Petroleum and Natural Gas Regulatory Board
(Technical Standards and Specifications including Safety Standards for
Petroleum and Petroleum Products Pipelines) Regulations, 2016
[12th
February, 2016]
In exercise of the powers
conferred by section 61 of the Petroleum and Natural Gas Regulatory Act, 2006
(19 of 2006), the Petroleum and Natural Gas Regulatory Board hereby makes the
following regulations, namely:—
Regulation - 1. Short title and commencement.
(1) These regulations may be
called the Petroleum and Natural Gas Regulatory Board (Technical Standards
and Specifications including Safety Standards for Petroleum and Petroleum
Products Pipelines) Regulations, 2016.
(2) They shall come into force
on the date of their publication in the Official Gazette.
Regulation - 2. Definitions.
(1) In these regulations,
unless the context otherwise requires,-
(a) “Act” means the Petroleum
and Natural Gas Regulatory Board Act, 2006;
(b) “ASME B 31.4” means
standard covering Pipeline Transportation Systems for Liquid Hydrocarbons and
Other Liquids referred to in Annexure IV;
(c) “Board” means the Petroleum
and Natural Gas Regulatory Board established under sub-section (1) of section 3
of the Act;
(d) “pumping station” means an
installation on the pipeline having pumping units to boost petroleum and
petroleum products pressure;
(e) “intermediate pigging
station” means an installation having facility for receiving and launching of
pigs for pigging operations;
(f) “onshore” means areas other
than offshore which shall form the scope of these regulations. Feeder lines
from/to jetty or other storage points shall also form a part of the onshore
pipelines;
(g) “operating company or
operator” means an entity engaged in the operation of petroleum and petroleum
products pipeline network;
(h) “petroleum” means any
liquid hydrocarbon or mixture of hydrocarbons, and any inflammable mixture
(liquid, viscous or solid) containing any liquid hydrocarbon, including crude
oil and liquefied petroleum gas, and the expression ‘petroleum product’ shall
mean any product manufactured from petroleum;
(i) “petroleum and petroleum
products pipeline” means any pipeline including branch or spur lines for
transport of petroleum and petroleum products and includes all connected
infrastructure such as pumps, metering units, storage facilities at
originating, delivery, tap off points or terminal stations including line
balancing tanks and tankage required for unabsorbed interface essential for
operating a pipeline system;
(j) “right of use or right of
way” means the area or portion of land within which the pipeline operator or
entity has acquired the right through the Petroleum and Minerals Pipelines
(Acquisition of Right of User in land) Act, 1962 or in accordance with the
agreement with the land owner or agency having jurisdiction over the land to
lay, operate and maintain the petroleum and petroleum products pipelines.
(2) Words and expressions used
and not defined in these regulations, but defined in the Act or in the rules or
regulations made thereunder, shall have the meanings respectively assigned to
them in the Act or in the rules or regulations, as the case may be.
Regulation - 3. Application.
(1) These regulations shall
apply to all the entities authorized by the Board to lay, build, operate or
expand petroleum and petroleum products pipelines under the Petroleum and
Natural Gas Regulatory Board (Authorizing Entities to Lay, Build, Operate or
Expand Petroleum and Petroleum Products Pipelines) Regulations, 2010 and any
other petroleum and petroleum products pipelines including dedicated pipelines.
(2) Definitions of design,
material and equipment, piping system components and fabrication, installation
and testing, commissioning, corrosion control, operation and maintenance and
safety of petroleum and petroleum products pipelines network shall be in
accordance with the requirements of ASME B31.4 except in so far as such
requirements are specifically cancelled, replaced or modified by the
requirements specified in these regulations.
Regulation - 4. Scope.
(1) Requirements of these
regulations shall apply to all existing and new petroleum and petroleum
products pipelines.
(2) These regulations shall
cover pipeline design, materials and equipment, piping system components and fabrication,
installation, testing, corrosion control, operation and maintenance and safety
of petroleum and petroleum products pipelines. The pipelines include dedicated
pipelines for specific consumers but excludes offshore crude pipelines, onshore
well flow, feeder and collector pipelines.
Regulation - 5. Objective.
These standards are
intended to ensure uniform application of design principles and to guide in
selection and application of materials and components, equipment and systems
and uniform operation and maintenance of the petroleum and petroleum products
pipelines system and shall primarily focus on safety aspects of the employees,
public and facilities associated with petroleum and petroleum products
pipelines.
Regulation - 6. The standard.
Technical Standards and
Specifications including Safety Standards (hereinafter referred to as Standard)
for petroleum and petroleum products pipelines are at Schedule I which cover
Design (Schedule 1A), Material and Equipment (Schedule 1B), Piping System Components
and Fabrication Details (Schedule 1C), Installation and Testing (Schedule 1D),
Corrosion Control (Schedule 1E), Operation and Maintenance (Schedule 1F),
Safety (Schedule 1G), Miscellaneous (Schedule 1H) as read with Annexure I to
Annexure IV.
Regulation - 7. Compliance to these regulations.
(1) The Board shall monitor the
compliance to these regulations either directly or through an accredited third
party as per separate regulations on third party conformity assessment.
(2) If an entity has laid,
built, constructed or expanded the petroleum and petroleum products pipelines
network based on some other standard or is not meeting the requirements
specified in these regulations, the entity shall carry out a detailed
Quantitative Risk Analysis (QRA) of its infrastructure. The entity shall
thereafter take approval from its Board or highest decision making body for
non-conformities and mitigation measures. Approval of the Board or highest
decision making body of entity along with the compliance report, mitigation
measures and implementation schedule shall be submitted to the Board within six
months from the date of notification of these regulations.
(3) The continuation of
operation of existing petroleum and petroleum products pipelines network shall
be allowed only if it meets the following requirements, namely:—
(i) The petroleum and petroleum
products pipelines system shall have been tested initially at the time of
commissioning in accordance with ASME B 31.4. The entity shall have proper
records of the same. Such test record shall have been valid for the current
operation. Alternatively, if such a record is not available, the entity shall
produce in service test record of the petroleum and petroleum products
pipelines network having been tested as per ASME B 31.4 or carry out
intelligent pigging survey along with fitness for purpose report:
Provided that—
(a) the entity shall submit
self-certification in support of meeting the above requirements within a month
but not later than three months of notification of these regulations;
(b) certifications referred to
in para (a) shall be done for petroleum and petroleum products pipelines in
construction and commissioning, operation and maintenance. The self
certification shall be submitted to the Board with mitigation plan and implementation
schedule;
(c) the critical components of
the system as identified by the Board for such existing networks shall be
complied with these regulations within a period specified at Appendix from the
date of coming into force of these regulations and the authorized entity shall
maintain the integrity of the existing petroleum and petroleum products
pipelines system at all times in accordance with separate regulations on
Integrity Management System; and
(d) provisions of these
regulations related to operation and maintenance procedures shall also be
applicable to all such existing installations.
Regulation - 8. Default and consequences.
(1) The entity shall provide a
system for ensuring compliance to the provision of these regulations through
conduct of technical and safety audits during the construction, commissioning
and operation phase.
(2) In the event of any default
in sub-regulation (1), the entity shall qualify as defaulting entity under the
regulation 16 of the Petroleum and Natural Gas Regulatory Board (Authorizing
Entities to Lay, Build, Operate or Expand Petroleum and Petroleum Products
Pipelines) Regulations, 2010.
(3) In case of any deviation or
shortfall including any of the following defaults, the entity shall be given
time limit for rectification of such deviation, shortfall, default and in case
of non-compliance, the entity shall be liable for any penal action under the
provisions of the Act or termination of operation or termination of
authorization, namely:—
(a) if an entity fails to
comply within the specified time limit of critical activities at Appendix;
(b) the entity defaults three
times under regulation 16 of the Petroleum and Natural Gas Regulatory Board
(Authorizing Entities to Lay, Build, Operate or Expand Petroleum and Petroleum
Products Pipelines), Regulations, 2010;
(c) the entity is found
operating the pipelines beyond the maximum allowable operating pressure (MAOP)
conditions (either the original or de-rated pressure);
(d) the entity is found
operating the pipeline system without conducting the hydro test as mentioned in
these regulations; and
(e) in the event the
installation is found unsafe to be operated as per the third party periodic
inspection assessment and compliance is not achieved within the notice period
by the Board.
Regulation - 9. Requirements under other statutes.
It shall be necessary to
comply with all statutory rules, regulations and Acts in force as applicable
and requisite approvals shall be obtained from the relevant competent
authorities for the petroleum and petroleum products pipelines system.
Regulation - 10. Miscellaneous.
(1) If any question arises as
to the interpretation of these regulations, the same shall be decided by the
Board.
(2) The Board may issue
guidelines consistent with the Act to meet the objective of these regulations
as deemed fit.
SCHEDULE 1
Technical
Standards and Specifications including Safety Standards
for
Petroleum and Petroleum Products Pipelines
Schedule-1A |
DESIGN |
Schedule-1B |
MATERIAL AND EQUIPMENT |
Schedule-1C |
PIPING SYSTEM COMPONENTS AND
FABRICATION DETAILS |
Schedule-1D |
INSTALLATION AND TESTING |
Schedule-1E |
CORROSION CONTROL |
Schedule-1F |
OPERATION AND MAINTENANCE |
Schedule-1G |
SAFETY AND FIRE PROTECTION |
Schedule-1H |
MISCELLANEOUS |
SCHEDULE 1A
DESIGN
1.1 General Provisions
1.1.1 The pipelines shall
be designed in a manner that ensures adequate public safety under all
conditions likely to be encountered during installation, testing, commissioning
and operating conditions. All materials and equipments shall be selected to ensure
safety and suitability for the condition of use.
1.1.2 The selection of
design for liquid hydrocarbon pipelines shall be based on the fluid properties,
service, required throughput, operating and environmental conditions.
1.1.3 All components of the
pipeline system shall be designed to be suitable and fit for the purpose
throughout the design life.
1.1.4 Cross country
pipeline of size less than NPS 4 inch shall not be used.
1.2 Other Design
Requirements
All necessary calculations
shall be carried out to verify structural integrity and stability of the
pipeline for the combined effect of pressure, temperature, bending, soil or
pipe interaction, external loads and other environmental parameters as
applicable, during all phases of work from installation to operation. Such
calculations shall include but not limited to the following:
(i) Buoyancy control and
stability analysis for pipeline section to be installed in areas subjected to
flooding or submergence.
(ii) Crossing analysis of rivers
by trenchless techniques, wherever sub-strata is favorable for such methods of
construction.
(iii) Evaluation of potential for
earthquake occurrence along pipeline route and carrying out requisite seismic
analysis to ensure safety and integrity of the pipeline system.
1.3 Design Temperature
1.3.1 Appropriate
temperature range for design of pipeline or piping system shall be determined
based on temperature of liquid hydrocarbon proposed to be transported through
the pipeline, ambient or sub-soil temperature.
1.3.2 Maximum temperature
for design of above ground section of pipeline or piping shall be the maximum
expected liquid temperature during operation or maximum ambient temperature
whichever is higher. In no case maximum temperature for carbon steel pipelines
shall be more than (+) 120 Deg C.
1.3.3 Maximum temperature
for design of buried section of pipeline or piping shall be maximum expected
liquid hydrocarbon temperature during operation or maximum sub-soil temperature
whichever is higher.
1.3.4 Minimum temperature
for design shall be minimum expected liquid hydrocarbon temperature during
operation or minimum ambient or sub-soil temperature whichever is lower. In no
case minimum temperature for carbon steel pipelines shall be less than (-) 29
Deg C.
1.3.5 When maximum liquid
hydrocarbon temperature during operation is below 65 Deg C, thermal expansion
and stresses in the above ground section of pipeline or piping shall be
evaluated considering pipe skin temperature of 65 Deg C.
1.4 Steel Pipe
1.4.1 Straight Pipe Wall
Thickness
The minimum nominal wall
thickness for steel pipe shall be as per ASME B31.4.
Wall thickness ‘t’ for
straight steel pipe under internal pressure shall be calculated by the
following equation:
Where,
D= outside diameter of pipe
Pi= Internal
Pressure
S= F×E× Specified minimum
yield strength of pipe.
Where,
F = Design factor
E=1 for Seamless, Electric
Welded (HFW) and Submerged Arc Welded (SAW) pipe
1.4.2 Additional
Requirement for Nominal Wall Thickness
Consideration shall also be
given to any additional loading while selecting Nominal Wall Thickness as per
ASME B 31.4.
1.4.3 Design Factors (F)
Design factors to be used
in design formula shall be as per Table 1 given below.
Table 1: Design
Factor (F) for Steel Pipe
Facility |
Design Factor (F) |
A. Pipelines, mains, and service lines |
0.72 |
B. Crossings of roads, railroads without casing: |
|
a) Private Roads, Unimproved Public Roads |
0.72 |
b) Roads, highways, public streets, with hard
surface |
0.72 (Note -1) |
c) Railroads |
0.60 |
C. Crossings of roads, railroads with casing |
0.72 |
D. Parallel Encroachment of Pipeline on Roads and
Railways: |
|
a) Private roads, Unimproved Public Roads |
0.72 |
b) Roads, highways, public streets, with hard
surface |
0.72 (Note -1) |
c) Railroads |
0.60 |
E. Pipelines on bridges |
0.50 |
F. River Crossings |
0.72 (Note -1) |
G. Dispatch terminal, intermediate pumping and
pigging station, receipt or terminal piping and other stations piping |
0.72 |
Notes:
(1) Higher thickness may be
used if required to reduce stresses or for providing stability during
installation and/or service.
1.4.3.1 The selected wall
thickness shall also be checked to ensure that the diameter to thickness (D/t)
ratio does not exceed 100 in order to avoid damage to pipe during handling and
transportation.
1.4.3.2 Other loadings
shall be considered and provided for in accordance with sound engineering
practices, such as:
(i) Loadings caused by scour,
erosion, soil movement and landslides, installation forces, wind loading,
earthquake loading etc.
(ii) Weight of water during
hydrostatic testing and weight of product during operation shall also be
considered.
(iii) Consideration shall be
given to the use of lower allowable design stress if there is likelihood of
repeated stress changes giving rise to fatigue conditions.
1.4.4 Pre-operational Stresses
Consideration shall be
given to but not restricted to the effect of the following pre-operational
loads:
(i) Transportation and
stockpiling of the pipe
(ii) Stringing, coating and
wrapping and laying
(iii) Backfilling
(iv) Loads imparted by
construction traffic
(v) Field bending
(vi) Pulling load during
horizontal direction drilling
(vii) Frictional load during
jacking and boring
(viii) Hydrostatic test pressure
loads (particularly when the pipeline is constructed as an above ground
installation or is buried in unstable soils)
1.4.5 Surge Analysis
1.4.5.1 A detailed surge
analysis shall be carried out during design stage considering the following
condition:
(i) Closure of sectionalizing
motor operated valve (MOV) or ROV or Actuator valves on the mainline
(ii) Closure of inlet MOV or ROV
or Actuator valves of the storage tanks during receipt
(iii) Closure of any MOV or ROV
or Actuator valves in the delivery pipeline
(iv) Stoppage of pump(s) at
originating or intermediate pump station
(v) Closure of valves during
emergency shut down
(vi) Combination of the above
(vii) Any other condition which
can generate surge pressure
1.4.5.2 In order to protect
the pipeline against surge pressure, surge relief valve or equivalent measures
such as suitable interlocks to trip the mainline pump through SCADA or station
control system shall be provided. The required capacity needed to be relieved
through surge relief valve shall be determined by carrying out the surge
analysis for above different scenarios under which a surge may occur in the
pipeline. The set pressure of surge relief valve shall be such that in any case
the overpressure in the pipeline or connected piping system does not exceed the
internal design pressure by more than 10%.
1.4.6 Anti-buoyancy Measure
Pipeline crossing water
bodies, marshy areas, swamps and areas with high water table, etc. shall be
checked for buoyancy and if required suitable anti-buoyancy measures such as
continuous concrete weight coating or concrete block, gravel filled geotextile
bags, anchors, increased pipeline cover, select backfill, etc. shall be
provided. The specific gravity of the same under empty or installation
conditions shall be minimum 1.1.
1.4.7 Corrosion
All underground pipes and
its components shall be protected against corrosion using suitable external
anti-corrosion coating or painting and cathodic protection system. All above
ground piping and its components shall be protected against corrosion by
providing suitable anti-corrosion painting or coating.
1.5 Location And Layout of
Pipeline Installations
1.5.1 Location
1.5.1.1 Originating,
intermediate and terminal facilities of cross country pipeline such as
Originating Pump Station or Originating Station, Intermediate pump or pigging
Station, Tap-off Station and Sectionalizing Valve Stations etc. shall be
located considering following aspects:
(i) Functional and pipeline
hydraulic requirements.
(ii) Environmental consideration
based on Environmental Impact Assessment (EIA) and Risk Analysis (RA) study for
the pipeline and stations.
(iii) The Hazard and Operability
(HAZOP) study and Hazard Analysis (HAZAN).
(iv) The availability of space
for future augmentation of facilities.
(v) Approachability, water
table and flood level and natural drainage.
(vi) Availability of electric
power and water.
(vii) Habitation.
1.5.1.2 In addition to
above, pipeline installations should be located so as to minimize the hazard of
communication of fire to the pump station from structures on adjacent property.
1.5.2 Layout
1.5.2.1 The following
aspects shall be considered while establishing station layout
(i) Station equipments and
their specifications including sump tanks(s), surge tanks etc.
(ii) P&I diagram for the
station.
(iii) Utility requirement
including other storage tanks like High Speed Diesel (HSD) for power generation
etc.
(iv) Storm water drainage
system.
(v) Operation & maintenance
philosophy of station equipments.
(vi) Fire station and allied
facility wherever required.
(vii) Proximity to over head
power lines. Overhead power lines should not be allowed directly above station
equipment or buildings.
(viii) High Tension (HT) Pole
structure, Transformers, Breaker and Master Control Centre (MCC) room etc. to
be located maintaining minimum inter distance requirement as per Annexure I.
(ix) Requirement of space and
access around the pump (including engine or motor) house or shed or building
and other equipments to permit the free movement of firefighting equipment,
emergency evacuation.
(x) Blow down facilities or
buried drum should be located at one corner of the plant farthest from any
fired Equipment and on the downward side of the station.
(xi) For LPG pipeline
facilities, Pipeline installation shall be located upwind of LPG bulk storage
facilities.
1.5.2.2 Minimum
Inter-distances between various station facilities and utilities shall be as
per Annexure I.
1.5.3 Piping Layout
1.5.3.1 Station piping may
be installed above ground or buried. Buried piping inside the terminal area
shall have a minimum cover of 1 m from top of pipe to finished ground or grade
level.
1.5.3.2 At internal storm
water drains underground piping shall be provided with a minimum cover of 300
mm with additional concrete slab extending at least 500 mm on either side of
the edge of the drain and pipe.
1.5.3.3 Where buried pipes
come above ground, the anti-corrosion coating on the buried pipe will continue
for a length of at least 300 mm above ground.
1.5.3.4 Minimum head room
should be kept as 2.2 m.
1.5.3.5 Piping Layout
should be designed for reducing the piping loads on the nozzles of critical
equipments.
1.5.3.6 Platforms and
crossovers with appropriate handrails shall be provided for accessibility, ease
of operation and maintenance of above ground piping and equipment where
required.
1.5.3.7 All the above
ground piping should be properly supported to withstand operational safety
requirements.
1.6 Protection of
Facilities
1.6.1 Properly laid out
roads around various facilities shall be provided within the installation area
for smooth access of fire tenders etc in case of emergency.
1.6.2 “Proper industry type
boundary masonry wall at least three (3) meters high with an additional 0.6
meters barbed wire or concertina coil on the top shall be provided all around
the installation i.e. pump station, booster station, Delivery, Dispatch and
Receiving Terminals with petroleum storage and other installations identified
as vital under Category-A based on the Risk Assessment carried out from time to
time in line with Ministry of Home Affairs (MHA) guidelines and
recommendations.
1.6.3 For other
installations like Intermediate Pigging (IP) stations, Sectionalizing Valve
(SV) stations etc. identified as vital under Category B and C, either proper
industry type boundary masonry wall or chain link fencing at least three (3)
meters high including 0.6 meters barbed wire or concertina coil on top may be
provided. However, Category B and C installations having chain Link Fencing
shall be required to carry out Risk Assessment at least once every year for
review of categorization of installation in line with MHA guidelines or
recommendations. The fencing shall be suitably earthed distinctly at minimum
two places and locked or attended for the protection of the property and the
public.
1.6.4 Emergency exit (to a
safe place) with proper gate(s) shall be provided at all installations such as
pump station, intermediate pump stations, pump stations with tank farm, delivery
or terminal stations. Emergency exit gate shall be away from main gate and
always be available for use of personnel evacuation during emergency.
1.6.5 At critical locations
like tank farm area, pump house, manifold or metering area, intermediate pigging
station etc., Close Circuit Television (CCTV) camera and/or intrusion alarm
system having SCADA facility may be provided. Cross country pipeline system
shall be equipped with following:
(i) Supervisory Control and
Data Acquisition (SCADA) System for pipeline length of 50 km and above or line
fill of 5000 kl and above except jetty pipelines.
(ii) Leak detection system with
provision for identification or location of leak and isolation of affected
section from remote operation for pipeline length of 50 km and above or line
fill of 5000 kl and above.
(iii) Communication facilities.
(iv) Emergency Response and
Disaster Management Plans (ERDMP).
1.7 SCADA Requirements
1.7.1 Pipeline system shall
be monitored and controlled using Supervisory control and Data Acquisition (SCADA)
or equivalent monitoring and control system to ensure effective and reliable
control, management and supervision of the pipeline.
1.7.2 Originating Pump
Stations, Intermediate Pump Station, Intermediate Pigging Stations,
Intermediate Delivery Station and Receiving or terminal Stations,
Sectionalizing Valve stations with remote operation capabilities as well as
Telecom Repeater Stations including voice communication facilities or Cathodic
Protection Stations (in case located independent of other facilities) should
have suitable field signals' connectivity with the control system.
1.7.3 Application software
modules or functions shall be based on the requirement of pipeline operating
company to enable as a minimum to detect the leak in the pipeline and also
enhance safety of the pipeline and personnel.
1.7.4 It is also
recommended that in the Application Software (APPS) modules or functions, the
following may be provided:
(i) Leak Detection and leak
location
(ii) Inventory Analysis.
(iii) Batch Tracking
(iv) Survival Time Analysis.
(v) Pipeline transportation
efficiency and scrapper tracking module.
(vi) Contingency Analysis.
(vii) Planning Module.
(viii) Predictive Module.
(ix) Pump driver power
Optimization.
(x) On line network simulation.
(xi) Flow management system.
1.7.5 The SCADA system
should be adequate (without adding any hardware to the system at Master Station
and remote workstations) to accommodate future expansion (w.r.t. additional
Programmable Logic Controllers (PLCs) and consequent pipeline length and
facilities, communication channels, additional remote workstations or stations
etc.) without any limitations and without affecting the various system
performance parameters.
1.7.6 The Communication
protocol with Remote Terminal Units (RTU) should conform to IEC 870 -5-101 or
DNP3 or MODBUS or TCP or IP or any other available protocol.
1.7.7 Master Station (MS)
should have the complete SCADA database and integrated alarm and event summary
for overall operations management and control of the entire pipeline network.
1.7.8 Control Station (CS)
or RCP (Repeater cum Cathodic Protection) location should not be located in low
lying areas prone to flooding. It should be preferably located in higher
elevations.
1.8 Pipeline System and
Component
1.8.1 Process Piping
All process piping at
station shall comply with the requirement of ASME B 31.4.
1.8.2 Valves
Valves shall be provided
for isolating sections of station piping in order to:
(a) Limit the hazard and damage
from accidental discharge from piping.
(b) Facilitate repair and
maintenance of piping facilities and critical equipments.
For LPG Pipeline
facilities, API SPEC 6D valves suitable for LPG services shall be provided. All
valves shall be fire safe conforming to API 607/6FA.
1.8.2.1 Station Block Valves
Block valves with remote
shut off provision from the control room shall be provided at the inlet
(downstream of Tee) and outlet (up stream of Tee) of the pump or intermediate
pigging or terminal or delivery station piping to isolate the pipeline from station
facilities in case of emergency at station. In addition, Block valves shall be
considered as under:
(a) At entry and exit of
pipeline stations boundary
(b) On each lateral takeoff
from a trunk line
1.8.2.2 Station By-pass
Station by-pass system
shall be provided to facilitate flow of liquid hydrocarbon in the pipeline
bypassing the pumping facilities inside the station premises.
1.8.2.3 Check Valves
Check Valves shall be
installed to provide automatic blockage of reverse flow in the piping system,
within the station, wherever required. Check valves, when provided to minimize
pipeline backflow at locations appropriate for the terrain features (e.g hills,
steep slopes, etc.), shall be suitable for passage of all types of pigs
including instrumented pigs.
1.8.2.4 Flow or Pressure
Control Valve
Design of control valves in
stations shall meet the requirement of part I of API 550 or API-RP-553, ISA
(Instrument Society of America) S- 75.01 -75.03, IEC -60079 and IEC-60529.
1.8.2.5 Thermal Safety
Valve for LPG Installations
Piping that can be isolated
and need thermal safety valves shall have minimum design pressure of 24 kg/cm2
or maximum pressure which could be developed by transfer equipment or any other
source etc. whichever is higher and conform to the provision of ASME B 31.4 or
equivalent.
1.8.2.6 Mainline or
Sectionalizing Valves
(i) Sectionalizing valves shall
be installed where required for operation and maintenance and control of
emergencies. Factors such as topography of the location, ease of operation and
maintenance including requirements for section line fill shall be taken into
consideration in deciding the location of the valves. However, in any case the
distance between two consecutive sectionalizing valves shall not be more than
50 km.
(ii) For LPG pipeline
facilities, mainline sectionalizing or block valves shall be installed at
maximum spacing of 12 km in industrial, commercial and residential areas.
(iii) For LPG installations,
Remotely Operated Sectionalizing or Mainline block valve(s) shall be provided
with blow down connection to isolate and evacuate the pipeline section in case
of emergency and repair. All blow down piping shall have double valve
segregation.
(iv) Mainline block valves shall
be installed on both sides of the major river crossings and public water supply
reservoirs. The valves shall be as close as possible near the upstream and
downstream bank of the river and public water supply reservoirs for isolation
of these portions of the pipeline and these valves must be remote operated.
(v) The valve stations shall be
located at a readily accessible location such as near roads and shall be
provided with an access road from the nearest all weather metalled road.
Overhead power lines shall not cross directly over the process area of the
valve station facilities.
(vi) The provisions of remote
operated feature should be as per the operation and control philosophy to be
adopted for the pipeline by the entity or operating company. For LPG
installations, Sectionalizing or Block valves with remote shut off provision
from the control room shall be provided at the boundary of station pipeline
inlet and outlet locations to isolate the station facility. At locations where
valve stations are combined with pump or repeater stations, the requirements of
safe distance and statutory clearance, as applicable, shall be followed.
(vii) Valve shall be installed
buried and provided with suitable stem extension for ease of operation.
Sectionalizing valve on the piggable section of pipeline shall be full bore
type to allow safe passage of pigs. The valve shall meet as minimum
requirements of API SPEC 6D or ISO-14313 - “Specification for pipeline valves”.
Isolation of earthing of actuator to be done to avoid interference in C.P.
(viii) Actuator for the actuated
valve may be selected based on type of valve, availability of power and project
philosophy. Pipeline sectionalizing valve may be electrically or pneumatically
or hydraulically operated. Valves used in mainline shall be with butt weld
ends. Valves used in buried portion shall be with butt weld joints only, except
at the locations where hot tapping operation is to be carried out for which,
buried flanged end valve may be provided.
(ix) Valve surface shall be
applied with suitable corrosion protection coating.
(x) All joints between the
mainline pipe and the first valve on the branch, including the inlet to first
valve, should be welded in order to restrict possible leakage which cannot be
isolated by the closure of the valve.
1.8.3 Pigging Facilities
1.8.3.1 All cross country
pipelines and feeder lines, spur lines and branch lines of 4” and above size
and length 10 km and above shall be provided with pigging facilities. However,
pigging facilities for pipeline from or to jetty or type of petroleum and
petroleum products handled may be provided on need basis.
1.8.3.2 Spacing between
consecutive pigging stations shall be determined based on the diameter of
pipeline, nature of pigging operation and capability of the pigs.
1.8.3.3 Pigging stations
shall be provided with access road from the nearest all weather road.
1.8.3.4 Pigging facilities
should be designed to be suitable for:
(i) access to the pig traps;
(ii) handling of pigs;
(iii) isolation requirements
necessary for pig launching and receiving;
(iv) draining of carried over
muck or condensate during pigging operation;
(v) direction of pigging
including bi-directional pigging;
(vi) minimum permissible bend
radius and the distances between bends or fittings;
(vii) variation in pipe diameter
and wall thickness;
(viii) internal coatings; and
(ix) Pig signalers.
1.8.3.5 The safety of
access routes and adjacent facilities shall be considered when determining the
orientation of pig traps.
1.8.3.6 Quick Opening End
Closure system shall be used for Trap in order to provide repeated access to
the interior of pigging system.
1.8.4 Bends
The minimum radius of Cold
Field Bend shall be as per Table 2.
Table 2: Minimum
Bend Radius
Nominal Pipe Size (inch) |
Minimum bend Radius |
12 and below |
18D |
14 |
21 D |
16 |
24 D |
18 |
27 D |
20 and above |
30 D |
Where ‘D’ is the outside diameter
of the steel pipe
1.8.4.1 Use of Miter bend
shall not be permitted.
1.8.4.2 The minimum bend
radius for hot bends shall be 3D.
1.8.5 Insulating Joints
1.8.5.1 Insulating joints
shall be provided to electrically isolate the buried pipeline from the above
ground pipeline, station piping and shall allow smooth passage of pigs.
1.8.5.2 Each insulating
joint shall be provided with surge diverters and shall have provision for
checking integrity of the insulating joint.
1.8.6 Branch Connection
1.8.6.1 Branch connections
of size below Nominal Pipe Size (NPS) 2 inch are not recommended in buried
pipeline section.
1.8.6.2 All branch
connections from mainline shall be provided with an isolation valve located at
a minimum possible distance from the main pipeline.
1.8.6.3 Where welded or
forged branch connections are installed in the pipelines designed for pigging,
special branch connection should be used to ensure that the pig is not damaged
while passing the connection.
1.8.6.4 All branch
connections or side tap on the piggable section of the pipeline having diameter
equal to or exceeding 40 percent of the main pipe diameter, shall be made using
flow tees or bar tees in order to enable smooth passage of all types of pigs.
1.8.7 Supports for Above
Ground Station Piping
1.8.7.1 If the liquid
hydrocarbon piping is required to operate below 20% of SMYS, supports or
anchors shall be directly welded to the pipe.
1.8.7.2 If a pipeline is
designed to operate at stress level of more than 20% of the specified minimum
yield strength of the pipe, all connections welded to the pipe shall be made to
a separate cylindrical member which completely encircles the pipe, and this
encircling member shall be welded to the pipe by continuous circumferential
welds at both ends.
1.8.8 Flanged or Threaded
Joints, Bolts, Nuts, Gasket and Other Fittings
1.8.8.1 Threaded joints
shall not be used in the underground section of cross country pipelines, spur
lines and branch lines. Threaded joints may be permitted in the above ground
stations or above ground section of SV stations only if a welded isolation
valve is provided before it. The number of threaded joints for station piping
shall be to the extent minimum. The threaded joints, after tightening, may be
seal welded.
1.8.8.2 The flange joint shall
be provided with either spiral wound metallic gaskets or metallic ring type
gaskets. Plain asbestos sheet or reinforced gaskets or Compressed Asbestos
Fiber (CAF) gaskets shall not be used. The number of flanged joints for station
piping for LPG shall be to the extent minimum.
1.8.8.3 For LPG
installation, flange connection ratings shall match with the design pressure of
the pipeline (on high pressure side) and in no case shall be less than 300
series rating (low pressure side) conforming to ANSI 16.5 or equivalent. All
tapping or opening shall be minimum 20 mm dia. The materials used shall conform
to ASME B 31.4 or equivalent.
1.8.9 Metering Facilities
Appropriate type of meters
or other equivalent measuring device with the desired accuracy shall be installed
at all pumping or terminal stations for leak detection or other purposes.
1.8.10 Electrical
Installations of Pipeline Station
1.8.10.1 Area
Classification of Pipeline Installation, as basis for Selection of Electrical
Equipment for liquid hydrocarbon Pipeline Station shall follow IS: 5572. The
specification of Electrical equipments shall be in line with IS: 5571, “Guide
for selection of Electrical Equipment for Hazardous Area”.
1.8.10.2 All electrical
equipment, systems, structures and fencing shall be suitably earthed in
accordance with IS: 3043.
1.8.10.3 The earthing
system shall have an earthing network grid with required number of electrodes.
All electrical equipment operating above 250 volts shall have two separate and
distinct connections to earth grids. Separate earthing grid shall be provided
for instrument and electrical system.
1.8.10.4 Lightening
protection shall be provided as per the requirements of IS: 2309. Self
conducting structures having metal thickness of more than 4.8 mm may not require
lightning protection with aerial rod and down conductors. They shall, however,
be connected to the earthing system, at least, at two points at the base.
1.8.10.5 Safety devices in
line with NACE SP-01-77 or BIS 8062 shall be installed for preventing damage to
the pipeline due to lightning or fault currents when the pipeline is installed
near electric transmission tower footings, ground cables etc.
1.8.11 Safety Instrumented
System (SIS)
1.8.11.1 Safety
Instrumented System (SIS) is composed of software and hardware which takes the
process to a safe state when predetermined conditions, as set on control
parameters like pressure, temperature, levels, flow etc. are violated. SIS
protects against the possibility of a process excursion developing into an
incident and limits the excursion potential.
1.8.11.2 SIS requirements
as a minimum are as under:
(i) Emergency Shutdown (ESD)
(ii) Surge Relief
(iii) Alarm for hydrocarbon level
in the tank
(iv) Thermal Safety Valve (TSV)
or Thermal Relief Valve (TRV)
(v) Hydrocarbon detectors
(vi) High level and High-High
level alarms for storage tanks and line balancing tank to be integrated with
SCADA of pipeline control room.
1.8.11.3 Adequate Safety
Instrumented System shall be designed for mainline pumps, motors, engines,
storage at receiving or delivery terminals etc.
1.8.11.4 Instrumentation
and control system for the pipeline system in totality shall meet the
requirement as per API Standard API-RP-551 to API-RP-556 “Manual on
Installation of Refinery Instruments and Control Systems”.
1.8.12 Communication
A reliable and dedicated
communication system to interact between all stations including sectionalizing
valve station with or without remote operation capability along the entire
pipeline shall be designed and installed and maintained to ensure safe
operations under both normal and emergency situations.
1.8.13 Pump Station
1.8.13.1 Pump Station shall
be designed in accordance with the requirements of ASME B 31.4.
1.8.13.2 No free water in
LPG being pumped shall be allowed as per IS 4576. Online water analyzer may be
installed at the originating pump station to detect any free water in the LPG
being pumped.
1.8.13.3 Typical facilities
at a typical pump station shall consist of following:
1.8.14 Pumps
1.8.14.1 Centrifugal type
pump shall conform to the requirement of API-610. Reciprocating Pump shall
conform to the requirements of API 674 or API 675 or API 676.
1.8.14.2 LPG Pumps shall
conform to API 610. LPG Pumps shall be provided with a high point vent to safe
height minimum 3 meters above the pump in case of no pump shed or 1.5 meters
above the pump house roof top or connected to a cold flare with flame arrestor.
1.8.14.3 All Pumps shall be
provided with suction and discharge pressure gauges and transmitters.
1.8.14.4 Check valve shall
be installed on the discharge side of all centrifugal pumps wherever installed
in parallel. Wherever pumps are installed in series, shall have check valve in
the header isolating the suction and discharge piping connection. The last pump
in the series shall have check valve on the discharge piping. Additional common
check valves shall be installed in the outlet header of the series pump
configuration. The suction and discharge side of the main pumps and booster
pumps shall have actuated valves.
1.8.14.5 Minimum flow
circulation line shall be provided for booster pumps or main pumps in line with
designer's or manufacturer's recommendation.
1.8.14.6 Mechanical Seal
with seal failure alarms and trips shall be provided. However, for LPG
services, Double Mechanical Seal with seal failure alarms and trips shall be
provided.
1.8.14.7 Pumps protection
and interlocks shall be provided in accordance with manufacturer's
recommendations.
1.8.14.8 For LPG pipeline
facilities, Following alarms and tripping shall be provided on pumps:
(a) Low suction pressure of
booster and main pump.
(b) High discharge pressure at
main pump.
(c) Low discharge pressure trip
on pump against pipe rupture to avoid liquid vaporization.
(d) High Casing temperature
(e) High bearing temperature
(f) Tripping of main or booster
pump in case of closure of suction or discharge MOVs.
1.8.14.9 Motor operated
valve limit switch position (open or close) to be interlocked with the start of
the pump. Pump shall operate in sequence with defined logic at starting and
shut down.
1.8.15 Pump Drivers
1.8.15.1 Electric Motors
with fixed speed drive or variable frequency drive (VFD) may be provided as
Pump Drivers. Electric Motors shall meet the requirement of API 540 “Electrical
Installation of Petroleum Processing Units”.
1.8.15.2 In case Internal
Combustion Engines as pump drivers is provided, this shall meet the requirement
of API standard 7C - 11F - “Recommended practice for Installation, Maintenance
and Operation of Internal Combustion Engines” or suitable BIS equivalent codes.
1.8.15.3 Air intake shall
be located in a non hazardous area. Screwed pipe fittings shall not be used on
any part of the fuel system piping or on the day service tank. Seamless tubing
with stainless compression fittings are recommended. If the flame arrestor or
traps are installed on the exhaust, it shall comply with BS 7244.
1.8.15.4 Exhaust manifolds
and turbocharger casing shall be cooled as per OEM recommendations.
1.8.15.5 The control panel
of the engine shall be designed for operating in hazardous area in case the
same is mounted adjacent to the engine.
1.8.15.6 All electrical
equipment installed in hazardous area shall be certified for use in hazardous area
including electric starter motor and starter solenoids.
1.8.15.7 The radiator fan
blades shall be as per OEM recommendations.
1.8.15.8 Safety
Instrumentation system on the mainline engine shall be provided. In addition to
this, provision shall be made for shut down of the engine on high coolant or
lubricating oil temperature.
1.8.15.9 Engines driving
pumps used for pumping petroleum products class A and Class B shall be
separated from the pump by means of fire wall of sufficient size to prevent
liquids leaking from the pump from spraying onto the engine.
1.8.15.10 In addition, pump
and pump driver (Engine or motors skids) should be equipped with vibration
monitoring devices with provisions for local and/or remote alarm shut down
capabilities.
1.8.16 Instrument and Plant
Air System
Depending upon requirement,
pump station should have an instrument air supply system for instrumentation
system, control valves etc. Electrical motor driven or engine driven air
compressors shall be used. Air receivers, air storage bottles and instrument
air dryer units shall be provided. Air receivers or air storage shall be
designed and installed in accordance with ASME Section VIII of the Boiler and
Pressure Vessel Code.
1.8.17 Delivery Storage
(LPG)
High level alarm and High
level alarm indication of storage vessel shall be set at 80% and 85% level of
volumetric capacity respectively. The audio visual indication shall be provided
at local panel and the pipeline control room. Pipeline delivery Remote Operated
Valves (ROVs)(supplier's and consumer's premises) shall close on actuation of
high level alarm.
1.9 Safety Devices and
Features
1.9.1 Emergency Shutdown
(ESD) Facilities for Stations
1.9.1.1 Pump station,
delivery cum tap off station and terminal station shall be provided with an
emergency shutdown system by means of which the operation can be safely
stopped. Operation of the emergency shutdown system shall also shutdown all
Pumps, Prime movers, Control valves and delivery manifold valves except those
that are necessary for protection of the equipment.
1.9.1.2 Emergency shutdown
system shall be operable from at least 2 locations away from the pump shed area
of the station out of which one should be located in the field outside the pump
shed building and another in the control room of the pump station.
1.9.2 Pressure Limiting
Devices
1.9.2.1 Any equipment or
section of the pipeline containing liquid hydrocarbon in the form of trapped
volume shall be protected against excessive pressure developed due to rise in
surrounding temperature by installing Thermal Relief Valves (TRVs). The
discharge of TRVs shall be connected to blow down drain connected to a sump
tank of appropriate capacity. For LPG installations, the discharge of TRVs
shall be connected to flare system wherever available. These TRVs shall have
isolation valves on both sides of safety valve. All TRV isolation valves
(upstream and downstream) shall be lock open.
1.9.2.2 In case of
non-availability of flare system, the discharge from safety valve shall be
vented vertically upwards to atmosphere at an elevation of 3 meter (minimum)
above ground or the tallest structure within a radius of 15 meter whichever is
higher for effective dispersion of hydrocarbons. In this case, isolation valves
on downstream of PSVs are not required. A weep hole with nipple at low point
shall be provided on the vent pipe in order to drain the rain water which may
get accumulated otherwise. Weep hole nipple shall be so oriented that in case
of safety valve lifting and consequent fire resulting from LPG coming out from
weep hole does not impinge on the structure or equipment. A loose fitting rain
cap with chain (non sparking) shall be fitted on top of the vent pipe.
1.9.2.3 Pressure safety
valves or other devices of sufficient capacity and sensitivity shall be
installed to ensure that the normal operating pressure of the system does not
exceed by more than 10%. If the normal operating pressure is the maximum
allowable operating pressure of the pipeline, then the set pressure for
pressure safety valve should be at a pressure 2 kg/cm2 above
the maximum allowable operating pressure (MAOP) or at a pressure equal to MAOP
plus 10%, whichever is less.
1.9.3 Sump Tank
Discharge from safety
valves shall be connected to a close blow down system having an underground
storage tank of appropriate capacity. In case surge protection measures are
installed, the sump tank shall have adequate capacity to store the excess
liquid hydrocarbon expected to be released as result of activation of surge
relief system.
1.9.4 Fire Protection
System
1.9.4.1 Ultra Violet or
Infra Red or Other Flame detectors or Heat detectors or a combination of flame
and heat detectors shall be installed in the pump shed to give automatic alarm
and/or shut down of the unit, isolation of the facilities in the event of
occurrence of fire. The same may be coupled with suitable extinguishing system
such as foam system for extinguishing the fire.
1.9.4.2 Smoke or multi
sensor detectors shall be provided in control room, Motor Control Center (MCC)
room and utility rooms, cable trenches etc. with provision of indication, alarm
and annunciation.
1.9.4.3 Break glass type
fire alarm system shall be installed at all strategic locations of the stations
and shall be integrated to the Fire Alarm Panel in the control room and the
same shall be extended to the marketing control room in delivery or terminal
stations. Manual call point with talk back facilities shall be installed in the
strategic locations of large size tank farm and to be hooked up with station fire
alarm panel.
1.9.4.4 Environmental
friendly fire extinguishing system shall be considered for control rooms,
switch gear and battery room, computer rooms of pump station, terminal station,
delivery or tap off stations.
1.9.4.5 Fire water network
with fire hydrants, long range monitors and fire water storage shall be
provided at all stations except scrapper stations and sectionalizing valve
stations.
1.9.5 Piping Requirement
for Refrigerated LPG Transfer
1.9.5.1 Piping system shall
be designed as per ASME B 31.3. The refrigeration system shall maintain the LPG
at a temperature at which LPG's vapour pressure does not exceed the piping
design pressure.
1.9.5.2 Pipe component
material specification should meet the temperature extremes for which it has
been designed. Low ductility materials such as cast iron, semisteel, malleable
iron and cast aluminum shall not be used in any pipe.
1.9.5.3 Shut off valves and
accessory equipment shall be constructed of material suitable for operating
pressure and temperature extremes to which they are subjected.
1.9.5.4 The insulation
shall contain a vapour barrier and shall be weather proofed. Insulation and
weather proofing shall be fire retardant. Steel surfaces covered by insulation
shall be properly coated to prevent corrosion.
1.9.5.5 When cold piping is
routed below ground provision like trenches, casing and other means shall be
made to permit expansion and contraction of the pipeline.
1.9.5.6 When storage
facility handles more than one type of product, dedicated loading and unloading
pipelines shall be considered for each type of product.
1.9.5.7 The vapour load
resulting from refrigeration shall be handled by one or a combination of the
following method.
(a) Recovery by a liquefaction
system
(b) Disposal by flaring
1.9.5.8 Provision shall be
made for emergency alarm to signal excess pressure build up in the pipeline
because of a failure of cooling medium.
SCHEDULE 1B
MATERIALS
AND EQUIPMENT
2.1 Materials and
Equipments
All materials and
equipments forming a permanent part of any piping system constructed according
to these Regulations shall comply with the design and service requirements and
shall be suitable for the intended fabrication and/or construction methods. For
sour liquid service requirements as per Schedule 1H shall be complied with.
2.2 Materials for use in
Cold Climates
Materials to be used in
facilities exposed to low ambient and/or low operating temperature shall have
adequate impact properties to prevent brittle fracture at such low
temperatures.
2.3 Material Specifications
In addition to standards
and specification covered in ASME B 31.4, standards and specifications listed
in Annexure II shall also be acceptable for manufacturing of various piping
components forming part of the liquid hydrocarbon pipelines and associated
facilities.
2.4 Steel Pipe
2.4.1 Carbon Steel line
pipe for use in liquid hydrocarbon pipeline system shall be Seamless, Electric
Welded (EW) or Submerged Arc Longitudinal or Helical Welded (SAWL or SAWH)
conforming to Line pipe Specification API 5L Product Specification Level (PSL)
- 2 or equivalent.
2.4.2 Pipes made of cast
iron shall not be used in sour multiphase service. Use of ductile iron pipes is
not permitted for liquid hydrocarbon pipelines.
2.4.3 Electric welded pipes
manufactured to API specification 5L shall also meet additional requirements
specified under Annexure III of these regulations.
2.5 Carbon Equivalent
2.5.1 The maximum limits on
Carbon Equivalent (CE) for Steel line pipes shall be as follows:
For pipes having Carbon Content
> 0.12%
CE (IIW) value shall be ≤
0.40%
For pipes having Carbon
Content ≤0.12%
CE (Pcm) value shall be ≤
0.20%
2.5.2 Ultrasonic testing
shall be carried out for 100% of the pipe weld seam. Ultrasonic testing for
pipe ends shall be mandatory.
2.6 Mill Hydrotest
Line pipes are recommended
to be hydrostatically tested in pipe mill using test pressure that produces a
hoop stress equal to 95% of SMYS irrespective of grade of pipe material. Test
pressures for all sizes of seamless pipe, and for welded pipe with D<= 457
mm (18 inch), shall be held for not less than 5 seconds. Test pressures for
welded pipe with D> 457 mm (18 inch) shall be held for not less than 10
seconds.
2.7 Fracture Toughness
Carbon steel line pipes
shall meet the fracture toughness requirements stipulated in ASME B 31.4.
2.8 Notch Toughness
Requirements
2.8.1 For carbon steel
pipes and other steel components of size NPS 2 inch and larger, notch toughness
values shall be determined to provide protection against fracture initiation and
propagation. Notch toughness values (minimum impact absorbed energy values)
shall be specified based on the design operating stress and the minimum design
temperature.
2.8.2 For carbon steel
pipes and other components smaller than NPS 2 inch proven notch toughness
properties are not mandatory.
2.9 Ductile Iron Pipe
Use of ductile iron pipes
is not permitted.
2.10 Pipes and Fittings
Pipes and fittings
manufactured to standards listed in Annexure II of these regulations should be
used.
2.11 Equipment Specifications
Equipment used in petroleum
and petroleum products pipelines manufactured to standards listed in Annexure
II of these regulations shall also be acceptable.
SCHEDULE 1C
PIPING
SYSTEM COMPONENTS AND FABRICATION
3.1 General
3.1.1 This section covers
the requirements for fabrication, installation and testing of piping systems
components for process and utility piping of the terminals forming an integral
part of liquid pipelines systems.
3.1.2 In general, all the
piping system components for respective terminals or stations shall be
designed, fabricated, erected, tested in accordance with the binding
requirement of applicable code (ASME B31.3 or 31.4). Unless otherwise
specified, the requirements specified in this section will supplement the
requirements specified in the respective piping codes and project
specifications.
3.2 References
3.2.1 Reference shall be
made to following standards, as applicable:—
ASME B31.3 : Process Piping
ASME B31.4: Pipeline
Transportation Systems for Liquid Hydrocarbons and Other Liquids
ASME VIII : Boiler and
Pressure Vessel Code
OISD-STD-141 :Design and
Construction Requirements for Cross Country Hydrocarbon Pipelines
3.2.2 The specifications
for piping material used in the petroleum and petroleum products pipeline shall
be as per Annexure-II.
3.3 Materials
3.3.1 The piping materials
shall be procured strictly in accordance with the applicable Piping Material
Specification (PMS) or Valve Material Specification (VMS) or material
specifications prepared for the purpose duly complying with the requirements
specified in applicable codes and standards.
3.3.2 Procedures for
off-loading, storage, receipt, control, traceability and inspection of piping
material supplied for fabrication and installation shall be prepared and
implemented.
3.3.3 Once delivered to
site for the fabrication or construction, the storage and preservation
procedures shall be prepared and implemented until the system is commissioned,
as applicable.
3.3.4 Storage of piping and
piping components and equipment shall be under cover and protected against
environmental degradation and/or corrosion.
3.3.5 The Carbon steel and
stainless steel components shall be segregated to avoid any cross
contamination.
3.3.6 All fittings and
equipment shall be protected against damage during handling. Special attention
shall be given to the sealing surfaces and bevelled areas.
3.4 Fabrication
3.4.1 General Requirements
3.4.1.1 The fabrication
yard shall be set-up for work with relevant materials and equipment.
3.4.1.2 All welded
attachments to piping, including pads etc. shall be of a material compatible
with the piping material.
3.4.1.3 Bending and forming
of pipe shall be carried out in accordance with ASME B31.4 and shall be
performed in accordance with documented procedures.
3.4.2 Welding and NDT
3.4.2.1 All welding and non
destructive testing (NDT) shall be in accordance with applicable design or
fabrication codes. Accordingly, the project specifications shall be developed
to include for type of materials, applicable welding compatibility of
consumables and welding procedures, Welding procedures, Pre-qualification test
(PQT), evaluation and acceptance of qualification, frequency of production
testing, acceptance and rejection criteria including heat-treatment
requirements, as applicable.
3.4.2.2 All butt welded
golden joints, which are not subjected to hydrostatic testing, shall be 100%
radiographically tested as well as 100% examination by ultrasonic technique.
Socket welded golden joints shall be examined by using Liquid Penetration
Inspection or wet Magnetic Particle Inspection technique.
3.4.3 Welds and Threads
3.4.3.1 Internals of
in-line valves and equipment that could be damaged due to heat transfer shall
be protected or removed prior to welding and/or heat treatment. Manufacturer's
recommendations shall be clearly defined and followed during welding of such
items.
3.4.3.2 Unless otherwise
stated on approved drawing or specifications, pipe threads shall conform to ASME
B1.20.1. All threading shall be carried-out after bending, forging or heat
treatment, but where this is not possible, suitable thread protection shall be
provided.
3.4.4 Dimensional Control
of Pre-fabricated Pipe-work
3.4.4.1 Dimensional control
of prefabricated piping spools shall be performed in a systematic manner,
assuring that the final installation will be correct. The applicable tolerances
shall be specified in Piping General Arrangement (GA) drawings, fabrication
drawings and/or isometrics as prepared specifically for the fabrication works.
3.4.4.2 Prefabricated pipe
spools shall be cleaned and applied with protective coatings (as required) and
preserved prior to installation.
3.4.4.3 Internal cleaning
of pipe spools may be done by hydro flushing or hydro jetting.
3.4.5 Branch Connections
3.4.5.1 Tees, weldolets,
nippolets, sockolets, and reinforcement pad connections shall be provided as
applicable for the branch connections.
3.4.5.2 Reinforcement pads
or saddles required by specifications and drawings shall be of the same
material as the main pipe (unless specified otherwise) and shall be formed to
provide a good fit to both main and branch pipe.
3.4.5.3 Branch
reinforcement pads or each segment thereof shall be provided with a minimum 3.0
mm drilled and tapped hole prior to fitting to the pipe, to ensure leak
detection, venting and testing facilities. Whenever possible, pad should be
made in one piece before fitting onto pipe. After welding and testing the hole
shall be permanently plugged, e.g. welded or metal plug in piping material.
3.5 Installation of Piping
3.5.1 General
All pipes shall be
inspected before erection to ensure that they are free from loose
contamination.
3.5.2 Erection of Piping
3.5.2.1 Pipe-work shall be
erected on permanent supports designated for the line.
3.5.2.2 Temporary supports
shall be kept to an absolute minimum, but to an extent sufficient to protect
nozzles and adjacent piping from excessive loads during the erection.
3.5.2.3 Pipe-work shall be
fitted in place without springing or forcing to avoid undue stressing of the
line or strain being placed on a vessel or item of equipment, etc.
3.5.2.4 All temporary pipe
spools and supports that are an aid to erection, testing or flushing,
fastening, etc. are to be specially marked for removal identification.
3.5.2.5 All valves shall be
protected against ingress of dirt, chemicals and moisture during any temporary
storage.
3.5.3 Flanged Joints
3.5.3.1 Before assembly,
flanges shall be adequately inspected and shall not have any damage that may
interfere with the integrity of the joint.
3.5.3.2 The flanges shall
be clean and free from any rust, dirt or other contamination. The joints shall
be brought up flush and square without forcing so that the entire mating
surfaces bear uniformly on the gasket and then mated-up with uniform bolt
tension.
3.5.3.3 With the piping
flange fitted and prior to bolting-up the joint, it shall be maintained that
(i) the bolting shall move freely through accompanying bolt-holes at right
angle to the flange faces (ii) there shall be a clear gap between two flange
faces before gasket installation (iii) there shall be sufficient flexibility to
install and replace gaskets.
3.5.3.4 The flange covers
shall be retained on all flange connections to valve or equipment, until ready
to connect the mating piping.
3.5.3.5 The equipment shall
be blanked, either by pressure test blanks, spades or blinds, to stop the
ingress of internal pipe debris.
3.5.3.6 The flange joint
shall be made using either spiral wound metallic gaskets or metallic ring type
gaskets. Plain asbestos sheet or reinforced gaskets shall not be used.
3.5.3.7 Fittings and
flanges made of cast iron and ductile iron shall not be used in petroleum and
petroleum products Pipelines.
3.5.4 Strain Sensitive
Equipment for Flanged Connections
3.5.4.1
When the flanges are to be connected to strain sensitive mechanical equipment
(e.g. pumps, compressors, turbines, etc.), then in such cases, the connecting
flanges shall be fitted-up in close parallel and lateral alignment prior to
tightening the bolting.
3.5.4.2
In general, flange connections to strain sensitive equipment shall be the last
connection made on completion of a line or interconnecting system of lines. The
connections to strain sensitive equipment shall be subject to stress analysis.
3.5.5 Gaskets
The gaskets shall be
supplied, stored and installed in accordance with manufacturers' instructions.
Gaskets shall not be reused. Gaskets shall not protrude into the bore of pipe.
3.5.6 Bolting
3.5.6.1 Bolting shall be in
accordance with applicable piping specification for the project.
3.5.6.2 Manually torqued
flange bolts and stud bolts shall extend fully through their nuts with minimum
one and maximum five threads.
3.5.6.3 The flange bolts,
stud bolts threads as well as nut spot faces shall be thoroughly lubricated
prior to fitting.
3.5.6.4 All bolted flange
connections shall have controlled tightening by means of manual torque wrenches
or hydraulic bolt tightening.
3.5.6.5 If required, the
bolts shall have extra over-length in order to accommodate tensioning tool.
3.5.7 Pipe Supports
3.5.7.1 Pipe supports shall
be in accordance with the valid pipe support detail drawings developed for the
project and/or piping support guide developed for the project.
3.5.7.2. For lines subject
to stress analysis, it shall be ensured that the stress isometric drawings
fully comply with the installed system with regard to pipe routing, pipe
support locations and support functionality.
3.5.7.3 Piping shall not be
forced to fit with support locations in such a manner that additional stress is
introduced. Pipes shall not be supported by other pipes, i.e. individual
supporting is required.
3.5.7.4 All stud bolts and
nuts used in petroleum and petroleum products pipelines should be hot dipped
galvanized as per ASTM A 153.
3.5.8 Installation
Tolerances
Installation tolerances of
piping components shall be as required by the individual service of the piping
component including requirements for maintenance access, position relative to
surrounding steelwork, equipment, cable tray and heating, ventilation and
air-conditioning duct routings, positioning of pipe supports relative to the
structural steel, pipe stress.
3.5.9 Expansion and
Flexibility Requirement
3.5.9.1 Piping shall be designed
to have sufficient flexibility to prevent excessive stresses in the piping
material caused from expansion or contraction, excessive bending moments at
joints, or excessive forces or moments at points of connection to equipment or
at anchorage or guide point.
3.5.9.2 Maximum temperature
for design of above ground section of pipeline or piping shall be the maximum
expected liquid temperature during operation or maximum ambient temperature
whichever is higher. When maximum temperature expected during operation is
below 65°C, thermal expansion and stresses in the above ground piping shall be
evaluated considering pipe skin temperature of 65°C.
3.6 Preparation of Piping
for Testing
3.6.1 General
3.6.1.1 The initial
flushing shall be carried out prior to pressure testing. The piping shall be
free from all foreign materials (e.g. dirt, grease, oxide scale, weld deposits
and temporary protective coating) which could cause operational disturbances.
All flushing shall be performed according to a documented procedure.
3.6.1.2 All items that can
be damaged during cleaning shall be removed or blocked prior to cleaning, e.g.
pressure gauges, flow meters, signal sensors, relief valves, permanent
strainers, check or globe or control valves having reduced cross sectional
areas, rupture discs, instrument probes, thermo wells, connection to vessels or
pumps level instruments, etc.
3.6.1.3 The orifice plates
shall be installed after flushing and pressure testing.
3.6.2 Hydro-flushing
3.6.2.1 Items which would
be sensitive to damage during hydro flushing shall be removed, blocked off or
isolated. Ball valves shall be flushed in fully open position. All piping
systems shall be flushed using high pressure jet-flushing equipment. The piping
system shall be hydro flushed to ensure that weld deposits are removed.
3.6.2.2 The flushing medium
shall be fresh water. The flushing water chloride-ion content shall be less
than 50 ppm and the pH value shall be in the range of 6.5 to 7.5.
3.6.2.3 After flushing, the
piping systems shall be completely drained and protected against corrosion.
3.6.3 Pressurized Air
Blowing
The pressurized air blowing
may be used as an initial cleaning method for instrument air, plant air and as
an alternative method for initial cleaning of small bore pipe (typical less
than 2 in). This method may also be used when there are problems removing
trapped liquid in the circuit, or to verify cleanness of small bore pipe or
where the inspection is inadequate due to pipe shape and configuration. Safety
precautions will be taken when using this method to avoid injuries.
3.6.4 Soft Pigging
3.6.4.1 If required, the
soft pig may be propelled using compressed air, vacuum, or water. Pressure
shall not exceed design pressure of the system. When using compressed air, a
procedure covering all safety aspects shall be established. The procedure shall
describe in detail the arrangement for catching or receiving the pig in a safe
manner. Items which can be sensitive to damage during soft pigging shall be
removed.
3.6.4.2 All systems shall
be internal visual inspected for acceptable cleanness by spot check during
construction.
3.7 Pressure Tests
The test pressure shall,
unless otherwise specified, be in accordance with ASME B31.4. The test pressure
shall be calculated based on the maximum design pressure of the piping class
(not the design pressure of the individual line). Suitable temperature
adjustments shall be made while calculating the test pressure.
3.7.1 Test Preparation
3.7.1.1 Pressure,
temperature and time recorders shall be used for all pressure tests. The
pressure shall be shown in barg. Pressure gauges and recorders used to indicate
and record test pressure shall be dead weight tested for accuracy according to
a procedure, dependent on type of equipment. Pressure and temperature gauges
and recorders shall be calibrated in accordance with recognized calibration
standards.
3.7.1.2 Piping joints,
welds (including those used in the manufacturing of welded pipe and fitting,
and structural attachment welds to pressure-containing components), and bonds
shall not be insulated or physically covered until satisfactory completion of
testing.
3.7.1.3 All piping shall be
adequately supported before the pressure test. Spring or other variable type
supports shall be blocked to prevent movement.
3.7.1.4 Unless otherwise
noted, all valves are to be through body tested. If valves are included in the
pressure test, the following applies: ball, plug, slab gate valves and other
valves where the cavity pressure may differ from the bore pressure, shall be
pressure tested in the half open position. All other valves shall be tested in
the fully open position. When check valves are included in pressure test they
shall be jacked open or have their internals removed.
3.7.1.5 Where the test
pressure to be applied to the piping is greater than the maximum allowable test
pressure for valves, the valves shall be blinded off on the side to be tested,
or removed and replaced by dummy spools. Turbines, pumps, compressors and
vessels shall be blinded off prior to pressure testing.
3.7.1.6 A list shall be
prepared for sensitive equipment (i.e. expansion joints, relief valves, inline
instruments, etc.) that shall be removed, blocked off or isolated during
testing. This list shall be a part of the test procedure.
3.7.2 Test Media
3.7.2.1 For hydrostatic
testing, the test medium shall in general be fresh water, except that other
suitable liquid may be used if the piping or inline equipment would be
adversely affected by water and shall be subject to prior agreement.
3.7.2.2 The piping shall be
properly drained as soon as possible after testing. Carbon Steel systems shall
be tested with an acceptable preservation fluid to prevent rust. The
anti-freezing compounds may be added if it is anticipated that the ambient
temperature may fall down below the permissible value.
3.7.2.3 For pneumatic
testing, the test media shall be oil free, dry air or any inert gas. The use of
air for testing shall be limited to a maximum pressure of 0.7 MPa overpressure.
Above this pressure nitrogen shall be used. The extent of pneumatic testing
shall be approved. All safety aspects using compressible test media shall be
evaluated.
3.7.2.4 For instrument or
utility air systems, where the introduction of water is undesirable, test media
shall be oil free dry air or any inert gas.
3.7.3 Hydrostatic Testing
3.7.3.1 The test pressure
shall be maintained for a sufficient length of time to permit visual
examination to be made of all surfaces, welds and connections. Over-pressuring
due to static head shall be avoided.
3.7.3.2 Hydrostatic testing
of station piping shall be carried out separately from main pipeline and same
shall be tested at minimum test pressure of 1.25 times the design pressure. The
test pressure shall be maintained for a minimum period of 4 (four) hours.
3.7.4 Pneumatic Testing
3.7.4.1 Pressure of
0.5kg/cm2 shall be introduced in the system and a leak test
performed. The pressure shall gradually be increased to 50 % of the specified
test pressure and kept for minimum 10 min to equalize strain. The pressure
shall then be increased in steps of 10 % of the specified test pressure, until
the specified test pressure is reached. At each step, the pressure shall be
kept for minimum 10 min to equalize strain. The specified test pressure shall
be kept for 1 hour. The pressure shall then be gradually released after
examining for leakage. The piping systems shall not show any sign of plastic
deformation or leakage.
3.7.4.2 All flanged joints
in above ground pipelines or piping, equipment and instrument impulse tubing
etc. shall be tested by pressurizing the piping system or equipment with dry
compressed air or water at a pressure of 3.0kg/cm2 g and
checked by means of soap solution or suitable digital gauge for leaks as
applicable. After hydrotesting of the pipeline sections or station piping the
section shall be dewatered immediately except when the section is filled with
inhibitor. After dewatering the section shall undergo swabbing.
3.7.5 After Completion of
Test
3.7.5.1 The tested systems
shall be depressurised by opening the depressurising valve in the test rig.
After depressurisation, all vents and low point drain valves shall be opened
and the system shall be thoroughly drained where the test medium is water.
Where required, blowing by dry air or pressurised air shock blowing to remove
any trapped water shall be performed to remove any residual or trapped water.
3.7.5.2 Systems with drying
requirement shall be dried out after hydro testing with dry oil free air. The
dew point shall be established depending upon location or elevation and the
level of dryness required. Drying may be terminated when the dew point at the
outlet is equal to the dew point at the inlet. Other methods (e.g. vacuum
drying) may also be used if the same dryness can be achieved.
3.7.5.3 Requirement for
drying shall be defined taking into consideration the time for start up of
system. If more than 3 months to commissioning, drying shall be followed by
preservation with nitrogen to keep the pipe system completely dry and to avoid
condensation of moisture. Other suitable preservation technique shall be
adopted to prevent corrosion during such period.
3.7.5.4 Reinstallation of
the system shall be performed in accordance with the test procedure. Where
permanent or temporary strainers have remained in place for the hydrostatic
pressure test, they shall be removed following the test and thoroughly cleaned
before reinstalling. Ends of pipes and nozzles shall be fully protected against
the ingress of foreign material by the use of caps, plugs or plate blinds
sealed with gaskets. These shall not be removed until just prior to final
assembly. Flange parallelism and alignment to equipment shall be checked prior
to reinstatement. All lines or joints that fail to pass the pressure test shall
be re-tested to the same procedure after repairs.
3.7.6 Test Acceptance
Criteria
The piping systems shall
not show any sign of plastic deformation or leakage.
3.7.7 Test Documentation
For all pressure tests,
documentation shall be fully traceable during the commissioning period of the
tested pipe. The documentation shall include, but not be limited to (i) a valid
test certificate specifying date, location, line numbers, test pressure, test
medium and test duration (ii) a test record chart fully specifying the pressure,
temperature and time relation during the test period.
SCHEDULE 1D
INSTALLATION
AND TESTING
Pipeline shall be buried
below ground level and unless construction above ground is found to be
desirable for exceptional reasons.
4.1 Pipeline Cover
4.1.1 Petroleum and
petroleum products pipelines shall be buried with a minimum cover as specified
in Table 3
4.1.2 In rocky areas and
areas with hard soils or gravels, minimum 150 mm thick padding of soft soil or
sand shall be provided all around the pipe. If required protective layer of
rock-shield or rock guard or concrete coating may be provided to prevent damage
to coating or steel pipe during installation and testing in place of soft
padding,
4.1.3 No dwellings or
construction in any form shall be permitted within RoU. Offenders or defaulters
shall be liable to prosecution as permitted under the Petroleum and Minerals
Pipelines (Acquisition of Right of User in land) Act, 1962 and its amendments.
4.2 Excavation
4.2.1 In cultivable land
and other specifically designated areas, the top 300 mm soil excavated from the
trench shall be stored separately. This top soil shall be replaced in original
position after backfilling and compacting of the rest of the trench.
4.2.2 The width of trench
shall be such that a minimum clear distance of 200 mm for trench in normal soil
and 300 mm for trench in rock is maintained between edge of pipe and the trench
wall at the bottom of the trench.
Table
3:
Minimum Cover Requirements for Pipelines
S. No. |
Locations |
Minimum Cover in meters [1] |
i) |
Normal or rocky terrain |
1.2 (normal) 1.0 (rocky) |
ii) |
Drainage, ditches at roads or railway crossing |
1.2 |
iii) |
Minor river crossings, tidal areas and other
watercourses [2] |
1.5 |
iv) |
Major river crossings [2] |
2.0 |
v) |
River with rocky bed |
1.5 |
vi) |
lined canals or drains or nalas etc. |
1.5 |
vii) |
Cased or uncased road crossing [3] |
1.2 |
viii) |
Cased Railways crossing [3] |
1.7 |
Notes:
(1) Cover shall be measured
from the top of coated pipe to the top of the undisturbed surface of soil at a
distance of 2 m or more from the edge or toe of ROU or ROW or the top of graded
working strip, whichever is lower. The fill material in the working strip shall
not be considered in the depth of cover.
(2) For river or watercourses
that are prone to scour and/or erosion, the specified cover shall be measured
from the expected lowest bed profile after scouring or erosion. Where scour
level is not known, an additional cover of at least 1 meter (Over and above the
cover mentioned as above in the Table 3) shall be provided from the existing
bed of the river or water course except in case of Rocky bed.
(3) The cover shall be measured
from the top of road or top of rail, as the case may be.
(4) Whenever the above
provisions of cover cannot be met due to site constraints, additional protection
in form of casing or concreting, soil bags, etc. shall be provided.
(5) When insisted by
authorities, the depth shall be maintained as per the directions of the
concerned authorities.
4.2.3 The location of a new
buried pipeline, when running parallel to an existing buried pipeline, should
be at a minimum clear distance of 5.0 meters from the existing underground
pipeline when heavy conventional construction equipment is expected to be
utilized. This distance may be reduced after careful assessment of construction
methodologies so that it does not result in unsafe conditions during
construction. In any case the minimum clear distance shall not be less than 3.0
meters. This can be permitted to be less than three meters in exceptional cases
if appropriate cathodic protection measures are implemented based on CP
interference survey results. Existing pipeline should be clearly marked on the
ground during construction. Bi-language (local language and Hindi or English)
caution signs should be installed while working in such areas.
4.2.4 While laying more
than one new pipeline in the same trench, clear separation of minimum 500mm
shall be maintained between adjacent pipelines.
4.2.5 No pipeline should be
located within 15.0 meters of any dwelling unit or any industrial building or
place of public assembly in which persons work, congregate or assemble, unless
it is provided with at least 300 mm of cover over and above minimum cover
specified in Table 3 or any other mitigation measure provided like higher pipe
wall thickness or protection with RCC Slab. No dwelling unit or permanent
structure in any form shall be permitted within the ROU or ROW.
4.3 Crossing
4.3.1 As far as possible,
pipeline should cross existing facility at right angles. Turning Points (TPs)
provided on either side of crossings shall be located at sufficient distance
away from RoU or RoW of existing facility to facilitate installation of bends
except when the pipeline runs parallel to existing facility. Minimum cover
shall be as per Table 3.
4.3.2 When insisted by
authorities, road or highway or rail crossing will be installed using a casing
pipe, minimum diameter, thickness and length of casing pipe shall comply with
API RP-1102. Carrier pipe shall be adequately supported inside casing pipe
using casing insulators made of durable and electrically non-conductive
materials to ensure no contact between carrier and casing pipe. Casing end
seals shall be installed to prevent ingress of water and/or foreign material
into casing in case the carrier pipe is protected with suitable sacrificial
anodes or impressed current cathodic protection. Vent and drains shall be
provided on and near ends of the casing pipe. If required, the carrier pipes
outside the casing pipe shall be independently supported.
4.3.3 Carrier pipe or
casing pipe may be installed by open cut, boring, jacking or other suitable
trench less techniques.
4.4 Crossing of Utilities
4.4.1 When a buried
pipeline has to cross any existing underground pipeline, cable, drain or other
services and/or structures, the pipeline shall be laid at least 500 mm below or
above such services. Where it is not possible to obtain the above mentioned
clearance, special design and construction shall be used. The existing pipeline
shall be properly supported during and after the construction activities.
4.4.2 When laid parallel to
any existing underground pipeline, cable, drain or other services and/or
structures, the underground pipeline shall be laid with a clear horizontal
distance of at least 500 mm. Where it is not possible to maintain the above
mentioned clearance, special design and construction shall be used.
4.4.3 A clearance
sufficiently large to avoid electrical fault current interference shall be
maintained between the pipeline and the grounding facilities of electrical
transmission lines unless electrical fault current interference mitigation
facilities are provided.
4.4.4 A minimum separation
of 3 meter should be maintained between pipeline and transmission tower
footings unless mitigation facilities are provided.
4.5 Cold Field Bends
4.5.1 The radius of cold
field bends shall be as specified in Table-2, Schedule 1A. The ends of each
bend length shall be straight and not involved anyway in the bending. In no
case shall the end of the bend be closer than 0.5 m or equal to pipe outside
diameter, whichever is more, from the end of a pipe. The ovality in each pipe
after bending shall be less than 2.5 percent of the nominal diameter, at any
point.
4.5.2 Bends shall be
checked by pulling a gauging pig fitted with gauging plate of diameter equal to
95 percent of the nominal internal diameter of the pipe. The pig shall have at
least two cups not less than 300 mm apart or pipe nominal diameter whichever is
larger.
4.5.3 Pipes with
longitudinal welds shall be bending in such a way that welds lie in the plane
passing through neutral axis of the bend. This requirement will not be
applicable for spiral welded pipes.
4.5.4 Corrosion coating
after bending shall be visually examined and holiday tested for defects. Any
defects or disbonding of the coating caused during bending (including forced
ridges in the coating) shall be repaired.
4.6 Lowering
4.6.1 Before lowering operations
are commenced, particular attention should be paid to the suitability of the
trench to allow the pipeline to be lowered without damage to the coating and to
give a reasonably even support to the pipeline.
4.6.2 All points on the
pipeline where the coating has been in contact with either the skids or with
the lifting equipment during the laying operation shall be carefully inspected
for damages, dents or other defects. Defect, if any, shall be completely
repaired.
4.6.3 Short completed
sections of the pipeline should be cleaned with compressed air in order to
remove dirt from the inside of pipe sections.
4.6.4 Before lowering in,
full circumference of the pipe shall be checked by holiday detector, set at an
appropriate voltage suitable for the applied coating, to detect any holiday in
the coating including field joint coating. Any coating defect or damage
identified by holiday detection shall be repaired.
4.7 Backfilling
4.7.1 Backfilling shall be
carried out immediately to the extent possible after the pipeline has been
lowered into the trench.
4.7.2 Excavated soil from
the trench shall be used for backfilling unless the same is not suitable. The
backfill material shall contain no extraneous material.
4.7.3 In cultivable land
and other specifically designated areas, top soil excavated from the trench and
stored separately, shall be restored to normal conditions.
4.7.4 Slope breakers or
other measures shall be installed in trenches dug in steep areas (slope of
generally 10 percent and more) to prevent erosion of the back fill.
4.8 Pipeline Markers
4.8.1 Pipeline markers to
indicate presence of pipeline and chainage shall be provided all along the
pipeline route at a maximum spacing of 1 km. The markers shall also be provided
on each side of highways (NH or SH), major district roads (MDR), railway
crossings, turning points and water body crossings. At other crossings where
third party activity is expected and at entrance to stations one marker shall
be provided.
4.8.2 Markers at crossings
shall display caution, words “High Pressure Pipeline” name of the operating
company, emergency telephone contact nos. etc. in regional or Hindi and English
languages.
4.9 Cleaning of Pipeline
4.9.1 Before hydro testing,
the section of the pipeline shall be cleaned and checked for the geometry of
the pipeline.
4.9.2 A gauging pig shall
be passed through the pipeline to prove the internal diameter of the entire
pipeline. The gauging plate shall have a diameter equal to 95% of the internal
diameter of the thickest line pipe used in the pipeline. The gauging plate
should preferably be made of Aluminum.
4.10 Testing After
Construction
4.10.1 Testing
4.10.1.1 All pipeline
sections shall be hydro tested after construction except for pre-tested pipes
used in tie-in spools.
4.10.1.2 No welding (other
than tie-in welds) and/or mechanical handling of pipe is permitted after
pressure testing.
4.10.1.3 Cased crossings
(rail or road) and rivers crossing sections shall be pressure tested before and
after installation for a period of at least four (4) hours. Such sections shall
be retested along with completed mainline sections.
4.10.1.4 Water should be
used as test medium. When required, test water may be dosed with required
quantity of corrosion inhibitors and oxygen scavenger depending upon quality of
the water.
4.10.1.5 API-1110 should be
used as guidance for the pressure testing of the pipeline.
4.10.2 Test Pressure and
Duration
4.10.2.1 Pipeline
(i) The minimum test pressure
at any point along the pipeline shall be as at least 1.25 times the internal
design pressure.
(ii) The maximum test pressure
shall not exceed the mill test pressure or pressure required to produce a hoop
stress equal to 95 percent of Specified Minimum Yield Strength (SMYS) of the
pipe material based on minimum wall thickness in the test section. Notwithstanding
above, pipeline shall be tested at a minimum test pressure of 1.25 times of
Design Pressure.
(iii) The test duration shall be
maintained for a minimum twenty four (24) hours or as required by statutory
authorities.
(iv) Mainline valves along with
branch pipe should be pressure tested before installation and shall be
installed after successful pressure testing of the pipeline.
(v) Mainline valves should be
installed after successful pressure testing of the pipeline
4.10.2.2 Acceptable
Pressure Variations
Pressure variations during
testing shall be acceptable, if caused by factors other than leakage, like
temperature variations. Maximum unaccounted pressure variation shall not exceed
0.3 bar. Pipelines not meeting the requirements shall be repaired and retested
in accordance with the requirements of these standards.
4.10.2.3 Above Ground
Station Piping
(i) Pressure testing of station
piping shall be carried out separately from pipeline.
(ii) Station piping shall be
tested at minimum test pressure of 1.25 times the design pressure.
(iii) The test pressure shall be
maintained for a minimum period of four (4) hours.
4.10.3 Dewatering and
Swabbing
After hydro testing of the
pipeline sections or station piping, the section shall be dewatered immediately
except when the section is filled with inhibitor. After dewatering, the
pipeline section shall undergo swabbing and station piping should also be blown
by compressed air to remove water.
4.10.4 Geometric Survey
4.10.4.1 Survey to
establish pipeline geometry using
Electronic Geometric Pigs
(EGP) shall be conducted after completion and acceptance of following pipeline
activities:
(i) Gauging and cleaning
(ii) Hydro testing
(iii) Installation of Mainline or
Sectionalizing Valve stations
(iv) All tie-ins.
(v) Completion of all
mechanical facilities on the pipeline.
4.10.4.2 Magnetic cleaning
pigs shall be propelled to ensure adequate cleanliness of pipeline. Number of
magnet cleaning pig runs and the type of magnet cleaning pig for each cleaning
run shall be suitable for adequate internal cleaning of pipeline. Ferrous
debris permitted with magnetic cleaning pig should not exceed 5 Kg/100KM.
4.10.4.3 In case debris
received is more than this amount, then subsequent run(s) are required until
the above limit is achieved.
4.10.5 Preservation of
Pipeline
4.10.5.1 If the pipeline
commissioning after pressure testing is anticipated to be delayed beyond six
(6) months, suitable preservation technique shall be adopted to prevent
internal corrosion during such period.
4.10.5.2 Pipeline may be
preserved using inhibited dosed water with adequate quantity of corrosion
inhibitors or by filling the line with any inert gas and at a positive pressure
4.10.6 Commissioning
4.10.6.1 There shall be
documented commissioning procedure to cover all the activities for pipeline
sections under commissioning and to ensure proper communication while
commissioning work.
4.10.6.2 The commissioning
operation shall be controlled and supervised by authorized personnel.
4.10.6.3 The local
administration and other statutory bodies what so ever applicable shall be
informed and work shall be carried out under an experienced person.
4.10.6.4 Upon completion of
the commissioning process there shall be a commissioning report endorsed by the
authorized person and the safety officer.
4.10.6.5 Before starting
commissioning activities, following shall be ensured:
(i) Commissioning Procedure in
place
(ii) Pressure testing is
completed for entire pipeline and associated station piping
(iii) Pressure leak check of the
above ground piping or flanged joints completed.
(iv) Pipeline has been cleaned
and debris etc. removed.
(v) All mainline or
sectionalizing valves are installed as per requirement.
(vi) All Golden joints are
inspected and accepted.
(vii) Geometric survey of
pipeline section is carried out, if applicable.
(viii) Trained and experience
personnel are available or deployed to carry out commissioning.
4.11 Documentation
Besides the details
mentioned in the ASME B31.4, the Pipeline entity shall also maintain following
records or documents:
(i) Design and Engineering
documents
(ii) Route maps, alignment
sheets, crossings, drawings, Piping and Instrumentation Diagrams, Station
layouts,
(iii) Vendor and subcontractor
details
(iv) Inspection and maintenance
reports
(v) Material certification
including dimension, metallurgy, performance and functional report
(vi) A complete pipe book.
(vii) Pressure test records
include location of leaks or failures, if any, and description of repair under
taken.
(viii) As - built drawings
including pipeline
(ix) Strength, tightness and
leak test reports
(x) Complete asset of each
location with identification.
(xi) NDT records of welds
(xii) Geometric survey reports,
if applicable.
(xiii) Cleaning records
(xiv) Commissioning reports
(xv) Non-conformance or
deviation reports
(xvi) Calibration records of
Inspection, Measuring and Metering and Test equipment
(xvii) Audit compliance reports
(xviii) Statutory clearances
(xix) Approved drawings or
documents
(xx) Relevant Standards and
Guidelines
(xxi) Equipment and operations
manuals.
SCHEDULE 1E
CORROSION
CONTROL
5.1 General
This section stipulates the
minimum requirements and procedures to control the external corrosion during
design, construction, operation and maintenance of exposed, buried and
submerged steel pipelines used for liquid hydrocarbon services. All operators shall
establish corrosion control program to comply the requirement of these
regulations, unless it is demonstrated that the results of corrosion control
programme of operating company meet or exceed the results of this section.
5.2 External Corrosion (New
Pipelines)
5.2.1 External Coating
5.2.1.1 All the buried
pipelines shall be externally coated as first line of defence against external
corrosion. External coating including field coating at girth weld joints or
patches etc. shall be selected after due consideration of service environment
(soil type etc.), handling, shipping, storing and cathodic protection
requirement.
5.2.1.2 Coating should at
least fulfil the following properties:
(i) Coating shall have good
dielectric strength to provide good electrical insulations between pipe surface
and environment.
(ii) Coating shall have
sufficient resistance to moisture transmission
(iii) Coating shall have
sufficient ductility to resist cracking
(iv) Coating shall have good
mechanical strength to resist damage during normal handling, storage, lowering,
soil stress etc.
(v) Coating shall have
resistance to disbondment, chemical degradation, change in electrical
resistivity etc. with time.
(vi) Coating shall be compatible
with cathodic protection system and field joint coatings or patches
(vii) Coating shall have good
adhesive property with minimal defects during applications
5.2.1.3 For buried carbon
steel pipelines of size NPS2 inch and above, 3 layer polyethylene or fusion
bonded epoxy or coal tar enamel coating is recommended. All buried bends and
fittings, field joints etc. shall be coated with heat shrink sleeves or two
layers high build liquid epoxy coating with minimum DFT 450 microns or any
other suitable type of coating. For heated pipelines the coating systems shall
be suitably designed.
5.2.1.4 The external
coating shall be applied as per established procedures in the mill and in field
and in a manner that ensures effective adhesion to the pipe avoiding voids,
wrinkles, etc.
5.2.1.5 Before application
of the coating, the pipe surface shall be made free of deleterious materials,
such as rust, scale, moisture, dirt, oils, lacquers, and varnish. The surface
of the pipe shall be inspected and prepared (protrusions would be removed and
the surface would be made upto the required surface finish or roughness) before
applying coating in the field to avoid any irregularities that could protrude
through the coating and damage it.
5.2.1.6 Before installation
of pipe in trench, external coating shall be inspected visually as well through
coating holiday detector. Defects or damage to coating, which can impair
effectiveness of external corrosion control, shall be repaired with compatible
field coating.
5.2.1.7 Care shall be taken
during handling, storage and laying of pipe, to prevent any damage to coating.
This can be minimised by careful handling during transportation, storage and
laying by using proper pads, slings and roller or cradles.
5.2.1.8 All exposed piping
or pipelines external surface shall be protected against external corrosion by
applying suitable coating or paint or jacket etc. Surface preparation may be
carried out compatible to such paint or coating and shall be applied according
to manufacturer's instructions and guidelines.
5.2.2 Cathodic Protection
(CP)
5.2.2.1 All the buried
pipelines shall be protected through permanent cathodic protection in
conjunction with external coating, unless it is demonstrated that the facility
installed is for a limited service life and may not be corroded to the extent,
to cause harm to public and environment during such period.
5.2.2.2 During construction
period, temporary cathodic protection shall be provided till permanent cathodic
protection system is commissioned. The temporary cathodic protection system
shall preferably be installed simultaneously keeping pace with the pipeline or
main laying or installation work and shall be monitored periodically.
5.2.2.3 Permanent cathodic
protection system shall be commissioned within one year of completion of
commissioning of pipeline system.
5.2.2.4 The cathodic
protection system shall be designed and operated in such a manner that it will
satisfy one or more criteria for cathodic polarization stated in NACE SP 0169
or BIS 8062-2006.
5.2.2.5 The design and
installation shall be done by competent or experienced person as per applicable
code, standards and practices with due consideration of pipe external coating,
soil resistivity etc. to ensure safe installation and operation during its life
time.
5.2.2.6 Design life of the
cathodic protection system shall be commensurate with the life of the pipeline
system. However, if required, augmentation of the system or parameters may be
taken up based on performance results.
5.2.2.7 Special conditions
such as elevated temperature, coating disbondment, bacterial attack, shielding,
unusual contaminates in electrolyte etc. may exist where Cathodic Protection is
in-effective. Deviation in special condition may be warranted, provided
operator is able to demonstrate the objectives in these regulations have been
achieved.
5.2.3 Electrical Isolation
5.2.3.1 Isolating devices
such as flange or coupling assembly or prefabricated insulating devices may be
installed at locations such as between over and underground junction of
pipeline, facilities changes ownership, interference locations etc. for
effective cathodic protection.
5.2.3.2 Where insulating
devices are installed to provide electrical isolation of pipeline systems to
facilitate the application of corrosion control, they shall be properly rated
for temperature, pressure, and electrical properties, and shall be resistant to
the liquid hydrocarbon carried in the pipeline systems. These devices shall not
be installed in enclosed areas where combustible atmospheres are likely to be
present unless precautions are taken to prevent arcing.
5.2.3.3 Pipes shall be
installed such that the below grade or submerged portions are not in electrical
contact with any casing, foreign piping systems or other metallic structures.
This shall not preclude the use of electrical bonds where necessary. In case
any shorting is observed with casing, suitable additional corrosion protection
measures should be considered.
5.2.3.4 Insulating devices
shall be protected against induced voltage due to lightening or ground fault at
nearby power line. Such protection can be achieved by providing Surge Diverter
or Grounding Cell across Insulating Joints or other suitable grounding
technique etc.
5.2.4 Electrical Connection
and Monitoring Points
5.2.4.1 Sufficient test
stations shall be provided along the pipeline route to check the adequacy of
cathodic protection system. This may essentially include the locations water or
rail or road crossing, cased installations, CP source locations, stray current
areas etc.
5.2.4.2 The electrical
leads shall be connected to pipeline through thermit welding or or Pin Brazing.
When thermit welding process is used for electrical lead installation on
pressurized pipelines, precautions shall be taken to avoid possible failure of
the pipeline during installation due to loss of material strength at the
elevated welding temperatures.
5.2.5 Electrical
Interference
In addition to protective
measures for interference locations due to DC traction, HVDC transmission,
other foreign pipeline or metallic structure presence etc., electrical
interference due to following shall also be considered in cathodic protection
design
5.2.5.1 Fault Currents
(i) Fault current interference
shall be taken into consideration. Fault current resulting from lighting or
upset conditions of electrical facilities could result in serious damage to
coating and pipe wall and danger to personnel. These adverse effects may occur
where a pipeline or main is close to the grounding facilities of electrical
transmission line structures, sub-stations, generating stations or other
facilities that have high short circuit current-carrying grounding networks.
(ii) Where a buried pipeline or
main is close to grounding facilities, remedial measures may be necessary to
control the effect of these fault currents in order to reduce the resultant
rise in potential gradient in the earth near the pipeline or main to an
acceptable level.
5.2.5.2 Induced Potential
Interference
(i) Pipelines or mains
paralleling alternating current electrical transmission lines are subject to
induced potentials. When studies or tests show that alternating current
potentials will be or are being induced on a buried pipeline or main, devices
shall be installed to reduce these potentials to a tolerable level.
(ii) When such pipelines or
mains are under construction, or when personnel are in contact with the
pipelines or mains, special precautions shall be taken to nullify the possible
effects of induced alternating current potentials.
(iii) After installation of
Permanent CP system, an Electrical interference survey shall be carried out
within one year to locate any potential interference current pick-up and
discharge location on the pipeline so that adequate interference mitigative
measures could be installed accordingly for the pipeline.
(iv) Pipelines installed
parallel to or near cathodically protected existing foreign pipeline, overhead
AC electric transmission line or DC Rail traction or adjacent to a switching yard
shall be protected against induced stray current.
Protective measures such as
metallic bonding, increased protection current, supplementary coating,
electrical isolation, galvanic anodes, De-coupling devices such as Polarization
cell or any other suitable method may be adopted for such interference
mitigation.
(v) Safety devices in line with
NACE-RP-01-77 shall be installed for preventing the damage to the pipeline due
to lightning or fault currents when the pipeline is installed near electric
transmission tower footings, ground cables etc.
(vi) While laying pipeline near
HT power lines, care should be exercised during construction to minimize
possible effects of induced alternating current potentials arising out of
capacity couplings.
(vii) The anode beds should be located
remote to pipeline such that there is minimum interference of anode potential
gradient zone with the existing underground metallic structures. Location of
anode beds shall be physically identifiable at the field and also properly
marked on the as built drawing. Adequacy of remoteness of anode bed to be
calculated and included in the cathodic protection design.
(viii) Fault current resulting
from lighting or upset conditions of electrical facilities could result in
serious damage to coating and pipe wall and danger to personnel. These adverse
effects may occur where a pipeline is close to the grounding facilities of
electrical transmission line structures, sub-stations, generating stations or
other facilities that have high short circuit current-carrying grounding
networks.
Electrical Bonding across
points shall be installed wherever pipelines and mains are to be separated.
(ix) It is not required to
provide additional shorting link metallic flange joint. However it shall be
ensured to maintain electrical continuity, before opening of any flange joint.
Before opening of the flange joint, a flexible cable shall be connected across
the flange by connecting at any two points on the succeeding and preceding
section of the flange being opened (either through crocodile clips or fixing
the wire with the bolts of any flange succeeding and preceding section of the
flange being opened) for avoiding any electrical spark generation during
opening of the flame.
(x) After installation of
electrical interference mitigation measures, interferences survey shall be
carried out again to determine the effectiveness of the measures.
5.3 Existing Installations
The cathodic protection
level shall be maintained for all buried pipeline in accordance with one or
more criteria specified for cathodic polarization in BIS 8062 or NACE STD SP
0169.
Cathodic Protection systems
shall also be maintained on any underground pipeline due to feeder electric
system being down or main temporarily out of service.
5.4 Monitoring of
Effectiveness of Corrosion Program
5.4.1 Effectiveness of
corrosion program shall be evaluated every year and appropriate mitigation or
corrective action shall be effected to remediate the condition which may affect
the protection against external corrosion.
5.4.2 The following records
may be considered for evaluating the performance monitoring:
(i) All the past leakages
history and leak survey records for reason of such leakages.
(ii) All ON or ON-OFF Pipe to
Soil Potential (PSP) records of inspection survey of cathodic protection
(iii) Parameters of CP rectifier
(CPTR or CPPSM) units and current density of the pipeline.
(iv) External Coating survey
Pearson Survey or Direct Current Voltage Gradient (DCVG) or Close Interval
Potential Logging (CIPL) survey or Current Attenuation Test (CAT) records
(v) DC or AC Interference
survey records
(vi) Intelligent pigging record
for external corrosion and/or coating defect indications vii. Any repair or
mitigation carried out in past
(vii) Evaluation of pipeline
thickness monitoring for Rate of corrosion if corrosion coupons are installed.
5.4.3 Mitigation measures
include based on indication observed but not limited to following:
(i) Augmentations of Cathodic
protection facility
(ii) Repair or replacement of
external coating
(iii) Electrical isolation at
interference and other locations
(iv) Stray current control
(v) Interference mitigation
(vi) Any other measure
5.4.4 When any mitigation
measure is not effective to adequately control the metal loss to acceptable
level, segment shall be replaced and suitably protected.
5.5 Records
Pipeline entity shall also
maintain following records or documents related to corrosion control:
(i) Cathodic Protection Design
documents
(ii) Soil Resistivity Survey
Report
(iii) Electrical Interference
Report and details of remedial measure with location
(iv) Inspection and maintenance
reports
(v) Material certification
including dimension, metallurgy, performance and functional report
(vi) Material test reports
(vii) Approved drawings or
documents
(viii) All records of welder’s
qualification, welding joints and testing shall be maintained.
SCHEDULE 1F
OPERATION
AND MAINTENANCE
6.1 General
6.1.1 A detailed “Standard
Operating Procedure” (SOP) is required to be developed for each pipeline
operating unit based on the experience and expertise within the Company and the
type of facilities provided and the conditions which are operated with adequate
safety.
6.1.2 The procedures set
forth in the SOP shall serve as a guide, but do not relieve the individual or
operating company from the responsibility of taking action based on the
circumstances or situation.
6.1.3 Suitable safety
equipment shall be made available for personnel use at all work areas and
operating facilities where hydrocarbon is present. Such safety equipment shall
include at least the following:
(i) Tight-fitting goggles or
full face shield;
(ii) Protective gloves
(iii) Protective boots;
(iv) Protective pants and jacket
or boiler suits;
(v) Easily accessible shower
and eye shower of clean running water at strategic locations.
(vi) Safety helmet
6.1.4 Protective clothing
shall be of cotton fabric or other anti-static material.
6.2 Operation Procedures or
Manuals
Each operating company
shall develop a comprehensive standard operating procedure (SOP) which shall
include the following but not limited to
(i) System Description
(ii) Operation set (trip or
alarm) points
(iii) Initial start up
(iv) Normal operations
(v) Normal shutdown procedure
(vi) Conditions under which
emergency shutdown is required
(vii) Emergency shutdown (ESD)
procedures including conditions causing ESD.
6.3 Display of Operating
Instructions
6.3.1 The gist of operating
instructions, emergency shutdown (ESD) procedure, ESD trip and pressure shall
be displayed or made readily available in the respective control room and also
near all important operating equipments.
6.3.2 If a piping system is
de-rated to a lower operating pressure in lieu of repair or replacement, the
new MAOP shall be determined and displayed prominently at an appropriate place
in the control rooms.
6.4 Management of Change
Modify the plans and
procedures of operating practice from time to time as experience dictates and
requires changes in operating conditions through the Management of change (MOC)
document. This document shall be serially numbered and maintained at the
headquarters with copies at the locations. The MOC shall include the reasons or
justifications requiring the change of operating conditions and the benefit
resulting thereof. Along with the completion of the changes, the MOC shall be
closed with amending the “as built” drawing and the changes made in the SOP as
applicable.
6.5 Operating Pressure
6.5.1 Care shall be
exercised to assure that at any point in the piping system the maximum steady
state operating pressure and static head pressure with the line in a static
condition do not exceed at that point the internal design pressure and pressure
ratings for the components used as specified and that the level of pressure
rise due to surges and other variations from normal operation does not exceed
the internal design pressure at any point in the piping system and equipment by
more than 10%.
6.5.2 If a piping system is
de-rated to a lower operating pressure in lieu of repair or replacement, the
new maximum steady state operating pressure shall be determined.
6.5.3 For existing systems
utilizing materials produced under discontinued or superseded standards or
specifications, the internal design pressure shall be determined using the
allowable stress and design criteria listed in the issue of the applicable code
or specification in effect at the time of the original construction.
6.6 Communications
A dedicated communications
facility shall be maintained to assure safe pipeline operations under both
normal and emergency conditions. Also a back-up communication link should be
available to ensure safe operation in an emergency and break of the normal
communication.
6.7 Emergency Response and
Disaster Management Plan (ERDMP)
A comprehensive ERDMP shall
be developed in accordance to the Petroleum and Natural Gas Regulatory Board
(Codes of Practices for Emergency Response and Disaster Management Plan
(ERDMP)) Regulations, 2010. The copies of the ERDMP for the pipeline and the
station specific shall be maintained at each control room along with necessary
maps and records to properly administer the plan, such as
(i) Necessary operational data
(ii) Pipeline patrolling records
(iii) Corrosion monitoring or
survey records
(iv) Leak or tapping records
(v) Routine or unusual
inspection records
(vi) Pipeline repair records
6.8 Right of Way or Right
of Use
6.8.1 Patrolling
6.8.1.1 Each operating
company shall maintain a periodic pipeline patrol program to observe surface
conditions on and adjacent to the pipeline right of way, indication of leaks,
construction activity other than that performed by the company, and any other
factors affecting the safety and operation of the pipeline. Special attention
shall be given to such activities as road building, excavations, and like
encroachments to the pipeline system.
6.8.1.2 Patrolling (ground)
shall be carried out atleast once in a week (urban and non-urban areas) or
aerial survey or other advance techniques shall be performed atleast once in
month. Underwater crossings shall be inspected periodically for sufficiency of
cover, accumulation of debris, or for any other condition affecting the safety
and security of the crossings, and at any time it is felt that the crossings
are in danger as a result of flood, storms, or suspected mechanical damage.
6.8.1.3 Line walk by the
officials of the Company shall be done atleast once in a year for the entire
length of the pipeline preferably to be done after monsoon.
6.8.1.4 Villagers or public
along the right of way shall be adequately made aware of the possible
consequence of hydrocarbon leaks and this shall be included as a part of
regular audit.
6.8.1.5 Regular liaison
shall be maintained with Police stations, Panchayat and district authorities
along the right of way about the possible consequence of hydrocarbon leaks and
pilferage.
6.8.1.6 Night patrolling by
line walkers or alternative security surveillance system shall be implemented
with increased frequency where the pipeline location is vulnerable from the
pilferage point of view.
6.8.2 Markers
6.8.2.1 Markers shall be
installed and maintained over each line on each side of road, highway,
railroad, and stream crossings to properly locate and identify the system.
Markers are not required for pipelines offshore.
6.8.2.2 Pipeline markers at
crossings, aerial markers when used, and other signs shall be maintained so as
to indicate the location of the line. These markers shall show the name of the
operating company, and where possible, an emergency telephone contact.
Additional pipeline markers shall be installed along the line in areas of
development and growth to protect the system from encroachment. API RP 1109
shall be used for guidance.
6.8.2.3 Markers to identify
the width of Right of Way has to be provided at visible locations and should be
so placed that it does not hinder agricultural activity or any movement
6.8.3 Right of Way or Right
of Use Maintenance
6.8.3.1 The right of way
should be maintained so as to have clear visibility and to give reasonable
access to maintenance crews.
6.8.3.2 Access shall be
well maintained to valve locations.
6.8.3.3 Diversion route of
water flow shall be maintained where needed to protect against washouts of the
line and erosion of the landowner's property.
6.9 Pigging
6.9.1 The frequency of
descaling of pipelines transporting crude petroleum and petroleum products
shall be as under:
(i) Non ATF Petroleum Products
Pipelines-Once in six months.
(ii) ATF pipelines also carrying
other petroleum products-Once in three months
(iii) Dedicated ATF
Pipelines-Once in a year
(iv) Crude Oil Pipelines-Once in
three months.
(v) LPG Pipelines-Once in a
year
6.9.2 Record of quantity
and quality of deposits (pig residue) collected after descaling shall be
examined to monitor condition of the Pipeline. Depending upon the outcome of
the chemical analysis and review, pigging frequency may be increased.
6.9.3 Instrumented or
Intelligent Pigging
The first inspection of
cross country pipeline by Instrumented or Intelligent pigging survey (IPS)
shall be carried out at the earliest but not later than 10 years of
commissioning. The result of this inspection shall be compared with original
commissioning data in order to assess the health of the pipeline and subsequent
periodicity of intelligent pigging. The interval between two Instrumented or
Intelligent pigging shall in no case exceed 10 years.
6.10 Maintenance Procedure
or Manual
6.10.1 A detailed
maintenance procedure or manual shall be developed for equipment or facility
wise installed in the entire pipeline system considering the recommendations
given by the Original Equipment Manufacturer (OEM) keeping in mind the local
conditions. The manual shall include preventive maintenance schedule with
periodicity i.e. daily, weekly, monthly, half yearly and yearly activities to
be carried out during each schedule of maintenance.
6.10.2 Procedures for
emergency repair of piping or pipelines using repair clamps, hot tapping and
stopple plugging, and other repair methods should also be included as part of
manual.
6.10.3 For repair or
maintenance works, work permit system in line with the industry or Statutory
Authorities shall be developed and compiled.
6.10.4 A comprehensive
manual for CP system monitoring, surveys, interference, mitigation programmes
as well as external and internal corrosion monitoring programmes shall be
developed and complied.
6.11 Load Lifting Equipment
All the lifting equipment,
wire ropes, tackles etc., shall be inspected once in a year as per Factory's
Act, local Statutory Authorities requirement. Relevant statutory authority's
guidelines or procedures shall be referred for guidance.
6.11.1 Pipeline Maintenance
Equipment
The specialized pipeline
maintenance equipment required for maintenance of pipeline shall be ensured to
be made available. An indicative list of equipment required to be kept by the
pipeline operator at suitable locations or service provider (s) locations as
mentioned below:
(1) Truck - 1 no.
(2) Tractor - 1 no.
(3) Trailer - 2 wheel - 2 nos.
(4) Air compressor - 2 nos.
(5) Jeep (large capacity) - 3
or 4 nos.
(6) Welding Generator - 2 nos.
(7) Welding transformer - 1 no.
(8) Power hacksaw machine - 1
no.
(9) Battery charger - 1 no.
(10) Drilling machine - Heavy
duty - 2 nos.
(11) Drilling machine - Light
duty - 1 no.
(12) Pipeline bending machine -
1 no.
(13) Oxygen cylinder - 2 nos.
(14) Acetylene cylinder - 1 no.
(15) Water Pump (5 BHP) - 3 nos.
(16) Hot Tapping (1 set) and
Stoppling Machine (2 sets)
(17) High Pressure Testing pump
- 1 no.
(18) Gas cutter, regulator,
nozzle - 1 set
(19) Dope kettle - 1 no.
(20) Aluminum ladder - 1 no.
(21) Cold cutting machine -
2nos.
(22) Semi Rotary Pump - 2 nos.
(23) Pneumatic Pump (for oil
recovery) - 1 No.
(24) Bench vice - 1 no.
(25) Chain pulley block - 2 ton
- 1 no.
(26) Hand blow for Smithy - 1
no.
(27) Pipe lifting clamp - 3 nos.
(28) Pneumatic grinder - 2 nos.
(29) Pneumatic Power Wrench - 1
no.
(30) LP gas cylinder - 1 no.
(31) Grinding machine - light
duty - 1 no.
(32) Grinding machine - heavy
duty - 1 no.
(33) Diesel engine driven water
pump - BHP-15 - 1 no.
(34) Engine driven hydraulic
pump - 1 no.
(35) Four wheel trailer - 1 no.
(36) Four wheel tractor trailer
- 1 no.
(37) Holiday detector - 1 no.
(38) Insulation flange tester -
1 no.
(39) Pearson Survey and Holiday
Detector - 1 no.
(40) Multi meter - 1 no.
(41) AVO meter - 2 nos.
(42) Multi Combination Corrosion
- Testing Meter - 1 no.
(43) Emergency Generator - 1 no.
(44) Tents etc for making
repairing base camp with all facilities to suit the remote place
(45) Communication system
(46) Lighting arrangement
(47) Hand tool set including
spanners, Files, cutters, brass hammer and Chisel
6.11.2 Mainline Block
(Sectionalizing Valves)
Pipeline block or
Sectionalizing valves shall be inspected, serviced where necessary and shall be
checked by operating partially or fully (as applicable) at least once in a year
to assure proper operating conditions or fit for the purpose it is meant.
6.11.3 Inspection of
Cathodic Protection System
6.11.3.1 Pipe to Soil
Potential (PSP) Readings shall be taken as follows:
(i) PSP readings at feeding
points shall be monitored fortnightly.
(ii) The PSP reading (ON
potential) at the test lead points for entire pipeline shall be taken once in a
quarter. The PSP survey results shall be plotted graphically to identify and
locate cathodic holidays.
(iii) Instant pipe to soil “OFF”
potential reading at test lead points of the entire pipeline shall be taken
once in a year. (Minimum acceptable criteria shall be as per BIS 8062 or ASME
B31.8 Appendix K or NACE SP - 0169 as applicable.)
(iv) The ON or OFF Pipe to Soil
Potential (PSP) survey data along with Pearson survey or Current Attenuation
Test (CAT) or Direct Current Voltage Gradient (DCVG) survey and soil
resistivity and soil chemical analysis data shall be plotted graphically in one
page or sheet to identify coating holidays.
6.11.3.2 The Criteria of
protection shall be as under:
(i) Pipe to soil polarized
potential of at least (-) 0.85 volts with respect to copper or copper sulphate
half cell. In areas where anaerobic bacteria are active, minimum PSP should be
more negative than -0.95 volts instead of -0.85 volts.
(ii) A minimum of 100 mV of
cathodic polarization between the structure surface and a stable reference
electrode containing the electrolyte. The formation of decay of polarization
can be measured to satisfy this condition.
(iii) Over protection of coated
pipeline shall be avoided by ensuring that polarization potential is not more
negative than (-) 1.2 volts with respect to copper or copper sulphate half
cells.
6.11.3.3 The instant OFF
PSP at the Test Lead Points (TLPs) should not be less negative than (-) 0.85
volt and should not be more negative than (-) 1.2 volt. Such measurement
wherever influenced by multiple pipelines in the same ROW or ROU to be valid
after switching off the other pipeline.
6.11.3.4 Current
consumption data shall be taken once in a year at the test stations where
current measurement facility exists. Cathodic protection rectifiers shall be
inspected once in three months.
6.11.3.5 All protective
devices shall be inspected once in three months.
Interference bonds shall be
inspected once a year.
6.11.3.6 Polarization cells
[electrolytic type] shall be inspected every three (3) months and electrolyte
level top up to be done after every inspection.
6.11.3.7 At the crossing
location of one pipeline with other pipeline, current and PSP data shall be
taken once in 3 months.
6.11.4 Coating Survey
6.11.4.1 Close Interval
Potential survey (CIPS) or Continuous Potential Logging (CPL) “On” and “Off”
survey for every meter of pipeline ROW should be carried out once in 5 years.
6.11.4.2 Coating survey
i.e. Pearson or Current Attenuation Test (CAT) or Direct Current Voltage
Gradient (DCVG) Survey shall be carried at probable coating defect location
identified by CPL survey done once in 5 years. The type of survey should be
decided based on coating condition. In case CAT survey is selected, it shall be
done at intervals not exceeding 50 Meters.
6.11.4.3 Survey Results to
be collated as Status Report and compared with Original Post Commissioning
survey results. If there is deterioration in the results, appropriate
corrective action needs to be taken.
6.11.5 Insulating Joint or
Insulating Coupling
Insulating joints and
couplings shall be inspected once in a year.
6.11.6 Soil Testing
If any industrial effluent
is flowing over the ROW or ROU or any environmental change is noticed on the
ROW, the soil samples shall be tested for determining the efficacy of the
existing coating and wrapping of the pipeline.
6.11.7 Back Up Power for CP
System
Wherever the availability
of power supply from State Electricity Board to the CP system is not reliable
suitable back up power (battery bank or Inverter or DG or Solar or TEG or Any
other suitable) shall be provided so as to provide minimum 90% time power to CP
system.
6.11.8 Safety Appliances
Safety appliances provided
against lightning, stray current interference from foreign objects at pipeline
crossings etc shall be maintained once in six months and updated records shall
be maintained.
6.11.9 Electrical Equipment
6.11.9.1 Maintenance and
Inspection of Electrical equipment shall be carried out in line with the
industry or good engineering practices or requirement of statutory authorities.
6.11.9.2 Internal Corrosion
Monitoring facilities i.e. corrosion coupons and probes based on electric
resistance technique (ER probes), electrochemical noise technique (ECN probes)
and/or Linear polarization technique (LPR probes), etc., shall be installed at
the stations to monitor the internal corrosion. If the rate of corrosion is
more than 1 MPY, suitable doses of corrosion inhibitor shall be dosed.
6.11.10 Inspection of
Pipes, Valves and Fittings
Above ground piping and
accessories shall be inspected visually once in a year for external corrosion.
Ultrasonic thickness measurements shall be taken on exposed sections of the
pipe once in 3 (three) years for sour crude and product and once in 4 (four)
years for sweet crude and product. Thickness measurement shall be taken at 4
locations (i.e. 12, 3, 6 and 9 O'clock positions) at the exits, bends and at
every ten meter interval of exposed piping and also at 5 meter interval for
underground piping after insulating coupling (wherever exist). Inspection of
pipes, valves and fittings shall be carried out as per relevant industry practice
or statutory authority requirement.
6.11.11 Inspection of
Pumps, Compressors, Control and Protective Equipment
Periodic inspection and
maintenance shall be carried out for control and protective equipment including
pressure limiting devices, regulators, controllers, relief valves and other
safety devices as per recommendations of OEM (Original Equipment Manufacturer)
or good engineering practices or relevant statutory authority requirements.
6.11.12 Leak Detection
System
If any leak detection
system is installed on the pipeline system, it shall be checked for
effectiveness of operation once in a year. Additionally, a daily, monthly and
yearly reconciliation record of crude or product received from tank, line fill
quantity and delivered quantity shall be maintained to ascertain the
transportation loss through pipeline. This loss should not be more than 0.015%
of the transported quantity through the pipeline on yearly basis. In case this
quantity is more than 0.015% of the yearly product transported, an internal
investigation shall be carried out to ascertain the probable cause of the loss.
6.11.13 Telecommunication
System or Equipment
6.11.13.1 Detailed System
functional tests shall be carried out once in six months.
6.11.13.2 Telecommunication
equipment shall be inspected as per manufacturer's recommendation.
6.11.14 Telemetry System or
Equipment
6.11.14.1 Detailed System
functional tests shall be carried out once in six months.
6.11.14.2 Telemetry
equipment shall be inspected as per manufacturer's recommendation.
6.11.15 Safety
Instrumentation
6.11.15.1 Operation system
interlock checking shall be carried out once in a year. Calibration,
Maintenance and Inspection of Safety Instrumentation shall be carried out as
per industry practice or recommendations of OEM or Statutory Authority
requirements.
6.11.15.2 Testing of
Pressure or Thermal Safety valves or Surge relief system shall be carried out
once in a year and proper authenticated document shall be maintained.
6.11.15.3 Emergency Shut
Down (ESD) systems shall be checked with actuation once in a year.
6.11.16 Fire Fighting
Equipment
6.11.16.1 Maintenance and
Inspection of Fire Fighting Equipment shall be carried out as per industry
practice or recommendations of OEM or Statutory Authority requirements.
6.11.16.2 Trial run of the
emergency equipment, Mock drill shall be done on regular basis as per industry
practice or Statutory Authority requirements.
6.12 Pipeline Repairs
6.12.1 General
6.12.1.1 Repairs shall be
carried by the Company as per their maintenance or job safety plan and shall be
performed under qualified supervision by trained personnel aware of and
familiar with the hazards to public safety, utilizing strategically located
equipment and repair materials. The maintenance plan shall consider the
appropriate information contained in API Publication 2200, API Publication
2201, API RP 1107 and API RP 1110 and any other relevant code or industry or
good ensuing practices. It is essential that all personnel working on pipeline
repairs understand the need for careful planning of the job, be briefed as to
the procedure to be followed in accomplishing the repairs, and follow
precautionary measures and procedures. Personnel working on repairs to
pipelines shall be informed on the specific properties, characteristics, and
potential hazards associated with precautions to be taken following detection
of a leak, and safety repair procedures set forth. Approvals, procedures, and
special considerations shall be observed for welding, as well as making hot
taps on pipelines, vessels, or tanks which are under pressure. Piping in the
vicinity of any repair shall be adequately supported during and after the
repair.
6.12.1.2 Each individual
pipeline operating company shall develop the methods or procedures for carrying
out various types of repairs in the pipeline in line with the requirement of
Statutory Authorities or industry practice.
6.12.1.3 In case of
corrosion of the pipe due to which thickness of the pipe is reduced to the
extent that maximum allowable operating pressure is required to be reduced from
original design to meet requirement of this standard, then either the pipe section
shall be repaired or replaced or the pipeline shall be de-rated to commensurate
with remaining strength of the pipe.
6.12.1.4 All dents as per
requirements of ASME B31.4 and all pipes containing leak shall be removed or
repaired.
6.12.1.5 Pipeline shall be
repaired by any one or the following:
(i) By cutting out cylindrical
piece of pipe containing the defect and replacing the same with a pre-tested
pipe of minimum 2 meter length meeting the required pipe specification.
(ii) By installing full
encirclement welded split sleeves or leak clamps to contain internal pressure
and shall have a design pressure of not less than the maximum allowable
operating pressure. This shall be fully welded both circumferentially and
longitudinally. However, this repair methodology shall not be considered as
permanent solution and the pipeline operator shall have a mechanism in place to
carry out repair as per (a) above at the earliest opportunity.
(iii) All repairs shall be
performed as per (a) and (b) above and shall be tested by radiography
examination and/or ultrasonic examination.
(iv) In case of repair of coated
pipe, all damaged coating shall be removed and new coating shall be applied.
6.12.2 Railroads and
Highways Crossings
6.12.2.1 When an existing
pipeline is to be crossed by a new road or railroad, the operating company
shall analyze the pipeline in the area to be crossed in terms of the new
anticipated external loads. If the sum of the circumferential stresses caused
by internal pressure and newly imposed external loads (including both live and
dead loads) exceeds 0.90 SMYS (specified minimum yield strength), the operating
company shall install mechanical reinforcement, structural protection, or
suitable pipe to reduce the stress to 0.90 SMYS or less, or redistribute the
external load acting on the pipeline. API 1102 provided methods that may be
used to determine the total stress caused by internal pressure and external
loads.
6.12.2.2 Installation of
uncased carrier pipe is preferred. Adjustments of existing pipelines in service
at a proposed railroad or high way crossing shall conform to requirements of
industry practices or Statutory Authority requirements.
6.12.3 Inland Waters
Platform Risers
Riser installations shall
be visually inspected annually for physical damage and corrosion in the splash
zone and above. The extent of any observed damage shall be determined, and, if
necessary, the riser installation shall be repaired or replaced.
6.13 Pump Station, Terminal
and Tank Farm Operation and Maintenance
6.13.1 General
6.13.1.1 Starting,
operating and shutdown procedures for all equipment shall be established and
the operating company shall take appropriate steps to see that these procedures
are followed. These procedures shall out line preventive measures and systems
checks required to ensure the proper functioning of all shutdown, control and
alarm equipment.
6.13.1.2 Periodic
measurement and monitoring of flow and recording of discharge pressures shall
be provided for detection of deviations from the steady state operating
conditions of the system.
6.13.2 Controls and
Protective Equipment
Controls and protective
equipment, including pressure limiting devices, regulators, controllers, relief
valves and other safety devices, shall be subjected to systematic periodic
inspections and tests, at least annually. However the following can be
reaffirmed with inspection done during the year:
(i) in good mechanical
condition;
(ii) Adequate from the
standpoint of capacity and reliability of operation for the service in which
they are employed.
(iii) set to function at the
correct pressure;
(iv) Properly installed and
protected from foreign materials or other conditions that might prevent proper
operation.
6.13.3 Storage Vessels
6.13.3.1 Storage vessels,
including atmospheric and pressure tanks, handling the liquid or liquids being
transported shall be periodically inspected and pertinent records maintained.
Points to be covered include:
(i) stability of foundation;
(ii) condition of bottom, shell,
stairs, roof;
(iii) venting or safety valve
equipment;
(iv) Condition of firewalls or
tank dikes.
(v) Earthing continuity, Rain
Water drain system as pre-monsoon check
6.13.3.2 Storage vessels
and tanks shall be cleaned in accordance with the industry practice.
6.13.4 Signs
(a) Suitable signs shall be
posted to serve as warnings in hazardous areas, high noise area preferably with
area segregation.
(b) Classified and high voltage
areas shall be adequately marked and isolated.
(c) Caution signs shall be
displayed indicating name of the operating company and, where possible an
emergency telephone contact.
6.13.5 Prevention of
Accidental Ignition
6.13.5.1 Smoking shall be
prohibited in all areas of a pump station, terminal, or tank farm in which the
possible leakage or presence of vapor constitutes a hazard of fire or
explosion.
6.13.5.2 Flashlights or
hand lanterns, when used, shall be of the approved type.
6.13.5.3 Welding shall
commence only after compliance of the safety precautions taken as listed in the
work permit.
6.13.5.3 Consideration
should be given to the prevention of other means of accidental ignition. See
NACE RP-01-77 for additional guidance.
6.14 Corrosion Control
Protection of ferrous pipe
and components from external and internal corrosion, including tests,
inspection and appropriate corrective measures, shall be as prescribed in ASME
B31.4.
6.15 Qualifying a Piping
System for a Higher Operating Pressure
6.15.1 In the event of
up-rating an existing piping system when the higher operating pressure will
produce a hoop stress of more than 20% of the specified minimum yield strength
of the pipe, the following investigative and corrective measures shall be
taken;
(i) The design and previous
testing of the piping system and the materials and equipment in it be reviewed
to determine that the proposed increase in maximum steady state operating
pressure is safe and in general agreement with the requirements of this Code;
(ii) The conditions of the
piping system be determined by leakage surveys and other field inspections,
examination of maintenance and corrosion control records, or other suitable
means;
(iii) Repairs, replacement, or
alterations in the piping system disclosed to be necessary by steps (1) and (2)
be made.
6.15.2 The maximum steady
state operating pressure may be increased after compliance with (a) above and
one of the following provisions;
(i) If the physical condition
of the piping system as determined by (a) above indicates that the system is
capable of withstanding the desired increased maximum steady state operating
pressure in accordance with the design requirement of this Code and the system
has previously been tested for a duration and pressure not less than that
required in ASME B31.4, for a new piping system for the proposed higher maximum
steady state operating pressure, the system may be operated at the increased
maximum steady state operating pressure.
(ii) If the physical condition
of the piping system as determined by (a) above indicates that the ability of
the system to withstand the increased maximum steady state operating pressure
has not been satisfactorily verified, or the system has not been previously
tested to the levels required by this Code for a new piping system for the
proposed higher maximum steady state operating pressure, the system may be
operated at the increased maximum steady state operating pressure if the system
shall successfully withstand the test required by this Code for a new system to
operate under the same conditions.
6.15.3 In no case shall the
maximum steady state operating pressure of a piping system be raised to a value
higher than the internal design pressure permitted by this Code for a new
piping system constructed of the same materials. The rate of pressure increase
to the higher maximum allowable steady state operating pressure should be gradual
so as to allow sufficient time for periodic observations of the piping system.
6.15.4 Records of such
investigations, work performed, and pressure tests conducted shall be preserved
as long as the facilities involved remain in service.
6.16 Abandoning a Piping
System
In the event of abandoning
a piping system, it is required that;
(i) Facilities to be abandoned
in place shall be disconnected from all sources of the transported liquid, such
as other pipeline, meter stations, control lines, and other appurtenances;
(ii) Facilities to be abandoned
in place shall be purged of the transported liquid and vapor with an inert
material and the ends sealed.
6.17 Training of Personnel
For the operation of the
facility in a safe and appropriate manner, it is required that the operating
and maintenance personnel shall suitably be trained every year on the following
aspects:
(i) Upgradation of operating
and maintenance skills
(ii) Updation of safety methods
and procedures
(iii) Technical Upgradation in
the field of operation or maintenance.
6.18 Records
For operation and
maintenance purposes, the following records shall be properly maintained:
(i) Necessary operational data;
(ii) Pipeline patrol records;
(iii) Corrosion records;
(iv) Leak or tapping and break
records;
(v) Records pertaining to
routine or unusual inspections, such as external or internal line conditions;
(vi) Pipeline repair records
SCHEDULE 1G
SAFETY
AND FIRE PROTECTION
7.1 General
All installations except
intermediate pigging station and sectionalizing valve stations shall have
following fire protection facilities. For intermediate pigging station and
repeater cum cathodic protection system, only portable fire extinguishers as
detailed in subsequent Para shall be provided.
7.2 Automatic Fire
Detection and Alarm System
7.2.1 Detection System:
7.2.1.1 Smoke or multi
sensor detectors shall be provided in control room, Motor Control Center (MCC)
room and utility rooms with provision of indication, alarm and annunciation.
7.2.1.2 Pumping unit sheds
shall be provided with flame or heat or a combination of flame and heat
detectors.
7.2.2 Fire Alarm System
(i) Manual call points at
strategic location shall be installed with hooter in fire alarm panel or
sounders in rooms, corridors etc.
(ii) Electric Operated Fire
siren with provision for assured power supply in case of power failure to be
provided. Range of fire siren shall be minimum 1 km.
(iii) Additionally hand operated
sirens shall be provided at strategic locations with similar range of
operation.
7.3 Fire Fighting Equipment
7.3.1 Fire Fighting
Equipment shall be provided at all installation as detailed below:
(i) Booster Pump area: 1 (One)
No. 9 Kg DCP per two pumps and 2 (two) No. 6.5 Kg CO2 extinguisher.
(ii) Main line pump shed (Engine
or Motor Driven): 1 (one) No. 75 Kg DCP, 1 (one) No. 9 Kg DCP and 2 (two) No.
6.5 Kg CO2 extinguishers per two pumps.
(iii) Scrapper Barrel area : 1
(one) No. 9 Kg DCP extinguisher.
(iv) Sump Pump, Transmix Pump
and Oil Water Separator Pump : 1 (one) No. 9 Kg DCP extinguisher.
(v) Control Room: 2 (Two) Nos.
2.5 Kg Clean Agent or 1 (one) No. 4.5 Kg CO2 extinguisher.
(vi) UHF or Radio Room: 2 (Two)
Nos. 2.5 Kg clean Agent and 1(one) No. 4.5 Kg CO2 extinguisher.
(vii) UPS or Charger Room: 1(one)
No. 4.5 Kg. CO2 extinguisher.
(viii) Meter Prover or Separator
Filter: 1 (One) No. 9 Kg DCP extinguisher.
(ix) UPS or Charger Room: 1(one)
No. 4.5 Kg. CO2 extinguisher.
(x) Mainline Emergency
Equipment Centre: 4 (Four) Nos. 9 Kg DCP and 2 (Two) Nos. 4.5 Kg CO2extinguishers.
(xi) Air Compressor area : 1
(one) No. 4.5 Kg CO2 and 1 and 1 (one) No. 5 Kg DCP extinguisher.
(xii) Workshop: 1 (one) No. 9 Kg
DCP extinguisher and 1 (one) No. 4.5 Kg CO2 extinguisher.
(xiii) Security Cabin: 1 (One) No.
9 Kg DCP extinguisher per cabin.
(xiv) Oil Sample Storage Room: 1
(one) No. 9 Kg DCP extinguisher per 100 m2 or minimum 1 No. 9
Kg extinguisher per room whichever is higher.
(xv) Effluent Treatment Plant
area : 1 (one) No. 75 Kg. and 2 (Two) nos. 9 Kg. DCP Extinguisher.
(xvi) Transformer area: 1 (one)
No. 9 Kg. DCP extinguisher per transformer.
(xvii) Office or Store or Canteen:
1 No. 9 Kg DCP extinguisher for 100 m2.
(xviii) MCC or DG Room or HT Room:
2 (Two) number of 4.5 kg CO2 based in each room or per 100 m2 floor
area.
(xix) Intermediate pigging
station: 1 (one) no. 75 kg and 1 (one) number 4.5 kg CO2 based.
(xx) Delivery or Terminal
station: 1 (one) no. 75 Kg and 1 (one) 9 Kg DCP based and 1 (one) number 4.5 kg
CO2based.
7.3.2 For LPG installation
following shall be minimum No. of extinguishers, namely:—
(i) LPG Pump- 1× 9Kg DCP/50 m2 Houses.
(ii) Office or Canteen or
Stores- 2× 9Kg DCP in each building.
(iii) MCC or DG Room or HT room-
2 × 4.5 Kg CO2 in each room or per 100 m2 floor
area. Four (4) sand buckets and stand shall be provided in DG room.
Note-1. Existing 10 kg DCP
extinguishers to be replaced with 9 kg capacity DCP extinguishers as and when
due for replacement.
7.3.3 Spares: 20% spares each for CO2 and
DCP extinguishers shall be stored. All fire extinguishers shall bear ISI or
equivalent mark. Manuals of each fire extinguisher shall be provided at every
location. The quantity and size of fire extinguishers required shall be
provided based on the nature of occupancy and class of fire or risk to be
protected.
7.3.4 The following shall
also be considered:
(i) Where cleanliness and
contamination of sensitive electrical equipment are of importance or likely to
get affected only CO2 or Clean Agent fire extinguishers shall
be provided.
(ii) Extinguishers shall be
installed within 15 m of the equipment so that travel distance for person is
not more than 15 m.
7.4 First Aid and Safety
Equipment
The following minimum
number of Personal Protective Equipment, First Aid Equipment and Safety
instruments shall be provided as indicated against each item at each pump
station or delivery or terminal station.
(i) Safety helmets - 1
No./person (minimum 08 nos.).
(ii) Stretcher with blanket- 2
Nos.
(iii) First aid box- 1 Nos.
(iv) Rubber hand gloves for
electrical purpose- 2 Nos.
(v) Fire proximity suit- 1 No.
(vi) Resuscitator - 1 No.
(vii) Red or green flags - 2 Nos.
In each color
(viii) Self contained breathing
apparatus with one spare cylinder (capacity 30 min) - 1 set with spare
cylinder.
(ix) Water gel blanket- 1 No.
(x) Portable multi gas detector
- 1 No.
(xi) Sand bucket - 5 Nos.
(xii) Low temperature rubber hand
gloves - 4 pairs (For LPG installations only)
(xiii) Low temperature protective
clothing- 2 sets (For LPG installations only)
7.5 Windsock
Windsock shall be provided
on an appropriately elevated structure like the control room or firewater pump
house. Wind socks shall be installed in such a way at several places that at
least one wind sock shall be visible from any point in the installation.
7.6 Emergency Power Supply
Emergency lighting shall be
provided for operating areas like generator room, diesel compressor room, PCC
or MCC room and control room. Emergency power supply shall also be provided to
panels of all fire alarms or detection system or other fire fighting system.
7.7 Communication System
(i) Communication system like
telephone, walkie-talkie etc. shall be provided.
(ii) All intermediate stations
including IP stations or Repeater stations shall be provided with proven
communication system. Security at unmanned station shall be trained to deal
with communication and emergency handling.
7.8 Fire Water System
7.8.1 The Fire water system
shall be provided at all pump stations and at all delivery and terminal
Stations consisting of:
(i) Fire water storage
(ii) Fire water Pumps
(iii) Fire water distribution
piping network
(iv) Fire hydrant or Monitors
7.8.2 The single largest
risk shall be considered.
7.8.3 The basis of design
of fire protection facilities should presume that no external fire-fighting
agencies would be available for main pump station, intermediate pump station
and pipeline terminal station for duration of minimum 4 hours.
7.8.4 All LPG pumps
(booster and mainline pumps), Pig launcher and receivers, metering area,
filtering area and receipt and delivery manifold area shall be fully covered by
medium velocity spray system.
7.8.5 Heat detectors
through thermal fuses or quartz bulbs (QB to blow at 79 °C) or
Electro-pneumatic (EP) detectors for detection of fire for automatic actuation
of medium velocity water sprinkler system shall be provided. The QB or EP
detectors shall be placed directly overhead or inside the hazard.
7.8.6 Terminal station
co-located in any marketing or refinery may be exempted for fire water storage,
fire fighting pumps. Only fire water network with hydrants and monitors in the
network connected to the fire water storage and pump to the co-located
installation is acceptable.
7.9 Design Flow Rate
7.9.1 The fire water
pumping requirement shall be calculated based on the following for other than
LPG pipeline installations:—
(i) Spray rate of 10.2 liter
per min per square meter (1pm/m2) of area for pump house shed based
on outer foundation column measurement (length × breadth).
(ii) Supplementary streams based
on using 4 single hydrant outlets and 1 monitor simultaneously. Capacity of
each hydrant outlet as 36 m3/hr and of each high volume monitors as 144 m3/hr
shall be considered at a pressure of 7 kg/cm2(g).
Design fire water flow rate
shall be maximum of flow rate calculated for (i) or (ii) above, whichever is
higher
7.9.2 The fire water
pumping requirement shall be calculated based on the following for LPG pipeline
installations:
7.9.3 The Fire water pumping
requirement for medium velocity spray system shall be calculated based on
following cooling rate:
(i) Pump Shed: Medium velocity
sprinkler system having remote and local operated deluge valve with spray
density 20.4 liters per min per meter square area (lpm/m2) of the
pump shed to be calculated considering outer foundation column distances.
(ii) Scraper area, Metering area
or Filtering area and receipt or delivery manifold area Medium velocity
sprinkler system with spray density 10.2 lpm/m2 of surface area
to be considered. Pump house shall be considered as single risk area.
Alternatively, it can be divided into suitable number of zones with minimum 10
meter width
7.9.4 The fire water system
in the plant shall be designed to meet the highest fire water flow requirement
of a single largest area risk at a time plus 288 m3/Hr for operating
2 Nos. of fire water monitors or supplementary hose requirements.
Note:
(i) If the pipeline
installation is having tank farm, the design fire water requirement shall be
calculated based on relevant design standards.
(ii) If the pipeline
installation is having LPG storage facilities line, horton spheres, bullets and
mounted bullets, relevant standards, to be followed for the design fire water
requirement.
7.10 Fire Water System
Design
(i) The fire water pressure
system shall be designed for a minimum residual pressure of 7.0 kg/cm2 (g)
at the hydraulically farthest point of fire water network.
(ii) A fire water ring main
shall be provided all around perimeter of the pump station and delivery or
terminal stations facilities with hydrants or monitors.
(iii) There shall be minimum two
(2) numbers of monitors located in such a way that it covers the pump area,
scrapper area and separator filter or strainer or flow meter area. Fire hydrant
network shall be in closed loops to ensure multidirectional flow in the system.
Isolation valves shall be provided where the length of the pipe section is more
than 300 meter.
7.11 Fire Water Storage
7.11.1 Water requirement
for firefighting shall be met through water storage tanks of steel or concrete
or masonry. The effective capacity of the tanks above the level of suction
point shall be minimum 4 hrs aggregate capacity of the pumps. Where make up
water supply system is 50% or more this storage capacity may be reduced to 3 hrs
of aggregate capacity of pumps.
7.11.2 Storage tank or
reservoir shall be in two interconnected compartments to facilitate cleaning
and repairs. In case of steel tanks there shall be a minimum of two tanks.
7.12 Fire Water Pumps
7.12.1
Centrifugal fire water pumps shall be installed to meet the designed fire water
flow rate and head. Pump shall have flooded suction.
7.12.2
Motor driven Jockey pump shall be installed to pressurize fire water network as
per design requirement.
7.12.3
The fire water pumps including the standby pumps shall preferably be diesel
driven. Where electric supply is reliable 50% of the pumps may be motor driven.
7.12.4
At least one standby fire water pump shall be provided for up to 2 nos. of main
pumps. For main pumps 3 nos. and above, minimum 2 nos. standby pumps of the
same type, capacity and head as the main pumps shall be provided.
7.12.5
The fire water pumps shall be provided with automatic starting facilities.
7.13 Fire Hydrant Network
7.13.1 Fire water ring main
shall be sized for 120% of the design water flow rate. Velocity of the water
shall not exceed more than 5 m/s in the fire water ring main. In case of sea
water service, the fire water main pipes shall be concrete or mortar lined
internally or thermoplastic material.
Fire water steel pipe ring
main, when installed above ground shall be at a height of 300 to 400 mm above
finished ground level and should be adequately supported at regular intervals.
Pipes made of composite material shall be laid underground. Above ground
portion of such networks shall be of carbon steel and translation shall be by
flanged connection stand post for monitors and hydrants shall be carbon steel.
7.13.2 Underground fire
water mains shall have minimum 1 m cover and shall be provided with suitable
coating or wrapping
7.13.3 Double headed
hydrants with two separate landing valves on 3” or 4” stand post shall be used.
All hydrant outlets shall be 1.2 meter above ground level or working platform
level.
7.13.4 Fire water monitors
shall be provided with independent isolation valves.
7.13.5 The deluge valve
shall be located at 15 meters from the risk being protected. A fire wall shall be
provided for the protection of the deluge valve and for operating personnel.
7.13.6 Hose Box with 2 Nos.
of hoses and a foam making branch pipe (FB-5×) or multipurpose branch or short
branch as per the requirement shall be provided between two hydrant stand
posts.
7.13.7 Fire Hydrants or
monitors shall be located at a minimum distance of 15 m from the hazardous
facility or equipment. In case of buildings this distance shall not be less
than 2 m and not more than 15 m from the face of building. Provisions of
hydrants within the building shall be in accordance with IS: 3844.
7.13.8 At least one hydrant
post shall be provided for every 30 m of external wall measurement or perimeter
of the battery limit. Monitors shall be placed at 45 m interval.
7.14 Medium Velocity
Sprinkler System
7.14.1 The medium velocity
spray system provided at all critical areas shall have spray nozzles directed
radially to the facilities intended for cooling at a distance of 0.6 m from the
surface of the equipment or facility. Only one type and size of spray nozzle
shall be used in a particular facility.
7.14.2 All spray nozzles
shall be inspected for proper positioning, corrosion and cleaned if necessary
at intervals not more than 12 months or earlier based on actual experience. Care
shall be taken in positioning nozzles so that water spray does not miss the
targeted surface and not reduce the efficiency or calculated discharge rate.
7.15 Gas Monitoring System
(i) The Gas Monitoring system
shall be provided for early warning on build up of dispersed gas concentration
below LFL (lower flammable level) limits. These detectors for the gas
monitoring system shall be located close to the potential source of leakage.
(ii) The control equipment shall
be able to generate at least two alarms at different level of LEL
concentration.
(iii) The detectors shall be
located at least 0.3 meter away from potential source of leakage at height not
more than 0.3 meter from the mounting level.
(iv) Detectors shall be placed
in the pump shed and near scraper or filter, cold vent and cold flare area.
(v) Each station should have
minimum 2 Nos. of spare detectors to facilitate immediate replacement.
7.15.1 Material
Specifications
All material used in fire
water system using fresh water shall be of the type indicated below:
(i) Pipes - Carbon Steel (CS)
IS: 3589 or IS: 1239 or IS: 1978 or Composite materials as per API 15 LR or API
15 HR or its equivalent shall be used.
(ii) In case saline or brackish
water or treated effluent water is used, the fire water main of steel pipes
shall be internally cement mortar lined or glass reinforced epoxy coated or
made of pipe material suitable for the quality of water. Alternatively, pipes
made of composite materials shall be used.
(iii) Cast iron pipes shall not
be used for fire water services.
(iv) Isolation valves shall be
gate valve with open and closed indication. Material shall be cast steel for
normal water and copper nickel for saline or brackish water service.
(v) Hydrant Stand post shall be
Carbon Steel. Monitors-carbon steel or Stainless steel
(vi) Outlet valves or landing
valves-Gunmetal or Aluminum or Stainless steel or Aluminum-Zinc alloy
(vii) Fire Hose-Reinforced rubber
lined hoses (63 mm), 15 m standard length conforming to IS: 636 (type A) or Non
percolating synthetic hose (Type B) or UL or equivalent standard.
(viii) The above ground fire water
main, hydrant post shall be painted with corrosion resistant “Fire Red” paints
as per IS: 5
(ix) Hose boxes, water monitors
and hydrant outlets shall be painted with “Yellow” paint as per IS:5
7.15.2 Hoses, Nozzles and
Accessories
(i) Hose Box- 1 No. for
catering to two hydrant stand post.
(ii) Fire hoses - 2 Nos. Per
hose box - Minimum 10 Nos.
(iii) Foam making branch pipe: 1
no. in each hose box.
(iv) In addition to the nozzles
provided in the hose boxes there shall be 1 set of spare nozzles for each
category viz-Jet Nozzle with branch pipes, Fog Nozzle, Universal Nozzle, water
curtain Nozzle.
(v) Minimum 2 Nos. or 25% spare
hoses shall be stored.
7.16 Records
Besides the details
mentioned in the ASME B 31.4, petroleum and petroleum products pipelines entity
shall also maintain following records or documents:
(i) Design or specification
documents
(ii) Route maps, alignment
sheets, crossings, drawings, Piping and Instrumentation Diagrams, station
layouts Pipe Book or Installation Records
(iii) Surveillance inspection and
maintenance reports
(iv) Records and maps showing
the location of CP facilities and piping
(v) CP Monitoring report
(vi) Leak burst and repair
records
(vii) History cards of equipment
viii. Pipeline Pigging Report
(viii) Material certification
including dimension, metallurgy, DT and NDT, strength, tightness, performance
and functional report
(ix) Welding records
(x) Procedure Qualification
Record (PQR), Welding Procedure Specification (WPS) and Welder qualification
records
(xi) Third Party technical audit
report of infrastructure before liquid IN.
(xii) Commissioning reports
(xiii) Non-conformance or
deviation reports.
(xiv) Calibration records of
Inspection, Measuring and Metering and Test equipment.
SCHEDULE 1H
MISCELLANEOUS
8.1 Materials for Sour
Multiphase Service
8.1.1 NACE Standard
MR-01-75 ‘Sulphide Stress Corrosion Cracking Resistant Metallic Materials for
Oil Field Equipment defines limiting concentrations on hydrogen sulphide in the
fluid transported’ for it to be considered as sour service.
Note:
While past experience has
indicated this to be the accepted minimum concentration at which sulphide
stress corrosion cracking may occur, the presence of other constituents in the
phases making up the multiphase fluid, such as carbon dioxide in the gas and
salt in the water or larger amounts of free water or gas, may cause problems to
occur at lower concentrations of hydrogen sulphide.
8.1.2 In addition to the
applicable requirements of ASME B31.4 and this standard, all materials used in
sour multiphase service shall meet the following requirements.
(i) Pipe, valve, fittings,
flanges bolting and other equipment exposed to or which are necessary to
contain sour multiphase fluids may be susceptible to stress corrosion cracking
and hydrogen induced stepwise cracking and thus due consideration shall be
given to material selection in design.
(ii) All Materials used for sour
multiphase service shall conform to the requirements of NACE Standard MR-01-
75, ‘Sulphide Stress Corrosion Cracking Resistant Metallic Material for Oil
Field Equipment’. Depending upon the service and the materials involved, the
additional tests for Sulphide Stress Corrosion Cracking (SSCC) and Hydrogen
Induced Cracking (HIC) as specified in NACE standards MR-01-75 and TM-02-84
respectively, should also be conducted for long and short term behavior of
material under corrosive environments.
(iii) Pressure containing
components (excluding pipe) intended for sour multiphase service shall be fully
identified with a permanent marking.
Annexure – I
Minimum
Inter Distances for Various Station Facilities (Other than LPG)
S. No. |
From or To |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
Booster or Mainline Pump Shed |
X |
16 |
× |
16 |
30 |
30 |
30 |
16 |
30 |
30 |
× |
× |
× |
× |
2 |
Scraper Launcher or Receiver |
16 |
× |
× |
16 |
30 |
16 |
16 |
16 |
30 |
16 |
× |
× |
× |
× |
3 |
Filters or Metering or Sampling point or Sump
Tanks |
× |
× |
× |
16 |
30 |
16 |
30 |
16 |
30 |
16 |
× |
× |
× |
× |
4 |
Control Room UPS or SCADA-Telecom or Office
building |
16 |
16 |
16 |
× |
16 |
16 |
× |
× |
30 |
× |
16 |
16 |
16 |
16 |
5 |
Fire Pump House or Fire water storage tanks |
30 |
30 |
30 |
16 |
× |
12 |
× |
16 |
60 |
× |
× |
30 |
30 |
30 |
6 |
Compound Wall |
30 |
16 |
16 |
16 |
12 |
× |
× |
6 |
16 |
× |
5 |
16 |
16 |
16 |
7 |
Elect Substation or Switch Yard or Transformers |
30 |
16 |
30 |
× |
× |
× |
× |
× |
# |
# |
16 |
30 |
30 |
30 |
8 |
Motor Control Centre or Power Control Centre or
Variable Frequency Drive |
16 |
16 |
16 |
× |
16 |
6 |
× |
× |
# |
# |
16 |
16 |
30 |
30 |
9 |
API Oil Water Separators (open type) |
30 |
30 |
30 |
30 |
60 |
16 |
# |
# |
× |
# |
× |
30 |
30 |
× |
10 |
Service Building (Stores or Amenities) |
30 |
16 |
16 |
× |
× |
× |
# |
# |
# |
× |
16 |
16 |
16 |
16 |
11 |
Station Block Valves |
× |
× |
× |
16 |
× |
5 |
16 |
16 |
× |
16 |
× |
× |
× |
× |
12 |
Metering System |
× |
× |
× |
16 |
30 |
16 |
30 |
16 |
30 |
16 |
× |
× |
× |
× |
13 |
Sump Tank (U/G) |
× |
× |
× |
16 |
30 |
16 |
30 |
30 |
30 |
16 |
× |
× |
× |
× |
14 |
API Separator (closed type) |
× |
× |
× |
16 |
30 |
16 |
30 |
30 |
X |
16 |
× |
× |
× |
× |
Notes:
(I) All distances are in
meters. All distances shall be measured between the nearest points on the
perimeter of each facility.
(II) #-Safety distances as per
OISD-STD-118.
(III) For other station
facilities not covered in the above shall be governed by OISD-STD-118.
(IV) ×-Any distance suitable for
constructional and operation convenience.
(V) Firewater hydrant or
monitors shall be installed at a minimum 15 m away from the equipment or
facilities to be protected.
(VI) For the distance from
compound wall, the distance mentioned in this table and the requirement of
local bylaws (if any) whichever is higher shall govern.
(VII) At pipeline's loop line
terminal location, distance between scraper barrel and compound wall shall not
be less than 5 meter.
(VIII) For SV station (motor
operated) distance between sectionalizing valve to premise boundary shall be
minimum 5 meter. All other safety distances at SV or CP stations to be kept as
per operational requirement and applicable local statutory authorities.
Annexure – II
List
of Specifications of Piping Materials used in Petroleum and Petroleum Products
Pipeline
Standard Number |
Title of Standard |
Steel Pipe |
|
API 5L : 2012 |
Specification for Line pipes |
ASTM A106 : 2014 |
Standard Specification for Seamless Carbon steel
Pipe for High Temperature service |
ASTM A333 : 2013 |
Seamless and Welded Steel Pipe for
Low-Temperature Service and Other Applications with Required Notch Toughness |
Valves |
|
API SPEC 6D : 2014 |
Specification for Pipeline and Pipeline Valves |
ISO - 14313 : 2007 |
Petroleum and natural gas industries -- Pipeline
transportation systems -- Pipeline Valve |
ASME B16.34 : 2013 |
Valves Flanged, Threaded and Welding End |
BS EN ISO 15761 : 2002 |
Steel gate, globe and check valves for sizes DN
100 and smaller for the petroleum, and natural gas industries. |
ISO 17292 : 2004 |
Metal ball valves for petroleum, petrochemical
and allied industries. |
BS 1873 : 1975 |
Specification for Steel globe and globe stop and
check valves (flanged and butt-welding ends) for the petroleum, petrochemical
and allied industries. |
Flanges and Blanks |
|
ASME B16.5 : 2013 |
Pipe flanges and flanged fittings - NPS 1/2 inch
through NPS 24 Metric/Inch Standard |
ASME B16.36 : 2009 |
Orifice Flanges |
MSS SP-44 : 2006 |
Steel Pipeline Flanges |
Fittings |
|
ASME B16.9 : 2012 |
Factory-Made Wrought Butt welding Fittings |
MSS SP-75 : 2014 |
High Strength, Wrought, Butt Welding Fittings |
MSS SP 97 : 2012 |
Integrally Reinforced Forged Branch Outlet
Fittings - Socket Welding, Threaded and Butt welding Ends. |
IS 1239 (PART 2) : 2011 |
Steel Tubes, Tubular and Other Wrought Steel
Fittings-Specification-part 1: Mild Steel Tubular and other wrought steel
pipe fittings. |
Stud Bolts and Nuts |
|
ASTM A194 : 2014 |
Standard Specification for Carbon and Alloy Steel
Nuts for Bolts for High Pressure or High Temperature Service, or Both.' |
ASTM A193 : 2014 |
Standard Specification for Alloy-Steel and
Stainless Steel Bolting for High Temperature or High Pressure Service and
Other Special Purpose Applications. |
ASTM A153 : 2009 |
Standard Specification for Zinc Coating (Hot-Dip)
on Iron and Steel Hardware. |
ASME B18.2.1 : 2012 |
Square, Hex, Heavy Hex and Askew Head Bolts and
Hex, Hex Flange, Lobed Head and Lag Screws (Inch Series). |
ASME B18.2.2 : 2010 |
Nuts for General Applications: Machine Screw
Nuts, Hex, Square, Hex Flange, and Coupling Nuts (Inch Series) |
Gaskets |
|
ASME B16.20 : 2012 |
Metallic gaskets for pipe flanges: Ring joint,
Spiral wind and Jacketed. |
High Pressure SS Tubing and Fittings |
|
ASTM A269 : 2014 |
Standard Specification for Seamless and Welded
Austenitic Stainless Steel Tubing for General Service. |
Pressure Safety Valve and Pressure Measuring
Equipment |
|
API 526 : 2009 |
Flanged Steel Pressure Relief Valves |
BS EN 837-1 : 1998 |
Pressure gauges - Part 1: Bourdon tube pressure
gauges; dimensions, metrology, requirements and testing. |
BS EN 837-2 : 1998 |
Pressure Gauges - Part 2: Selection and
Installation Recommendations for Pressure Gauges. |
BS EN 837-3 : 1998 |
Pressure gauges - Part 3: Diaphragm and capsule
pressure gauges. Dimensions, metrology, requirements and testing. |
ASME Section VIII : 2010 |
Boiler and Pressure Vessel Code: Rules for
Construction of Pressure Vessels : Filters |
Annexure – III
Additional
Requirements for Electric Welded Pipes
Electric Welded pipes shall
meet following requirements.
Reverse
Bend Tests
Reverse bend tests shall be
performed on the pipe piece cut from the crop end, selected from the front end
of the first length and the back end of the last length produced from each
coil. The specimen shall be 100 mm to 115 mm long and shall be reverse bend
tested in accordance with procedure given below:
Selection of Mandrel
The reverse bend test shall
be carried out with a mandrel, whose radius (R), width (A) shall be calculated
for any combination of diameter, wall thickness and grade with the formula:
Where, D - Outside diameter
of pipe
t - Wall thickness of pipe
1.4 - Peaking factor
e - Strain
Minimum values of ‘e’ shall
be as follows:
Grade of Steel |
Min ‘e’ value |
API 5LB |
0.1375 |
API 5L ×-42 |
0.1375 |
API 5L ×-46 |
0.1325 |
API 5L ×-52 |
0.1250 |
API 5L ×- 56 |
0.1175 |
API 5L ×- 60 |
0.1125 |
API 5L ×- 65 |
0.1100 |
API 5L ×- 70 |
0.1025 |
API 5L ×- 80 |
0.0950 |
Procedure
The mandrel is to be
plugged into the specimen, with the weld in contact with mandrel, to such a
depth that the angle of engagement between mandrel and specimen reaches 600 (see
Fig. above). If the combination of diameter and wall thickness of pipe and
radius of mandrel is such that the angle of engagement does not reach 600,
the mandrel shall be plugged into the specimen until opposite walls of the
specimen meet.
Acceptance
Criteria
A specimen which fractures
completely prior to the specified engagement of mandrel and specimen, or which
reveals cracks and ruptures in the weld or heat affected zone longer than 4 mm,
shall be rejected. Cracks less than 6 mm long at the edges of the specimen
shall not be cause for rejection.
Micrographic
and Hardness Examination
A test specimen shall be
taken across the longitudinal weld from one length of finished pipe from each
lot of maximum 100 lengths from the same heat manufactured from the same
process.
These specimens shall be
polished and etched for micro-examinations. The examinations shall provide
evidence that heat treatment of weld zone is adequate and there is no
untempered martensite left.
The Manufacturer shall make
hardness measurements on each specimen as indicated in Fig. below in accordance
with ASTM E-32. The maximum difference in hardness between base material and
any reading taken in the heat affected zone shall be less than 80 points
Vicker's HV10.
Location
where hardness measurement to be carried out
Annexure – IV
List
of Applicable Standards and References
Standard Number |
Title of Standard |
ASME B31.4 : 2009 |
Pipeline Transportation Systems for Liquid
Hydrocarbons and Other Liquids. |
API 1102 : 2007 |
Steel Pipelines Crossing Railroads and Highways. |
API 1104 : 2013 |
Welding of Pipelines and Related Facilities. |
API 1109 : 2010 |
Marking Liquid Petroleum Pipeline Facilities. |
API 1110 : 2013 |
Recommended Practice for the Pressure Testing of
Steel Pipelines for the Transportation of Gas, Petroleum Gas, Hazardous
Liquids, Highly Volatile Liquids, or Carbon Dioxide. |
API RP 500:2012 |
Recommended Practice for Classification of
Locations for Electrical Installations at Petroleum Facilities Classified as
Class I, Division I and Division 2(viii) API- 5L 2012, Standard Specification
for Line pipes. |
API SPEC 6D : 2014 |
Specification for Pipeline and Pipeline Valves(x)
ASME Section VIII;, 2013, Boiler and Pressure Vessel Code Division 1 Pressure Vessels Division 2 Alternate Rules for Pressure Vessels |
ASME Section IX: 2013 |
Welding, Brazing, and Fusing Qualifications:
Qualification Standard for Welding, Brazing, and Fusing Procedures; Welders;
Brazers; and Welding, Brazing and Fusing Operators. |
MSS-SP-58 : 2009 |
Pipe Hangers and Supports - Materials, Design,
Manufacture, Selection, Application, and Installation. NACE-SP 01-69; 2013,
Control of External Corrosion on Underground or Submerged Metallic Piping
Systems. |
NACE-SP-01-06 : 2006 |
Control of Internal Corrosion in Steel Pipelines
Systems. |
ISAS-75.01 : 2012 |
Flow evaluation for sizing control valve |
ISAS-75.02 : 1996 |
Control valve test procedure |
IEC-60079 : 2011 |
Electrical Apparatus for Explosive Gas
Atmosphere. |
IEC-60529 : 2013 |
Degree of protection Provided by Enclosures. |
OISD-STD- 118:2008 |
Layouts for Oil and Gas Installations. |
OISD-STD-141 : 2012 |
Design and Construction requirements for cross
country hydrocarbon pipelines. |
IS-5572 : 2009 |
Classification of hazardous areas (other than
mines) having flammable gases and vapours for electrical installation. |
IS-5571 : 2009 |
Guide for selection of Electrical Equipment for
Hazardous Area (other than mines). |
IS 3043 : 1987 |
Code of practice for earthing |
IS:2309 : 1989 |
Code of practice for the protection of buildings
and allied structures against lightning [ETD 20: Electrical Installation]. |
ISO 14313 : 2007 |
Petroleum and natural gas industries-Pipeline
transportation systems - Pipeline valves. |
NACE SP-0177 : 2014 |
Mitigation of Alternating Current and Lightning
Effects on Metallic Structures and Corrosion Control System. |
APPENDIX
List
of Critical Activities
In
Petroleum and Petroleum Products Pipelines
Sr. No. |
Critical Infrastructure or Activity or Processes |
Time period for Implementation and Compliance |
Implementation plan |
1 |
Test record for radiography, ultrasonic test or
other applicable NDT methods (as carried out before commissioning) |
6 months |
to be complied within 6 months |
2 |
Hydro-test (as carried out before commissioning)
Report as per Regulation 7(3) |
6 months |
to be complied within 6 months |
3 |
Pipeline cathodic protection record |
6 months |
to be complied within 6 months |
4 |
Pipeline As-built records |
6 months |
to be complied within 6 months |
5 |
Intelligent pigging shall be carried out to
detect metal loss for the pipelines of size 6 inch (168.3 mm) and above and
length of 10 Km and above. |
2 years |
If the pigging has not been done for more than 5
years for sour liquid petroleum and petroleum products pipelines and 10 years
for other liquid petroleum and petroleum products pipelines, then, the
intelligent pigging shall be carried out within two years, otherwise relevant
records shall be submitted. |
6 |
HSE Management System (including fire protection
system) |
6 months to 12 months |
To be implemented |
7 |
Environmental friendly fire extinguishing system
for closed space. |
1 year |
For control room, switch gear and battery room,
etc. (CO2 is acceptable only for unmanned station) |
8 |
HAZOP shall be done for all the pipeline
facilities |
|
HAZOP to be carried out and mitigation plan to be
implemented |
Note: For Sr. No. 1, 2 and 4,
if documents are not available or maintained, certification by the Pipeline
Head to be submitted.