunting. The rail spur should be designed in line
with the Railway Guidelines;
(8) Layout should consider the
space requirements for—
(i) Maintenance and inspection
of each equipment or facility;
(ii) Dedicated area for
construction or fabrication activities; and
(iii) Future expansion for
addition of facilities;
(9) Vehicles with spark
ignition engine shall not be allowed in the hazardous area. Vehicles with
internal combustion engine (compression ignition) such as tank truck (fuelled
by HSD) required to be permitted for business shall have Petroleum and
Explosives Safety Organization (PESO) approved tank body with approved spark
arrestor fitted on the vehicle; and
(10) Layout drawing indicating
hazardous and non-hazardous area segregation or demarcation shall be available.
Hazardous area segregation or demarcation shall be as per IS 5572 : 2009.
1.2 LAYOUT OF FACILTIES.—To prepare a layout,
information should be collected on all applicable affecting aspects and not
limiting to following, namely:—
(1) Storage tanks, utility
requirements;
(2) Town planning;
(3) Product receipt or dispatch
and mode of transport (Rail, Road, Pipeline and Tanker or Barge);
(4) Warehouses, storage areas
for bitumen or asphalt, lube and like other lubricants and other open storage
areas like scrap yards and dumping ground;
(5) Chemicals or Toxic
chemicals storage, Sludge, hazardous waste storage or disposal facilities and
like other facilities;
(6) Service buildings, fire
station and allied facilities;
(7) Site topography including
elevation, slope, and drainage;
(8) Meteorological data;
(9) Bathymetric data (high tide
level, surge wave height and like other tidal surge) for installations in
coastal areas;
(10) Seismic data and
probability of Tsunami in coastal areas;
(11) Highest flood level in the
area, water table, natural streams or canals;
(12) Approach roads for
functional areas;
(13) Aviation considerations to
and from adjacent facilities;
(14) Environmental
considerations including water treatment plant and reuse of treated water, rain
water harvesting and roof top solar system with connectivity to grid; and
(15) Statutory requirements.
1.2.1 GENERAL CONSIDERATION.—While locating the
various facilities the following should be considered, namely:—
(1) Tank farm, loading or
unloading gantry, utilities, Effluent Treatment Plant (ETP) or mechanised OWS,
Drains and culverts and approach roads should be suitably constructed to
prevent flooding;
(2) Control room should be
located in a non-hazardous area, upwind (Majority of the year) of hydrocarbon
storage and handling facilities and at a distance from potential leak sources.
It shall not be located on a lower level than surrounding plants and tank
farms. There shall be no structure in close vicinity that would fall on the
control room in case of a blast. Control Room should be situated at such a
place in the layout from which most of the facilities or activities of the
location are visible;
(3) In case, it is unavoidable
to comply with inter distance requirements for control room, the control room
shall be made blast resistant;
(4) The control room for
Pipeline Tap off Point (TOP) (if applicable) at the same location of the same
company, shall be in the same building where the Control room for Depot or
installation is located;
(5) Utility block should be
located outside the hazardous area;
(6) Overhead power transmission
lines shall not pass over the installation including the tank truck parking
areas. Horizontal clearance shall be in line with the Central Electricity
Authority;
(7) High Tension (HT) line and
HT sub-station shall be terminated or located outside the hazardous area as per
distance as specified in Table-1 in this Part;
(8) Tank truck movement inside
the installation shall be kept to minimum and for this purpose the truck
loading or unloading facilities should be located at a safe distance near the
gate meant for its movement and should be oriented to provide one-way traffic
pattern for entrance and exit. Tank truck in the gantry shall always be in
drive out position for easy escape in case of emergency;
(9) Rail loading or unloading
facilities should be located along the boundary of the installation. In case
Tank wagon (TW) unloading facilities are located outside of installation
boundary that should also have a boundary wall as per MOHA or Government
Guidelines;
(10) Drain shall be provided
around the TT gantry loading platform area to collect product due to accidental
spill over or leakage and shall be routed to OWS or ETP. The drains shall
always be maintained clean;
(11) Effluent Treatment Plant
should be located at a distance as per distance as specified in Table-1 in this
Part. This should be closer to disposal point by the side of the boundary and
at lower grade to facilitate gravity flow of effluent;
(12) Roads should be provided in
a symmetric manner to serve all areas requiring access for the operation,
maintenance and firefighting;
(13) Smoking booths shall not be
provided in Petroleum Installations, but, drinking water booths can be provided
at prominent work stations like TLF, TW siding and like other places;
(14) Firewater storage and
firewater pump house should be located upwind of hydrocarbon storage area with
straight approach from outside area to enable easy receipt of mutual aid and
make up water;
(15) The provision shall be made
to receive water from external sources directly into fire water storage tanks
and this can be from mutual aid members, fire brigade and like other devices;
(16) All buildings which are not
related to terminal operation should be located at upwind of hydrocarbon
storage and handling facilities and they shall be located outside the hazardous
area, and such areas include administration, canteen with a separate entry and
special care needs to be taken for canteen location where any spark or open
flame is likely to exist;
(17) Congestion inside the
hazardous area because of buildings, structures, pipelines, trees and like
other things shall not be allowed. The location of such addition of facilities
in existing installation shall be decided based on Risk Assessment;
(18) Room for storing
hydrocarbon samples shall be provided with bottom exhaust for release of
flammable vapours. The racks and flooring should be made of fire resistant
material. Electrical fittings as well as electrical equipment shall be
flame-proof. Adequate number of portable fire extinguishers should be placed,
where required;
(19) The additives or blue dye
and like other substances should be stored at the designated or segregated area
as per respective Material Safety Data Sheet; and
(20) Special precautions should
be taken as required where ambient temperatures or the handling temperatures
are higher than the flash point of the product or where product handled is
artificially heated to a temperature above its flash point.
1.2.2 LAYOUT OF STORAGE
TANKS:
1.2.2.1 Dyked Enclosures.—
(1) Petroleum storage tanks
shall be located in dyked enclosures. Each dyke shall have roads all around for
access for normal operation and maintenance as well as for emergency handling.
Aggregate capacity (Combined safe capacity) of tanks located in one dyked
enclosure shall not exceed following values, namely:—
(i) 60,000 KL for a group of
fixed roof tanks.
(ii) 120,000 KL for a group of
floating roof tanks
Safe Capacity limits do not
apply to a single tank in a dyke.
Fixed cum floating roof
tanks shall be treated as fixed roof tanks but, in case these tanks are provided
with windows opening on the shell and these windows will not get blocked in any
case, then they shall be considered as floating roof tanks.
If a group of tanks
contains both fixed and floating roof tanks, then, it shall be treated as a
group of fixed roof tanks for the purpose of above limits specified in clauses
(i) and (ii).
(2) Dyked enclosure shall be
able to contain the complete contents of the largest tank in the dyke in case
of any emergency. A free board of 200 mm above the calculated liquid level or
10% of calculated dyke capacity, whichever is higher, shall be provided for
fixing the height and capacity of the dyke.
Enclosure capacity shall be
calculated after deducting the following volumes, namely:—
(i) Volume of the tanks other
than largest tank up to enclosure height without free board;
(ii) Volume of all tank pads;
(iii) Volume of fire breaks
walls; and
(iv) Volume of pipes/supports or
steps and like other volume.
(3) The height of tank
enclosure dyke (including free board) shall be at least 1.0 M and shall not be
more than 2.0 M above average inside grade level, and—
(i) Tank farm area shall be
covered through CCTV surveillance system and same shall be continuously
monitored;
(ii) The dyke wall made up of
earth, concrete or solid masonry shall be designed to withstand the hydrostatic
load and shall be impervious;
(iii) Dyke enclosure area (inside
area of the dyke) shall be also impervious to prevent the ground water
pollution;
(iv) Dyke enclosure (entire area
of the dyke) shall have impervious layer of suitable material such as EPDM
(ethylene propylene di-monomer) liner or polyethylene sheet to prevent the
ground water contamination in addition to brick or stone pitching PCC and like
other materials;
(v) The dyke and the enclosures
will be inspected for cracks, visible damage and like other deficiencies. every
six months (pre and post monsoons) and after every major repair in the tanks or
dykes and like other appliances so as to keep it impervious;
(vi) The dyke area shall have
proper slope outward of tank pad towards the inner periphery of the dyke
enclosure to prevent reverse flow;
(vii) Earth-pits shall be
provided outside of Dyke area and strips buried under the earth except at
termination points from a shortest possible distance. The earthing lay out
diagram of each facility should be displayed near each facility for reference;
(viii) For excluded petroleum, the
capacity of the dyked enclosure should be based on spill containment and not
for containment on tank rupture. The minimum height of dyke wall in case of
excluded petroleum shall be 600 mm;
(ix) Pump stations and piping
manifold should be located outside dyke areas by the side of roads;
(x) Horizontal above ground
tanks mounted on pedestals shall meet separation distances and shall have dyked
enclosure;
(xi) The construction of dyke
exceeding 2 M may be considered where there is severe constraint on space
availability. In such case, additionally following conditions must be
fulfilled, namely:—
(a) Total dyke capacity shall
be based on containment of largest tank capacity;
(b) Monitors on raised platforms,
if required, shall be provided so that throw of the monitors are not
restricted;
(c) All the tanks inside such
dyke shall be provided with sprinkler system, irrespective of the tank dia; and
(d) Tank farm area shall be
covered through CCTV surveillance system and same shall be continuously
monitored.
(xii) In case of Under Ground
Tanks:—
(a) kerb wall of minimum 300 mm
height shall be provided in the UG tank Farm Area to contain accidental
overflow;
(b) a minimum of 3 M clear
distance around the tank shall be maintained (from structures or boundary
wall);
(c) vents shall be
located/terminated at a distance of 15 M from electrical hazards.
(d) pressure or Vacuum vents
for —a class intends that a product and free vents for other class of products
shall be provided and vent shall be at minimum 4 M height from the grade level;
(e) the open end of free vent
pipe shall be covered with two layers of non-corrodible metal wire gauze having
not less than 11 meshes per linear centimetre and shall be further protected
from rain by hood or by suitably bending it downward;
(f) the petroleum products
shall enter a tank through closed piping system or coupled electrically
continuous and sound hose;
(g) under Ground tanks for
Ethanol service shall be provided with Silica Gel Traps in the Vents to prevent
moisture ingress;
(h) the manholes should be 30
cm above the grade level; and
(i) corrosion control measures
shall be undertaken.
1.2.2.2 Grouping of Storage
tanks.—
(1) Grouping of tanks in a dyke
should be made by grouping the storage tanks in a dedicated dyke according to
their respective classification of petroleum product;
(2) In case, different class of
products are stored in any combination of product classification, the following
shall, be applicable, namely:—
(i) Grouping of petroleum
products for storage shall be based on the product classification. Class-A and
Class-B petroleum may be stored in the same dyked enclosure and such Class—A
and Class—B are stored in common dyke, so that fixed water spray system shall
be provided on all tanks except for small installations as mentioned in
paragraph 5.1.2 (8) of this schedule and the Rim seal fire detection and
extinguishing system shall be applicable only to floating roof tanks on Class —
A service.
(ii) Class-C petroleum should
preferably be stored in separate enclosure;
(iii) Where Class-C petroleum is
stored in a common dyke along with Class-A and/or Class-B petroleum, the fixed
water spray system shall be provided on all Class C tanks irrespective of
diameter except for small installations as mentioned in paragraph 5.1.2 (8) of
this schedule;
(3) Excluded petroleum shall be
stored in a separate dyked enclosure and shall not be stored along with
Class-A, Class-B or Class-C petroleum. In case, it is stored in the same dyke,
the requirements that is to say Firefighting, interlocks, alarms, foam and like
other requirements shall be in line with the requirements for the Class of
product that is to say Class-A or Class-B or Class-C stored in the same dyke.
(4) Tanks shall be arranged in
maximum two rows so that each tank is approachable from the road surrounding
the enclosure and such arrangements need not be applied to tanks storing
excluded petroleum class;
(5) Tanks having 50,000 KL
capacities and above shall be laid in single row.
(6) For tertiary containment,
provision shall be made to prevent escape of spills due to failure of secondary
containment for any reasons and not to allow such spill over to outside of the
boundary of the installation that may lead to any damage to outside; and to
meet the objective, all installations shall be provided with boundary wall with
gates and sluice gates on drain. Pipe line openings and like openings shall be
sealed. Efforts should be made to minimize such openings for drainage.
1.2.2.3 Fire walls inside
dyke enclosure.
(1) In a dyked enclosure where
more than one tank is located, firewalls of minimum height of 600mm shall be
provided to prevent spills from one tank endangering any other tank in the same
enclosure;
(2) A group of small tanks each
not exceeding 9 meters in diameter and in all not exceeding 5,000 KL in
capacity shall be treated as one tank for the provision of firewall; and
(3) For excluded petroleum
product storage, firewall of height not less than 300 mm shall be provided by
limiting the number of tanks to 10 or the capacity of group of tanks to 5,000
KL, whichever is lower.
1.2.2.4 General.
(1) The tank height shall not
exceed one and half times the diameter of the tank or Maximum 20 m, whichever
is less;
(2) Every Piping from or to any
tank including connected sprinkler or foam line shall comply the following,
namely:—
(i) It shall not pass through
any other dyked enclosure;
(ii) It shall run directly to
outside of dyke to minimise piping within the enclosures; and
(iii) It shall not pass through
other tank areas or fire walls.
(3) Piping layout design inside
tank dyke area should ensure easy accessibility for any operations in the tank
farm and wherever necessary, well designed, cross-overs shall be provided to
cross the pipelines running within the dyke area. Elevated Catwalks connecting
the tank manifold to the dyke wall above the height of the dyke wall shall be
provided for safe access and exit in case of normal or emergency situations.
The catwalks shall run at the same level and terminate directly outside the
dyke;
(4) No part of the dyked
enclosure shall be below the level of surrounding ground immediately around the
outside of dyke area;
(5) The minimum distance
between a tank shell and the inside toe of the dyke wall shall not be less than
half the height of the tank; and
(6) Properly laid out road
shall be provided for easy access on all four sides of each dyke.
1.2.2.5 Protection of
facilities.
(1) Properly laid out roads
around various facilities shall be provided within the depot or terminal for
smooth access of fire tenders and like other trends in case of emergency;
(2) The boundary wall shall be
constructed as per the directives of the Ministry of Home Affairs or any other
Government directive. In any case the boundary wall shall be of minimum 3 M
height from either side of boundary wall with V/U shaped barbed wire fencing on
the wall with 600 mm diameter concertina coil on top;
(3) There shall be a pedestrian
patrolling track along the inside perimeter of the boundary wall for security
patrolling. Security watchmen tower (if provided) shall have clear access;
(4) The emergency gate shall be
away from the main gate for evacuation of vehicles and personnel in emergency
and shall always be kept available and free from obstruction;
(5) CCTV shall be installed in
depot or terminal locations covering entry or exit gate, periphery of
installation and all critical operating areas (such as Tank farm, TT or TW
operating area, product pump house, fire water pump house and like other
places) which shall be monitored continuously;
(6) The CCTV monitoring station
shall be provided in control room, Security cabin and in-charge room. The CCTV
data shall be stored for a minimum period of 60 days or in line with prevailing
IB norms;
(7) Proper sized TT parking
area based on fleet size shall be provided with following facilities, namely:—
(i) Well laid out hydrant
system with alternate double headed hydrant post and water or water cum foam
monitors covering the parking area;
(ii) Segregation of parking area
through chain link fence or boundary wall;
(iii) Separate entry and exit
gate with access control; and
(iv) Parking lane demarcation or
slotting to ensure independent and quick evacuation in emergency.
(8) Hydrocarbon (HC) detectors
shall be installed near all potential leak sources of class “A” petroleum
products that is to say that tank dykes, tank manifolds and pump house manifold
and such detectors shall be placed in a way that entire possible source of
leaks and collection of products are continuously detected and alarm is set at
20% of lower explosive limit of class “A” petroleum products. (Refer clause
5.8.1 for details).
1.2.2.6 Separation
distances.
(1) Minimum separation distances
between various facilities specified in preceding paragraph 1.2.2.5 shall be as
per Table-1 in this part and the table shall be read in conjunction with the
notes specified with the table.
(2) The layout shall also take
into account findings or recommendations Risk Analysis or Assessment study,
which shall be carried out at all the stages of facility development process.
1.2.2.7 Separation
Distances between tanks or offsite facilities.—The following conditions shall apply for
the separation distances for above ground tanks storing petroleum products,
namely:—
(1) For larger installation,
minimum separation distances shall be as specified in Table- 2 and Table-3 in
this part and the Tables are applicable where total storage capacity for
Class-A and Class-B petroleum products is more than 5000 KL or the diameter of
Class-A or Class-B product tank is more than 9 meters;
(2) For smaller installation,
minimum separation distances shall be as specified in Table-4 in this part and
the Table is applicable where total storage capacity of Class-A and Class-B
petroleum is less than 5000 KL and diameter of any tank storing Class-A and
Class-B petroleum product does not exceed 9 meters. Table-4 in this Part shall
also be applicable for the installation storing only Class-C petroleum;
(3) Excluded petroleum should
be treated as Class-C petroleum for the purpose of separation distances and
Table—4 in this Part shall be applicable for their separation distances; and
(4) Separation distances
between the nearest tanks located in separate dykes shall not be less than the
diameter of the larger of the two tanks or 30 meters, whichever is more.
TABLE — 1
SEPARATION
DISTANCES BETWEEN FACILITIES
|
S. No.
|
From/To
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
11
|
12
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1
|
Control Room (Note —1)
|
X
|
Note-2
|
Note-3
|
30
|
45
|
12
|
X
|
6
|
15
|
30
|
X
|
15
|
|
2
|
Storage Tanks Class-A
|
Note-2
|
Note-4
|
Note-4
|
Note-4
|
30
|
60
|
30
|
T2
|
60
|
50
|
60
|
60
|
|
3
|
Storage Tank Class-B
|
Note-3
|
Note-4
|
Note-4
|
Note-4
|
30
|
60
|
30
|
T2
|
30
|
50
|
30
|
30
|
|
4
|
Storage Tank Class-C
|
30
|
Note-4
|
Note-4
|
Note-4
|
30
|
60
|
30
|
T2
|
30
|
50
|
15
|
30
|
|
5
|
Bulk Loading or unloading PETROLEUM (Rail or
Road)
|
45
|
30
|
30
|
30
|
Note-5
|
60
|
Note-6
|
T2
|
30
|
30
|
30
|
30
|
|
6
|
Fire water storage and pump house
|
12
|
60
|
60
|
60
|
60
|
X
|
30
|
X
|
12
|
50
|
6
|
6
|
|
7
|
Rail Spur-stabling line
|
X
|
30
|
30
|
30
|
Note-6
|
30
|
X
|
20
|
6
|
50
|
6
|
15
|
|
8
|
Boundary wall around installation
|
6
|
T2
|
T2
|
T2
|
T2
|
X
|
20
|
X
|
6
|
15
|
15
|
6
|
|
9
|
Service buildings
|
15
|
60
|
30
|
30
|
30
|
12
|
6
|
6
|
X
|
50
|
12
|
6
|
|
10
|
OWS or effluent Treatment Plant or Oil sludge pit
|
30
|
50
|
50
|
50
|
30
|
50
|
50
|
15
|
50
|
X
|
45
|
30
|
|
11
|
Electrical Sub Station
|
X
|
60
|
30
|
15
|
30
|
6
|
6
|
15
|
12
|
45
|
X
|
6
|
|
12
|
Utilities (Broad Definition)
|
15
|
60
|
30
|
30
|
30
|
6
|
15
|
6
|
6
|
30
|
6
|
X
|
General Notes to Table-1:
(a) All distances are in
meters. “T” indicates the Table number in this part to be referred;
(b) All distances shall be
measured between the nearest points on the perimeter of each facility except
(i) in case of tank vehicle loading or unloading area where the distance shall
be from the centre of nearest bay;
(c) Service building shall have
minimal manning and normally no hot work would be done there;
(d) “X” means any distance suitable
for constructional or operational convenience; and
(e) Fire station shall be in
safe area or at least 60 m from other facilities.
Specific Notes to Table-1:
Note-1 : These distance
norms are applicable to the locations where product receipt is through cross
country pipelines. At all other locations, the building or room housing, the
automation equipments or system shall be treated as utility building for the
purpose of separation distance;
Note-2 : The distance shall
be 60 meters for non-blast resistant construction and 30 meters for blast
resistant construction;
Note-3 : The distance shall
be 45 meters for non-blast resistant construction and 30 meters for blast
resistant construction;
Note-4 : Separation
distances between the nearest tanks located in two dykes shall be equivalent to
the diameter of the larger tank or 30 M, whichever is more. For distances
within a dyke, it shall be as per Table-2 and Table-3 in this part;
Note-5 : Separation
distance between—
(i) tank truck gantry and tank
wagon gantry shall be 50m;
(ii) distance between two Tank
trucks gantries shall be 15 M; and
(iii) distance between two tank
wagon gantries shall be 50 M.
Note-6 : Separation
distance between tank truck gantry and rail spur-stabling line shall be 50 M.
TABLE – 2
SEPARATION
DISTANCES BETWEEN TANK OR OFFSITE FACILITIES
Applicable for large
installations where total storage capacity for Class-A and Class-B petroleum
products is more than 5000 kl or the diameter of Class-A or Class-B product
tank is more than 9 meters.
|
Tanks or Facility
|
1
|
2
|
3
|
4
|
5
|
6
|
|
1
|
Storage Tank for Petroleum Class A or Class B.
|
T3
|
T3
|
30
|
30
|
8
|
0.5 D Min 20 m
|
|
2
|
Storage Tank for Petroleum Class C
|
T3
|
X
|
30
|
X
|
X
|
0.5 D Min 20 m
|
|
3
|
Tank vehicle loading or Unloading for petroleum
class A or class B
|
30
|
30
|
X
|
X
|
8
|
20
|
|
4
|
Tank Vehicle loading or unloading for Class C
|
30
|
X
|
X
|
X
|
X
|
10
|
|
5
|
Flame proof Electric Motor
|
8
|
X
|
8
|
X
|
X
|
X
|
|
6
|
Boundary wall
|
0.5 D
Min 20 m
|
0.5 D
Min 20 m
|
20
|
10
|
X
|
X
|
TABLE — 3
SEPARATION
DISTANCES BETWEEN STORAGE TANKS WITHIN A DYKE
(For large installations where
total storage capacity for Class-A and Class-B petroleum products is more than
5000 cum, or, the diameter of Class-A or Class-B product tank is more than 9
meters)
|
Item
|
Between floating Roof Tanks Class —(A and A) or
(A and B)or (B and B)
|
Between fixed Roof Tanks Class —(A and A) or (A
and B) or (B and B)
|
Between fixed and Floating roof Tanks Class-(A
and A) or (A and B) or (Band B)
|
Between Class C Petroleum Storage tanks
|
|
1
|
All tanks with Diameter up to 50 meters
|
(D+d)/4 or Min 10 m
|
(D+d)/4 or
Min 10 m
|
(D+d)/4 or
Min 10 m
|
(D+d)/6 or
Min 6 m
|
|
2
|
Tanks with Diameter exceeding 50 meters.
|
(D+d)/4
|
(D+d)/3
|
(D+d)/3
|
(D+d)/4
|
General notes to Table - 2
and 3
(a) All distances are in
meters;
(b) “x” indicates suitable
distance as per good engineering practices to meet construction, operational
and maintenance requirements;
(c) D and d stands for diameter
of larger and smaller tanks;
(d) In Table - 2 all distances
shall be measured between the nearest points on the perimeter of each facility
except in the case of tank vehicle loading or unloading area where the distance
shall be measured from the centre of each bay;
(e) In Table -3, distances
given are shell to shell in the same dyke;
(f) For different combination
of storage tanks, the stringent of the applicable formulae shall be considered
for minimum separation distance;
(g) The distance of storage
tanks from boundary wall is applicable for;
(i) floating roof tanks having
protection for exposure; and
(ii) tanks with weak
roof-to-shell joint having approved foam or inert gas system and the tank
diameter not exceeding 50 meters;
(h) Distances mentioned in
Table-2 are for electric pump motor located outside dyke, but, for side entry
mixer attached to tank shell, the motor can be mounted on the tank shell; and
(i) For the facilities not
covered in Table- 2, refer Table-1.
TABLE — 4
SEPARATION
DISTANCES BETWEEN TANKS OR OFFSITE FACILITIES
(For small installations
where total storage capacity of Class-A petroleum and Class-B petroleum is less
than 5000 kl and diameter of any tank storing Class-A and Class-B petroleum
product does not exceed 9 meters. This Table shall also be applicable for the
installation storing only Class-C Petroleum and Excluded Petroleum)
|
1
|
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
|
2
|
Storage Tank Class A petroleum
|
0.5D
|
0.5D
|
0.5D/6.0
|
15
|
15
|
15
|
3
|
15
|
15
|
15
|
|
3
|
Storage Tank Class B petroleum
|
0.5D
|
0.5D
|
0.5D/6.0
|
9
|
4.5
|
4.5
|
3
|
4.5
|
D
Min
4.5
|
D
Min
4.5
|
|
4
|
Storage Tank Class C petroleum
|
0.5D/6.0
|
0.5D/6.0
|
X
|
9
|
4.5
|
X
|
X
|
X
|
0.5D
Min
3.0
|
0.5D
Min
3.0
|
|
5
|
Tank truck Loading or unloading Class — A
petroleum
|
15
|
9
|
9
|
X
|
9
|
9
|
3
|
9
|
9
|
9
|
|
5
|
Tank truck Loading or unloading Class — B
petroleum
|
15
|
4.5
|
4.5
|
9
|
X
|
4.5
|
1.5
|
4.5
|
4.5
|
4.5
|
|
6
|
Tank truck Loading or unloading Class — C
petroleum
|
15
|
4.5
|
X
|
9
|
4.5
|
X
|
X
|
X
|
3
|
3
|
|
7
|
Flame proof Electric motors
|
3
|
3
|
X
|
3
|
1.5
|
X
|
X
|
3
|
X
|
X
|
|
8
|
Non Flame proof Electric motors
|
15
|
4.5
|
X
|
9
|
4.5
|
X
|
3
|
X
|
X
|
X
|
|
9
|
Office building, stores, amenities
|
15
|
D
Min
4.5
|
0.5 D
Min
3.0
|
9
|
4.5
|
3
|
X
|
X
|
X
|
X
|
|
10
|
Boundary wall
|
15
|
D
Min
4.5
|
0.5D
Min
3.0
|
9
|
4.5
|
3
|
X
|
X
|
X
|
X
|
General notes to Table —4:
(a) All distances are in meter
and the table specifies the minimum requirement;
(b) “x” indicates suitable
distance as per good engineering practices to meet construction, operational
and maintenance requirements;
(c) “D” indicates the diameter
of the larger tank;
(d) Distances given for the
tanks are shell to shell in the same dyke;
(e) Where alternate distances
are specified (like 0.5 D/6.0), the minimum thereof shall be used;
(f) All distances shall be
measured between the nearest points on the perimeter of each facility except in
case of tank truck loading or unloading area where the distance shall be from
the centre of each bay;
(g) Pig launcher or receiver at
liquid hydrocarbon handling pipeline installations should be located at least 5
m from boundary wall; and
(h) Distances mentioned in the
Table-4 for electric pump motor located outside dyke, but for side entry motor
attached to tank shell, the mixer can be mounted on the Tank Shell.
PART — B
(Design
Considerations)
2.0 DESIGN CONSIDERATIONS.
(1) External Floating roof
tanks (EFRT) with single deck pontoon roof or Double deck or Internal Floating
Roof Tanks shall be designed as per API STD 650;
(2) Atmospheric or low pressure
fixed roof tanks shall be designed as per API STD 650 or API STD 620;
(3) Selection of type of tank
generally depends on ambient conditions and the product handled;
(4) The external floating roof
storage tanks with Pan Roof shall not be used as they are considered unsafe;
(5) IFRT and EFRT shall be
provided with double seal with minimum vapour recovery of 96%;
(6) Primary seal shall be
liquid or shoe mounted for EFRT and vapour mounted for IFRT. Maximum seal gap
width should be 4 cm and maximum gap area should be 200 cm2/m of tank
diameter;
(7) Secondary seal shall be rim
mounted. Maximum seal gap width should be 1.3 cm and maximum gap area should be
20 cm2/m of tank diameter; and
(8) Tank bottoms shall be of
cone up or cone down (“Apex down”).
2.1 TANK APPURTENANCES.
(1) Ladders and Handrails shall
be such that individual tank shall be provided with access to the roof. A
platform with railing should be provided from the top of the stairway to gauge
well and roof ladder. On floating roof tanks, non-sparking self-levelling tread
type rolling ladder with suitable double earthing connection are to be
provided;
(2) Stairs should be made of
grating. All staircases shall have resting or landing platform for every 5m
height;
(3) Number of manholes shall
depend on diameter of the tank as per API650; and
(4) Walkway with handrail on
the roof of the tank should be provided to facilitate inspection or checking of
vents or flame arrestor and like other devices so that movement of personnel on
roof is safer.
2.2 TANK FARMS OR
MANIFOLDS:
2.2.1 Tank Farm Drains.
(1) The dyke drain shall be
provided along the inside periphery of the dyke enclosure wall and in case
circular drain around tank pad is provided, the same needs to be connected to
the peripheral drain;
(2) The outlet from dyke shall
have the provision to either divert to the effluent Treatment plant or OWS or
to main storm water drain; and
(3) Dyke drain Valves shall be
provided with position indication and alarm system in the event of opening the
valve.
2.2.2 Tank Manifold.
(1) The number of inlet or
outlet connections to the tank shell should be kept minimum;
(2) Tank body valves on process
lines (inlet, outlet and recirculation) of all storage tanks storing class-A
and class-B products shall be remote operated shut off valves. Mitigation
measures due to sudden closure of shut off valve shall be incorporated in the
design;
(3) The second valve which is
motor operated valve (MOV)on inlet, outlet and recirculation lines should be
outside the dyke;
(4) Tank body valves including
remote operated shut off valves should remain shut after closure of day
operations.
(5) For positive isolation a
suitable Valve other than Hammer Blind shall be provided so that under no
circumstances the product is exposed to atmosphere from the valves and in any
case Hammer blind valves of any type shall not be used in the depot or
terminals.
(6) ROSOV shall be fail safe
and fire safe (shall close in case of signal failure) and the actuator shall be
failsafe. The cables leading to the control room shall be fire resistant;
(7) ROSOV shall have only close
operation from control room or at a strategic remote location;
(8) The Open or Close push
buttons of ROSOV shall also be provided in field that is to say just outside
the dyke and such push buttons shall have distinctive feature so that opening
is different than action required for closing (such as pull type and push
type). The push button assembly shall be mounted at a place where it is easily
visible and accessible to the operator;
(9) MOV or DBBV shall have open
and close remote operation from control room and at field outside of dyke;
(10) Tank manifold, if provided,
shall be located outside the dyke area. The floor underneath the manifold shall
be paved and have Kerb walls and connected to oil water drainage system leading
to ETP or OWS;
(11) Thermal safety valve (TSV)
or Expansion line shall be provided for blocked portion of pipe line to take
care of the thermal expansion of product due to rise of temperature;
(12) TSV outlet line or
expansion line shall be connected back to tank or tank inlet or outlet line
before ROSOV is connected with suitably positioned isolation valve. One
isolation valve on TSV outlet line or expansion line shall be installed close
to the tank shell or inlet or outlet line to the maximum extent possible;
(13) The expansion lines to be
connected at roof tops in case of CRVTs and through combined gauge well in case
of FRVTs or IFRVTs and shall be extended inside up to the tank bottom to avoid
freefall of product through vapour space with provision of siphon breaker on
top and expansion lines should be provided with class 800 flanged gate valves;
(14) Termination of expansion
line on tank roof top shall not be allowed as free fall through vapour space is
unsafe;
(15) At existing locations where
ever the arrangement specified in the paragraph 2.2.2(13) does not exist, the
same shall be provided on all tanks during scheduled tank maintenance or
cleaning;
(16) Any electrical fittings and
fixtures inside the dyke shall be as per the hazardous area classification.
but, such fittings and fixtures except for actuators of ROSOV or MOVs or HC
detectors or PESO approved ex-proof water flow switch or ex-proof pressure
transmitter should be above the dyke height.
2.2.3 Tank Settlement.—Settlement of tanks takes
place over a period of time and a depression is formed on tank pad along the
circumference and the same should be effectively made up with proper slope to
avoid rain water accumulation and subsequent corrosion of the bottom plate and
where large settlement is anticipated, supporting arrangement for the connected
piping shall be suitably designed to take care of the settlement.
2.3 TANK HEATERS.—Tank heating can be
accomplished either by steam heating or electric tracing or hot oil circulation
and Heating flues using fired burners shall not be permitted.
2.3.1 Heaters.—Tank heaters shall be
designed to hold the product at the specified storage temperature when tank is
filled up to safe filling height. For design calculations, it is necessary to
specify average wind velocity and minimum ambient temperature over extended period
of time.
2.3.2 Steam Heating.—Manway and such heaters
consist of a tube bundle, usually of hairpin type, fixed through a manhole of
the tank and such heaters shall be designed so that its removal can be done
without the requirement of person entering in the tank. Steam coils should have
no flange connections inside the tank and provision should exist in condensate
outlet lines to check for oil leak. Gradient of the coil bundle inside the tank
should be such that condensate accumulation is avoided.
2.3.3 Electric Heating.—Electric tracing of one
or more courses of shell can be provided, but, the classification and thermal
rating of electric tracing should be verified before application and the
electric conduits and cabling should conform to Classification of Areas for
Electrical Installations.
2.3.4 Crude tanks : Crude
tanks may be provided with side entry swivel angle type mixers.
2.4 DRAINS FROM THE TANKS:
2.4.1 Bottom Drains.
(1) Drains should be provided
in all tanks for draining water and also for emptying out the tank for cleaning
and such arrangement would also be useful for draining water after a hydro test
or initial flushing during a start-up operation. Number and details of the
drains shall be as per the applicable tanks design standard.
(2) Each drain line shall have
minimum two isolation valves separated by spool piece and pipe shall be
extended beyond tank pad up-to drain point. One of such valves shall be of
quick closing type. Ends of each drain point should have provision of blind
flange or capping arrangement.
2.4.2 Floating Roof Drains.
(1) Roof drain shall be of
robust design to prevent oil coming out during draining operation. Maximum
hourly rainfall rate during the past 15 years shall be considered for designing
the number and size of drains for open floating roof tank. Rain water should
not be taken directly into the tank;
(2) The roof drain system shall
have provision for connection to the drain through a suitably designed robust
system and shall include a suitable outlet valve;
(3) Due care shall be taken
while designing to ensure the system integrity and performance when roof is
resting on the low legs; and
(4) The inlet of roof drain
shall have a check valve to prevent product from flowing to the roof in the
event of failure of the system.
2.4.3 Emergency Roof Drain.—Emergency drain for
floating roof tank shall be provided on the roof to take care of disposal of
water in case of choking or malfunctioning of the primary roof drain. It shall
have water seal arrangement to prevent oil spill on the roof.
2.5 VENTS:
2.5.1 Open Vents.—Flash Back Arrester
(Flame arrester) should be fitted to Vents as per IS 11006 : 2011. For sizing
the vents API STD 2000 is to be referred and the following are the basic
guidelines need to be considered, namely:—
(1) Maximum and minimum ambient
temperatures;
(2) Vapour pressure of the
product at operating or design temperature;
(3) Maximum pumping in and out
rates. In the event of change in any operating parameters involving change in
pumping rates complete end to end system check shall be done in line with
Management of Change; and
(4) Blending components likely
to be handled in the tank.
2.5.2 Breather Valve.
(1) The breather valves for the
blanketed tanks and low-pressure tanks shall be provided as per API STD 650 and
API STD 620 respectively and the tank breathes - in air will be when the tank
pressure is lower than the atmospheric pressure and breathes-out will be when
tank pressure is greater than the set pressure;
(2) Pressure and Vacuum
Relieving Valves (PVRVs) provided on cone roof tanks usually have 20%
accumulation and while designing, it is necessary to ensure that under full
relieving conditions, the design pressure or vacuum in the tank is not
exceeded. Set pressure of PVRV shall be decided according to API STD 2000.
(3) Breather vents or flame
arrestors are known to fail through the formation of crystalline waxy or heavy
hydrocarbon deposits or ice on the seats of valve diaphragms or inside the
nozzle connection upon which the valve is mounted, as such Breather vents or
flame arrestors shall not be recommended on these services, instead only open
vents should be provided; and
(4) Where tanks are blanketed,
breathing-in will be from the blanketing gas system and necessary control valve
shall be provided for supply of blanketing gas at constant pressure. The tank
shall be provided with a safety valve by way of lift disc or diaphragm or any
other suitable device. Gauge hatch and other manholes shall be of gas tight
construction.
2.5.3 Emergency Vents.—Emergency Vents shall be
provided for the tanks as per API STD 2000.
2.6 DIP HATCH OR SAMPLING.
(1) Dip hatch or gauge hatch is
used for gauging the height of the liquid in a tank as well as to take out
samples for testing as such, the gauge hatch shall be non-sparking (or lined
with non-sparking material) and self-closing type;
(2) Gauge well pipe should be
provided with slots; and
(3) The gauge well shall be
properly supported by means of angles or strips with bottom plate of the tank
and such arrangement also makes the tank safer with respect to dissipation of
static charge accumulation.
2.7 INSTRUMENTATION:
2.7.1 Safety Integrity
Level (SIL).—The
SIL classification study shall be carried out to determine the required SIL
level. SIL of the safety instrumented function for the tank including overfill
protection shall meet the requirement of Part 1 of IEC 61511. The SIL level of
the entire interlock loop shall also meet the requirement of IEC 61511.
2.7.2 Level controls on
Tanks.—For
all storage tanks storing Class A/B products, the following instruments or
alarms shall be provided, namely:—
(1) High Level (H), High High
Level (HH) alarms, that is to say that each tank shall have provision of level
instruments for sending audio visual alarms to the control rooms. All the
alarms shall be of different type so that the “H” level alarm and “HH” alarms
can be distinctively identified;
(2) Level for “H” and “HH”
alarms shall be decided based on site specific operating parameter that is to
say diameter of tank, flow rate and operators response time for corrective
measures to stop product level reaching curb angel or maximum floating
position, but such, these levels shall be lower than the level corresponding to
PESO approved safe filling capacity;
(3) Independent level switch
shall be provided at the “HHH” which in any case shall not be above the level
corresponding to PESO approved safe filling capacity of the tank;
(4) The level switch shall
enable initiation of action for closure of the respective inlet valve that is
to say the ROSOVs, MOVs and product pumps so that the entire receipt operation
closes on safe mode and the product does not over flow;
(5) Two nos. independent level
instruments shall be provided out of which one instrument shall be of radar
gauge type and each of the instruments shall have provision both for “H” and
“HH” alarms. Provision shall be made in the system configuration for
transmitting only two signals (one for “H” and one for “HH”). The signals that
is to say the “H” and “HH” from each level instrument shall be available
parallel in the control room using OR gate PLC logic;
(6) Over spill Level switch,
that is to say that an independent hardwired level switch like Vibrating Fork
and like other switches shall be provided for actuating remote operating shut
off valve. Over spill level switch should be connected to remote operating shut
off valve through safety PLC for SIL loop compliance;
(7) For tanks storing class
that is to say that C products two nos. independent level instruments shall be
provided out of which one instrument shall be of radar gauge type. Each of the
level instruments shall have provision for both “H” and “HH” alarms and the
signal transmitting shall be as so explained;
(8) There shall be exchange of
signals between the receiving and dispatch location in case of receipt of
product through cross country pipe lines and provision shall be made for
monitoring of level of the receiving tank along with pressure in the pipe line
and ROSOV status and to ensure safe shut down of the system in case of any
abnormal situation; and
(9) Care need to be taken for
tanks receiving product from ship or cross country pipeline at high flow rates
for surge pressures due to sudden closures of valves and accordingly where ever
required, suitably designed Surge relief system or pump tripping to be
provided.
2.7.3 Tank farm management
system integration.—TAS
(terminal automation system) including TFMS (tank farm management system) shall
be integrated with software for back up at remote location (DRC) with provision
for recording of all critical events in the system and back up data shall be
retained for a minimum period of 30 days and if in the event, the backup data
is proposed to be stored within the same installation then, and if in the room
for storing the backup data shall be blast resistant at a secured place.
2.7.4 Temperature and
Insulation.—When
product storage temperatures are likely to be higher than 100°C, a remote
temperature indicator with alarm should be provided in addition to local
indicators. For tank capacity higher than 5000 kl a minimum of two numbers of
local temperature indicators should be so located (within 500 mm above the
inlet or outlet nozzle) as not to sense the direct heat of the coil. Insulation
shall be provided for heat conservation. The tanks having higher surface
temperature shall have insulation up to minimum 2 meters high for personal
protection and also, patch insulation should be provided on the shell along
with spiral stairway and provision for inspection.
2.8 PIPING OR VALVES OR
FLANGES:
2.8.1 Piping.
(1) Piping shall be designed
for handling of hydrocarbon liquid as per “ASME B 31.3 : Process Piping” or
ASME B 31.4 (for cross country pipelines only entering the terminal) or API 5L
or equivalent as applicable;
(2) Pipe joints should be
welded as far as practicable with full penetration weld and number of flanged
or threaded joints should be kept to a minimum;
(3) In case sampling point is
provided on receipt line for operational requirement, the same should be
provided outside of dyke in the manifold;
(4) Sectionalizing of the pipe
lines with isolation valves and arrangements for injection or draining of water
shall be provided for facilitating hydro-testing of the pipe lines;
(5) Buried piping shall be
protected against physical damage and corrosion with suitable protective
coating;
(6) At road crossings, in
addition to protective coating, pipes should pass through secondary encasing
with properly sealed at both the ends;
(7) The pipe lines should be
provided with low point's drains and high point vents to facilitate emptying or
hydro-testing and like other testings and ends of each drain point shall have
provision of blind flange or capping arrangement; and
(8) Jetty lines should be
provided above ground properly spaced and approachable to maintain the lines.
2.8.2 Valves.—Steel valves conforming
to relevant API standards shall be used. Cast iron valves should not be used.
2.8.3 Fittings.
(1) Steel flanges and flanged fittings
shall conform to relevant ASME or ASTM or ANSI or equivalent;
(2) Slip on or weld neck
flanges should be used;
(3) Screwed flanges for sizes
50 mm or smaller may be used;
(4) Steel flanges should
conform to the applicable provisions of ASME B 16.5 or equivalent;
(5) Steel screwed fittings and
couplings shall conform to ASME B 16.11 or equivalent;
(6) Steel unions shall have
ground metal to metal seats. Gasket type unions shall not be used;
(7) Plugs shall be of steel.
Cast iron or brass plugs shall not be used; and
(8) Electrical continuity
across flange joints shall be maintained by providing metallic gaskets or
jumpers.
2.9 BULK LOADING OR
UNLOADING OPERATIONS:
2.9.1 Loading or unloading
Pumps.
(1) Pumps conforming to
relevant API standards shall be used;
(2) Product pumps shall be
provided with suitable sized strainers on suction and NRVs on discharge lines.
All drain points of strainers shall be provided with double isolation valve and
ends having provision for blind flange or screw capped;
(3) Pumps shall be located in
an exclusive paved area with drainage facilities routed to OWS or ETP;
(4) Tank lorry loading or
unloading pump house shall be positioned at an elevated level and shall be well
ventilated on all four sides;
(5) Open roof Pump house are to
be provided with suitable IP protection for the equipment;
(6) In case of sunken pump
house for Tank Wagon unloading facilities, Pump house shall be so positioned
that it ensures proper ventilation and efficient disposal arrangements of
accumulated products;
(7) To avoid wide variation in pressure,
leading to a ‘kick’ or ‘hammering’ in header and hoses, it is necessary to
choose pumps with flat characteristic curves;
(8) Locations having automation
shall be provided ESD feature through Automation system;
(9) Dedicated pumps for
individual products shall be provided. Minimum one stand by pump for each
product shall be provided;
(10) Separate pumps shall be
provided for Tank truck loading/unloading and wagon loading or unloading; and
(11) All closed sections of
pipings shall be provided with thermal safety relief device to relieve pressure
due to ambient temperature rise. Thermal Safety relief device may vent into a
tank or piped to OWS located in safe area and when connected to tank, TSV shall
be provided with isolation valves. One isolation valve shall be installed close
to the tank shell to the maximum extent possible. The vent should be piped to
closed blow-down system.
2.9.2 Tank truck and tank
Wagon Loading Gantries.
(1) Loading points shall have
quick shut-off valves such as Cast steel Plug or Ball Valves;
(2) No vehicle shall be loaded
at a rate exceeding (volumetric flow rate corresponding to linear velocity one
meter per second at the delivery (at the least dia fitting) and of the filling
pipe until the filling pipe is completely submerged in petroleum and thereafter
the loading rate should be gradually increased but it shall at no point of time
exceed six meters per second at the delivery end of the filling pipe;
(3) Location should be provided
with facilities where loading and unloading of Tank trucks is possible in a
closed loop system that is to say top or bottom loading provisions with Vapour
Recovery System;
(4) Where flow indicators or
totalizers are provided for gantries, vapour eliminators shall be incorporated;
(5) The provision for Kerosene
and MS or Naptha loading in TT (tank truck) loading gantry shall not be in the
same bay;
(6) For safety reason the level
adjustment in the tank lorry compartments should be done through suitable
system wherein product is not exposed in open atmosphere at any point of time;
(7) In case of loading hoses,
only neoprene impregnated hoses having electrical continuity between nozzle and
flange shall be used;
(8) All tank wagons and tank
trucks shall have a fill pipe extended up to the bottom to avoid splash
filling;
(9) The splash filling is
permissible for asphalt loading in tank truck or tank wagons;
(10) Where bottom loading is
done, deflector plates in the trucks to be ensured;
(11) Bottom flameproof lighting
shall be provided for night time checking of wagon bottom leaks and also for
proper sealing and inspection, wherever loading or unloading during night is
required to be done;
(12) Loading gantry should be
provided with at least one suitable explosion-proof telephone or paging device
for communication with pump house, control room and like other communication in
normal and emergency operations and in addition, operating personnel shall be
provided with intrinsically safe walky-talky suitable for use in oil
installations;
(13) Tank wagon and truck
loading gantries shall be suitable for all weather conditions;
(14) Tank Truck loading gantries
shall be provided with safety harness to protect the operating crew against
fall from height;
(15) Swing type loading ladders
with counter weight and hand railing shall be light in construction. Neoprene
packing shall be provided at the bottom rest to avoid spark generation due to
impact.
(16) Proper handrail arrangement
shall be provided on platforms and stairs for safe movement of personnel;
(17) Adequate safe escape
ladders including from overhead platform shall be provided at intervals on the
gantry for emergency use and escape ladders shall be prominently identified
from distant view;
(18) Protection against pressure
surge in the loading header due to sudden change in loading rate need to be
considered and provision of shock absorber as one of the surge protection
method at suitable locations on rail or road loading header should be
considered;
(19) Provision shall be made for
quick isolation of main product headers in case of emergency and for such
purpose, suitable type hand operated valves or remote operated valves shall be
considered as per the site conditions and overall automation system in the
installation;
(20) Loading gantry area
including areas below railway lines shall be paved for smooth draining and
collection of spillages into drains;
(21) Open drains along the
railway line or gantry shall be covered with gratings so as not to endanger
movement of personnel;
(22) All trucks entering truck
loading gantry shall be PESO approved and provided with approved spark arrestor
or flame arrestors at the exhaust. The Vehicle conforming to emission level BS
IV and beyond are exempt from fitment of spark arrestor;
(23) Oil and water collected
from loading or unloading areas shall be routed to Oil water separator system
or Effluent Treatment Plant or similar facility and a slop tank should be
earmarked for storing separated oil;
(24) The tank truck gantry shall
be so designed that all the compartments of the tank truck are filled at one
bay only. The layout shall ensure that all operations are planned in a manner
so that no zigzag movement of the tank truck around the gantry should take
place;
(25) For tank wagon gantry where
placement of tank wagon is by electrical LOCO, traction line must terminate 15
M short of the first loading or unloading point at all Installations;
(26) For placement, brake van or
dummy wagons shall be used. Separate segregation gate shall be provided at
terminating point and area between boundary wall and segregation gate should be
declared de-licensed;
(27) Main railway track shall be
isolated from wagon gantry siding at least 15 meters from 1st loading or
unloading point by providing insulation joint at terminating point and loco
shall stop before the insulation joint; and
(28) Sampling points shall be
provided as per requirement of Industry Quality Control Manual (IQCM).
2.10 Design layout for
handling of sick wagon.—When a wagon is found leaking during loading, provision shall be
kept for safe handling of such wagons and such methods should include the
following, namely:—
(1) Arresting of leaks using
cold weld as a first aid measure till the wagon is unloaded safely at the
gantry itself and in no case such wagons to be used for transportation;
(2) A dedicated drain header
for instantaneous unloading of the sick wagons shall be provided and
alternately, the existing headers may be utilized for immediate decantation of
product from sick wagons by providing suitable arrangements in the manifold;
and
(3) A portable pump with flame
proof or explosion proof motors and other electrical fittings to be used with
suitable flexible hose connection for quick withdrawal of products into sump
tanks and such drained products to be handled further as per IQCM (Industry
Quality Control Manual).
2.11 Design Layout for
handling slop:
2.11.1 Collection and
Drainage.—A
network of drainage system shall be provided to collect oil drains from various
equipments, gantry areas, pump houses and like other passages and they should
also collect surface drains from places where oil spillages are likely to occur
and such drainage shall lead to OWS or ETP as the case may be.
2.11.2 Mechanised OWS.—The receiving sump of the
OWS shall have suitable arrangement for skimming off upper layer of accumulated
oil and provision shall be made for directing the collected oil to the slop
tank.
2.12 Layout and Selection
of electrical equipment.
(1) Electrical equipment
including the lighting system shall conform to hazardous area classification.
The hazardous area shall be classified as per IS : 5572. The electrical
fittings or equipment in the respective classified area or zone shall be of a
type suitable for the particular area or zone as per classification in line
with IS : 5571;
(2) Electrical equipment shall
be selected, sized and installed so as to ensure adequacy of performance,
safety and reliability and the equipment in general shall conform to relevant
Indian Standards and shall be suitable for installation and satisfactory
operation in the service conditions envisaged;
(3) The protective system shall
be designed to ensure Protection of Personnel and plant equipment against
damage which can occur due to internal or external short circuits, overloading,
abnormal operating conditions, switching, lightning surges, and like other
damages accordingly, relays and protective devices shall be suitably selected
and installed. All the protective relays for the Generator, Transformer, Motors
and Switchgears shall be tested at least once in a year and test records
maintained;
(4) The outer PVC sheath of all
cables used inside the dyke shall be fire retardant type conforming to category
AF as per IS : 10810;
(5) All cables shall be laid in
proper cable trenches or cable trays suitably designed to ensure their
protection and identification at all times;
(6) All power and control
cables shall have extruded inner and outer sheaths and such cables should be
Aluminium or Copper Conductor, PVC or XLPE insulated, PVC sheathed and armoured
type;
(7) Instrument and signal
communication cables shall not be laid in the same trench or tray along with
electrical cables and the overall cable layouts shall be designed for minimum
interference between signal and power cables; and
(8) Cable route markers shall
be installed at every 30 metres intervals all along the cable routes and also
at cable joints and locations where the direction of cable trench changes.
2.12.1 Earth resistance.
(1) Earth resistance can be
directly read through an earth resistance tester which has associated Test,
auxiliary Current and Potential electrodes and such instrument shall be a
combination of ohmmeter and generator works on ‘fall of potential’ principle
and the test voltage shall be derived from the generator of the earth
resistance tester. Earth resistance also can be measured through Direct Earth
Clamp Tester (DECT);
(2) The testing of the Earth
Pits shall be done six monthly, once in dry and once in wet weather and records
thereof shall be maintained;
(3) Removable link shall be
provided to allow measurement of an earth electrode-resistance;
(4) The resistance value of an
earthing system to general mass of the earth should not exceed,—
(i) 4 Ohms for electrical
systems and metallic structures;
(ii) 7 Ohms for storage tanks;
(iii) 1 Ohm for main earth grid,
and bonding connections between joints in pipelines and associated facilities;
and
(iv) 2 Ohms for each electrode
to the general mass of the earth.
(5) Earth resistance can be
directly read through an earth test Megger which has associated Test, auxiliary
Current and Potential electrodes and such instrument shall be a combination of
ohmmeter and generator works on ‘fall of potential’ principle and the test
voltage shall be derived from the generator of the Megger.
2.12.2 INSTALLATION
EARTHING.
(1) Installation earthing
design shall be carried out in accordance with the requirements of Central
Electricity Authority Regulations -2010 and IS : 3043 or equivalent system
recognised by statutory authorities under the law in force relating petroleum
and electricity and all earth connections should be visible for inspection to
the extent possible. The earthing system shall have an earthing network with
required number of earth electrodes connected to it.
(2) Earthing system shall be
designed for the following, namely:—
(a) System neutral earthing;
(b) Protective Equipment
Earthing for personnel safety;
(c) Protection against Static
discharges;
(d) Lightening Protection; and
(e) Earthing for Data
Processing system.
2.12.2.1 Electrically
independent earth electrodes.
(1) Earth electrodes shall be
located at such a distance from each other so that the maximum current likely
to flow through one of them does not significantly affect the potential of the
other;
(2) The Lightning Arrestor (LA)
of the Two Pole or Four Pole structure shall be connected to two distinct earth
pits. The strips shall run on insulators or isolators so as not to come in
contact with the Pole structure. Connections shall be made to the pit directly
and then pits will be connected to each other to form a grid. The Grid of LA
shall be distinct and shall not be connected to any other earth Grid;
(3) The Two Pole or Four Pole
structure shall be earthed with two distinct earth connections. The Gang
Operated Switch shall also be earthed;
(4) Fencing of Two Pole or Four
Pole, Transformer yard shall be earthed and also electrical continuity between
various structures the fencing shall be ensured;
(5) The Neutral of the
Transformer shall be earthed with two distinct earth pits separately.
Connections will be made to the pit directly and then pits will be connected to
each other to form a grid and such Grid shall be distinct and shall not be
connected to any other earth Grid;
(6) The Neutral of the Diesel
Generator shall be connected to two distinct earth pits separately. Connections
shall be made to the pit directly and then pits will be connected to each other
to form a grid and such Grid shall be distinct and shall not be connected to
any other earth Grid;
(7) The transformer body shall
be earthed at two points separately leading to earthing system;
(8) All Metallic non-current
carrying parts of all electrical apparatus shall be earthed to ensure that the
exposed metallic parts do not become dangerous by attaining high voltages i.e.
exceeding 650 volts in case of faults.
(9) All the electrical equipment
operating above 250 volts shall have two separate connections to the earth Such
as Sub Station Panels, Motors, FLP JBs and like other separate connections;
(10) All Steel structures,
loading platform or gantries and like other structures shall have two separate
and distinct connections and such connections will be made to the pit directly
and then pits will be connected to each other to form a grid; and
(11) Product Storage Tanks and
like other storage chamber shall have two separate and distinct connections and
each connection will be made to the respective earth pit directly, then, such
earth pits should be inter-connected to form a dedicated grid for Tank Farm.
The number of earth pits or connections to be increased for large tanks so that
the distance between the connections does not exceed 30 meters on the tank
perimeter.
2.12.3 Bonding.
(1) All flanged connections
shall be effectively bonded by strips of suitable material.
(2) Continuity between rail
spur and gantry in tank wagon loading or unloading gantry shall be ensured by
checking at a suitable frequency. The gantry structure to be suitably earthed
in earthing pits of standard specifications and the tank wagon siding to be insulated
from main running track.
(3) In tank truck loading and
unloading gantry, 6 mm Sq. braided copper wire with one end firmly bolted to
the Loading Unloading Arm or hoses and the other end provided with G.I or
Copper or Non-corrodible metal crocodile clips shall be used and the crocodile
clips being attached to the tank-truck under loading or discharging, for
External Bonding of Loading unloading arms or hose with the Tank Truck.
(4) For sampling jars to be
inserted into product tanks, use only manila or sisal ropes.
2.12.4 Static earthing.
(1) Static earthing (earthing
for static charge dissipation) shall be provided at Tank Lorry or Wagon Filling
or Decantation Gantries, to prevent building up of Static Charges; and
(2) Earthing connections for
static charge dissipation, electrical system, structure and instrumentation
system shall be separate from each other, but such separate leading strips can
be connected with main grid below the ground.
2.12.5 Lightning Protective
System.
(1) Lightning protection shall
be provided for the equipment, structures and buildings which are higher than
20 meters or as per the risk index analysis worked out as per IS 2309;
(2) Self-conducting structures
(having min thickness 4.8 mm) do not require lightning protection with aerial
rod and down conductors and they shall be connected to the earthing system at
two points of the base; and
(3) If lightning arrester is
provided an independent earthing network shall be provided for lightning
protection.
2.12.6 Earthing for data
processing system.
(1) Low noise earthing is
required for critical data processing equipments and such earthing shall be
independent of any other earthing of the Building. The RFI (Radio frequency
interference) suppression filters fitted to the data processing equipment may
produce high earth leakage current and in such cases failure of protective
earth connection may lead to high touch voltages; and
(2) Where ever isolation
transformers are used the output neutral of the transformer shall be
independently earthed so as to ensure that the Earth-Neutral Voltage is less
than 1 volt.
2.12.7 Minimum Permissible
Sizes of the Earthing Conductors:
Size of the conductor shall
be selected, based on the fault current that is required to be dissipated
during emergencies.
2.12.8 No of earth pits.—The earth is a minimum
requirement and additional earth pits shall be made such as to maintain Grid
Values below 1 Ohm.
|
Equipment
|
Nos
|
|
Earthing for Lightning Arrestor
|
2 Nos independent
|
|
For Di or Four Pole Structure, GO, Fence
|
2 Nos (All metal bodies connected)
|
|
Neutral of the transformer
|
2 Nos independent
|
|
Neutral of the DG Set
|
2 Nos independent for each DG Set
|
|
Body of DG Set or control panel for DG Set
|
2 Nos
|
|
Sub-station —PMCC Room
|
4 Nos
|
|
Fire Pump House
|
2 Nos
|
|
Air Comp House
|
2 Nos
|
|
All structures Shed of Pump House or Fire Engine
or Loading unloading Gantry or Air Compressor or Engg. Store and like other
structures
|
2 Nos for each structures
|
|
Static Earth for Loading or unloading Gantry
(Tank Truck) operations.
|
2 Nos earth pits for 8 bay gantry.
|
|
Static Earth for Loading unloading Gantry (Tank
Wagon) operations.
|
Min. 4 nos. earth pits for each (single or two
spur) gantry. For rail track as per railway norms.
|
|
All 3 Phase Motors or FLP lights in each shed
|
2 Nos
|
|
High Mast Tower (HMT)
|
2 Nos for each HMT
|
|
Admin Blocks
|
2 Nos
|
|
Data Processing
|
One for Metallic body parts of equipments and one
for neutral of isolation-transformer
|
|
Inspection Platform or Watch Tower or Weigh
Bridge
|
1 Nos each
|
|
Water Storage Tanks (Fire Water Tank)
|
2 per tank
|
|
Product Storage Tank
|
Minimum 2 nos and further as defined in Clause
2.12.2 (11) above.
|
2.12.9 General.
(1) Fail safe Interlock or
change over switch shall be provided between the Grid Power and the DG power to
ensure that the equipments get supply from one source only;
(2) Insulation mats shall be
provided in the Sub Station, control panels and like other points;
(3) Relays/Cables shall be
tested once in a year and records maintained.
(4) Transformer oil shall be
tested once in a year and records maintained.
2.12.10 Emergency Feeder.—Emergency Feeder shall
host the Jockey Pump, Critical lighting, Fire Siren, Borewell, Gate Barrier,
safety instrumentation and interlocks such as CCTV, Hydro Carbon detector, Dyke
drain valve system, UPS of automation and supply to essential fire-fighting
equipment.
2.13 INSTALLATION LIGHTING.
(1) Sufficient lighting shall
be provided so as to enable terminal operators to move safely within the
accessible areas of installation and to perform routine operations. In the
event of normal power failure, emergency lighting shall be provided in critical
areas;
(2) Normal lighting system
shall be on 415/240V AC supply. Emergency lighting shall be provided in
critical areas like Sub-Station, D G Room, Control Room and Security cabin;
(3) Under normal operation,
both emergency and normal lighting shall be fed by normal power source. On
failure of normal supply, emergency lighting shall be available until the start
of D.G.;
(4) Lighting shall be provided
for the various facilities in the Depot or Terminal as per good engineering
practice;
(5) The Illumination in the
operational areas including inside the dyke and manifold shall be such that
adequate visibility is there at all times for emergency and normal operations;
(6) Lighting requirements
provided during the failure of power supply is intended broadly to such
failure;
(7) Facilitate carrying out of
specified operations, for safe shutdown of the installation;
(8) Gain access and permit
ready identification of firefighting facilities such as fire water pumps, fire
alarm stations and like other facilities;
(9) To gain access to escape
route for safe evacuation of operating personnel; and
(10) Depending on the nature of
job activities carried out, the minimum illumination levels for various areas
shall be as specified in the table below, namely:—
|
Area
|
Lux Level
|
|
Main roads (Gate entry or exit, roads around TT
gantry
|
20
|
|
Secondary roads (along storage tanks and
Periphery and like other places)
|
10
|
|
Tank farm area
|
20
|
|
Pump or Compressor or Dosing Sheds or Fire Pump
House
|
100
|
|
Main Operation Platforms and Access Stairs (TT
and TW gantry, Tank manifold)
|
100
|
|
Ordinary Platforms
|
20
|
|
OWS or ETP Area
|
60
|
|
Sub Station or PMCC room
|
150
|
|
Transformer yard or HT Di pole area
|
100
|
|
Battery room, Charger or UPS rooms
|
100
|
|
Control Room building or laboratory
|
150
|
|
Lube Warehouse
|
100
|
|
Admin Building
|
200
|
|
Security Cabin or Watch Booth
|
100
|
|
Stairs
|
80
|
|
Corridors
|
70
|
|
Tank truck Parking area
|
40
|
Notes:
(a) The lighting fixtures on
various circuits shall be suitably designed so that failures of any one circuit
do not result in complete darkness.
(b) Switches controlling the
lighting fixtures and exhaust fan shall be installed outside the battery room.
(c) Switches of lighting panels
installed in hazardous area, shall have a pole to break the neutral, in
addition to the poles for phases.
(d) Low pressure sodium vapour
lamps shall not be installed in hazardous areas.
PART — C
(Safe
Operating Practices)
3.0 Safe Operating
Practices.
(1) Operational safety aspects
for Petroleum Product terminal or depot shall be built into the design which
should also be reviewed during the construction phase from safety or
maintenance point of view and only skilled and trained personnel shall be
deployed for effective operation, inspection, maintenance and like other work
for the installation;
(2) The operating procedures
shall provide plant specific instructions on what steps to be taken or followed
while carrying out Start-up, Normal operation, Temporary operation, Normal
shut-down and Emergency operation and shut-down;
(3) Manuals of operating procedures
shall be made available to the employees. Training shall be imparted to the
operators on operating procedures and should be certified as competent;
(4) When changes are made in
facilities, operating procedures should be reviewed as part of the management
of change procedure. In addition, operating procedures should be reviewed
periodically to verify that they reflect current and actual operating
practices. Operating manuals should be certified as updated by authorized or
competent person every year; and
(5) The Safe Operating
Practices (SOPs) mentioned in paragraph 3.1 shall outline the general
guidelines and are not intended to override sound engineering practices and
safety parameters regarding when and where the operating procedures should be
used and any additional steps that may be sought to be included to ensure
process safety.
3.1 Safe Operating
Practices (for general guidelines), namely.—Safe Operating Practices to outline the
general guidelines shall include the following
(1) Terminal or depot Control room
where ever provided shall be manned on continuous basis during operations and
in emergency;
(2) No Person shall be allowed
to smoke, carry matches, lighters, flammable material or any other appliances
capable of producing ignition or explosion inside the licensed area of the
installation;
(3) Non-flame proof or
Non-intrinsically safe Mobile phones and any other source of ignition shall not
be allowed inside the Petroleum Installation operational areas where petroleum
products are stored pumped and handled;
(4) Site specific Standard
Operating Procedures (SOPs) for each operation or activity shall be developed
and complied with;
(5) SOPs shall be periodically
reviewed, updated and records and maintained especially whenever any changes or
modifications to the facilities are made as per Management of Change procedure
(MOC);
(6) The critical operating
steps based on Safe Operating Practices (SOPs) shall be displayed on the board
near the location wherever applicable. In local language also and shall be made
simple and user friendly;
(7) All operations shall be
carried out under supervision of designated personnel;
(8) All precautions shall be
taken to ensure isolation of sources of ignition during maintenance (such as
welding, cutting, and other process) from potential sources of flammable
vapours. Presence of vapour at location of maintenance and its surrounding
shall be constantly monitored by suitable portable device for flammable gas
detection;
(9) Maintenance or repair work
or entry into confined space including closed drains or manholes shall be
carried out in accordance with the Work Permit System;
(10) Non-Sparking tools shall be
used to carry out the maintenance jobs in operational areas where flammable
materials are handled or stored;
(11) Check list for operators
for monitoring and checking safety system and equipment shall be prepared,
followed and records maintained thereof;
(12) Roads inside the hazardous
area of Installation shall be restricted to vehicles required for operational,
maintenance and safety or security reasons and allowed only with proper safety
fittings and authorization from designated officer;
(13) Vehicles with internal
combustion engine (compression ignition) such as tank truck required to be
permitted for business shall have Petroleum and Explosives Safety Organization
(PESO) approved spark arrestor fitted on the vehicle. Vehicles with spark
ignition engine shall not be allowed inside hazardous area;
(14) TTs to be parked in
drive-out position in parking area having separate entry and exit gates;
(15) All electrical equipment
shall be maintained to ensure its integrity and type of protection as well as
electrical area classification;
(16) Suitable interlocks shall
be provided for tripping or alarm or remote valves operation based on the
events such as low level, high level, high-high level, high pressure, low
pressure and like other events;
(17) The contents of the dyke
drain generated from draining of tanks, any other spillage or effluent
containing oil shall be diverted to Oil Water separator (OWS) or Effluent
Treatment Plant for safe disposal;
(18) Personnel protective
equipment such as safety shoe, hand gloves, apron, safety goggles, safety belt,
helmet, ear muff, dust respirator, self-contained breathing apparatus (SCBA),
resuscitator, fire proximity suits and like other protection equipments as
applicable shall be worn while carrying out operations in normal and emergency
situations;
(19) Intrinsically safe handsets
working on VHF or UHF or any other acceptable frequency band shall be used in
operating areas;
(20) Manning level in the shift
shall be adequate to ensure coverage for normal and emergency operations;
(21) The Petroleum Installation
shall have provisions for handling leakage or spills at high risk areas, tank
lorries and tank wagons;
(22) Hydrocarbon Gas detection
system shall be installed with audio or video alarm system in the control room
as well as in the effective risk zones or areas;
(23) All personnel who are
handling petroleum products shall be suitably trained on use of firefighting,
equipment and first aid. Thorough training shall be incorporated to all
personnel on various levels of emergency response;
(24) All other contract personal
and supervisors entering the premises shall have basic safety training and
should be aware about emergency duty and knowledge of the emergency exit route
at all work locations;
(25) The Petroleum Installation
shall have effective CCTV system covering the entry or exit gate roads,
periphery of installation and all critical operating areas (such as Tank farm,
TT or TW operating area, product pump house, Fire water pump house and TT
Parking area and like other areas) which shall be monitored continuously; and
(26) The CCTV monitoring station
shall be available in Control room, Security cabin and Depot in-charge room.
The CCTV data shall be stored for a minimum period of 60 days.
3.2 Tank Farm area.
(1) Ladders and Handrails of
the product tank shall be free from any obstruction and to be in impeccable
condition. The platform and railing on the top of the stairway to gauge well
and roof ladder should have free access. Walkway with handrail on the roof of
the tank should be inspected or checked, so that movement of personnel on roof
is safe;
(2) The tank farm management
system shall be integrated with Enterprise Resource Planning (ERP) or Terminal
Automation System (TAS) with provision of recording and display of real time
inventory levels and ensure the effectiveness at regular interval and whenever
the system is by pass, all necessary record shall be maintained;
(3) Dyke drain Valves shall be
provided with position indication and alarm system in the event of opening the
valve. The dyke drain shall be provided along the inside periphery of the dyke
enclosure wall and in case circular drain around tank pad is provided, the same
needs to be connected to the peripheral drain. The outlet from dyke shall have
the provision to either divert to the effluent Treatment plant or OWS or to
main storm water drain;
(4) Dyke drain valves shall be
in closed condition and shall be operated only under supervision of an
authorized person and log book maintained. Piping through dyke wall, if any,
shall be sealed to make dyke impervious;
(5) All electrical fittings and
fixtures inside the dyke shall be as per the hazardous area classification and
its integrity maintained;
(6) The dyke and the enclosures
shall be inspected for cracks, visible damage and like other damages every six
months (pre and post monsoons) and after every major repair in the tanks or
dykes and like other devices so as to keep it impervious;
(7) All the tanks inside the
dyke shall have fire-fighting system in operating condition;
(8) There shall be ensured “No”
chocking of water spray nozzles.
(9) The dyke area shall have
proper slope outward of tank pad towards the inner periphery of the dyke
enclosure to prevent reverse flow;
(10) The Remote Operated Shut
Off Valve (ROSOV) and Motor Operated Valve (MOV) of the tanks and pipeline
manifold (inlet, outlet and recirculation) of all storage tanks storing class A
and class B products shall be operational and should remain shut after closure
of day operations;
(11) ROSOVs and MOVs shall be
fail safe and fire safe (shall close in case of signal failure). The actuator
shall be fail-safe. The cables leading to the control room shall be fire
resistant and the ROSOVs shall be operational from the field and also from
control room;
(12) Thermal safety valve (TSV)
and Expansion line shall be connected for blocked portion of pipe line to take
care of the thermal expansion of product due to rise of temperature.
Temperature Safety Valves (TSV's) and downstream valves shall be always kept
open and its discharge should be routed to slop collection system and
alternatively, the discharge may be connected to a common header and back to
the tank through NRV;
(13) The area floor underneath
of the pipeline manifold shall be paved and the Kerb walls or drain connected
to oil water drainage system leading to ETP or OWS;
(14) Product storage Tanks must
be periodically inspected and checked for leakages or sweating. Repairs must be
immediately carried out, whenever scaling or pitting are observed;
(15) Movement of floating roof
must be smooth during operation. Free movement of rolling ladder must be
ensured by proper lubrication of moving parts and ensure free movement of
wheels;
(16) Floating roof deck must be
kept clean and free from all foreign materials or dust and like other materials
so as to avoid clogging of roof drain sump;
(17) Tank farm area shall be
covered through CCTV surveillance system and monitored;
(18) Water seal must be
maintained in the emergency drain in floating roof tanks and it shall be
ensured that adequate water is maintained in the water pot of the emergency
drains;
(19) Proper earthing and bonding
shall be maintained and ensured at all times for the tank body, electrical
continuity from shell to ladder and from ladder to floating roof;
(20) Safe Operating Practices
(SOPs) for entry on floating roof or confined spaces for maintenance and
inspection (when the tank is with product for normal operation) shall consider
the following, namely:—
(i) Floating roof is levelled,
free of oil and excessive water and is at higher operating level;
(ii) Adequate manpower with a
canister mask or breathing apparatus and like other apparatus is deputed;
(iii) A life line with safety
belt to be used for entering into confined space and the other end of the line
held by the standby person at the top of platform; and
(iv) In case of requirement of
going on floating roof deck for inspection during normal operation, at least
one person should accompany the person making the inspection.
(21) No gauging or sampling of
tanks shall be undertaken during thunder or hail storms;
(22) Water draining from tanks
should be done under close supervision as per approved Safe Operating Practices
(SOPs);
(23) Receipt and withdrawal rate
from the tanks shall be limited to the design parameters of the tank below and
the flow velocity at tank inlet shall not exceed 1 m/s until the inlet is
completely submerged;
(24) Breather vents provided on
cone roof tanks shall be checked to ensure normal operation and ensure its
effectiveness;
(25) Special attention shall be
given during receipt as well as transfer from the floating roof tanks when roof
is in semi floating condition that is to say operating in erroneous zone;
(26) Safety shoe (Conductive
type) shall be worn while gauging, sampling or taking temperatures;
(27) Tank dip pipes shall be
extending to tank bottom and if dip pipes are not provided, give a settling
time of 30 minutes after receipt or discharge before sampling or gauging;
(28) Synthetic fibre cord shall
not be used for sampling, dipping, gauging and like other process If in the
sampling, gauging, dipping, like other process, equipment is a conductor, the
cord must be conductive, such as a metal wire. Metal chains shall not be used,
instead Natural fibres such as sisal and manila which have sufficient
conductivity to prevent the operator from becoming charged by handling it, can
be used;
(29) There shall be ensured that
gauge tapes and other sampling equipment are of non-sparking type;
(30) During receipt, tank level
shall be monitored at regular intervals. Effective communication shall be
provided in the tank farms, which may include Intrinsically safe VHF or UHF or
any other acceptable frequency band handset and like other devices and such
system can also be utilised for communication during emergency;
(31) Cleaning of tanks should be
carried out as per plan in line with the approved Safe Operating Practices
(SOPs). Gas oil spray and steam shall not be used for cleaning of Class A and
class B tanks;
(32) Earthing and bonding
connections shall be ensured during the entire operating process. The earthing
system shall be checked for bonding and earth continuity as required and the
records maintained thereof;
(33) Hydrocarbon (HC) detectors
shall be installed near all potential leak sources of class “A” petroleum
products that is to say tank dykes, tank manifolds and pump house manifold And
such detectors shall be placed in a way that entire possible source of leaks
and collection of products is continuously detected and alarm is set at 20% of
lower explosive limit of class A petroleum products; Further, hydrocarbon
detectors shall be installed near all potential leak sources of class “B”
petroleum products as and when such effective and proven detectors are
available.
(34) Fire-fighting system
provided for above ground Tanks shall be operational, and the effectiveness of
the system to be ensured checked periodically for operation as per design
capacity;
(35) The tank farm must be kept
clean and shall be free from dry vegetation;
(36) OWS system shall be
maintained clear by periodic cleaning. End of the vent of Inspection chamber of
the OWS system shall be provided with wire mesh. The accumulated oil from the
OWS sumps shall be collected and sent to slop tanks at regular intervals;
(37) Disposal of sludge
collected during cleaning of the tanks shall be done as per the applicable
guidelines; and
(38) The product storage tanks
shall have level indicators as well level alarms and interlocking with MOV and
ESD. The effectiveness of the system or interlocking shall be checked
regularly. The interlocking or ESD shall not be bypassed. In case of any such
exigency, the approval from authorised person in this behalf shall be taken
with requisite precautions and records maintained thereof.
3.3 Bulk handling:
3.3.1 Tank Truck (TT)
Loading or Unloading.—Transportation
of petroleum products by road is regulated by PESO in accordance with the
provisions of the Petroleum Rules, 2002 the carriage by Road act, 2007 (Act 4
of 2007) and the rules made thereunder and the Central Motor Vehicle Rules,
1989, Legal Metrology Act, 2009 (Act 1 of 2010).
3.3.1.1 Before Commencement
of Loading or Unloading.
(1) Open source of ignition
shall not be allowed in any part of the Petroleum Installation operational area
including tank lorry loading or unloading area;
(2) The following shall be
ensured in a tank truck as per statutory regulations before accepting it for
filling, namely:—
(i) Provision of PV vent,
emergency vent, Master valve and other safety fittings;
(ii) Fire screen between cabin
and tank is provided and for such purpose, cabins with metallic back cover
without any opening will be considered as fire screen;
(iii) Provision of 2 nos. of Fire
Extinguishers of ISI mark (1 No. × 10 or 9 kg DCP and 1 No. 1 kg CO2 or DCP or
equivalent approved fire extinguisher);
(iv) Spark arrestors of the
approved designed shall be welded with the exhaust in front of the vehicle and
the vehicle shall have valid Explosive License and RTO certificate along with
PESO approved drawings of the tank and such arrangement in case of BS-IV and
future models may not be required if exempted by PESO;
(v) Availability of brazed
copper strip for earthing or bonding connection; and
(vi) Tank trucks should be
equipped with ABS.
(3) The Double pole master
switch shall be put off immediately after parking the truck in the position. No
electrical switch on the truck shall be turned “on” or “off” during the loading
or unloading operation;
(4) Wheel choke shall be placed
at wheels to prevent accidental movement of the truck and hand brakes should
also be applied during the entire loading or unloading operation;
(5) The first process after
positioning the truck shall be to provide appropriate earthing and after the
loading or unloading operation, earthing shall be disconnected just before the
release of the truck;
(6) Vapour Space of 3% of its
capacity shall be kept in each tank truck in respect of Petroleum Class A and
Class B products and 2% vapour space in tank trucks in respect of Petroleum
class C products;
(7) No repairs shall be made on
the Tank Lorries, while it is in the loading or unloading area;
(8) Personnel deployed in the
loading or unloading area shall make use of Personal Protective equipment and
wear all throughout the working period;
(9) Loading or unloading area
pipeline manifold shall have provision of quick shut-off valves;
(10) No tank vehicle shall be
loaded at a rate exceeding (volumetric flow rate corresponding to linear
velocity) one meter per second at the delivery (at the least dia fitting) and
of the filling pipe until the filling pipe is completely submerged in petroleum
and thereafter the loading rate should be gradually increased, but it shall at
no point of time exceed six meters per second at the delivery end of the
filling pipe;
(11) Oil and water collected
from loading or unloading areas shall be routed to Oil water separator system
or Effluent Treatment Plant or similar facility. A slop tank should be
earmarked for storing separated oil;
(12) The tank truck gantry shall
be so designed that all the compartments of the tank truck are filled at one
bay only and the layout shall ensure that all operations are planned in a
manner so that no zigzag movement of the tank truck around the gantry should
take place; and
(13) The maximum safe carrying
capacity in weight of Petroleum that can be carried in a tank vehicle shall not
exceed the difference between the unladen weight of the vehicle and the maximum
gross weight permitted for the class of vehicle under the appropriate transport
regulations.
3.3.1.2 During Loading or
Unloading Operation.—The
following shall be ensured during the loading and unloading operation, namely:—
(1) Move truck to the loading
or Unloading bay and position the TT in the loading or unloading bay and place
wheel chokes at front and rear wheels of the vehicle. Keep the TT in neutral
mode with hand brakes;
(2) Certified ISI Mark fire
extinguishers shall be placed near the tank trucks, during loading or unloading
operations at a designated marked place;
(3) Stop the engine of TT and
“Switch off” Master switch, so that the TT cannot be started incidentally, and
the TT electrical supply shall be disconnected totally;
(4) The TT driver and cleaner
shall be outside the vehicle to meet any exigency, and “no” person shall be in
the driver's cabin;
(5) Provide earthing
connections of the vehicle at specified point on tanker tank to the fixed
grounding system;
(6) Ensure that TTs manifold
valve are closed and capped;
(7) Test the connections for
any product leakages;
(8) Loading of TTs shall be
through dedicated loading arms and through flow meters. The correctness of the
mass flow meter shall be ascertained periodically. Splash loading shall be
avoided;
(9) Start the loading
operations with initially loading rate which shall not exceed 1 m/s till fill
pipe is completely submerged with petroleum products and there after gradually
increased loading rate but shall not exceed 6 m/s (should preferably not exceed
4 m/s);
(10) The quantity loaded into
the truck can be assessed by—
(i) Liquid level through manual
dipping; and
(ii) Filling through Flow meter;
(11) Filling or transfer
operations shall be suspended immediately in the event of—
(i) Uncontrolled leakage
occurring; or
(ii) A fire occurring in the
vicinity; or
(iii) Lightning and thunder
storm;
(12) The personal working
engaged in loading unloading operation, shall use fall protection system
designed for the purpose;
(13) An authorized person of the
company shall supervise the filling operation and respond immediately in the
event of an emergency; and
(14) Trucks meant for loading
may be inducted in line with approved acceptance checklist, Filling Checklist
and records thereof shall be maintained.
3.3.2 Tank Wagon (TW)
Loading or Unloading.—Before
Commencement of Loading/Unloading, the following shall be complied with,
namely:—
(1) Ensure that the loco is at
least at a distance of 15 metre from the first loading/unloading point when the
wagons are being placed or removed in the gantry for loading or unloading;
(2) Main railway track shall be
isolated from wagon gantry siding at least 15 meters from 1st loading or
unloading point by providing insulation joint at terminating point and loco
shall stop before the insulation joint using adequate number of dummy wagons;
(3) The loading or unloading
operation shall be carried out under close supervision of authorized person;
(4) After the wagons have been
placed at the gantry for loading or unloading breaks are to be applied before
detaching the loco;
(5) Open source of ignition
shall not be allowed in any part of the area where product transfer operations
are being carried out. Use of mobile phone is prohibited in the zone or area;
(6) Ensure that all fittings on
the tank wagons are checked physically that is to say before and after loading
or unloading;
(7) Always use gantry platform
for movement from one wagon to other wagon. Movement from wagon to wagon is
prohibited, but moment from wagon to wagon with adequate Fall protection system
or Safety harness shall be permitted;
(8) The first operation after
positioning the wagon shall be to provide appropriate earthing of all the tank
wagons. Ensure that electrical continuity of the system is intact by providing
bonding in flanges and checking of continuity;
(9) Ensure all the firefighting
equipments are in good working condition, and the fire fighting ring main
system is pressurized and maintained;
(10) The loading unloading
system or equipment's shall not operate more than its designing capacity;
(11) Any non-routine work in the
operational area shall be permitted with work permit only;
(12) Every individual working in
the Tank Wagon operating area must be familiar with all the firefighting
equipment, their care and their use in the event of fire;
(13) Use of right kind of
equipment to handle loading or unloading operation. After using the equipment
or material or tools shall not be placed at rail track;
(14) Maintenance jobs on rail
track during placement or removal of rake are strictly prohibited;
(15) Oil and water collected
from loading or unloading areas shall be routed to Oil water separator system
or Effluent Treatment Plant or similar facility. A slop tank should be
earmarked for storing separated oil;
(16) Open drains along the
railway line or gantry shall be covered with gratings so as not to endanger
movement of personnel;
(17) Minimum Vapour space for
tank wagons carrying different classes of petroleum products shall be for
Petroleum Class A - 4% and for Petroleum Class B and C - 2.5%;
(18) Tank wagon loading or
unloading operations shall be suspended immediately in the event of
uncontrolled spill, or fire in the vicinity;
(19) Before the wagons are moved
from the spur, brakes on all the wagons shall be released;
(20) The railway siding railway
track shall be properly insulated from the main line and grounded, vis-a-vis
main rail track;
(21) Wagon to be checked for
mechanical condition, dents, and leaks and the report of defective wagons to be
provided to Railways;
(22) All drain and vent point in
pipe line shall be kept closed and caped; and
(23) Good housekeeping to be
ensured all the time in Railway siding or gantry and all the personnel working
in the area shall wear Personal Protective equipment.
3.3.2.1 During Tank Wagon
Loading Operation.—During
tank wagon loading operation, the following shall be observed, namely:—
(1) Accept the tank wagons for
loading only after the railway staff declares the tank wagons are fit for
loading or unloading operation;
(2) Before loading of a wagon,
a bonding connection shall be made before opening of manhole cover and shall
remain in place until filling is completed and all dome covers shall be closed
and secured;
(3) Dip tape or sampler shall
not be lowered during loading time or just after completion of loading in a wagon
to permit relaxation of charges; and
(4) No Wagon shall be loaded at
a rate exceeding (volumetric flow rate corresponding to linear velocity) one
meter per second at the delivery or at the least smallest pipe fitting and of
the filling pipe until the filling pipe is completely submerged in petroleum
and thereafter the loading rate shall be gradually increased but it shall at no
point of time exceed six meters per second at the delivery end of the filling
pipe.
3.3.2.2 During Tank Wagon
Un-Loading Operation.—During
tank wagon un-loading operation, the following shall be observed, namely:—
(1) Ensure health of unloading
pumps required for unloading of wagons;
(2) Ensure mobilization of
required hoses, gaskets, adapters, nuts, bolts and like other devices at the site;
(3) Ensure correct line up from
unloading pump discharge to product tank;
(4) Record all seals numbers,
density and DIP in “sick wagon unloading register”;
(5) Confirm the correctness of
the line-up hoses and product pipeline connections. Recheck and ensure that
product exchange shall not take place;
(6) Ensure earth continuity
from Wagon to unloading point by providing required copper jumpers at flange
joints;
(7) Measure the initial dip of
the tank wagon prior to unloading;
(8) Record the initial dip of
the tank wagon and the designated tank dip prior to unloading;
(9) Open air vent valve and
filling pipe cover for air breathing;
(10) Open the master valve and
bottom valve of the tank wagon; and
(11) Monitor the physical dip of
the product in the Tank wagon, particularly towards end of the unloading.
3.3.3 Handling and
Unloading of Sick Tank Wagon.—While handling and unloading Sick Tank
Wagon, the following shall be observed, namely:—
(1) In case of minor leak, try
to arrest the leak at the site with the help of railway staff only through cold
repair methods only;
(2) When a wagon is found
leaking during loading or unloading, provision shall be kept for safe handling
of such wagons and as a first aid measure arresting of leaks using cold weld
compounds at gantry itself and in no case such wagon to be used for
transportation;
(3) If the leak is minor and
not stopped by TXR staff or Maintenance, then, make arrangements to decant the
wagon into Product Tank;
(4) If the leak is major, then,
immediately inform the concerned Railway staff and in the meantime try to
contain the spill using container or drums;
(5) Connect the un-loading hose
to wagon's unloading flange and nearest sick wagon unloading point of the
gantry;
(6) Product should be then
transferred to suitable storage and leakage shall be arrested by cold repair
methods and in case leakage cannot be arrested, wagon shall be declared sick in
concurrence with the railways staff and emptied out completely;
(7) A dedicated drain header
shall be provided for instantaneous unloading of the sick wagons and alternately,
the existing headers may be utilized for immediate decantation of product from
sick wagons by providing suitable arrangements in the manifold; and
(8) A portable pump with flame
proof or explosion proof motors and other electrical fittings to be used with
suitable flexible hose connection for quick withdrawal of products into sump
tanks and such drained products to be handled further as per IQCM (Industry
Quality Control Manual).
3.3.4 Tank Wagon Unloading
in Slop Tank.—While
Tank Wagon unloading in Slop Tank, the following shall be observed, namely:—
(1) Ensure earth continuity
from Wagon to unloading point by providing required copper jumpers at flange
joints and appropriate earthing connection shall be made before the start of
unloading activity;
(2) Ensure that required ullage
is present in the slop vessel to accommodate the quantity to be unloaded from
the sick tank wagon and check the dip of product in the slop vessel physically
and record it;
(3) Ensure mobilization of
required hoses, gaskets, adapters, nuts, bolts and like other devices near the
sick wagon;
(4) Ensure that the all other
stub or branch pipe of the sick wagon unloading header throughout the gantry
are properly blinded;
(5) Record the product
specification and density and DIP in “sick wagon unloading register”;
(6) Confirm the correctness of
the line up to the slop vessel;
(7) Connect the un-loading hose
to wagon's unloading flange and nearest sick wagon unloading point of the
gantry;
(8) Open air vent valve and
filling pipe cover of wagon for air breathing;
(9) Open the master valve and
wagon bottom valve of the wagon;
(10) Continuously monitor the
dip level of the wagon during unloading operation;
(11) Check and ensure that there
is no leakage of product from other flanges of the unloading header in the
gantry area;
(12) Monitor level of product in
the slop vessel;
(13) Monitor the physical dip of
the product in the Tank wagon, particularly towards end of the unloading;
(14) Check the emptiness of the
wagon;
(15) Disconnect the flexible
hose carefully; decant the remaining material of the hose into slop vessel;
(16) Close bottom valve as well
as master valve of the tank wagon;
(17) Place the unloading hoses
and other material at designated place;
(18) Check the closing stock or
physical dip of product in slop vessel and record it; and
(19) Reconcile the quantity
unloaded from Tank Wagon and quantity received in the slop vessel.
3.4 Transfer of Product
through Pipeline.—Where
ever pipe line transfer is envisaged between various entities, a mass flow
meter with integrator shall be installed on receipt line at both ends that is
to say dispatch and receipt ends and signal shall be provided in the control
rooms of both dispatching and receiving companies or locations for monitoring.
The following safe
practices to be followed, namely:—
(1) Gauging procedure shall be
completed and line shall be made through;
(2) Physical inspection shall
be carried out up to the exchange manifold for any leakage or damage and like
other harms;
(3) Monitoring systems such as
SCADA shall be installed in cases of cross country pipeline transfers;
(4) Seal the pressure relief
lines of receipt nozzles of product tanks connected to the same common receipt
header;
(5) After ensuring that there
are no leaks, pumping shall be commenced;
(6) Pumping shall be commenced
initially at low flow rate and only after stabilizing of flow and the flow rate
may be increased;
(7) Product shall not be pumped
beyond safe filling height of the tank and necessary alarms and interlocks in
the automation shall be put in place to ensure the safe filling;
(8) After completion of the
receipt, pumps must be stopped;
(9) In case of Emergency
Shutdown, care shall be taken so that back pressure is not developed in the
pipelines and pump head;
(10) Sampling shall be carried
out as per provisions of Industry Quality Control Manual (IQCM);
(11) Pipe Line transfer (PLT)
shall not be taken simultaneously in more than one tank; and
(12) In case product is required
to be taken into more than one tank, tank shall be switched over after
completion of operation in first tank, close all valves to the first tank, make
line through for the second tank as per procedure.
3.5 Marine Loading or
Unloading.
(1) Marine facilities handling
petroleum products shall have clearly marked out escape route, and at the same
time have sufficient access to fire fighting.
(2) Fire fighting facility for
a marine facility handling petroleum products shall be provided as per design
standard.
(3) Vessels berthed at the
wharf shall be fastened with mooring ropes, ensuring that the vessel is well
secured to the wharf.
(4) Before commencement of
loading or discharge of the vessel, shore and vessel representatives to jointly
sign off safety check list covering all aspects of the vessel loading or
discharge shall be ensured and such safety Check list shall also cover
emergency evacuation measures in event of emergency on shore and on board the
vessel.
(5) Clear communication channel
shall be established between vessel and shore terminal.
(6) Loading pumps capable of
building up pressures that exceed the safe working pressure of cargo hose or
loading arms shall be provided with bypasses, relief valves, or other
arrangements to protect the loading facilities against excessive pressure.
Relief devices shall be tested at least annually to determine that they
function satisfactorily at their set pressure.
(7) Vessel tanks nominated for
loading petroleum products shall have oxygen content below 8% to ensure safe
loading operation and such safe loading operation has to be ensured in all
vessel or tanks nominated for loading, before any product loading can commence
into any of the vessel tanks.
(8) Loading or unloading arms
or hoses connected to the vessel for loading or unloading shall have facility
for emergency shut off and break away.
(9) Loading or unloading
quantity and rates shall be monitored on an hourly basis and corresponding ship
and shore figures shall be hourly compared.
(10) Loading or unloading arms
or hoses shall be inspected hourly for leakages during the operations.
(11) Vessel shall ensure and
confirm to shore on hourly basis and the status of various vessel tanks shall
ensure that no product migration is taking place between vessel tanks.
(12) Abnormalities observed
during operations shall be immediately communicated between ship and shore. In
case of abnormality in operations, operations shall be stopped immediately.
Operations shall only commence after conditions have been restored to normal.
Abnormalities which shall be considered are the following, namely:—
(a) Large differences between
vessel and shore tank hourly quantity;
(b) Variation in product
densities from the certified density of the product under operation; and
(c) Leakages observed on board
vessel or shore pipelines or hoses or spillage observed in the sea water.
(13) Mechanical work shall not
be performed on the wharf during cargo transfer, except under special authorization
based on a review of the area involved, methods to be employed, and precautions
necessary.
3.6 Ethanol Handling.—In case ethanol is used
for blending with Motor Spirit at the petroleum installation, facilities for
storing and handling of ethanol shall be provided and all practices as being
followed in handling Class ‘A’ Petroleum Products are required shall be adhered
to while handling Ethanol and Ethanol Blended Motor Gasoline.
3.6.1 Receipt, storage and
handling of ethanol.
(1) Ethanol shall be received
at installations/depots in dedicated tank trucks and all care shall be taken to
prevent ingress of water into the compartments during transportation.
(2) The fittings in tank trucks
used for transportation of Ethanol to receiving locations shall be the same as
used for storage and handling of Class ‘A’ Petroleum products.
(3) Ethanol can be stored in
above ground or underground tanks depending on local requirement.
(4) The unloading operations
shall be carried out through special Nitrile rubber or any other compatible
hoses. Hose shall have external bonding wire to ensure electrical continuity.
(5) Ethanol being hygroscopic
in nature, utmost precaution needs to be taken to ensure that there is no
ingress of water or humidity. Both the ends of the hoses after use shall be
capped and 80 mesh strainers shall be provided before the pump or tank inlet,
as the case may be.
(6) Appropriate recommended
dosage of Corrosion inhibitor shall be added during the decantation of Ethanol
from tank truck into the storage tank, so as to ensure homogeneity of additives
with ethanol in the storage tank.
(7) Storage tanks and allied
facilities for Ethanol shall be positively segregated and the tank shall be
absolutely free from water at all times.
(8) Ethanol, being hygroscopic,
will absorb moisture from the air and Silica Gel trap shall be provided in the
vent pipe of the tank to prevent ingress of moisture into the tank. Regular
check on the colour of silica gel shall be maintained (Blue Colour) and shall
need immediate replacement on showing signs of saturation by way of change of
colour.
(9) Ethanol storage tanks shall
be cleaned once in two years or more frequently depending on the need.
(10) Storage tank openings or
pipeline fittings shall be airtight and the threaded connections if any shall
be tightened with the help of Teflon paste or Teflon tapes and Bolted
connections shall have gaskets of Teflon.
(11) To ensure uniform doping of
Ethanol with Motor Gasoline, on line doping of Ethanol shall be carried out
through a closed system, with proper interlocks, while maintaining efficacy of
mixing Ethanol in the right proportion of % v/v as per specification.
(12) An 80-mesh filter shall be
provided on the delivery side of Ethanol storage tank that is to say between
pump and tank lorry filling (TLF) Gantry point.
(13) Safety requirements as
specified in Material safety data Sheet (MSDS) shall be ensured.
(14) “Safe Operating Practices
(SOP)” shall be displayed. Persons handling ethanol shall be trained for
handling of ethanol.
(15) Emergency instructions and
hazardous instruction shall be displayed and PPE as per MSDS requirement shall
be in place.
PART – D
(Commissioning
or De-commissioning of facilities)
4.0 Commissioning or
De-commissioning of facilities.—Commissioning is the process of assuring
that all systems and components of a facility, a process, or a plant are
installed, tested, and operated according to the design parameters and operational
requirements. Decommissioning is the process of assuring that all systems and
components of a facility, a process, or a plant are tested and confirmed that
there is no Hazard available or balance, which may cause any potential damage
to the personal and also equipment or facilities installed in the vicinity
before shutdown of the facility. The commissioning or de-commissioning process
shall include the following aspects, namely:—
(1) Standard operating
procedures for commissioning or decommissioning of the equipment and facility
shall be formulated, reviewed and approved by designated personnel;
(2) Only experienced and
trained personnel shall be deployed for commissioning or de-commissioning
activities;
(3) The de-commissioning or
commissioning of the facility shall be carried out under the close supervision
of the experienced and expert supervisors;
(4) The role and
responsibilities of each personnel associated with the commissioning or
de-commissioning activities shall be clearly defined and approved;
(5) The commissioning process
comprises the integrated application of a set of engineering techniques and
procedures to check, inspect, test, and verify every operational component of
the project, from individual functions, such as stand-alone equipment and
instrumentation to complex combinations of modules, subsystems and systems;
(6) There shall be an approved
commissioning or de-commissioning plan for each facility or process unit of the
project;
(7) The procedures shall be
developed taking into account the various hazards that are likely to be
encountered during the commissioning process and shall also address the
prevention or mitigation systems that need to be in place prior to commencing
each activity;
(8) The procedure referred to
in clause (7) should also take into account any risks to the operators,
facility, and environment based on a risk assessment;
(9) Procedures shall ensure
that all necessary checks or safeguards are correctly addressed. Procedures
shall be supported with proper checklists for verifying compliance;
(10) Pre-commissioning
activities like vessel entry, work at height, hot work, and all commissioning
or decommissioning activities shall be carried out complying with work permit
system;
(11) Compliance to work permit
requirements should be monitored via regular safety inspection;
(12) All staff and the
associated contractors, vendor representatives at site shall use Personal
Protective Equipment (PPE) as specified for such purpose;
(13) In the event of an
emergency occurring in the Project site or area, the emergency response shall
be in accordance with the established Emergency Response Procedures;
(14) Hazardous waste and
non-hazardous waste produced in the pre-commissioning or commissioning activity
(that is to say flushing lube oil, oil contaminated water or soil) shall be handled
in accordance with established environmental procedures of waste management;
(15) A comprehensive testing
procedure shall be developed which address the safety of all personnel involved
therein and include the provision of specific work instructions and related
training and induction for all personnel involved in testing operations. The
testing must be supervised by trained and experience personnel. Coordination
and team work between Construction, QA or QC, Safety, and Contractor is very
important;
(16) Any pressure test activity
shall have approved pressure test Certificates of relevant testing equipment or
instruments, work permit and job safety analysis;
(17) The hydrostatic and
pneumatic test pressure utilized for testing of systems shall be as indicated
in the data sheet and the relevant Codes and Specifications for the system
shall be used for determining the hydrostatic or pneumatic test pressures;
(18) Test facility shall be set
up with provision of a relief valve and calibrated pressure gauge (at least two
units in the test loop) shall be deployed;
(19) Prior to commencement of
any pressure test, the relief valves shall be correctly set and not isolated,
and the pressure gauges shall be functional;
(20) Equipment or piping system
isolation spades, gaskets, flanges and like other devices should be checked for
correct size, thickness and rating;
(21) All vents and other
connections which can serve as vents shall be open during filling, so that all
air is vented prior to applying test pressure to the system;
(22) Temporary spades and blanks
installed for testing purposes shall be designed to withstand the test pressure
without distortion;
(23) Piping shall be tested
prior to installation of inline items such as rupture discs, displacement and
turbine meters, orifice plates, flow nozzles, level gauges, rotameters,
strainers and like other devices; and
(24) Many potential hazards can
be realized during start-up or shut-down of a plant or a process unit. Specific
Emergency procedures should be provided which take into account all possible
eventualities.
PART — E
(Fire
Protection and Prevention Facilities)
5.0 Fire Protection and
Prevention Facilities:
5.1 Fire Protection
Philosophy.—Fire
protection philosophy is based on loss prevention and control. It considers
that a depot or terminal carries an inherent potential hazard due to flammable
nature of petroleum products stored therein. A fire in one facility can
endanger other facility of the depot or terminal, if not controlled or
extinguished as quickly as possible to minimize the loss of life and property
and to prevent further spread of fire.
5.1.1 Fire protection.—Depending on the nature
of risk, following fire protection facilities shall be provided in the
installation, namely:—
(i) Fire Water System-(storage
or pumps or distribution piping network with hydrant or monitors);
(ii) Fixed Water Spray System;
(iii) Foam System;
(iv) First Aid Fire Fighting
Equipment;
(v) Trolley mounted or Mobile
Fire Fighting Equipment;
(vi) Carbon Dioxide System or Clean
Agent Fire Fighting System or Dry Chemical Fire Fighting System;
(vii) Dry Chemical Extinguishing
System;
(viii) Clean Agent Protection
System;
(ix) Leak detection System and
Alarm System;
(x) Fire Detection and alarm
systems; and
(xi) Communication System.
5.1.2 Design criteria for
fire protection system.
(1) Facilities shall be
designed on the basis that city fire water supply is not available close to the
installation. The Installation or Depot should have its own independent Fire
Fighting System. Pipeline installation co-located with Refinery or Marketing
installation may be covered by fire fighting system of later and need not
require independent fire fighting system.
(2) The fire water pumps shall
be provided with auto start facility with pressure drop in fire water network.
(3) The fire water system shall
be based on single contingency for all locations where total storage capacity
in the location is up to 30,000 KL (Including storage of Class C products if
stored with Class A and/or Class B). Wherever water replenishment @ 50% or more
is available, the storage capacity can be reduced to 3 hours aggregate rated
capacity of main pumps.
(4) The fire water system shall
be provided based on two largest fire contingencies simultaneously for all
locations where total storage capacity in the location is above 30,000 KL
(Excluding Class-C products stored in a separate dyke conforming to prescribed
separation distances) and wherever water replenishment @ 50% or more is
available, single fire contingency shall be considered for Fire water storage.
This clause shall not be applicable for locations exclusively storing class C
and/or excluded products.
(5) At locations where cluster
of OMCs exist, fire water shall be shared. Water requirement shall be worked
out based on fire scenario of single largest tank, CR or FR tank, as the case
may be. At locations where single OMC exist, it shall have water requirement
for 4 hours.
(6) For location or dyke
storing exclusively Class C or excluded or combination of Class-C and excluded
products, the water requirement shall be based on 1 monitor of 144 k1/hr and 4
hose streams of 36 k1/hr that is to say a total of 288 kl per hr for four hrs.
(7) The hazardous areas shall
be protected by a well laid combination of hydrants and monitors and the
installations having aggregate above ground storage capacity of less than 1000
KL (Class A+B+C) are exempted from such protection.
(8) The installations storing
Class A petroleum in above ground tanks shall have fixed water spray system,
but the installations above 1000 KL storage fulfilling the following both
conditions are exempted from the provision of fixed water spray system,
namely:—
(i) Aggregate above ground
storage of Class A and Class B petroleum up to 5000 KL; and
(ii) Floating roof tank storing
Class A petroleum having diameter up to 9 M.
(9) Class ‘B’ above ground
Petroleum storage tanks (fixed roof or floating roof) of diameter larger than
30 m shall be provided with fixed water spray system.
(10) Fixed foam system or
Semi-fixed foam system shall be provided on all tanks (floating roof or fixed
roof) exceeding 18 m diameter storing Class A or Class B petroleum.
(11) When Class A and Class B
above ground storage tanks are placed in a common dyke then, the fixed water
spray system shall be provided on all tanks except for small installations as
mentioned in sub-para (8).
(12) Installations where inter
distances between tanks in a dyke or within dykes are not conforming to these
regulations, the following additional facilities shall be provided to enhance
safety namely:—
(i) The fixed water sprays
system on all tanks, irrespective of diameter in the installations; and
(ii) The Fixed or semi fixed
foam system on all tanks, irrespective of diameter in the installation.
(13) Tank Truck (TT) or Tank
Wagon (TW) loading or unloading gantries or facilities, Manifold area of
product pump house and Exchange pit shall be fully covered with alternate
hydrant and water cum foam monitors of approved make having multipurpose
combination nozzles for jet, spray and fog arrangement and located at a spacing
of 30 M on both sides of gantry ensuring minimum foam application rate of 6.5
lpm/sq.m (in line with NFPA-11 for spill fire more than 1 inch deep) to the
target zone (3 adjacent segments of 15 meters each for TW gantry and 08 bays
for TT gantry) of the relevant facility.
(14) The hydrants and monitors
shall be located at a minimum distance of 15 m from the hazard (such as TW and
TT loading or unloading facilities) to be protected.
(15) Tank wagon loading gantries
shall be provided with manually operated fixed water spray or sprinkler system.
The gantry shall be divided into suitable number of segments (each segment
having minimum length of 15 m length and width of 12 m) and three largest
segments operating at a time shall be considered as single risk for calculating
the water requirement and accordingly, a provision shall be made to actuate the
water spray system from a safe approachable central location that is to say
affected zone and adjoining zones.
(16) Portable monitors or foam
hose streams shall be provided for fighting fires in dyke area and spills.
(17) Medium expansion foam
generators shall be provided for dyke area to arrest vapour cloud formation
from spilled volatile hydrocarbons.
(18) Installation of medium
expansion foam generator shall be as per following criteria, namely:—
(i) Class A tanks : Two Nos.
Fixed type foam generators (minimum) for each tank dyke, and
(ii) Class B tanks : Two Nos.
Portable foam generator (minimum) for each location.
(19) Remote or manually operated
high volume long range water cum foam monitors (capacity 500/750/1000 GPM and
above) to fight tank fires shall be provided at petroleum installations.
Numbers and Capacity of monitor or foam pourer shall be provided in such a way
that the foam delivery rate from the monitors' meets requirement of foam
application rate (8.1 LPM/m2) for full surface tank fire.
(20) The location of HVLRs
monitors shall be planned in such a way that the very purpose of such monitors
is served and throw of the monitors is safely delivered at the aimed object and
such high volume long range monitors shall be positioned located at a distance
of 15 m to 45 m from the hazardous equipment subject to the following, namely:—
(i) Monitors shall be
positioned in such a way that throw of monitors are safely directed to the
target tank under full surface fire without damaging tank shell, tank pad and
other objects; and
(ii) The throw is directed on
the inner upper surface of the tank and not in the middle of the tank to
prevent splash over.
(21) Fixed or mobile HVLRs shall
be used for fighting full surface fire on external floating roof tanks.
(22) Care need to be taken for
petroleum installations located in habituated areas or adjoining to other
objects such as High tension line and like other objects and there should not
be any High tension line passing through the depot or installation.
(23) Water cum foam monitors
shall be installed in such a way that all the tanks in the installation are
within the horizontal range of foam throw.
(24) Additional monitors shall
be provided in such a way that each tank is in the coverage area of at least
two monitors.
(25) Provision for connecting or
hooking the portable monitor shall be made in the hydrant system around the
fixed roof tanks at various strategic points.
(26) Well laid procedures and
plans shall be made and put into use for use of HVLRs to combat emergencies
without loss of much time.
(27) For determining the total
foam solution requirement, potential foam loss from wind and other factors
shall be considered while designing.
(28) Adequate foam drum or tank or
reliable replenishment for foam induction system shall be provided.
(29) Automatic actuated rim seal
fire detection and extinguishing system shall be provided on all existing as
well as new external floating roof tanks storing Class A petroleum. The detection
and extinguishing system shall have the following features, namely:—
(i) The system must detect fire
in Rim Seal area immediately but not later than 10 seconds and extinguish the
fire in its incipient stage that is to say within 40 seconds of its indication;
(ii) The system must be robust,
such as it should not be affected by environmental conditions like low or high
ambient temperature, dust, external corrosion, hydrocarbon vapour, rain and
like other environmental conditions;
(iii) The extinguishing foam must
apply in the seal area @18 LPM per square meter in a uniform manner in maximum
of 40 seconds; and
(iv) The detection and
extinguishing system shall be coupled with fire control panel with audio-visual
alarm for necessary fire alert.
(30) In alternative to the
system specified in sub-paragraph (29), the following system can be provided,
namely:—
(i) The detection system shall
detect the fire immediately but not later than 10 seconds;
(ii) The actuation system shall
be actuated immediately on detection of fire;
(iii) Minimum 10 minutes foam
discharge for below seal application or minimum 20 minutes discharge for above
seal application shall be undertaken; and
(iv) The application rate shall
be 20.4 lpm/m2 of the area.
(31) In addition, the individual
components shall have certification from competent authority for suitability
for applicable hazardous zone.
(32) Fixed water spray system
shall also be provided in lube oil drum areas if located in hazardous area.
(33) Clean Agent (Halon
substitute) based flooding system should be provided for control rooms,
computer rooms or repeater station and pressurized rooms in major locations
having automated pipeline receipt or dispatch or TW or TT loading facilities.
Selection of clean agent and design of fire protection system for control
rooms, computer rooms and pressurized rooms should follow the Standard on
“Clean Agent Extinguishing systems NFPA Standard 2001 including its safety
guidelines with respect to “Hazards to Personnel”, electrical clearance and
environmental factors in line with environmental considerations of Kyoto and
Montreal Protocol and MOEF&CC regulations.
5.1.3 In case, combined
Petroleum and LPG facilities have been provided in the same premises, the
common water storage facility for fire fighting purpose may be shared between
Petroleum Installation and LPG Plant under following conditions, namely:—
(1) If both locations are
located within same premise, then, one largest fire scenario to be considered
and water requirement shall be worked out accordingly. In case, the premises
are separate, water requirement to be worked out for independent location;
(2) Each Petroleum or LPG
facility shall independently meet the design, layout and fire protection system
requirements of PNGRB regulations and have common boundary wall and ownership
of both the facilities under same company; and
(3) The pump house may be
common or separate and in case common pump house is provided the control of the
pump house shall remain with group whose premises such pump house is situated.
5.2 Fire water system
design.—Fire
water system shall be designed for a minimum residual pressure of 7 kg/cm2 at
hydraulically remotest point in the installation considering the design flow
rate, namely:—
(1) A fire water ring main
shall be provided all around perimeter of the location facilities with hydrants
or monitors spaced at intervals not exceeding 30 M when measured aerially. Fire
hydrants and monitors shall not be installed within 15 Meters from the
facilities or equipment to be protected, and
(2) The installation shall have
facilities for receiving and diverting all the water coming to the installation
to fire water storage tanks in case of an emergency.
5.2.1 Fire water design
flow rate.—
(1) Fire water flow rate for a
tank farm shall be aggregate of the following, namely:—
(i) For water flow
calculations, all tanks farms having Class A or Class B petroleum storage shall
be considered irrespective of diameter of tanks, whether fixed water spray
system is provided or not;
(ii) Water flow calculated, for
cooling a tank on fire at a rate of 3 lpm/sqm of tank shell area;
(iii) Water flow calculated, for
exposure protection for all other tanks falling within a radius of (R +30) m
from centre of the tank on fire (R-Radius of tank on fire) and situated in the
same dyke, at a rate of 3 lpm/sq.m of tank shell area;
(iv) Water flow calculated, for
exposure protection for all other tanks falling outside a radius of (R+30) m
from centre of the tank on fire and situated in the same dyke, at a rate of 1
lpm/m2 of tank shell area;
(v) Water flow required for applying
foam on a single largest tank by way of fixed foam system, where provided, or
by use of water or foam monitors whichever is higher (Foam solution applicable
rate for cone roof tanks shall be taken as 5 lpm/sqm and for floating roof rim
seal protection it shall be 12 lpm/sqm); and
(vi) Various combinations shall
be considered in the tank farm for arriving at different fire water flow rate
and the largest rate to be considered for design.
(2) For location or dyke
storing exclusively Class C or excluded products, the water requirement shall
be based on 1 monitor of 144 kl/hr and 4 hose streams of 36 kl/hr that is to
say a total of 288 kl per hr for four hrs.
(3) Fire water flow for product
pump house shed for depot or terminal and cross country pipe line installations
with or without tankage shall be at a rate of 10.2 lpm/sqm.
(4) Pumps of volatile products
located under pipe rack fire water flow rate shall be calculated at a rate of
20.4 lpm/sqm.
(5) Fire water flow rate for TT
and TW loading Gantry in a depot or terminal shall be calculated at a rate of @
10.2 lpm/sq.m. The gantry shall be divided into suitable number of segments
(each segment having minimum length of 15 m length and width of 12 m) and three
largest segments operating at a time shall be considered as single risk for
calculating the water requirement. Design flow rate shall be largest of
5.2.1.a, 5.2.1.b, 5.2.1.c, 5.2.1.d and 5.2.1.e. Design flow rate for roof
sinking case of largest tank shall be calculated and wherever, the design flow
rate of roof sinking case is higher than single or two contingencies, as the
condition applicable, the same shall be considered for calculating water
requirement.
(6) Fire water flow rate for
supplementary streams shall be based on using 4 single hydrant outlets
simultaneously. Capacity of each hydrant outlet as 36 k1/hr shall be considered
at a pressure of 7 kg/cm2 and the supplementary water stream requirement shall
be in addition to the design flow rates.
5.2.2 Fire water storage.
(1) Water for the fire fighting
shall be stored in easily accessible surface or underground or above ground
tanks of steel, concrete or masonry.
(2) The effective capacity of
the reservoir or tank above the level of suction point shall be minimum 4 hours
aggregate rated capacity of pumps. Subject to the design criteria specified in
sub-paragraph (3) and sub-paragraph (4) of paragraph 5.1.2.
(3) Fresh water should be used
for fire fighting purposes and in case sea water or treated effluent water is
used for fire fighting purposes, the material of the pipe selected shall be
suitable for the service.
(4) Storage reservoir (RCC)
shall be in two equal interconnected compartments to facilitate cleaning and
repairs and in case of steel tanks there shall be minimum two tanks and all the
tanks shall be of equal height or depth to prevent any migration or overflow
due to difference in height or depth. During maintenance of water tanks,
availability of at least 50% of the water capacity shall be ensured.
(5) Large natural reservoirs
having water capacity exceeding 10 times, the aggregate fire water requirement
can be left unlined.
5.2.3 Fire water pumps.
(1) Fire water pumps having
flooded suction shall be installed to meet the design fire water flow rate and
head. If fire water is stored in underground tanks, an overhead water tank of
sufficient capacity shall be provided for flooded suction and accounting for
leakages in the network, if any and pumps shall be provided with suitable sized
strainers on suction and NRVs on discharge lines.
(2) The pumps shall be capable
of discharging 150% of its rated discharge at a minimum of 65% of the rated
head. The Shut-off head shall not exceed 120% of rated head for horizontal
centrifugal pumps and 140% for vertical turbine pump.
(3) At least one standby fire
water pump shall be provided up to 2 nos. of main pumps. For main pumps 3 nos.
and above, minimum 2 nos. standby pumps of the same type, capacity and head as
the main pumps shall be provided. Fire water pumps shall be of equal capacity
and head.
(4) The fire water pump
including the standby pump shall be of diesel engine driven type. Where
electric supply is reliable, 50% of the pumps can be electric driven. The
diesel engines shall be quick starting type with the help of push buttons
located on or near the pumps or located at a remote location. Each engine shall
have an independent fuel tank adequately sized for 6 hours continuous running
of the pump. Fuel tank should be installed outside of fire pump house and shall
have provision for venting. If tanks are located inside the pump house, the
vent shall have provision for venting outside the pump house.
(5) Fire water pumps and
storage shall be located far away from the potential leak sources or tankage
are and shall be at least 60 M (minimum) away from equipment or where
hydrocarbons are handled or stored.
(6) Fire water pumps shall be
exclusively used for fire fighting purpose only.
(7) Suction and discharge
valves of fire water pumps shall be kept full open all the times.
(8) Jockey pump shall be
provided for keeping the hydrant system or line pressurized at all times. The
capacity of the pump shall be sufficient to maintain system pressure in the
event of leakages from valves and like other devices and besides the main
jockey pump the stand by pump of same capacity and type shall be provided.
(9) Auto cut-in or cut-off
facility should be provided for jockey pumps to maintain the line pressure.
(10) The fire water pumps shall
be provided with auto start facility which shall function with pressure drop in
hydrant line and specified logic even if initial pump does not start or having
started, fails to build up the required pressure in the fire water ring main
system and the next pump shall start and so forth and so on.
(11) The fire hydrant system
should be able to maintain a pressure of minimum 7 kg/cm2 in
the line at the farthest end.
5.2.4 Fire hydrant network.
(1) The fire water network
shall be laid in closed loops as far as possible to ensure multi-directional
flow in the system. Isolation valves shall be provided in the network to enable
isolation of any section of the network without affecting the flow in the rest.
The isolation valves shall be located normally near the loop junctions.
Additional valves shall be provided in the segments where the length of the
segment exceeds 300 M.
(2) Fire hydrant ring main
shall be laid above ground ensuring that—
(i) the pipe line shall be laid
at a height of 300 mm to 400mm above finished ground level;
(ii) the pipe support shall have
only point contact. The mains shall be supported at regular intervals;
(iii) for pipeline size shall be
less than 150 mm and support interval shall not exceed 3 meters;
(iv) the pipe line size shall be
150mm and above not exceeding 6 meters or design approved; and
(v) the system for above ground
portion shall be analysed for flexibility against thermal expansion and
necessary expansion loops where called for shall be provided.
(3) Fire hydrant ring main may
be laid underground at the following places, namely:—
(i) At road crossings;
(ii) Places where above ground
piping is likely to cause obstruction to operation and vehicle movement;
(iii) Places where above ground
piping is likely to get damaged mechanically; and
(iv) Where Frost conditions warrant
and ambient temperature is likely to fall below zero degree Centigrade, then,
underground piping at least 1 meter below the ground level should be provided
and alternatively, in such cases for above ground pipelines, water circulation
to be carried out.
(4) Fire water ring main laid
underground shall ensure the followings, namely:—
(i) Pipes made of composite
material shall be laid underground;
(ii) The Ring main shall have at
least one-meter earth cushion in open ground, 1.5 m cushion under the road
crossings and in case of crane movement area pipeline shall be protected with
concrete or steel encasement as per design requirement and in case of rail crossing,
provisions stipulated by Indian Railways shall be complied;
(iii) The Ring main shall be
suitably protected against soil corrosion by suitable coating or wrapping with
or without cathodic protection; and
(iv) In case of poor soil
conditions it may be necessary to provide concrete/masonry supports under the
pipe line.
(5) Size of hydrant pipeline
shall be as specified below, namely:—
(i) The hydraulic analysis of
network shall be done at the design time and whenever fire water demand
increases due to addition of facilities or extensive extension of network,
fresh hydraulic analysis shall be carried out;
(ii) The velocity of water shall
not exceed 5 meter per second in fire water ring main;
(iii) Fire water ring main shall
be sized for 120% of the design water flow rate and design flow rates shall be
distributed at nodal points to give the most realistic way of water
requirements in an emergency. It may be necessary to assume several
combinations of flow requirement for design of network; and
(iv) The stand post for hydrants
and monitors shall be sized to meet the respective design water flow rates.
(6) The following requirements
shall be complied with, namely:—
(i) Fire water mains shall not
pass through buildings or dyke areas. In case of underground mains the
isolation valves shall be located in RCC or brick masonry chamber of suitable
size to facilitate operation during emergency and maintenance;
(ii) Associated Sprinkler or
foam riser or branch connections meant for storage tanks, if applicable, shall
be taken directly to the outside of tank dyke and shall not pass through fire
wall of any adjacent tanks; and
(iii) The riser connections shall
be taken directly from the mains and provided with separate isolation valve
outside of dyke. Suitable strainer shall be provided on sprinkler branch connection
and shall be located outside of dyke.
5.2.5 Hydrant or monitors.
(1) Hydrants or monitors shall
be located considering various fire scenario at different sections of the
premises to be protected and to give most effective service.
(2) At least one hydrant post
shall be provided at every 30 mtrs. of external wall measurement or perimeter
of battery limit in case of high hazard areas and for non-hazardous area, the
hydrant post shall be spaced at 45 mtrs. intervals. The horizontal range and
coverage of hydrants with hose connections shall not be considered beyond 45
mtrs.
(3) Hydrants shall be located
at a minimum distance of 15 mtrs. from the periphery of storage tank or
equipment under protection and in case of buildings such distance shall not be
less than 2 mtrs. and not more than 15 mtrs. from the face of building.
(4) Provision of hydrants
within the building shall be provided in accordance with IS : 3844.
(5) Hydrant or Monitors shall
be located along road side berms for easy accessibility.
(6) Fixed water or water cum
foam monitors on the network shall be provided with independent isolation
valves and Double headed hydrants with two separate landing valves. Hydrants or
Monitors shall be located with branch connection.
(7) Double headed hydrants and
monitors on suitably sized stand post shall be used. All hydrant outlets or
monitor isolation valves shall be situated at workable height from ground or
hydrant or monitor operating platform level.
(8) Monitors shall be located
to direct water on the object as well as to provide water shield to firemen
approaching a fire. The requirement of monitors shall be established based on
hazards involved and layout considerations.
(9) Hydrants and monitors shall
not be installed inside the dyked areas, but, as an additional requirement, oscillating
monitors shall be provided in inaccessible area within the dyke with isolation
valve or ROV outside the tank farm (in cases inter distances between tanks in a
dyke or within dykes are not meeting the requirements).
(10) TW or TT loading and
unloading facilities shall be provided with alternate hydrant or water cum foam
monitor of suitable capacity and size to ensure adequate coverage and located
at a spacing of 30 M on both sides of the gantry.
(11) The hydrants and monitors
shall be located at a minimum distance of 15 M from the hazard (such as TW and
TT loading or unloading facilities) to be protected.
5.2.6 Material
specifications.—The
materials used in fire water system shall be of approved type as indicated
below, namely:—
(1) In respect of pipes, Carbon
Steel as per IS : 3589/IS : 1239/IS : 1978 or Composite Material or its
equivalent for fresh water service and in case saline, brackish or treated
effluent water is used, the fire water ring main of steel pipes, internally cement
mortar lines or glass reinforced epoxy coated or pipes made of material
suitable for the quality of water able to withstand the temperature and
pressure shall be used and alternately, pipes made of composite materials shall
be used. The composite material to be used may be as per API 15LR/API
15HR/IS12709. In case composite pipes are used they shall be used underground;
(2) In respect of Isolation
Valves, Gate valve or quick shut off type isolation valves made of Cast Steel
having open or close indication shall be used and other materials such as
cupro-nickel for saline or brackish water can be used and the material of the
valve shall be suitable for the service.
(3) In respect of Hydrants
post—
(i) Stand post made of Carbon
Steel shall be used; and
(ii) Outlet valves made of
Gunmetal or Aluminium or Stainless or Steel or Al-Zn Alloy shall be used.
(4) Monitors or High Volume
Long Range Water Cum Foam Monitors (HVLR) or Rim seal shall be approved or
listed by any of the national or international certifying agencies like UL, FM,
VdS or LPC, BIS or any other like agency and the electrical or hydraulic remote
control mechanism shall be in line with Hazardous Area Classification;
(5) In respect of Fire Hoses,
Reinforced Rubber Lined Hose shall be as per IS 636 (Type A) or Non-percolating
Synthetic Hose (Type B) or Equivalent Standard.
(6) In respect of Painting,—
(i) Fire water mains, hydrant
and monitor stand posts, risers of water spray system shall be painted with
“Fire Red” paint as per of IS : 5;
(ii) Hose boxes, water monitors
and hydrant outlets shall be painted with “Luminous Yellow” paint as per IS :
5; and
(iii) Corrosion resistant paint
shall be used in corrosion prone areas.
5.2.7 Fixed water spray
system.
(1) Fixed water spray system is
a fixed pipe system connected to a reliable source of water supply and equipped
with water spray nozzles for specific water discharge and distribution over the
surface of area to be protected and the piping system is connected to the
hydrant system water supply through an automatically or manually actuated valve
which initiates the flow of water and in case the system is manually actuated,
the isolation valve shall be located outside the dyke for ease of access and
operation.
(2) Spray nozzles shall be
directed radially to the tank at a distance not exceeding 0.6 M from the tank
surface.
(3) While calculating the water
rates for spray application for cases other than tanks such as pump house and
tank wagon gantry, the area should be divided into suitable segments so that
maximum water requirement can be optimized.
(4) For TW loading gantry,
sprinklers shall be provided to ensure full surface coverage and three largest
segments shall be considered for water requirement.
(5) For Tank Truck loading
gantries specifically for those cases which have obstructions in water throw,
sprinklers should be provided.
(6) The flow rate in the
sprinkler system shall be either 1 lpm or 3 lpm depending upon whether tank is
outside or within a distance of R+30 m from the tank on fire.
5.3 Foam protection system:
5.3.1 Storage tank:
5.3.1.1 Floating roof tank.—For floating roof tank,
foam shall be poured at the foam dam to blanket the roof seal and the features
of foam system for floating roof tank protection shall be as follows, namely:—
(i) The system shall be
designed to create foam blanket on the burning surface in a reasonably short
period;
(ii) The foam shall be applied
to the burning hazard continuously at a rate high enough to overcome the
destructive effects of radiant heat; and
(iii) The foam makers or foam
pourers shall be located not more than 24 M apart on the shell perimeter based
on 600 mm foam dam height. The height of foam dam shall be at least 51 mm above
the top of metallic secondary seal.
5.3.1.2 Fixed roof tank.—Foam conveying system
shall have same features as of floating roof tank as specified in paragraph
5.3.1.1 excepting that a vapour seal chamber is required before the foam
discharge outlet and features of the foam system for fixed roof protection
shall be as follows, namely:—
(1) The vapour seal chamber
shall be provided with an effective and durable seal, fragile under low
pressure, to prevent entrance of vapour into the foam conveying piping system
and
(2) Where two or more pourers
are required such pourers shall be equally spaced at the periphery of the tank
and each discharge outlet shall be sized to deliver foam at approximately the
same rate. Tanks should be provided with foam discharge outlets or pourers as
indicated below, namely:—
|
Tank diameter (In M)
|
Requirement of Foam Pourer (Minimum.
Nos.)
|
|
Above 18 and up to 20
|
2
|
|
Above 20 and up to 25
|
3
|
|
Above 25 and up to 30
|
4
|
|
Above 30 and up to 35
|
5
|
|
Above 35 and up to 40
|
6
|
|
Above 40 and up to 45
|
8
|
|
Above 45 and up to 50
|
10
|
In case foam pourers are
provided on tanks having diameter up to 18 m, minimum 2 nos. foam pourers shall
be provided.
5.3.1.3. Floating cum fixed
roof tank.—Protection
facilities shall be provided as required for fixed roof tank.
5.3.1.4 Protection for dyke
area or spill fire.
(1) Portable monitors or foam
hose streams shall be provided for fighting fires in dyked area and spills; and
(2) In addition to as specified
in clause (i), Medium expansion foam generators shall be provided to arrest
vapour cloud formation from spilled volatile hydrocarbons and the installation
of medium expansion foam generator shall be as per following criteria, namely:—
(i) Class A tanks : 2 nos.
Fixed type foam generators (minimum) for each tank dyke;
(ii) Class B tanks : Two nos.
portable foam generators (minimum) for each location.
5.3.2 Foam application:
5.3.2.1 Application rate.—The minimum delivery rate
for primary protection based on the assumption that all the foam reaches the
area being protected shall be as indicated below, namely:—
(1) For cone roof tanks
containing liquid hydrocarbons, the foam solution delivery rate shall be at
least 5 lpm/sqm of liquid surface area of the tank to be protected and for
floating roof tanks containing liquid hydrocarbons foam solution, delivery rate
shall be at least 12 lpm/sqm of seal area with foam dam height of 600 mm of the
tank to be protected; and
(2) The height of foam dam
shall be at least 51 mm above the top of metallic secondary seal. In the case
of Floating roof tank roof sinking, the application rate shall be considered as
8.1 lpm/sqm. In determining total solution flow requirements, potential foam
losses from wind and other factors shall be considered.
5.3.2.2 Duration of foam
discharge.—The
equipment shall be capable of providing primary protection at the specified
delivery rates for the following minimum duration namely:—
(1) Tanks (fixed roof or
floating roof) containing Class ‘A’ and Class ‘B’, the minimum duration shall
be 65 minutes, and
(2) Where the system's primary
purpose is for spill fire protection such as dyked area and non dyked area (TT
and TW and like other non dyked) the minimum duration shall be 30 minutes.
5.3.2.3 Water for foam
making.—Water
quantity required for making foam solution depends on the percent concentration
of foam Compound and foams in normal use shall have a 1% to 6% proportioning
ratio, but foam supplier data shall be used for determining water requirement.
5.3.2.4 Foam quantity
requirement.—The
foam quantity requirement shall be based on the following, namely:—
(1) Foam solution application
shall be at the rate of 5 lpm/sqm. for the liquid surface of the single largest
cone roof tank;
(2) Foam solution application
shall be at the rate of 12 lpm/sqm. of seal area of the single largest floating
roof tank;
(3) Floating roof sinking case
also shall be considered for foam compound requirement and storage. Application
@ 8.1 lpm/sq.m by required Nos. HVLR of installed capacity and minimum
aggregate foam storage shall be total of (1) + (2) or (3), whichever is higher;
and
(4) In case of Aviation
Fuelling Stations, where aggregate product storage capacity is less than 1000
KL, foam quantity for spill fire protection of 30 minutes shall be made.
5.3.2.5 Foam compound
storage.
(1) Foam compound should be
stored as explained in IS-4989 or equivalent standard. Type of foam compound to
be used can be protein, fluro-protein or AFFF. Alcohol Resistant Foam shall be
used for handling methanol or ethanol or furfural fires. Minimum 1000 litres of
Alcohol Resistant Foam compound shall be maintained at the installation to
handle methanol or ethanol or furfural fire.
(2) Shelf life of foam compound
shall be taken from manufacturer's data. Foam compound shall be tested
periodically as per OEM guidelines to ensure its quality and the deteriorated
quantity shall be replaced. The deteriorated foam compound can be used for fire
training purposes.
(3) Care shall be taken to
avoid mixture of two or more different grades or batches of foam in a foam
storage tank. In such cases foam shall be tested on yearly basis to check its
efficacy and record shall be maintained thereof.
(4) For details of type of
tests and their periodicity, IS 4989 or equivalent Standard shall be referred.
(5) Quantity of foam compound
as per paragraph 5.3.2.4, should be stored in the Installation. At locations
where cluster of OMC exists, foam requirement can be uniformly distributed at
respective location. The stored quantity shall be made available to needy
company in case of any emergency.
(6) Foam may be stored either
in storage tanks of fixed type or mounted on mobile trolleys.
5.4 Control room and
computer room protection.
(1) Control room and computer
room should be protected by Clean Agent Fire Extinguishing System.
(2) In order to minimize the exposure
to Clean Agent Fire Extinguishing System, persons should be evacuated from the
areas before the system comes into operation.
(3) Clean agent fire
extinguishing system as per NFPA-2001 shall be provided for the protection
system. Each hazard area to be protected by the protection system shall have an
independent system. The time needed to obtain the gas for replacement to
restore the systems shall be considered as a governing factor in determining
the reserve supply needed and 100% standby containers shall be considered for
each protected hazard. Storage containers shall be located as near as possible
to hazard area, but they shall not be exposed to fire. Storage containers shall
be carefully located so that they are not subjected to mechanical, chemical or
other damage.
(4) All the components of the
system shall be capable of withstanding heat of fire and severe weather
conditions.
5.5 First aid fire fighting
equipment:
The fire extinguishers
shall be provided as per the Table given below, namely:—
|
Sr. No.
|
Type of Area
|
Scale of Portable Fire Extinguishers
|
|
(i)
|
Lube Godown
|
1 No. 9 Kg DCP extinguisher for every 200 m2 or
min. 2 Nos. in each Godown, whichever is higher.
|
|
(ii)
|
Lube Filling Shed
|
1 No. 9 Kg DCP extinguisher for 200 m2 or
min. 2 Nos. in each Shed, whichever is higher
|
|
(iii)
|
Storage of (Class A or Class B)
in packed containers and stored in open or
closed area.
|
1 No. 9 Kg DCP extinguisher for 100 m2 or
min. 2 Nos. in each Storage Area, whichever is higher.
|
|
(iv)
|
Pump House (Class A or Class B) Up to 50 HP
(Class A and Class B) Above 50-100 HP Beyond 100 HP
|
1 No. 9 Kg DCP for 2 pumps.
1 No. 9 Kg DCP for each pump.
2 Nos. of 9. kg or 1 no. of 25 kg DCP for each
pump.
|
|
(v)
|
Pump House (Class C) Up to 50 HP Above 50 HP
|
1 No. 9KgDCP for every 4 pumps up to 50 HP.
2 Nos. 9 Kg DCP or 1×25 kg DCP for 4 pumps.
|
|
(vi)
|
Tank Truck loading and unloading gantry for POL
or Special products
|
1 No. 9 Kg DCP extinguisher for each bay plus 1
No. 75 Kg DCP extinguishe r for each gantry.
|
|
(vii)
|
Tank Wagon loading and unloading gantry or siding
|
1 No. 9 Kg DCP extinguisher for every 30 m of or
siding plus 1 No. 75 Kg DCP extinguisher for each gantry or siding.
|
|
(viii)
|
A or G Tank Farm
|
2 Nos. 9 Kg DCP extinguishers for each tank plus
4 Nos. 25 Kg DCP extinguishers for each Tank Farm positioned at four corners.
In case of adjoining tank farms, the no. of 25 Kg extinguishers may be
reduced by 2 nos. per tank farm.
|
|
(ix)
|
U/G Tank Farm
|
2 Nos. 9 Kg DCP extinguisher for each Tank Farm
|
|
(x)
|
Other Pump Houses
|
1 No. 9 Kg DCP extinguisher for every two pumps
or min 2 Nos. 9 Kg DCP extinguisher for each Pump House whichever is higher.
|
|
(xi)
|
Administration Building or Store House
|
1 No. 9 Kg DCP extinguisher for every 200 m2 or
min. 2 Nos. 9 Kg DCP extinguishers for each floor of Building or Store
whichever is higher.
|
|
(xii)
|
DG Room
|
2 Nos. each 9 Kg DCP&4.5 Kg CO2 extinguishers
for each DG room.
|
|
(xiii)
|
Main switch Room or Sub-Station
|
1 No. 4.5 Kg CO2 extinguisher for every 25 m2 plus
1 No. 9 Liter sand bucket per transformer bay.
|
|
(xiv)
|
Computer Room or Cabin
|
2 Nos. of 2 Kg CO2 or 2 Nos. of 2.5 Kg Clean
Agent extinguisher per Computer Room and 1 No. 2 Kg CO2 or 1 No. 1.0 Kg Clean
Agent extinguisher per cabin.
|
|
(xv)
|
Security Cabin
|
1 No. 9 Kg DCP extinguisher per cabin.
|
|
(xvi)
|
Canteen
|
1 No. 9 Kg DCP extinguisher for 100 m2.
|
|
(xvii)
|
Workshop
|
1 No. 9 Kg DCP extinguisher and 1 No. 2 Kg CO2
extinguisher.
|
|
(xviii)
|
Laboratory
|
1 No. 9 Kg DCP extinguisher and 1 No. 4.5 Kg CO2
extinguisher.
|
|
(xix)
|
Oil Sample Storage Room
|
1 No. 9 Kg DCP extinguisher per 100 m2 or
min. 1 no. 9 Kg extinguisher per room, whichever is higher.
|
|
(xx)
|
Effluent Treatment Plant
|
1 No. 75 Kg. and 2 Nos. 9 Kg. DCP Extinguisher
|
|
(xxi)
|
Transformer
|
1 No. 9 Kg. DCP extinguisher.
|
|
(xxii)
|
UPS or Charger Room
|
1 No. 2 Kg. CO2 extinguisher.
|
Notes:
(1) All fire extinguishers
shall conform to respective BIS or equivalent codes, such as 9 Kg DCP Type (IS
: 15683), 4.5/6, 8 Kg CO2 Type (IS : 2878) and 25/50/75 Kg DCP Type (IS :
10658) and bear ISI mark. BIS or Equivalent certificates of all extinguishers
shall be maintained at the location;
(2) While selecting the
Extinguisher, due consideration should be given to the factors like flow rate,
discharge time and throw in line with IS : 2190 or equivalent;
(3) The Dry Chemical Powder
used in extinguisher and carbon dioxide gas used as expelling agent shall be as
per relevant BIS or Equivalent code;
(4) While selecting the dry
chemical powder, due consideration should be given to the typical properties
such as Apparent Density (0.65 +/-0.05), Fire Rating (144B), Thermal
Gravimetric Analysis (with decomposition at around 250°C) and foam
compatibility;
(5) Siliconised Potassium
bicarbonate DCP powder (IS 4308 : 2003) or Mono-ammonium phosphate based DCP
powder (IS : 14609) can also be used for recharging DCP fire extinguishers;
(6) Spare CO2 cartridges and
DCP refills as required based on their shelf life should be maintained, but
minimum 10% of the total charge in the extinguishers should be maintained at
the location;
(7) Portable fire extinguishers
shall be located at convenient locations and are readily accessible and clearly
visible at all times;
(8) The sand buckets shall have
round bottom with bottom handle having 9 litre water capacity conforming to IS
: 2546. The sand stored in bucket shall be fine and free from oil, water or
rubbish;
(9) Rain protection of suitable
design should be provided for all extinguishers and sand buckets;
(10) The maximum running
distance to locate an extinguisher shall not exceed 15 m; and
(11) The extinguisher shall be
installed in such a way that its top surface is not more than 1.5m above the
floor or ground level.
5.6 Emergency trolley and
emergency kit.
(1) A trolley containing Fire
Proximity Suit, B.A. Set, Water Jel Blanket, Resuscitator, First Aid Box,
Stretcher with blanket, Spare fire hoses, Special purpose nozzles, Foam branch
pipes, Explosive meter, P.A. System shall be readily available at the location
and positioned to have easy access to it during emergency situation.
(2) An emergency kit shall be
provided consisting of safety items shall be readily available at the
terminals. All the items of the kit shall be kept on a trolley specifically
designed for the purpose.
5.7 Motorable arrangement
for towing or carrying mobile fire fighting equipment such as Foam trolleys,
Portable water-cum-foam monitors and like other monitors should be made and
available on sharable basis.
5.8 Hydrocarbon detection
and annunciation, dyke drain valve annunciation system and emergency shutdown
logic:
5.8.1 Hydro carbon
detection and annunciation system.—Hydrocarbon detectors shall be installed
near all potential leak source of class-A that is to say tank dykes, tank
manifolds, pump house manifold and like other manifolds and Hydrocarbon
detector of proper type shall be selected and also shall be proof tested and
shall be maintained in good condition. The other details are specified as
below, namely:—
(1) General:
(i) The best method of
prevention of explosion is to avoid basic build-up of Explosive Vapour
concentration immediately on occurrence of leakage, and such method would
require basically a reliable and continuous Hydro Carbon detection system with
warning annunciation to alert the operating personnel to take timely corrective
action;
(ii) The Hydro Carbon Detection
System shall provide early warning on build-up of Vapour concentration below
the LFL limits.
(2) Application:
(i) Hydrocarbon (HC) detectors
shall be installed near all potential leak sources of Class-A Petroleum
products such as tank dykes, tank manifolds and pump house manifold and such
detectors shall be placed in a way that entire possible source of leaks and
collection of products is continuously detected and alarm is set at 20% of
lower explosive limit of Class-A petroleum products;
(ii) The detection control
equipment should be provided in the control room and the field for continuous
monitoring should be provided even during power failure.
(3) Power Supply:
The supply to the system
shall be through a reliable on line uninterrupted power supply. (online UPS).
(4) Architecture Components:
The main components shall
be as specified below, namely:—
(i) Hydro Carbon Detectors;
(ii) Field Transmission units or
Signal scanners;
(iii) Control system or PC;
(iv) Display;
(v) Annunciation System and
like other system;
(vi) Cables, hooters, repeater,
Power Supplies and like other devices; and
(vii) All the components
installed in the hazardous area shall confirm to the Hazard Area Classification
applicable and shall be certified by PESO or Authorized lab by the country of
the origin.
(5) Annunciation System:
(i) Appropriate annunciation
system shall be available to ensure that all the alarms generated, both, audio
and visual are reported to the installation personnel at local and remote
control panel. The alarms both, audio and visual can be repeated at additional
location to ensure corrective action is taken;
(ii) Hydro Carbon Detectors
should be available as per requirement;
(iii) The detectors shall be able
to detect the presence of Hydro Carbon Vapours well below the LEL level;
(iv) Any one or more in
combination from the following types can be provided Namely:—
(a) Catalytic detectors;
(b) Infra-red detectors; and
(c) Line or Path detectors;
(v) The system shall be
available at all times;
(vi) The control equipment
should have data logging facilities to provide print outs of the history of the
events with date and time of leakages; and.
(vii) The control equipment
should be able to generate at least two alarms at different levels of LEL
concentration of Hydro Carbons.
(6) Inspection and Testing:
(i) Calibration of the
detectors shall be done as per OEM recommendation or once in six month,
whichever is earlier;
(ii) The drift in the
sensitivity of the individual detectors shall be recorded in maintenance
history log book during calibration and the detectors with abnormal or wide
drift in sensitivity shall be rectified or replaced; and
(iii) Standard calibration kit
must be available in the location for periodic performance test of hydrocarbon
detectors.
5.8.2 Dyke Drain valve
Annunciation system.
(1) All the dyke valves will be
fitted with a proximity switch or sensor for indication of the position of the
valve. The valves of the Dyke shall remain in closed position. In case any
valve is open, then, Audio alarm and visual indication shall come at control
panel for suitable corrective measures.
(2) In case of automated
locations existing PLC can be used, but where the locations are not automated,
a standalone system shall be provided.
5.8.2.1 Power Supply.—The supply to the system
shall be through a reliable on line uninterrupted power supply/(Online UPS).
The main components in the Architecture Components shall be as below, namely:—
(i) Proximity Switches or
Sensors;
(ii) Field transmitter unit or
Signal Scanners;
(iii) Control System or PC or
TAS;
(iv) Display;
(v) Annunciation System and
like other systems; and
(vi) Cables, hooters, Mimic,
Power Supplies and like other systems.
5.8.2.2 All the components
installed in the hazardous area shall confirm to the Hazard Area Classification
applicable and shall be certified by Central Institute of Mining and Fuel
Research (CIMFR) or Petroleum and Explosive Safety Organization (PESO) or
Authorized lab by the country of the origin.
5.8.2.3 Appropriate
annunciation system shall be available to ensure that all the alarms generated,
both, audio and visual are reported to the installation personnel at local and
remote control panel on real time basis and the alarms both, audio and visual
should be repeated at additional location to ensure corrective action is taken.
5.8.2.4 The control system
shall be available at all times and the control equipment should have data
logging facilities to provide print outs of the history of the events with date
and time of open and close position of the valves.
5.8.2.5 Inspection and
Testing:
(i) The system shall be checked
by the safety officer on a daily basis.
(ii) The system shall be
thoroughly inspected every month by opening and closing the valves and
verifying that the Audio Video alarms are generated at local and remote panel
and records maintained.
5.8.3 Emergency shut Down
(ESD) logic for Terminal Automation System (TAS).—The ESD for TAS enabled
locations shall be provided in control room as well as at various strategic
locations. ESD system shall be only through push buttons with wired connection.
The other details are specified as below, namely:—
(1) Actuation or/pressing of
any ESD shall initiate following actions, namely:—
(a) Process Shutdown;
(b) Power Shutdown; and
(c) Process Shutdown shall
include the following, namely:—
(i) To stop product loading
pumps;
(ii) Barrier gates to open;
(iii) All ROSOVs and MOVs to
close;
(iv) Tank lorry filling (TLF) or
tank wagon filling (TWF) operations through the batch controllers to stop; and
(v) Fire siren to blow;
(2) Power Shutdown shall
initiate the following, namely:—
(i) Trip all the panels other
than Emergency panel. The Emergency panel should host fire siren, bore wells,
jockey pumps, critical High Mast tower lights outside the licensed area,
security cabin, fire pump house, Critical lights in TLF, Admin block, MCC room
and power to the control room or Automation system;
(ii) There should be interlock
between ESD for Process shut down and ESD for Power shut down so that full
power shut down takes after a time lag required for closing the ROSOV or MOVs
and full closure of valves shall be ensured. The time lag shall be location
specific; and
(iii) At pipe line locations
alarm signal shall be exchanged between the two control rooms so that necessary
actions are taken by the operating personnel at both ends;
(3) Inspection and Testing:
The system shall be checked
during each fire drill conducted with full system shut down and records shall
be maintained.
5.9 Mock drills and Mutual
aid.
(1) Instructions on the action
to be taken in the event of fire should be pasted at each siren point and
familiarity with such instructions ensured and recorded.
(2) Monthly fire drills
considering various scenarios shall be conducted regularly with full
involvement of all employees of the installation. The mock drill shall include
the full shut down system activation once in six months.
(3) The offsite disaster mock
drills shall be conducted periodically as per local statutory requirements.
(4) The company should approach
and coordinate with the district authority for conducting “Offsite Mock Drills”.
(5) The post drill analysis
should be carried out and discussed emphasizing areas of improvements.
(6) The record of such drills
should be maintained at the location.
(7) Mock drill scenarios shall
include all probable scenarios and the key areas like tank Farm, Rim seal fire,
Gantry, Pump House, Tank Wagon gantry and like other key areas, shall be
covered at least once in six months.
(8) Security staff should be
trained as first responders for fire fighting and rescue operation along with
plant operating personnel.
(9) Installation shall have a
‘Mutual Aid’ arrangement with nearby industries to pool in their resources
during emergency.
(10) Mutual Aid agreements shall
be prepared and signed by all Mutual Aid members. Fresh agreement shall be made
on expiry of 2 years or whenever there is change in the signatories to the
agreement. Quarterly meeting of Mutual Aid members shall be conducted and the
minutes shall be recorded and the minutes shall be reviewed in the subsequent
meetings.
5.10 ERDMP (Emergency
Response and Disaster Management Plan).
(1) A comprehensive ERDMP shall
be developed in accordance to the Petroleum and Natural Gas Regulatory Board
(Codes of Practices for Emergency Response and Disaster Management Plan
(ERDMP)) Regulations, 2010 and the copies of the ERDMP shall be available to
all personnel in the installation.
(2) The key action points of
the comprehensive ERDMP referred in sub-paragraph (1) shall be displayed at
strategic locations in the installation for ready reference.
5.11 Fire Protection system
: Inspection and Testing.
(1) The fire protection
equipment shall be kept in good working condition all the time.
(2) The fire protection system
shall be periodically tested for proper functioning and logged for record and
corrective actions.
(3) One officer shall be
designated and made responsible for inspection, maintenance and testing of fire
protection system.
(4) The responsibilities of
each officer shall be clearly defined, explained and communicated to all
concerned in writing for role clarity.
5.11.1 Fire water pumps.
(1) Every pump shall be test
run for at least half an hour or as per OEM guidelines, whichever is higher
twice a week at the rated head and flow.
(2) Each pump shall be checked,
tested and its shut-off pressure observed once in a month.
(3) Each pump shall be checked
and tested for its performance once in six months by opening required nos. of
hydrants or monitors depending on the capacity of the pump to verify that the
discharge pressure, flow and motor load are in conformity with the design
parameters.
(4) Each pump shall be test run
continuously for 4 hours at its rated head and flow using circulation line of
fire water storage tanks and observations relating thereto shall be logged once
a year.
(5) The testing of standby
jockey pump, if provided shall be checked weekly. Frequent starts and stops of
the pump indicate that there are water leaks in the system which should be
attended to promptly.
5.11.2 Fire water ring
mains.
(1) The ring main shall be
checked for leaks once in a year by operating one or more pumps and keeping the
hydrant points closed to get the maximum pressure.
(2) The ring mains, hydrant,
monitor and water spray header valves shall be visually inspected for any
missing accessories, defects, damage and corrosion every month and records
thereof shall be maintained.
(3) All valves on the ring
mains, hydrants, monitors and water spray headers shall be checked for leaks,
smooth operation and lubricated once in a month.
5.11.3 Fire water spray
system.
(1) Water spray system shall be
tested for performance that is to say its effectiveness and coverage once in
six months.
(2) Spray nozzles shall be
inspected for proper orientation, corrosion and cleaned, if necessary at least
once a year.
(3) The strainers provided in
the water spray system shall be cleaned once in a quarter and records thereof
shall be maintained.
5.11.4 Fixed and semi fixed
foam system.—Fixed
or Semi fixed foam system on storage tanks should be tested once in six months
and such testing shall include the testing of foam maker or chamber. The foam
maker or chamber should be designed suitably to facilitate discharge of foam
outside the cone roof tank and after testing foam system, piping should be
flushed with water.
5.11.5 Clean agent system.—Clean agent fire
extinguishing system should be checked as below, namely:—
(1) Agent quantity and pressure
of refillable containers shall be checked once every six months; and
(2) The complete system should
be inspected for proper operation once every year (refer latest NFPA 2001 for
details of inspection of various systems).
5.11.6 Hoses.—Fire hoses shall be
hydraulically tested once in six months to a water pressure as specified in
relevant IS/UL/equivalent codes.
5.11.7 Communication system.—Electric and hand
operated fire sirens should be tested for their maximum audible range once a
week.
5.11.8 Fire water tank or
reservoir.
(1) Above ground fire water
tanks should be inspected externally and internally.
(2) The water reservoir shall
be emptied out and cleaned once in 3 years, but floating leaves, material or
algae, if any, shall be removed once in 6 months or as and when required.
5.11.9 Fire extinguishers.—Inspection, testing
frequency and procedure for fire extinguishers should be in
line with design standard.
PART — F
(Maintenance
and Inspection)
6.0 MAINTENANCE AND
INSPECTION.—Each
facility shall have a documented operating manual including operations,
maintenance, training procedures, purging and record keeping based on
experience and conditions under which the Petroleum Installation is operated,
and a documented maintenance manual and such facility shall also have written
operating, maintenance, and training procedures based on experience, knowledge
of similar facilities, and conditions under which they will be operated.
6.1 Basic Requirements.—Each facility shall meet
the following requirements, namely:—
(1) Have written procedures
covering operation, maintenance, and training;
(2) Keep up-to-date drawings of
plant equipment, showing all revisions made after installation;
(3) Revise the plans and
procedures as operating conditions or facility equipment require;
(4) Establish a written
emergency plan;
(5) Establish liaison with
appropriate local authorities such as police, fire department, or hospitals and
inform them of the emergency plans and their role in emergency situations;
(6) Analyze and document all
safety-related malfunctions and incidents for the purpose of determining their
causes and preventing the possibility of recurrence;
(7) As per maintenance
philosophy, the activities should be identified that would be contracted to
third party contractors for maintenance and support;
(8) The activity supervisors
shall be identified according to the level of supervision required;
(9) The supervisors referred to
in clause (8) shall be given safe supervisor training by designated staff and
then they shall be put on the job;
(10) The contractors staff shall
be engaged in toolbox talk given on relevant topics are held with the Contract
holders and owners; and
(11) OEM service engineers are
involved in critical overhauls for better quality assurance and for first time
activities.
6.2 The operating manual
for petroleum storage, handling and loading or unloading facilities shall
include standard operating procedures which shall include procedures for the
following, namely:—
(1) Handling, maintenance,
inspection and fire protection facilities;
(2) Determining the existence
of any abnormal conditions, and the response to such conditions in the plant;
(3) The safe transfer of
petroleum including prevention of overfilling of vessels;
(4) For the proper startup and
shutdown of all components;
(5) To ensure that each control
system is adjusted to operate within its design limits;
(6) For monitoring operations;
and
(7) Emergency preparedness and
handling
6.3 The operating
procedures manual shall be accessible to all plant personnel and shall be kept
readily available in the operating control room. The operating manual shall be
updated when there are changes in equipment or procedures. All petroleum plant
components shall be operated in accordance with the standard operating
procedures as per operating manual.
6.4 The periodic
inspections and tests shall be carried out in accordance with generally
accepted engineering practice or recommendations of Original Equipment
Manufacturer to ensure that each component is in good operating condition.
6.5 Each facility
operator shall ensure that when a component is served by a single safety device
only and the safety device is taken out of service for maintenance or repair,
the component is also taken out of service.
6.6 It shall be ensured
that where the operation of a component that is taken out of service could
cause a hazardous condition, a tag bearing the words “Do Not Operate,” or the
equivalent thereto, is attached to the controls of the component, and wherever
possible, the component shall be locked out.
6.7 Stop valves for
isolating pressure shall be locked or sealed open and such stop valves shall
not be operated except by an authorized person.
7.0 Maintenance Manual:
7.1 Each facility
operator shall prepare a written manual that sets out an inspection and
maintenance program for each component that is used in the facility.
7.2 The maintenance
manual for facility components shall include the following, namely:—
(1) The manner of carrying out
and the frequency of the inspections and tests as specified in this behalf;
(2) All procedures to be
followed during repairs on a component that is operating while it is being
repaired to ensure the safety of persons and property at the facility; and
(3) Each entity shall conduct
its maintenance program in accordance with its written manual for facility
components, and in addition, the history card of all critical equipments,
instruments and systems shall be maintained.
7.3 Maintenance Work flow.
(1) The objective of the work
flow is to provide an integrated proactive and reactive work plan so that
repair work is minimized and reliability and availability are optimized.
Maintenance execution begins with the receipt of a work request and concludes
with the close out of the work order.
(2) Correct prioritization of
work and proactively preparing activities through high quality work
preparation, combined with accurate scheduling, will lead to a more stable work
environment and reduce deferments and breakdowns, improve integrity and safety,
and provide additional job satisfaction and ownership to technicians.
(3) The management and control
of day-to-day maintenance on all process units and utilities of a site is to
provide—
(a) support for a maintenance
strategy based on doing programmed maintenance on time;
(b) safe, healthy and
environmentally sound execution of maintenance work;
(c) availability of equipment; and
(d) business efficiency.
(4) The designated person for
issue of work permit shall verify the execution of preparation activities
before issue of the work permit.
(5) Maintenance work shall be
undertaken in accordance with work permit requirements.
(6) Inspection personnel should
be notified on time at which moment witnesses or hold points set.
(7) A verification of the HSE
requirements should be carried as the maintenance execution includes HSE review
and a toolbox talk as outlined in the work permit or work pack.
(8) The maintenance supervisor
should ensure that a toolbox talk is held before work commences.
(9) Upon completion of the job,
the job site should be left safe, clean and tidy and any excess materials
should be returned to the stores and tools should be cleaned and returned to
the workshop or put away in the correct storage place.
(10) On a daily basis, the
progress of work should be reported. If the work is not completed, it should
continue the next working day after taking requisite permission and approval
from work permit issuing personnel.
(11) The work permit duly signed
shall be returned to issuing authority on completion of job, removal of all
material from site and handing over of facilities to user and like other
events.
7.4 Maintenance Strategy.
(1) The facilities should be
designed for minimum maintenance intervention.
(2) The maintenance
requirements should be clearly defined and further optimized based on
maintenance strategy reviews using tools such as reliability centred
maintenance, Risk Based Inspection and Risk Assessment Matrix (RAM), after
detailed equipment specifications are known.
(3) The criticality of the
equipment shall be taken into account during the maintenance strategy
selection.
(4) Appropriate diagnostic
tools and staff competencies shall be provided to facilitate rapid fault
finding and rectification and also to provide opportunistic maintenance during
outages.
(5) Maintenance strategies
shall maximize non-intrusive and on line data acquisition to support planning
and analysis.
(6) Special Critical Equipment
shall have OEM defined performance standards which shall be periodically tested
and verified.
(7) Structural and pipeline
survey and painting shall be done on a regular basis.
7.5 The entity shall
prepare a written plan for preventive maintenance covering the scope,
resources, periodicity and like other particulars. The corrective measures
should include the preventive maintenance, scheduling, execution and closure.
7.6 Each facility should
have well defined system for identification of spare part; rationalization and
optimization to minimize any supply chain or logistics constraints and risks.
7.7 Well defined Roles
and Responsibilities matrix should be available made for each machine as well
as activity to be carried out in the workshop and the procedure for Audits and
Review of the workshop shall be documented and adhered to.
8.0 Inspection.
(1) Each facility shall have
written inspection, testing and commissioning program in place. Inspection
shall include before commissioning during installation as well as during
regular operation of the Petroleum Installation.
(2) All documents related to
design, installation procedure of the respective vendors and the manufacturer's
instruction for pre-commissioning and commissioning of the equipment, systems,
instruments, control systems and like other devices shall be properly stored
and followed.
(3) Inspection shall cover the
review of test protocols and acceptance criteria that such procedures are in accordance
with the protocols and acceptance criteria specified in line with OEM specific
requirements
(4) Inspection shall cover that
the equipment is installed in accordance with design, and any deviations
documented and approved.
(5) All safety systems are installed
inspected and tested as per design or OEM requirement.
(6) Inspection shall cover that
all safety devices are installed and are in working condition as per the design
or OEM requirements.
(7) Inspection shall cover the
verification of various safety interlocks and ESD provided in the design.
(8) Inspection shall cover the
adequacy of sealing systems.
(9) Inspection shall cover the
electrical systems, check its integrity, earthing resistance, bonding and like
other requirements.
(10) Inspection shall cover the integrity
of mechanical and rotating equipment.
(11) The integrity and efficacy
of gas detection, fire protection and fighting system and connected equipments
shall be covered in the inspection.
(12) Inspection shall cover the
efficacy of corrosion system.
(13) Inspection shall cover and
review the mechanical completion records that the PSVs are of the correct type
and sizing as per the P and IDs/data sheets.
(14) Inspection shall cover
location of inlet pipe-work to relieving devices in relation to potential
restrictions (such as above liquid levels, vessel internals, and like other
potential restrictions).
(15) Inspection shall cover and
review P and IDs to check the position of isolation valves for relieving
devices, their capacities. Inspection to confirm by review of all vent
locations (atmospheric vent from drums or equipment seals) that they vent to
safe location and in the event of liquid carry over will not discharge to areas
that may cause a hazard to personnel.
(16) Inspection shall review the
area classification layouts and associated studies to confirm that all possible
hazards have been appropriately considered (including possible migration) and
the hazardous area drawings correctly account for the actual location of the
sources of release the hazardous areas have been appropriately defined.
(17) Inspection shall cover that
all ESD devices move to their safe condition on loss of system output,
hydraulic power or instrument air. All ESD Valves and actuators shall remain
functional following an explosion or under fire conditions for a sufficient
time period to perform their intended function.
(18) The maximum allowable back
pressure and minimum design temperature of the relief system shall be checked
for suitability for the highest identified flow rate.
(19) Control System shall include
all status monitoring and actions to and from the Control Rooms.
(20) Inspection shall cover the
escape and evacuation passages.
(21) Inspection shall cover the
emergency communication system for its effectiveness during emergency
situations.
PART – G
(Competence
Assurance and Assessment)
9.0 COMPETENCE ASSURANCE
AND ASSESSMENT:
9.1 Every entity shall
develop, implement, and maintain a written training plan to instruct all
Petroleum installation personnel with respect to the following, namely:—
(1) Carrying out the emergency
procedures that relate to their duties at the petroleum installation as set out
in the procedure manual and providing first aid;
(2) Permanent maintenance,
operating, and supervisory personnel with respect to the following, namely:—
(i) The basic operations
carried out at the petroleum installation;
(ii) The characteristics and
potential hazards of petroleum and other hazardous fluids involved in operating
and maintaining the petroleum installation;
(iii) The methods of carrying out
their duties of maintaining and operating the petroleum installation as set out
in the manual of operating, maintenance and transfer procedures;
(iv) Fire prevention, including
familiarization with the fire control plan, fire fighting, the potential causes
of fire, the types, sizes, and likely consequences of a fire at petroleum
installation; and
(v) Recognizing situations when
it is necessary for the person to obtain assistance in order to maintain the
security of the petroleum installation.
9.2 Each entity shall
develop, implement, and maintain a written plan to keep its personnel
up-to-date on the function of the systems, fire prevention, and security at the
petroleum installation.
9.3 The Refresher
programs for training of all personnel shall be conducted an interval not
exceeding 3 years to keep personnel updated on the knowledge and skills.
9.4 Every entity shall
maintain a record for each employee that sets out the training given to the
employee under this Part.
9.5 Each entity shall
ensure that petroleum installation personnel receive applicable training and
have experience related to their assigned duties. Any person who has not
completed the training or received experience shall work under the control of
trained personnel.
9.6 For the design and
fabrication of components, each entity shall use personnel who have
demonstrated competence by training or experience in the design of comparable
components and for fabrication who have demonstrated competence by training or
experience in the fabrication of comparable components.
9.7 Supervisors and other
personnel utilized for construction, installation, inspection, or testing shall
have demonstrated their capability to perform satisfactorily the assigned
function by appropriate training in the methods and equipment to be used or
related experience and accomplishments and further their capability shall be
assessed periodically.
9.8 Each entity shall
utilize for operation or maintenance of components only such personnel who have
demonstrated their capability to perform their assigned functions by successful
completion of the training as specified in this behalf and possess experience
related to the assigned operation or maintenance function.
9.9 Corrosion control
procedures including those for the design, installation, operation, and
maintenance of cathodic protection systems, shall be carried out by, or under
the direction of, a person qualified by experience and training in corrosion
control technology.
9.10 Personnel having
security duties shall be qualified to perform their assigned duties by
successful completion of the training as specified in this behalf.
9.11 There shall be a
minimum level maintained with men apart from the security personnel for
monitoring the facilities even during non operational hours.
9.11.1 During all operations
even after the general shift, a dedicated fire fighting team should be present.
Alternatively, the security personnel shall be trained and certified for
operation of fire fighting and emergency handling.
9.11.2 A dedicated,
qualified and experienced officer should be designated as ‘Safety Officer’ of
the Terminal after training. He shall be given exposure to Hazop, Risk
Assessment, Safety Audit and upkeep of fire fighting facilities and conducting
Safety Meetings.
9.12 Each entity shall
follow a written plan to verify that personnel assigned operating, maintenance,
security, or fire protection duties at the petroleum installation do not have
any physical condition that would impair performance of their assigned duties.
The plan shall be designed to detect both readily observable disorders, such as
physical handicaps or injury, and conditions requiring professional examination
for discovery.
9.13 Operations and
Maintenance training.—Each
entity shall provide and implement a written plan of initial training to
instruct, the personnel as specified in succeeding paragraph 9.13.1 to 9.13.3.
9.13.1 All permanent
maintenance, operating, and supervisory personnel;—
(1) about the characteristics
and hazards flammable fluids used or handled at the facility, including,
flammability of mixtures with air, odourless vapour, boil off characteristics,
and reaction to water and water spray;
(2) about the potential hazards
involved in operating and maintenance activities; and
(3) to carry out aspects of the
operating and maintenance procedures that relate to their assigned functions.
9.13.2 All personnel of
petroleum installation shall be trained to carry out the emergency procedures
that relate to their assigned functions; and to give first-aid;
9.13.3 All operating and
appropriate supervisory personnel of petroleum installation shall be trained to
understand detailed instructions on the facility operations, including
controls, functions, and operating procedure.
9.14 Security Training.—Personnel responsible for
security at petroleum installation shall be trained in accordance with a
written plan of initial instruction to—
(1) recognize breaches of
security;
(2) carry out the security
procedures that relate to their assigned duties;
(3) be familiar with basic
plant operations and emergency procedures, as necessary to effectively perform
their assigned duties; and
(4) recognize conditions where
security assistance is needed.
9.15 Fire Protection and
Fighting Training.—All
personnel including officers, operators, security, T/T drivers and contract
workmen, clericals who are likely to be present/working in the petroleum
installation shall be trained in accordance with a written plan of initial
instruction, including plant fire drills, to —
(1) know and follow the fire
prevention procedures as specified in this behalf;
(2) know the potential causes
and areas of fire determined;
(3) know the types, sizes, and
predictable consequences of fire determined;
(4) know and be able to perform
their assigned fire control duties according to the procedures and by proper
use of equipment provided;
(5) each employee who undergo a
refresher course once in every three years after initial training; and
(6) every employee or
authorized person of contractor working in the installation who shall be
familiarized with fire siren codes and the location of fire siren operating
switch nearest to his place of work.
9.16 Training Records.—Each entity shall
maintain a system of records which—
(1) Shall provide evidence that
the training programs required under this part have been implemented;
(2) Shall provide evidence that
personnel have undergone and satisfactorily completed the required training
programs; and
(3) Shall ensure that the
records maintained for one year after personnel are no longer assigned duties
at the petroleum installation.
PART — H
(Vehicle
Management System)
10.0 Vehicle Management
System.—The
transportation management document shall describe the procedures for effective
day-to-day management of Road Transport and such management shall include
driver selection, recruitment and training, health screening, working hours and
other terms and conditions relating thereto.
10.1 Driver Management.—The selection and
training of drivers shall be in consonance with conditions as specified in
succeeding paragraph 10.1.1 and 10.1.2.
10.1.1 Qualification of
driver.
(1) The driver shall hold a
valid driving license for type of vehicle to be driven and shall be authorized
to drive vehicles carrying specific class of product under local Dangerous Goods
regulations.
(2) The age of the driver shall
not be less than 25 years with minimum of 3 years' experience of driving
vehicles for which he is licensed to drive.
(3) The driver can demonstrate
knowledge of local road or highway regulations.
(4) The driver can able to read
and write in local language and comply with local legal regulations in terms of
qualifications and requirements for him.
(5) Competence assessment of
the driver should be carried out by a company-approved driving examiner with
on-road test.
10.1.2 Training and
communications.—The
following shall be ensured, namely;—
(1) That the driver has
completed induction training on company rules and emergency response
procedures;
(2) That the driver has
attended defensive driving course within last two years;
(3) That the driver has
undergone training on first aid procedures;
(4) That the driver has
completed necessary training as per hazardous good transportation procedures;
(5) That the driver should
attend regular tool box meeting, safety meetings; and
(6) That the driver should
attend daily/trip wise counselling on journey management.
10.2 Journey Management:
10.2.1 Journey management
plans and controls shall have the following elements, namely:—
(1) Routes between supply point
and major destination shall be drawn up using effective journey management
system in order to avoid unsuitable roads and congested areas as far as
practicable;
(2) Journey time shall be
established for such routes and rest and reporting points designated on the
long routes which exceed normal driver shift time;
(3) Resting points where
suitable accommodation is available to be designated by management;
(4) Competent person supervise
the journey management plan and procedures;
(5) System to be in place for
deployment of emergency response procedures;
(6) Known en-route hazards,
such as steep gradients, narrow bridges, poor road surface to be identified and
recorded in the journey management plan;
(7) Route hazards maps to be
produced and made available to drivers; and
(8) Trip time and other special
route hazard information to be given to driver with customer invoice paperwork.
10.2.2 Driving and duty
hours.
(1) Comply to legal
requirements, if any, irrespective of any limits specified in the succeeding
sub-paragraph and the drivers shall not drive or be requested to drive when
feeling tired and effective fatigue management procedures should be in place.
(2) The continuous driving
shall not exceed three hours and it should be followed by minimum 15 minutes
rest. The rest shall be taken on continuous block and either away from vehicle
or, if taken in a sleeper cab, while vehicle shall be stationary and
alternatively, two drivers can be used with a monitoring system for rest after
every three hours.
(3) Tachograph or in vehicle
monitoring system to be fitted for vehicles.
10.3 Vehicle Management.—All vehicles shall comply
with local legal requirements and respective company standards and the vehicles
shall be designed and equipped for local environments and intended range of
operation and the following shall be ensured, namely:—
(1) The tank truck shall be
visually “well maintained “and capable of meeting basic safety inspection
consistent with safe manoeuvering at low speeds within confines of loading or
delivery location. The inspection includes brake operation and tyre inspection.
(tie having a visible tread pattern and no obvious damage);
(2) Three-point inertia reel
seat belts to be fitted for crew;
(3) The tank truck shall be
fitted with an external engine cut-off device;
(4) The tank truck shall be
fitted with audible reversing alarm;
(5) The tank truck should have
product tank with an internal valve to prevent product leakage if an external
outlet valve is damaged;
(6) The tank truck shall have
an exhaust system adequately shielded from direct contact with fuel from
overfilled tanks leaks;
(7) The tank truck shall have
overfill protection system (compatible with loading rack facilities);
(8) The tank trucks shall be
loaded and operated within maximum permissible gross weight and in accordance
with national regulation and approved limits by RTO for both rigid chasis and
trailer body;
(9) Trailer tank to be fitted
with overturn protection that gives effective protection to man lids in the
event of vehicle roll-overs;
(10) Tank top safety rail or
harness system to prevent driver from falling when or if working on tank top;
(11) Tank truck shall be
provided with a spill kit capable of dealing with small spills < 10 ltrs.”;
and
(12) In case of Dangerous Goods,
HGVs to be fitted with at least three number of dry powder fire extinguisher
two of which are easily accessible on either side of tank and CO2 is
an acceptable alternative for an extinguisher.
PART – I
(Safety
Management System)
11.0 Safety Management
System.—The
organization should establish a safety management system which shall be an
integral part of the overall management system. Safety Management System (SMS)
should be based on PDCA (Plan, Do, Check and Act) cycle which comprises of-(
(1) Policy setting which
includes policy, corporate acceptance of responsibility, objectives,
requirements, strategies;
(2) Organization which includes
structure, accountability and safety culture, involvement of the workforce,
systems for performing risk assessment;
(3) Planning and execution
which includes operational standards and procedures for controlling risks,
permit to work, competence and training, selection and control over
contractors, management of change, planning and control for emergencies and
occupational health;
(4) Measuring and evaluating
which includes active monitoring, recording and investigation of incidents or
accidents, auditing and handling of non-conformities; and
(5) Continuous improvement
which includes review and application of the lessons learnt and Safety
management system should not degenerate into a paper exercise only, conducted
solely to meet regulatory requirements.
11.1 Elements of Safety
Management system.—Safety
management system should include at least the basic elements as specified in
the succeeding paragraph 11.2 to 11.15.
11.2 Safety Organization.—Leadership and Management
Commitment should be clearly visible in the SMS. Management should develop and
endorse a written description of the company's safety and environmental
policies and organizational structure that define responsibilities,
authorities, and lines of communication required to implement the management
program. Management should review the safety and environmental management
program to determine if it continues to be suitable, adequate and effective at
predetermined frequency. The management review should address the possible need
for changes to policy, objectives, and other elements of the program in light
of program audit results, changing circumstances and the commitment to
continual improvement. Observations, conclusions and recommendations of
management review should be documented.
11.3 Safety Information.—Comprehensive safety and
environmental information for the facility, which includes documentation on
process, mechanical and facility design, should be developed and maintained
throughout the life of the facility.
11.4 Process Hazard
Analysis.—The
purpose of Process Hazard Analysis (PHA) is to minimise the likelihood of the
occurrence and the consequences of a dangerous substance release by
identifying, evaluating and controlling the events that could lead to the
release. Process hazards analysis should be performed for any facility to
identify, evaluate, and reduce the likelihood or minimize the consequences of
uncontrolled releases and other safety or environmental incidents and human
factors should also be considered in this analysis. The process hazard analysis
should be updated and revalidated by a team, having requisite back ground, at
least every 5 years after the completion of initial process hazard analysis.
Recommendations resulting from the PHA should be completed before start-up for a
new process or facility, or modification in existing facility.
11.5 Operating Procedures.—Written down operating
procedures shall be available describing tasks to be performed, data to be
recorded, operating conditions to be maintained, samples to be collected and
safety and health precautions to be taken for safe operation. Operating
procedures should be based on process safety information so that all known
hazards are taken care of. The human factors associated with format, content,
and intended use should be considered to minimize the likelihood of procedural
error.
11.6 Safe Work Practices.—The entity shall maintain
procedures that address safe work practices to ensure the safe conduct of
operating, maintenance, and emergency response activities and the control of
materials that impact safety and such safe work practices may apply to multiple
locations and will normally be in written form (safety manual, safety
standards, work rules, and like other written forms) but site-specific work
practices shall be prepared and followed. In cases where an employee believes
that following a procedure will cause an unsafe condition, he shall have
authority to stop work and get permission from appropriate level to deviate and
deviations should be documented for future analysis.
11.7 Training.—The training program
shall establish and implement programs so that all personnel including
contractors are trained to work safely and are aware of environmental
considerations, in accordance with their duties and responsibilities. Training
shall address the operating procedures, the safe work practices, and the
emergency response and control measures and any change in facilities that
requires new or modification of existing operating procedures may require
training for the safe implementation of such procedures and the training should
be provided by qualified instructors and documented.
11.8 Management of Change
(MOC).—There
should be procedures to identify and control hazards associated with change and
to maintain the accuracy of safety information and for each MOC, the operator
shall identify the potential risks associated with the change and any required
approvals prior to the introduction of such changes. The types of changes that
a MOC procedure addresses shall include—
(i) technical;
(ii) physical;
(iii) procedural; and
(iv) organizational,
and such procedure shall
consider permanent or temporary changes and the process shall incorporate
planning for the effects of the change for each situations relating thereto and
the procedures should cover the following, namely:—
(i) The process and mechanical
design basis for the proposed change;
(ii) An analysis of the safety,
health, and environmental considerations involved in the proposed change,
including, as appropriate, a hazards analysis;
(iii) The necessary revisions of
the operating procedures, safe work practices, and training program;
(iv) Communication of the
proposed change and the consequences of that change to appropriate personnel
and the necessary revisions of the safety and environmental information;
(v) The duration of the change,
if temporary; and.
(vi) Required authorizations to
effect the change.
11.9 Contractors.—When selecting
contractors, operators should obtain and evaluate information regarding a
contractor's safety and environmental management policies and practices, and
performance there under, and the contractor's procedures for selecting
subcontractors. The entities shall communicate their safety and environmental
management system expectations to contractors and identify any specific safety
or environmental management requirements which they have for contractors.
Interfacing of SMS of various entities (operator, contractor or service
provider, subcontractor and third-party) should be ensured through a well
written bridging document. Entity shall document the clear roles and
responsibilities with its contractors.
11.10 Assurance of quality
and mechanical integrity of critical equipment.—Procedures should be in
place and be implemented so that critical equipment for any facility is
designed, fabricated, installed, tested, inspected, monitored, and maintained
in a manner consistent with appropriate service requirements, manufacturer's
recommendations, or industry standards. Entity shall maintain inspection and
testing procedures for safety-related equipment. Human factors should be
considered, particularly regarding equipment accessibility for operation,
maintenance and testing.
11.11 Pre-startup Safety
Review.—Before
a new or modified unit is started, a systematic check should be made to ensure
that the construction and equipment are in accordance with specifications;
operating procedures have been reviewed; hazards analysis recommendations have
been considered, addressed and implemented; and personnel have been trained. It
should be ensured that programs to address management of change are in place.
11.12 Permit to Work (PTW)
System.—PTW
system is a formal written system used to control certain types of work which
are identified as potentially hazardous. Essential features of permit-to-work
systems are as specified below, namely:—
(i) Clear identification of who
may authorize particular jobs (and any limits to their authority) and who is
responsible for specifying the necessary precautions;
(ii) Training and instruction in
the issue, use and closure of permits;
(iii) Monitoring and auditing to
ensure that the system works as intended;
(iv) Clear identification of the
types of work considered hazardous; and
(v) Clear and standardized
identification of tasks, risk assessments, permitted task duration and
supplemental or simultaneous activity and control measures.
11.13 Emergency Planning
and Response.—A
comprehensive Emergency Response and Disaster Management Plan (ERDMP) shall be
developed in accordance with the Petroleum and Natural Gas Regulatory Board
(Codes of Practices for Emergency Response and Disaster Management Plan
(ERDMP)) Regulations, 2010. The copies of the ERDMP shall be maintained at each
petroleum installation. The emergency response planning shall have clear
written procedures for expected actions during anticipated emergencies and
emergency response plan shall include operational and procedural requirements
for various emergency scenarios that are relevant for the installation and the
emergency procedures shall contain inter alia as specified below, namely:—
(i) The emergency procedures
shall include, at a minimum, emergencies that are anticipated from an operating
malfunction of any component of the petroleum storage, handling and
transportation facilities, personnel error, forces of nature, and activities
carried on adjacent to the facilities;
(ii) The emergency procedures
shall include but not be limited to procedures for responding to controllable
emergencies, including the following, namely:—
(a) The notifying of personnel;
(b) The use of equipment that
is appropriate for handling of the emergency;
(c) The shutdown or isolation
of various portions of the equipment; and
(d) Other steps to ensure that
the escape of gas or liquid is promptly cut off or reduced as much as possible;
(iii) The emergency procedures
shall include procedures for recognizing an uncontrollable emergency and for
taking action to achieve the following, namely:—
(a) Minimize harm to the
personnel at the petroleum storage, handling and loading or unloading
facilities and to the public;
(b) Provide prompt notification
of the emergency to the appropriate local officials, including the possible
need to evacuate persons from the vicinity of petroleum installation;
(c) The emergency procedures
shall include procedures for coordinating with local officials in the
preparation of an emergency evacuation plan that sets forth the steps necessary
to protect the public in the event of an emergency, including the following, namely:—
(i) Quantity and location of
fire equipment throughout the petroleum installation;
(ii) Potential hazards at the
petroleum installation; and
(iii) Communication and
emergency-control capabilities at the petroleum installation.
11.14 Incident
Investigation and Analysis.—Procedures for investigation of all incidents as per the
Petroleum and Natural Gas Regulatory Board (Codes of Practices for Emergency
Response and Disaster Management Plan (ERDMP)) Regulations, 2010 shall be developed.
Incident investigations should be initiated as promptly as possible,
considering the necessity of securing the incident scene and protecting people
and the environment. The intent of the investigation should be to learn from
the incident and help to prevent similar incidents. A corrective action program
should be established based on the findings of the investigation to prevent
recurrence.
11.15 Compliance Audit.—Safety Audits are the
periodic examination of the functioning of safety system and it gives an idea
about how effectively the safety system is implemented and how they are being
accomplished and it is the feedback mechanism that provides management with the
status and measurement of effectiveness of the various safety system elements
and activities and leads to the appropriate control over such efforts. The
audit program and procedure should cover the following, namely:—
(i) The activities and areas to
be considered in audits;
(ii) The frequency of audits
(a) Internal Audit : Every year
(including those years in which External Audit is undertaken);
(b) External Audit : Once in
three year;
(iii) The audit team;
(iv) How audits will be
conducted; and
(v) Audit Reporting;
and the findings and
conclusions of the audit should be provided to the management and the
management should establish a system to determine and document the appropriate
response to the findings and to assure satisfactory resolution. The audit
report should be retained at least until the completion of the next audit.
11.15.1 Internal and
External Safety Audits.—Audit conducted by Internal Audit teams of the organization
shall be categorized as Internal Safety Audit. Internal Safety Audits shall be
coordinated by local management under the overall direction from the respective
Corporate Offices. External Safety Audits shall be carried out through PNGRB
empanelled third party agency or multidisciplinary team constituted by PNGRB.
Annexure 1 — List of Applicable Standards and References
|
Standard Number
|
Title of Standard
|
|
API STD 650
|
Welded Tanks for Oil Storage.
|
|
API STD 620
|
Design and Construction of Large, Welded,
Low-pressure Storage Tanks.
|
|
API STD 2000
|
Venting Atmospheric and Low-Pressure Storage
Tanks.
|
|
API 5L
|
Specification for Line Pipe.
|
|
API 15LR
|
Low Pressure Fiberglass Line Pipe.
|
|
API 15HR
|
High-pressure Fiberglass Line Pipe.
|
|
NFPA 2001
|
Standard on Clean Agent Fire Extinguishing
Systems.
|
|
NFPA 11
|
Standard for Low-, Medium-, and High-Expansion
Foam.
|
|
ASME B 31.3
|
Process Piping Guide.
|
|
ASME B 31.4
|
Pipeline Transportation Systems for Liquid Hydrocarbons
and Other Liquids.
|
|
ASME B 16.5
|
Pipe Flanges and Flanged Fittings : NPS 1/2
through NPS 24 Metric or Inch Standard.
|
|
ASME B 16.11
|
Forged Fittings, Socket — Welding and Threaded.
|
|
IS 12709
|
Installation of Glass Fibre Reinforced Plastic
(GRP) Piping System Code of Practice.
|
|
IS 5572
|
Classification of Hazardous Areas (Other Than
Mines) Having Flammable Gases and Vapours for Electrical Installation.
|
|
IS 11006
|
Flash Back Arrestor (Flame Arrestor).
|
|
IS 5571
|
Guide for Selection and installation of Electrical
Equipment for Hazardous Areas (other than mines).
|
|
IS 10810
|
Methods of Test for Cables.
|
|
IS 3043
|
Code of practice for earthing.
|
|
IS 2309
|
Code of practice for the protection of buildings
and allied structures against lightning.
|
|
IS 3844
|
Code of Practice for Installation and Maintenance
of Internal Fire Hydrants and Hose Reels on Premises.
|
|
IS 636
|
Non-percolating flexible delivery hose for fire
fighting.
|
|
IS 1978
|
Specification for Line Pipe.
|
|
IS 15683
|
Portable Fire Extinguishers-Performance and Construction—Specification.
|
|
IS 4991
|
Criteria for Blast Resistant Design of Structures
for Explosions Above Ground.
|
|
IS 10658
|
Specification for Higher Capacity Dry Powder Fire
Extinguisher.
|