Petroleum and Natural Gas Regulatory Board
(Technical Standards and Specifications including Safety Standards for
Liquefied Natural Gas Facilities) Regulations, 2018
Petroleum and Natural Gas
Regulatory Board (Technical Standards and Specifications including Safety
Standards for Liquefied Natural Gas Facilities) Regulations, 2018
[18th
January, 2018]
In exercise of the powers
conferred by Section 61 of the Petroleum and Natural Gas Regulatory Act, 2006
(19 of 2006), the Petroleum and Natural Gas Regulatory Board hereby makes the
following Regulations, namely:—
Regulation - 1. Short title and commencement.
(1) These regulations may be
called the Petroleum and Natural Gas Regulatory Board (Technical Standards
and Specifications including Safety Standards for Liquefied Natural Gas
Facilities) Regulations, 2018.
(2) They shall come into force
on the date of their publication in the Official Gazette.
Regulation - 2. Definitions.
(1) In these regulations,
unless the context otherwise requires,—
(a) “Act” means the Petroleum
and Natural Gas Regulatory Board Act, 2006;
(b) “Board” means the Petroleum
and Natural Gas Regulatory Board established under sub-section (1) of Section 3
of the Act;
(c) “Boil off gas” (BOG) means
the gas produced due to vaporisation of cryogenic liquid by heat conducted
through the insulation;
(d) “bunkering” means the
loading of a ship's bunker or tank with liquid fuel for use in connection with
propulsion or auxiliary equipment;
(e) “container” means a vessel
for storing liquefied natural gas - such a vessel may be above, partially
below, or totally below ground and may consist of an inner and outer tank;
(f) “container, pre-stressed
concrete” means a concrete container which is considered to be pre-stressed
when the stresses created by the different loading or loading combinations do
not exceed allowable stresses;
(g) “compressed gas” means any
permanent gas, liquefable gas, or cryogenic liquid under pressure or gas
mixture which in a closed pressure vessel exercise a pressure exceeding one
atmosphere (gauge) at the maximum working temperature and includes Hydrogen
Fluoride. In case of vessel without insulation or refrigeration, the maximum
working temperature shall be considered as 55°C;
(h) “critical temperature”
means the temperature above which gas cannot be liquefied by the application of
pressure alone;
(i) “cryogenic liquid” means
liquid form of permanent gas having normal boiling point below minus 150 0C;
(j) “cryogenic pressure vessel”
means a pressure vessel irrespective of water capacity intended for storage or
transportation of cryogenic liquid and includes cold converters, vacuum
insulated vessels, vacuum insulated storage or transport tanks and thermosyphon
tanks”;
(k) “design” includes drawings,
calculations, specifications, codes and all other details necessary for
complete description of the pressure vessel and its construction;
(l) “design pressure” means the
pressure used in the design of equipment, a container, or a vessel for the
purpose of determining the minimum permissible thickness or physical
characteristics of its different parts. Where applicable, static head shall be
included in the design pressure to determine the thickness of any specific
part;
(m) “dyke” means a structure
used to establish an impounding area;
(n) “Emergency Release Coupler”
(ERC) means the coupler fitted in each arm together with quick - acting
flanking (double blocked) valves so that a dry-break release can be achieved in
emergency situations;
(o) “Emergency Shutdown System”
(ESD) means a system that safely and effectively stops whole plant or an
individual unit during abnormal situation or in emergency;
(p) “failsafe” means a design
feature that provides for the maintenance of safe operating conditions in the
event of a malfunction of control devices or an interruption of an energy
source;
(q) “fired equipment” means any
equipment in which the combustion of fuels takes place and includes, among
others, fired boilers, fired heaters, internal combustion engines, certain
integral heated vaporisers, the primary heat source for remote heated vaporisers,
gas-fired oil foggers, fired regeneration heaters and flared vent stacks;
(r) “flammability range” means
the difference between the minimum and maximum percentage by volume of the gas
in mixture with air that forms a flammable mixture at atmospheric pressure and
ambient temperature;
(s) “gas free” means the
concentration of flammable or toxic gases or both if it is within the safe
limits specified for persons to enter and carry out hot work in such vessels;
(t) “hazardous fluid” means a
LNG or liquid or gas that is flammable or toxic or corrosive;
(u) “ignition source” means any
item or substance capable of an energy release of type and magnitude sufficient
to ignite any flammable mixture of gases or vapours that could occur at the
site;
(v) “impounding basin” means
impounding basin container within or connected to an impounding area or spill
collection area where liquid hydrocarbon spills can be collected and safely
confined and controlled;
(w) “impounding area” means an
area that may be defined through the use of dykes or the topography at the site
for the purpose of containing any accidental spill of LNG or flammable
refrigerants;
(x) “Liquefied Natural Gas”
(LNG) means a fluid in the liquid state composed predominantly of methane (CH4)
and which may contain minor quantities of ethane, propane, nitrogen, or other
components normally found in natural gas;
(y) “LNG facility” means a
group of one or more units or facilities, that is, unloading or loading,
storage, regasification, associated systems like utilities, blow down, flare system,
fire water storage and fire water network, control room and administration
service buildings like workshop, fire station, laboratory, canteen etc.;
(z) “Maximum Allowable Working
Pressure” means the maximum gauge pressure permissible at the top of equipment,
a container or a pressure vessel while operating at design temperature;
(aa)
“NDT” means Non Destructive Testing
methods like Dye Penetration Inspection, Wet Fluorescent Magnetic Particle
Inspection, Ultrasonic thickness checks, Ultrasonic Flaw Detection,
Radiography, Hardness Test and other relevant Inspection procedures carried out
to detect the defects in the welds and parent metal of the pressure vessel;
(bb)
“pressure vessel” means any closed metal
container of whatever shape, intended for the storage and transport of any
compressed gas which is subjected to internal pressure and whose water capacity
exceeds one thousand liters and includes inter connecting parts and components
thereof upto the first point of connection to the connected piping and
fittings;
(cc)
“primary components” include those whose
failure would permit leakage of the LNG being stored, those exposed to a
temperature between (−51°C) and (−168°C) and those subject to thermal shock but
shall not be limited to the following parts of a single-wall tank or of the
inner tank in a double-wall tank, namely, shell plates, bottom plates, roof
plates, knuckle plates, compression rings, shell stiffeners, manways, and
nozzles including reinforcement, shell anchors, pipe tubing, forging, and
bolting. These are the parts of LNG containers that are stressed to a
significant level;
(dd)
“process plant” means the systems
required to condition, liquefy or vaporise natural gas in all areas of
application;
(ee)
“safety relief device” means an automatic
pressure relieving device actuated by the pressure upstream of the valve and
characterized by fully opened pop action intended to prevent the rupture of a
pressure vessel under certain conditions of exposure;
(ff)
“secondary components” include those
which will not be stressed to a significant level, those whose failure will not
result in leakage of the LNG being stored or those exposed to the boil off gas
and having a design metal temperature of (−51°C) or higher;
(gg)
“source of ignition” means naked lights,
fires, exposed incandescent materials, electric welding arcs, lamps, other than
those specially approved for use in flammable atmosphere, or a spark or flame
produced by any means;
(hh)
“transfer area” is that portion of an LNG
plant containing piping systems where LNG, flammable liquids, or flammable
refrigerants are introduced into or removed from the facility, such as ship
unloading areas, or where piping connections are routinely connected or
disconnected. Transfer areas do not include product sampling devices or
permanent plant piping;
(ii)
“transfer system” includes transfer
piping and cargo transfer system;
(jj)
“vaporiser” means a heat transfer
facility designed to introduce thermal energy in a controlled manner for
changing a liquid to vapour or gaseous state;
(kk)
“vessel” means a pressure vessel and
includes a cryogenic pressure vessel;
(ll)
“water capacity” means capacity in
litres of the pressure vessel when completely filled with water at 15°C;
(2) Words and expressions used
and not defined in these regulations, but defined in the Act or in the rules or
regulations made thereunder, shall have the meanings respectively assigned to
them in the Act or in the rules or regulations, as the case may be;
Regulation - 3. Application.
Definitions of design,
material and equipment, piping system components and fabrication, installation
and testing, commissioning, corrosion control, operation and maintenance and
safety of LNG facilities including jetty facilities shall be in accordance with
the requirements of these regulations.
Regulation - 4. Scope.
(1) Requirements of these
regulations shall apply to all LNG facilities including terminals.
(2) These regulations lay down
minimum requirements of layout within the plant boundary for unloading or loading,
storage, regasification, transfer and handling and tank truck loading
facilities for LNG facilities.
(3) These regulations covers
safety in design and operational aspects of process systems, storage tanks,
regasification facilities, ship shore interlock, berthing conditions for the
ship, receiving facilities including jetty and port.
(4) These regulations also
cover engineering considerations in design, operations, maintenance, inspection
and installations including fire protection and safety systems.
Regulation - 5. Objective.
These standards are
intended to ensure uniform application of design principles and to guide in
selection and application of materials and components, equipment and systems
and uniform operation and maintenance of the LNG terminals or facilities and
shall primarily focus on safety aspects of the employees, public and facilities
associated with LNG terminals.
Regulation - 6. The standard.
Technical standards and
specifications including safety standards (hereinafter referred to as standards)
for Liquefied Natural Gas Facilities shall be as specified in Schedule - 1
which cover design and layout, electrical systems, process system, maintenance,
inspection, competency assessment, fire prevenvtion, leak detection, fighting
system and safety management system.
Regulation - 7. Compliance to these regulations.
(1) The Board shall monitor the
compliance to these regulations either directly or through an accredited third
party as per separate regulations on third party conformity assessment.
(2) Any entity intending to set
up LNG facilities shall make available its detailed plan including design
consideration conforming to these regulations to PESO for their approval prior
to seeking registration with the Board.
(3) If an entity has laid,
built, constructed, under construction or expanded the LNG terminal based on
some other standard or is not meeting the requirements specified in these
regulations, the entity shall carry out a detailed Quantitative Risk Analysis
(QRA) of its infrastructure. The entity shall thereafter take approval from its
Board for non-conformities and mitigation measures. The entity's Board approval
along with the compliance report, mitigation measures and implementation
schedule shall be submitted to the Board within six months from the date of
notification of these regulations.
Regulation - 8. Default and Consequences.
(1) There shall be a system for
ensuring compliance to the provision of these regulations through conduct of
technical and safety audits during the construction, commissioning and
operation phase.
(2) In case of any deviation or
shortfall including any of the following defaults, the entity shall be given
time limit for rectification of such deviation, shortfall, default and in case
of non-compliance, the entity shall be liable for any penal action under the
provisions of the Act or termination of operation or termination of
authorization.
Regulation - 9. Requirements under other statutes.
It shall be necessary to
comply with all statutory rules, regulations and Acts in force as applicable
and requisite approvals shall be obtained from the relevant competent
authorities for LNG facilities.
Regulation - 10. Miscellaneous.
(1) If any question arises as
to the interpretation of these regulations, the same shall be decided by the Board.
(2) The Board may at any time
effect appropriate modifications in these regulations.
(3) The Board may issue
guidelines consistent with the Act to meet the objective of these regulations
as deemed fit.
SCHEDULE 1
(see
Regulation 6)
Schedule – 1A: DESIGN AND
LAYOUT OF FACILITIES
Schedule – 1B: ELECTRICAL
SYSTEMS
Schedule – 1C: PROCESS
SYSTEM
Schedule – 1D: MAINTENANCE
AND INSPECTION
Schedule – 1E: COMPETENCY
ASSURANCE AND ASSESSMENT
Schedule – 1F: FIRE
PREVENTION, LEAK DETECTION AND FIGHTING SYSTEM
Schedule – 1G: SAFETY
MANAGEMENT SYSTEM
Schedule - 1A
1.0 DESIGN AND LAYOUT OF
FACILITIES
1.1. Philosophy
LNG Terminal lay out
philosophy must consider location of the facilities at a site of suitable size,
topography and configuration with a view to designing the same to minimise the
hazards to persons, property and environment due to leaks and spills of LNG and
other hazardous fluids at site. Before selecting a site, all site related
characteristics which could affect the integrity and security of the facility
shall be determined. A site must provide ease of access so that personnel,
equipment, materials from offsite locations can reach the site for firefighting
or controlling spill associated hazards or for the evacuation of the personnel.
1.2. Basic Information
1.2.1. Information on
following items should be collected before proceeding with the development of
overall plot plan.
(i)
Terminal
capacity
(ii)
Process
units and capacities
(iii)
Process
flow diagram indicating flow sequence
(iv)
Utility
requirements
(v)
Unloading
system along with tanker berthing system with capacity
(vi)
LNG
storage tanks, sizes and type of storage tanks
(vii)
Other
storage tanks
(viii)
LNG
transfer and vaporization
(ix)
Tank
truck loading/unloading
(x)
No.
of flares
(xi)
Provision
for spill containment and leak control
(xii)
Inter
distances between the equipment
(xiii)
Operating
and maintenance philosophy for grouping of utilities
(xiv)
Plant
and non-plant buildings
(xv)
Environmental
considerations
(xvi)
Fire
station
(xvii) chemical storage
(xviii)
Ware
house and open storage areas.
1.2.2. Information related
to each item should include, but not limited to, following:
(i)
Extreme
temperatures and pressures for normal operations as well as emergency
conditions.
(ii)
Concrete
structures subject to cryogenic temperatures
(iii)
Fail
safe design
(iv)
Structural
requirement
(v)
Requirement
of dyke and vapour barrier
(vi)
Shut
off valves and relief devices.
1.2.3. Data on terminal and
infrastructure facilities should be identified and collected before detailed
layout activity is taken up. Due consideration should be given while
deciding/finalising terminal layout to the following:
(i)
Site
location map
(ii)
Seismic
characteristics and investigation report.
(iii)
Soil
characteristics
(iv)
Prevailing
wind speed and direction over a period
(v)
Meteorological
data including corrosive characteristics of the air and frequency of lightening
(vi)
Area
topography contour map
(vii)
High
flood level in the area and worst flood occurrence.
(viii)
Source
of water supply and likely entry/exit point
(ix)
Electric
supply source and direction of entry point
(x)
LNG
entry point/Gas exit point
(xi)
Minimum
inter distances between facilities as well as between facilities &
boundaries
(xii)
Storm
water disposal point and effluent disposal point
(xiii)
Approach
roads to main Terminal areas
(xiv)
Surrounding
risks
(xv)
Air
routes and the proximity of the Airports.
(xvi)
Environment
impact assessment
1.2.4. Emergency
communications equipment shall not be adversely affected by the operation of
other devices/equipment in close proximity (electromagnetic compatibility).
Emergency communications equipment shall not create additional hazards during
an emergency situation GA control systems to be protected against fire, blast
and credible accident events, by location or otherwise, such that its ability
to function is not impaired for the time taken to muster after a major accident
event.
1.2.5. Facilities with the
potential to generate waste e.g. process waste water, sanitary sewage or storm
water should incorporate necessary precautions to avoid, minimize and control
adverse impacts to health, safety or the environment.
1.2.6. Plans shall be
developed that considers prevention, reduction, reuse, recovery, recycling,
removal and disposal of wastes (including hazardous waste) generated during all
project phases and modes of operation.
1.2.7. The project to
address potential environmental impacts on existing conditions such as surface,
groundwater and soils.
1.2.8. Plans shall be
developed to minimize or reduce emissions as far as reasonably practicable,
resulting from commissioning, testing activities and operation.
1.2.9. All escape routes
including emergency exit doors to be readily accessible, non-slip, marked,
signposted and clear of obstructions.
1.2.10 Markings and signs to
be clearly visible if there is loss of artificial lighting outside daylight
hours.
1.2.11 All escape doors
shall be of a type that can easily be opened in an emergency situation.
1.2.12 Rescue breathing
apparatus sets and other equipment necessary shall be located at strategic
locations around the facilities to allow prompt rescue of personnel.
1.2.13 The communication
systems shall be protected by, location of equipment, spatial diversity and
equipment redundancy. Internal and external telecommunications in order to
perform the emergency function defined by project requirements shall be
confirmed between the Control Room, vessel/s and storage/pumping locations and
Muster area.
1.2.14 PA/GA cables should
be located so that they are protected against accidental loads as far as
possible and shall be fire resistant to specifications. PA/GA system shall
provide a means of alerting all personnel to the existence of an emergency
situation, provide the means to communicate additional information to personnel
during an emergency and shall be capable of operating without impairment for
the minimum time required to escape to muster locations and then to evacuate to
a place of safety after the start of a major accident.
1.2.15 The provision and
minimum alarm noise level above local ambient is in accordance with design
requirements. In areas with greater ambient noise levels, visual alarms shall
also be provided.
1.3. Blocks
1.3.1. In addition to points
indicated in (NFPA 59A), as applicable, containment of potential spills of LNG
or other hazardous liquid, especially in case of LNG storage and jetty area
should also be considered.
1.3.2. Layout of
Blocks/Facilities
The LNG may consist of the following
basic blocks/facilities:
(i)
The
Jetty for berthing of ship and unloading/loading of LNG.
(ii)
Unloading/loading
line from Jetty to shore terminal.
(iii)
LNG
Storage
(iv)
Re-gasification
consisting of pumping and vaporisation.
(v)
Tank
truck loading/unloading
(vi)
Utility
Block
(vii)
Fire
Station
(viii)
Flare
system
(ix)
Control
Room
(x)
Administrative
Block
(xi)
Workshop
(xii)
Warehouse
(xiii)
Electrical
Substation.
(xiv)
Laboratory
(xv)
Road
loading
1.4. Roads
Access to the moored ships
shall be provided. If necessary, a separate road should lead to the berths in
order to provide the crew with a free access to the ship.
(i)
All
process units and dyked enclosures of storage tanks shall be planned in
separate blocks with roads all around for access and safety.
(ii)
Primary
traffic roads in the installation should be outside hazardous areas. Roads
separating the blocks shall act as firebreaks.
(iii)
Pedestrian
pathways should be provided/marked alongside the primary traffic roads.
(iv)
Alternative
access shall be provided for each facility so that it can be approached for
fire fighting in the event of blockage on one route.
(v)
Road
widths, gradient and turning radii at road junctions shall be designed to
facilitate movement of the largest fire-fighting vehicle in the event of
emergency.
(vi)
Layout
of the facilities shall be made to minimize truck traffic ingress in the plant.
(vii)
Two
road approaches from the highway/major road should be provided. Both these
approaches should be available for receipt of assistance in emergency.
(viii)
Conflict
of people movement and vehicle movement shall be avoided.
1.5. Location
(i)
The
receiving terminal should be as close as possible to the unloading jetty.
(ii)
The
location shall minimize the level of risk outside the boundary plant taking
into account adjacent existing and identified future developments
1.6. General Considerations
The layout shall consider
two specific zones i.e. Gas Zone and Non-Gas Zone and identify the applicable
blocks within each zone. Minimum inter-distances between blocks/facilities
shall be maintained as specified in the regulations or as per the risk analysis
studies whichever is higher.
1.7. Spacing requirement of
LNG Tanks and Process Equipment
1.7.1. LNG Tank Spacing
(i)
LNG
tanks with capacity more than 265 m3 should be located at
minimum distance of 0.7 times the container diameter from the property line but
not less than 30 meters. Minimum distance between adjacent LNG tanks should be
1/4 of sum of diameters of each tank. The distance between tanks should be
further reviewed in accordance with Hazard assessment, but in no case it shall
be less than the criteria mentioned above.
(ii)
Inter
distances between LNG Storage tank shall be as under:
Table - 1 Distances from Impoundment Areas to Buildings and Property Lines
|
Container Water Capacity (m3)
|
Minimum Distance from Edge of
Impoundment or Container Drainage System to Buildings and Property Lines (m)
|
Minimum distance between adjacent
containers (m)
|
|
<0.5
|
0
|
0
|
|
0.5-1.9
|
3
|
1
|
|
1.9-7.6
|
4.6
|
1.5
|
|
7.6-63
|
7.6
|
1.5
|
|
63-114
|
15
|
1.5
|
|
114-265
|
23
|
|
|
>265
|
0.7 times the container diameter but
not less than 30m
|
1/4 of the sum of the diameters of
adjacent than 1.5m
|
Table - 2 Distances from underground containers and Exposures
|
Container Water Capacity (m3)
|
Minimum Distance from Edge of
Impoundment or Container Drainage System to Buildings and Property Lines (m)
|
Minimum distance between adjacent
containers (m)
|
|
<68.1
|
4.6
|
4.6
|
|
68.1-114
|
7.6
|
4.6
|
|
>114
|
12.2
|
4.6
|
Note: i. A clear space of
at 0.9m shall be provided for access to all isolation valves serving multiple
containers.
ii. Any LNG storage/process
equipment of capacity more than 0.5 M3 shall not be located in buildings.
1.7.2. Vaporiser Spacing
Vaporisers and their
primary heat sources unless the intermediate heat transfer fluid is
non-flammable shall be located at least 15m from any other source of ignition.
In multiple vaporiser installations, an adjacent vaporiser or primary heat
source is not considered to be a source of ignition. Integral heated vaporisers
shall be located at least 30m from a property line that may be built upon and
at least 15m from any impounded LNG, flammable liquid, flammable refrigerant or
flammable gas storage containers or tanks. Remote heated, ambient and process
vaporisers shall be located at least 30m from a property line that can be built
upon. Remote heated and ambient vaporisers may be located within impounding
area. The inter distances in multiple heated vaporisers a clearance of at least
2m shall be maintained.
1.7.3. Process Equipment
Spacing
(i)
For
Process equipment spacing shall be in line with process design requirements
keeping in view the operation, maintenance and safety considerations.
(ii)
Fired
equipment and other sources of ignition shall be located at least 15m from any
impounding area or container drainage system.
The minimum separation
distances between various blocks, process units and other facilities shall be
as per Annexure-II.
1.7.4. Unloading Facilities
1.7.4.1 General
Requirements
(i)
The
LNG jetty should comply with the requirement as specified in “Site Selection
and Design for LNG Ports and Jetties”- Information paper no. 14, February 1997
and also “Liquefied Gas Handling Principles on Ships and in Terminals”
published by Society of International Gas Tankers and Terminals Operators
(SIGTTO).
(ii)
General
cargo, other than ships' stores for the LNG tanker, shall not be handled over a
pier or dock within 30m of the point of transfer connection while LNG are being
transferred through piping systems. Ship bunkering shall not be permitted
during LNG unloading operations.
(iii)
Vehicle
traffic shall be prohibited on the berth within minimum 30m of the loading and
unloading manifold while transfer operations are in progress. Warning signs or
barricades shall be used to indicate that transfer operations are in progress.
(iv)
Prior
to transfer, the officer in charge of vessel cargo transfer and the officer in
charge of the shore terminal shall inspect their respective facilities to
ensure that transfer equipment is in the proper operating condition. Following
this inspection, they shall meet and determine the transfer procedure, verify
that adequate ship-to-shore communications exist, and review emergency
procedures.
(v)
Interlocking
between ship and terminal control room to be established and the control of
unloading operations shall be monitored from the terminal control room.
(vi)
Terminal
Security. An effective security regime should be in place to enforce the
designated ignition exclusion zone and prevent unauthorised entry of personnel
into the terminal and jetty area, whether by land or by sea.
(vii)
Operating
Limits. Operating criteria, expressed in terms of wind speed, wave height and
current should be established for each jetty. Such limits should be developed
according to ship size, mooring restraint and hard arm limits. Separate sets of
limits should be established for:
(a) berthing,
(b) stopping cargo transfer,
(c) hard arm disconnection, and
(d) departure from the berth.
1.7.4.2 The ships should be
berthed in such way that in case of emergency the ship can sail out head on
immediately. All other instructions and procedures of Port Regulatory Authority
are to be observed.
(i)
A
jetty shall be earmarked for LNG unloading/loading and if other liquefied gases
and petroleum products are also proposed to be handled at the same jetty, risk
assessment shall be carried out for consideration in design basis as well as
the minimum inter distance requirements between various facilities at jetty.
Further, the minimum distance between the jetties shall be finalized based on
the risk analysis or recommendations of port authorities whichever is higher.
(ii)
The
number and size of the berths should be determined by the quantity of LNG
delivered, the size of the ships, time intervals between two ships & site
conditions. The berths may be installed either parallel or perpendicular to the
bank at the end of the jetty depending on the water depth, prevailing wind
speed and the location of the basin.
(iii)
The
berth may include either simple dolphins or sophisticated platform which
includes the unloading arms. Access to the moored ships shall be provided. if
necessary, a separate road may lead to the berths in order to provide the crew
with a free access to the ship.
(iv)
Mooring
layout. The jetty should provide mooring points of strength and in an array
which would permit all LNG carriers using the terminal to be held alongside in
all conditions of wind and currents.
(v)
Exclusion
of ignition Sources: No uncontrolled ignition source should be within a
predetermined safe area, centred on the LNG carrier's cargo manifold. The
minimum area from which all ignition sources must be excluded should be
determined from the design considerations and dispersion studies envisaged in
the risk analysis report.
(vi)
A
pier or dock used for pipeline transfer of LNG shall be located so that any
marine vessel being loaded or unloaded is at least 30m from any bridge crossing
a navigable waterway. The loading or unloading manifolds shall be at least 60m
from such a bridge.
(vii)
LNG
and flammable refrigerant loading and unloading connections shall be at least
15m from uncontrolled sources of ignition, process areas, storage containers,
control room and important plant structures. This does not apply to structures
or equipment directly associated with the transfer operation.
(viii)
Quick
Release Hooks. All mooring points should be equipped with quick release hooks.
Multiple hook assemblies should be provided at those points where multiple
mooring lines are deployed so that not more than one mooring line is attached
to a single hook.
1.8. LNG Road Tanker
Loading/Unloading Facilities
(i)
The
layout of the LNG facilities including the arrangement and location of plant roads,
walkways, doors and operating equipment shall be designed to permit personnel
and equipment to reach any area affected by fire rapidly and effectively. The
layout shall permit access from at least two directions.
(ii)
LNG
tank lorry loading gantry shall be covered and located in a separate block and
shall not be grouped with other facilities.
(iii)
Adequate
space for turning of tank Lorries shall be provided which is commensurate with
the capacities of the tank trucks. However, the space for turning of tank Lorries
with minimum radius of 20 M to be provided.
(iv)
Maximum
number of LNG tank lorry bays shall be restricted to 8 in one group. Separation
distance between the two groups shall not be less than 30 M.
(v)
The
layout of the loading location shall be such that tank truck being loaded shall
be in drive out position.
(vi)
The
weigh bridge of adequate capacity shall be provided and proper manoeuvrability
for vehicles.
(vii)
The
consideration to be given for the dedicated parking area for LNG tank trucks
with controlled access of other vehicles. The parking area shall be located in
a secured area and provided with adequate no. of hydrants/monitors to cover the
entire parking area. The suitable arrangement for safe venting of vapor
generated during waiting period in the parking area, preferably to a closed
system should be considered.
(viii)
Escape
routes shall be specified and marked in LNG plants for evacuation of employees
in emergency. Properly laid out roads around various facilities shall be
provided within the installation area for smooth access of fire tenders etc. in
case of emergency.
1.8.1. Confinement
Confined or partially
confined zones shall be avoided as far as possible, in particular:
(i)
Gas
and LNG pipe-work shall not be situated in enclosed culverts when it is
possible to avoid this for example where road bridges cross pipe ways;
(ii)
The
space situated under the base slab of raised tanks, if any, shall be
sufficiently high to allow air to circulate;
(iii)
Where
cable culverts are used they shall be filled with compacted sand and covered
with flat slabs featuring ventilation holes to minimise the possibility of
flammable gases travelling along the culverts through voids above the sand. As
the sand settles the slabs will sink. They can be restored to their original
elevation by adding sand.
1.8.2. Impounding basin
The extent of the
impounding basins and spillage collection channel for LNG and hydrocarbon
pipework and equipment shall be evaluated as a part of the hazard assessment.
In general it has been found that the collection of spill from interconnecting
LNG and hydrocarbons piping, without branch, flanges or instrument connections,
is not justified by hazard assessment. If required, it shall be designed to
accommodate potential leaks that will be identified in the hazard assessment.
Possible LNG spills should be drained into impounding basins, with foam
generators or other measures for improved evaporation control. The location of
the impounding basin with respect to adjacent equipment shall have regard to
the hazard assessment and heat flux. In addition, means for limiting
evaporation and reducing the rate of burning of ignited spills and consequences
should be considered.
1.8.3. Control Room And
Substation:
(i)
The
minimum distance of 60m shall be maintained from control room and substation to
LNG Storage Tank and process area
(ii)
In
case, control room and/or substation is within 60 metres from LNG Storage Tank
and process area due to operational requirement, it shall be made blast proof
and safety measures as recommended in risk assessment study shall be taken.
1.8.4. Buildings And
Structures
Buildings or structural
enclosures in which LNG, flammable refrigerant and gases are handled shall be
of lightweight, non-combustible construction with non-load-bearing walls.
2.0 STORAGE TANK
The Liquefied Natural gas
is stored at about -159°C to -168 °C. LNG tanks are required to be designed to
ensure proper liquid retention, gas tightness, thermal insulation and
environment safety.
2.2. Selection Criterion
2.1.1. The selection of
storage tanks shall be decided based on the location, adjacent installations,
habitation on the surrounding, operational, environmental, safety and
reliability considerations. The main criteria for selection of the type of tank
shall be decided based on the risk analysis study and the level of risk it is
posing on the surrounding.
2.1.2 The following list
summarises a number of loading conditions and considerations that have
influence on the selection of the type of storage tank.
(i)
The
factors which are not subjected to control:
(a) Wind
(b) Snow, Climate
(c) Objects flying from outside
the plant.
(ii)
The
factors that are subjected to limited control
(a) Earth quake - OBE/SSE event
(b) In plant flying objects
(c) Maintenance Hazards
(d) Pressure waves from
internal plant explosions
(e) Fire in bund or at adjacent
tank or at plant.
(f) Overfill, Overpressure
(process), block discharge
(g) Roll over
(h) Major metal failure e.g.
brittle failure
(i) Minor metal failure e.g.
leakage
(j) Metal fatigue, Corrosion
(k) Failure of pipe work
attached to bottom, shell or roof
(l) Foundation collapse.
(iii)
The
factors that are subjected to full control
(a) Proximity of other plant
(b) Proximity of control rooms,
offices and other buildings within plant
(c) Proximity of habitation
outside plant
(d) National or local authority
requirements
(e) Requirements of the applied
design codes.
2.1.3 There is no limit on
the height of the tank envisaged other than engineering and aviation
considerations.
2.1.4 No capacity
restriction for LNG tank is envisaged considering the technological
developments in this area.
2.2. The tanks shall be
designed as per EN14620 or API 620 and API 625. The impounding Area and
Drainage System and Capacity shall be in accordance with NFPA 59A.
2.3. Maximum allowable
working pressure should include a suitable margin above the operating pressure
and maximum allowable vacuum.
2.3.1. Material of
construction:
The material for various
parts of LNG container which will be in contact with LNG or cold vapour shall
be physically and chemically compatible with LNG. Any of the materials
authorised for service at (-) 168°C by the ASME Boiler and Pressure Vessel Code
shall be permitted. Normally, for single containment tank, improved 9% Ni
steel/Austenitic stainless steel/Aluminium Magnesium alloy are used. For
double, or full containment tanks, 9% Ni steel with impact testing is used. In
case of membrane tanks, normally austenitic stainless steel is used as material
of construction for membranes.
2.3.2. Liquid loading
(i)
The
maximum filling volume of LNG container must take into consideration the expansion
of the liquid due to reduction in pressure to avoid overfilling.
(ii)
For
double containment and full containment, the primary container shall be
designed for a liquid load at the minimum design temperature specified. The
design level shall be the maximum liquid level specified or the level 0.5m
below the top of the shell, whichever is lower.
(iii)
The
outer tank for Double containment, Full containment and membrane tanks, shall
be designed to contain the maximum liquid content of the primary container at
the minimum design temperature specified. Outer concrete tank shall have 9%
nickel steel secondary bottom and 9% nickel steel insulated ‘Thermal Corner
Protection’ (TCP) alternatively, austentic stainless steel can be used for
membrane tanks as specified in EN 14620. These are linked together. The top of
the TCP is anchored into pre-stressed concrete wall, at least 5 meters above
the base slab.
2.3.3. Insulation
(i)
The
LNG tanks shall be adequately insulated in order to minimise the boil off gas
generation due to heat leak from ambient. The extent of insulation depends on
boil off considerations for which the storage tank is designed. Proper
insulation shall be ensured in tank base, tank shell, tank roof, suspended deck
etc.
(ii)
The
possibility of an adjacent tank fire must be taken into consideration when
designing insulation for LNG storage tanks. Tank spacing, water deluge systems,
quantity and hazard index of LNG contents must be considered when specifying
insulating materials
2.3.4. Soil Protection
(i) The soil under the on
ground LNG storage tank shall not be allowed to become cold. To prevent such
occurrence heating system shall be provided in the foundation to maintain the
tank foundation at its coldest location within acceptable temperature range
i.e. +5°C to +10°C with an automatic on/off switch system. As an alternative to
electrical bottom heating system free ventilated tank bottom by elevated
structure is also used. Also slope shall be ensured for the paved portion below
the tank from centre to periphery to avoid accumulation of liquid. Gas
detectors shall be provided for detection of any leakage and accumulation below
the tank.
(ii) Electrical heating system
shall consist of a number of independent parallel circuits so designed that
electrical failure of any one circuit does not affect power supply to the
remaining circuits. Electrical heating shall be so designed that in the case of
electrical failure of a main power supply cable or a power transformer,
sufficient time is available to repair before damage occurs due to excessive
cooling. Alternatively, provision for connecting a standby heating power source
should be made.
2.3.5. Leak Detection
Leak detection facility
shall be provided in the space between primary container and secondary
container. Liquid may be present in the annular/insulated space due to spillage
from inner tank or leak of the inner tank. Temperature sensors shall be used
for leak detection. A system alarm shall be provided if there is a malfunction
in the monitoring system.
2.3.6. Pressure and Vacuum
relief system
The following guidelines
for the design of pressure and vacuum relief system of cryogenic LNG tanks
shall be provided;
(i)
Pressure
relief valve shall be entirely separate from the vacuum relief valve. Pressure
relief valve shall relieve from inner tank. In order to take care of
mal-function/maintenance of any of the relief valves due to blockage in the
sensor line, one extra relief valve (n+1) shall be installed. Pilot operated
pressure relief valves are preferred over pallet operated relief valves.
Suitable system/mechanical interlocks shall be provided to ensure that the
requisite no of PRV in line all the time.
(ii)
Vacuum
relief valves (n+1 philosophy) shall relieve into the space between the outer
roof and suspended roof. Pilot operated vacuum relief valves are not acceptable
for vacuum protection as the valve action is not fail safe against main valve
diaphragm or bellows rupture. Conventional pallet type vacuum relief valves
shall only be used. Suitable system/mechanical interlocks shall be provided to
ensure that the requisite no of VRV in line all the time.
(iii)
Relief
valves or rupture disc to atmosphere should be adequately sized which shall be
capable of discharging flow rates from any likely combination of the following:
(a) evaporation due to heat
input in tank, equipment and recirculation lines;
(b) displacement due to filling
at maximum possible flow-rate or return gas from carrier during loading;
(c) flash at filling;
(d) variations in atmospheric
pressure;
(e) vapourised LNG in de-super
heaters;
(f) recirculation from a
submerged pump;
(g) roll-over.
to relieve the worst case
emergency flows, assuming that all outlets from the tank are closed, including
the outlet to flares and also boil off gas. Vapours may safely be disposed to
atmosphere, provided that this can be accomplished without creating problems
like, formation of flammable mixture at ground level or on elevated structure
where personnel are likely to be present and in no case it shall be less than
3m from nearest platform.
(iv)
Provision
shall be made to inject nitrogen or dry chemical powder at the mouth of
pressure safety relief valve discharge.
(v)
Vacuum
relief should be based on: withdrawal of liquid at the maximum rate, withdrawal
of vapour at the maximum compressor suction rate, variation in atmospheric
pressure etc.
(vi)
A
hot flare shall be provided for system to maintain pressure. The flare stack
should be continuously purged in order to avoid air ingress and shall be
provided with pilot burner.
(vii)
Provision
shall be made to maintain the internal pressure of LNG container within the
limits set by the design specification by releasing to flare via a pressure
control valve installed in the BOG line from tank to compressor. Factors that
shall be considered in sizing of flare system shall include the following:
(viii)
Operational
upsets, such as failure of control device/BOG compressor tripping etc.
(ix)
Vapour
displacement and flash vaporisation during filling
(x)
Drop
in barometric pressure
(xi)
Reduction
in vapour pressure resulting from the introduction of sub cooled LNG into
vapour space.
(xii)
For
the pressurised systems, the safety relief valve vent shall be so positioned to
release the hydrocarbon at safe height.
(xiii)
Relief
from tank PSV shall not form a cloud on the tank and the PSV discharge shall be
routed to safe height in accordance with dispersion study and risk analysis.
2.3.7. Tank Roll Over
2.3.7.1. Under certain
conditions “roll over” of the liquid in the LNG tank can occur resulting in the
rapid evolution of a large quantity of vapour with the potential to over
pressurise the tank. Stratification can occur in an LNG tank if the density of
the liquid cargo charged to the tank is significantly different from the left
over LNG in the tank. Inlet piping must be designed to avoid stratification of
LNG. This can be done by having top and bottom fill lines to inject denser LNG
at the top and lighter LNG at bottom. This can also be done by providing
distribution holes along the fill line extending to the bottom. Temperature
sensors are put to monitor the temperature of the liquid throughout the liquid
height at regular intervals. Provision for density measurement on tank shall be
provided for the entire height of the tank.
2.3.7.2. For taking care of
over pressurisation due to roll over, one of the following options shall be
provided, namely:—
(i)
Calculation
of pressure relief valves or Flare/vent system shall to be designed to account
for rollover scenario;
(ii)
Rupture
disc if provided on the tank with isolation valve (lock open condition) releasing
to atmosphere;
(a) Means to check rupture disc
integrity should be provided. Fragments of the rupture disc should not fall
into the tank;
(b) Failure of the rupture disc
shall trip all the boil off gas compressors automatically.
2.3.8. Over-Fill of Inner
Tank
(i)
Two
independent type level measuring instruments shall be provided. The level
instrument shall be equipped to provide remote reading and high level alarm
signals in the control room. In addition, an independent transmitter for high
level alarm and high - high level alarm with cut off shall be provided. The
high - high level should be hard wired directly to close the liquid inlet
valves to the tank.
(ii)
The
tank shall not be provided with overflow arrangement.
2.3.9. The membrane
containment tank systems shall also meet the additional requirements as
specified in NFPA 59A.
2.3.10. Dyke
(i)
Dyke
shall be provided for the following types of LNG storage tanks
(a) Single containment tank
(b) Double containment with
metallic outer tank
(c) Full containment with
metallic outer tank
(d) Membrane tank with metallic
outer tank
Dyke is not required for
full containment or membrane containment tanks with pre stressed concrete wall.
2.3.11. Other
Considerations
(i)
Where
cryogenic storage tanks are located near process plants with a likelihood of
exploding process equipment, the impact of flying object on the tank, one 4″
valve travelling at 160 km/h (object of 50 kg weight with a speed of 45 m/sec)
shall be considered.
(ii)
For
the tank located within the flight path of an airport, the impact of a small
aircraft or component shall be taken care of.
(iii)
Impact
of explosion wave due to major leak from a nearby natural gas pipeline or a
major spill of LNG may also be considered.
(iv)
Failure
of inner tank: Where a sudden failure of inner tank is considered, the outer
tank shall be designed to withstand the consequent impact loading.
(v)
Earthquakes:
The risk level is determined on the basis of the seismic classification of the
location. The data pertaining to the seismic activity level having been
ascertained, the structure is to be designed taking into consideration of
IS-1893 and other relevant codes.
(vi)
Rainfall
runoff from the tank roof should be directed to a curbing and collecting system
around the outer edge of the roof. Collected rainwater shall be carried by a
drainage piping system that directs the rainwater away from any LNG spill
carrying surfaces and to graded drainage areas that are beyond (outside) the
ring road.
2.3.12. Nozzles
There shall be no
penetrations except for anchor straps, of the primary and secondary container
base or shell walls for LNG tanks to ensure fluid tightness
In addition to the nozzles
used for regular operations like liquid inlet, pump outlet, vapour outlet and
instrument connections the following provision shall also be provided.
(i)
Nitrogen
connections for:
(a) inertisation of inner tank
(b) outer tank and insulating
material.
(ii)
Chill
down connections for the inner tank.
(iii)
Depressurisation
and purging of the in-tank pump column.
2.4 Instrumentation and
Process Control for Tanks
The instrumentation shall
be suitable for the temperature at which LNG is stored. All instrumentation
shall be designed for replacement or repair under tank operating conditions in
a hazardous gas zone area. Instrumentation for storage facilities shall be designed
in such a way that the system attains fail-safe condition in case of power or
instrument air failure.
The Level instrumentation
for ESD function shall be separate and independent of the device for
monitoring.
2.4.1. Level
(i)
LNG
containers shall be equipped with two independent liquid level gauging devices
to monitor tank levels.
(ii)
Each
system shall have High and High High Level alarms.
(iii)
Local
Level indication should be available at grade apart from remote indication in
the control room.
(iv)
Density
variation shall be considered in the selection of gauging devices.
2.4.2. Pressure
(i)
The
storage tank shall be provided with pressure transmitters to continuously
monitor and control pressure with an indication in the control room and
indication in field at grade level.
(ii)
Instrument
for detecting High Pressure shall be independent of the tank pressure
monitoring instrument.
(iii)
The
sequence for over pressure control and protection shall be as follows:
(a) High pressure alarms
(b) Increasing the BOG system
to the full load.
(c) Further increase in
pressure shall be controlled by releasing to Flare.
(d) Further increase in
pressure shall be controlled by closing of inlet automated valve.
(e) The final over pressure
protection shall be PSV and tank design pressure.
All the above pressure
control and actuation shall be on independent pressure transmitters.
(iv)
Independent
Pressure transmitters shall be provided for low pressure detection that will
trip the boil off gas compressors.
(v)
In
the event of continued drop in tank pressure, three layers of protection
against vacuum shall be provided.
(a) The trip of the BOG
compressors.
(b) The trip of the pumps.
(c) Automatic admission of
natural gas from outside source into the tank vapour space.
(d) In the unlikely event this
is not sufficient, a set of vacuum breakers installed will admit air into the
space between the suspended deck and outer roof to prevent permanent damage to
the tank.
(vi)
The
independent pressure transmitters shall be provided for the natural gas
admission for vacuum protection.
2.4.3. Temperature
(i)
As
LNG is a product of varied compositions, it would be necessary to measure
temperature of liquid and vapour over the full tank height; the sensors being
located at 2 meter intervals or every 10% interval of the tank height,
whichever is less.
(ii)
Measuring
and recording the formation of layers of liquid with different temperatures
should warn the operator of a possible roll over phenomenon.
(iii)
In
addition, for monitoring of the initial chill down operation, temperature
elements are required to be provided at tank base and shell of both the primary
and secondary containers.
(iv)
These
temperature elements must be provided at various heights and at various
locations of the base to ensure monitoring and proper chilling of the tanks.
2.4.4. Gas Detectors
Automatic gas detection
system for monitoring leakage of LNG to be installed. Adequate number of gas
alarm sensors shall be placed on the tank roof in the vicinity of roof nozzles
and locations where the possibility of gas or liquid release exists including below
elevated tanks. The facility shall be equipped with Emergency shutdown system.
The ESD should be able to operate remotely/locally. Need for any automatic
actuation of ESD may be assessed based on risk perceptions.
2.4.5. Leak Detectors
(i)
Monitoring
leaks through the primary container in double containment systems shall be
provided by one of the following means:
(a) Temperature measurement
sensors in annular/insulated space.
(b) Gas detection
(ii)
The
arrangement shall have redundancy to prevent spurious alarms.
(iii)
Tank
external leak/spillage detection shall be installed at every location where
leaks are credible. These detectors may activate appropriate process shutdowns
or isolation, activate remote operated fire protection systems or initiate
emergency actions by Operators.
(iv)
The
following leak detection devices shall be considered:
(a) Low temperature sensors for
LNG spills.
(b) Flammable gas detection of
IR type. Battery limit fences shall have open path type detectors.
(c) Flame detectors of the
UV/IR type
(d) Heat temperature detectors
for protection of tank relief valve fires and activation of tail pipe
extinguishing packages, if provided.
(e) Smoke detectors of the
ionisation type
(f) CCTV systems in unmanned
areas and unloading Jetty, capable of detecting vapour clouds, fitted with
motion sensor alarms.
(g) Communication system
between field operators, Jetty terminal and pipeline dispatching centre.
2.4.6. Density Meters
(i)
Density
Meters shall be provided on the storage tanks to check the homogeneity of LNG.
(ii)
The
density of LNG in the Tank shall be monitored at all levels and analysis
performed to alert the operator of any density layering.
2.4.7. The Linear and
Rotational inner tank movement should be considered in the design for the
relative movement of the liquid container with respect to outer tank.
2.4.8. A provision in the
tank for endoscopic inspection (through insertion of camera) should also be
considered. This will be helpful to know the health of the tank in the absence
of visual inspection of the tank.
2.4.9. An Uninterruptible
Power Supply (UPS), with battery back-up shall be provided to all critical
instrumentation control and safety (F&G) systems so that plant may be kept
safe in case of emergencies.
3.0 REGASSIFICATION
FACILITY
3.1. Vaporisers and Connected
Piping
(i)
Vaporisers
shall be designed for working pressure at least equal to the maximum discharge
pressure of the LNG pump or pressurized container system supplying them,
whichever is greater.
(ii)
Manifold
vaporisers shall have both inlet and discharge block valves at each vaporiser.
(iii)
The
outlet valve of each vaporiser, piping components and relief valves installed
upstream of each vaporiser outlet valve shall be suitable for operation at LNG
temperature
(iv)
Suitable
automatic equipment shall be provided to prevent the discharge of either LNG or
vaporized gas into a distribution system at a temperature either above or below
the design temperature of the send out system. Such automatic equipment shall
be independent of all other flow control systems and shall incorporate shut
down valves used only for contingency purposes.
(v)
Isolation
of an idle manifold vaporiser to prevent leakage of LNG into that vaporiser
shall be accomplished with two inlet valves with safe bleed arrangement in
between.
(vi)
Each
heated vaporiser shall be provided with safety interlock to shut off the heat
source from a location at least 15m distant from the vaporiser. The device
shall also be operable at its installed location.
(vii)
A
shutoff valve to be installed on the LNG line inlet to a heated vaporiser to be
at least 15m away from the vaporiser. This shutoff valve shall be operable
either at installed location or from a remote location and the valve shall be
protected from becoming inoperable due to external icing conditions.
(viii)
If
a flammable intermediate fluid is used with a remote heated vaporiser, shutoff
valves shall be provided on both the hot and cold lines of the intermediate
fluid system. The controls for these valves shall be located at least 15m from
the vaporiser.
(ix)
The
vaporisers shall be fitted with local as well as control room indications for
pressure and temperature of both fluid streams at inlet and outlet.
(x)
Instrumentation
for storage, pumping and vaporization facilities shall be designed for failsafe
condition in case of power or instrument air failure.
3.3. Relief Devices on
Vaporisers
(i)
Each
vaporiser shall be provided with safety relief valves sized in accordance with
the following as applicable:
(a) The relief valve capacity
of heated or process vaporisers shall be such that the relief valves will
discharge 110 percent of rated vaporiser natural gas flow capacity without
allowing the pressure to rise more than 10 percent above the vaporiser maximum
allowable working pressure.
(b) The relief valve capacity
of ambient vaporisers shall be such that the relief valves will discharge at
least 150 percent of rated vaporiser natural gas flow capacity without allowing
the pressure to rise more than 10 percent above the vaporiser maximum allowable
working pressure.
(ii)
Relief
valves on heated vaporisers shall be so located that they are not subjected to
temperature exceeding 60°C during normal operation unless designed to withstand
higher temperature.
(iii)
The
discharges from the relief valves shall be located at a safe height from
adjoining operating platform.
(iv)
The
safety relief valves may discharge directly to the atmosphere to a safe
location. If this is not possible, the discharge of the safety relief valves
shall be routed to the flare or to the vent.
4.0 LOADING/UNLOADING ARM
AND MARINE FACILITIES
4.4. Loading/Unloading Arms
(i)
Unloading
arm consist of pipe length connected to each other by swivel joints, moved by
hydraulic actuators. The connection of the arm end to the ship crossovers
flange shall be provided with a special automatic ERC (Emergency Release
Coupler) device. During emergency this automatic device will come into
operation and de-coupling system gets activated.
(ii)
Each
unloading arm shall be fitted with an Emergency Release System (ERS) able to be
interlinked to the ship's ESD system. This system must operate in two stages;
the first stage stops LNG pumping and closes block valves in the pipelines; the
second stage entails automatic activation of the dry-break coupling at the ERC
together with its quick-acting flanking valves. The ERS System should conform
to an accepted industry standard.
(iii)
Provision
should be given to collect the LNG from the unloading arm to a closed system by
way of providing blow down vessel or any other suitable arrangement. No drain
shall be open to atmosphere.
(iv)
The
size of the arms depends on the unloading flow rate.
4.1.1. Flexible Hoses
(i)
Flexible
hoses may be used to make small temporary connections for the transfer of LNG
and other cryogenic liquids such as refrigerant and liquid nitrogen, for
example when emptying or filling road tankers of LNG or liquid nitrogen and
they can also be used for transfer operations between small LNG carriers and
LNG satellite plants. The use of flexible hoses shall be in accordance with the
hazard assessment as per EN-1473.
(ii)
Flexible
hoses shall not exceed 15m in length and 0.5 m3 in volume.
Their design pressure shall be limited to PN 40.
(iii)
Flexible
hoses shall not be used for the routine transfer of LNG between large LNG
carriers and shore at conventional LNG terminals.
(iv)
Flexible
hoses shall be designed in accordance with relevant codes and/or standards,
such as EN 12434.
4.4. Loading/Unloading Line
(i)
The
unloading and transfer lines for LNG should have minimum number of flange
joints (expansion bellow system should be avoided, expansion loop shall be
provided). Consideration should be given to provide cold sensors for flanges of
size 200 mm and above as well as where there are clusters of flanges.
(ii)
Length
of the unloading line should be kept minimum. In case it is not feasible,
alternative options available are:
(a) To have additional line
running parallel
(b) To have booster pump
(c) Increase size of line
(iii)
The
unloading line should be kept in cold condition to avoid stress and cyclic
fatigue due to frequent warm-up and cooling down operation.
(iv)
In
case of unloading line is used for loading also adequate safety measures to be
provided in engineering and design and risk assessment should be done in
addition to the requirements as specified in clause 6.0 - Piping.
(a) Quantative risk analysis
(QRA)
(b) Hazarad and Operability
study (HAZOP)
(c) Standard Operating
Procedures (SOP)
(d) Surge analysis
(e) Interlock logics
5.0 FLARE
The following major process
components and function shall comprise pressure relief and blow down system.
(i)
Emergency/operational
flare system for LNG regasification system (vapour)
(ii)
Flare
equipment including stack, tip and flame front generator.
(iii)
Flare
System with flare stack
The following shall be the
criteria for designing various equipment under these systems.
5.1 Flare Header
5.1.1. Following systems are
connected to flare header:
(i)
Blow-down
from LNG vaporisers
(ii)
Relief
from LNG recondenser
(iii)
Relief
from BOG compressors
(iv)
Relief
from Fuel Gas System
(v)
Blow-down
from LNG Tanks vapor system
(vi)
Blow-down
from Natural gas send out header.
5.1.2. However the relief
from the following system shall be given to atmosphere to avoid increase of
flare load:
(i)
LNG
vaporisers (SCV, Shell & Tube)
(ii)
LNG
Storage Tanks
(iii)
Natural
gas send out header
5.2 Emergency
Depressuring
5.2.1 A depressurising
system shall be provided to reduce the internal pressure, reduce the effect of
leakage and avoid the risk of failure of LNG, hydrocarbon refrigerant or gas
filled pressure vessels and piping from external radiation.
5.2.2 Devices for
depressurising high pressure equipment shall allow the pressure of one or more
item of equipment to be reduced quickly. These gases shall be sent to the flare
system which shall be capable of handling the low temperatures generated during
depressurising.
6.0 PIPING
6.1. All Nozzles for the
Piping requirements for an LNG tank shall be from the top. Side penetration
shall be avoided to minimise risk of serious leakage. The piping requirements
includes the following but not limited to:
(i) Fill lines
(ii) Withdrawal line (Intank
pump column)
(iii) Boil-off line to remove LNG
vapour.
(iv) Cool down line for initial
cooling of tanks during commissioning of the tank.
(v) Nitrogen purge lines to
purge the inner tank and annular space.
(vi) Nitrogen purging line for
pump column and foot valve sealing.
(vii) Instrument nozzles.
(viii) Pressure make-up line.
(ix) Pump re-circulation line.
(x) Purge release vent line.
(xi) Pressure relief valve line
(xii) Vacuum relief line
6.2. LNG lines are
normally fully filled lines. However, during specific operating conditions
could result in differential temperatures at the top and bottom of the pipe
causing bowing of pipes and potential spills. Piping design should include
stress analysis, expansion loops, and supports as well as proper piping and
equipment cool down procedures should address differential contraction covering
all anticipated operation and upset conditions.
6.3. Physical phenomenon
such as surge pressure in LNG receipt and transfer lines, flashing and two
phase flow shall be addressed in the piping and equipment design. ESD valves
shall be fail-safe and fire safe.
6.4. Piping loads and
thermal expansion/contraction of piping should not be transferred to the Tank
nozzle connections. Bellows expansion joints should be avoided in LNG lines.
6.5. Valves shall be
designed and manufactured for Cryogenic service. Extended bonnet valves are
used in cryogenic service with stems in the vertical position.
6.6. LNG heats up and expands,
if confined to a fixed volume. Hence any potentially blocked piping or
equipment should be provided with thermal expansion relief valves with
discharge to closed system.
6.7. Inlet piping shall be
designed to minimize stratification/layering of LNG [Stratification occurs when
heavier LNG has been added at the bottom of a tank with partially filled
lighter LNG or lighter LNG added at the top of the heavier LNG or due to ageing
(storing for long duration) of LNG. This leads to sudden and rapid release of
vapour, called Roll-over].
(i) This can be prevented by
having two fill lines one ending at the top of the tank and other extending to
the bottom, to inject denser LNG at the top and lighter LNG at the bottom.
Mixing nozzles may also be used to avoid stratification.
(ii) Rollover conditions shall
be prevented by active management of stored LNG which includes monitoring
temperatures and densities, mixing the tank contents by appropriate top and
bottom filling or by circulation.
6.6. Vaporiser piping
involves high flow rates, pressures as well as transition from cryogenic piping
materials to carbon steel material. This could result in embrittlement failure
if cold gas or liquid were to come in contact with carbon steel, in case of
failure of process interlocks.
6.6. The effect of low
temperature fluid spills on adjacent plant, equipment and structural steel
shall be assessed and measures taken to prevent incident escalation and/or
endangerment of emergency response personnel, through suitable selection of
materials of construction or by embrittlement protection.
Such protection shall be
achieved by an appropriate material selection (concrete, stainless steel etc.)
or by a insulating with material that will protect the equipment and structural
supports from cold shock. Insulation shall be designed and installed in
accordance with appropriate standards and provision taken to protect outer
surfaces from wear and tear.
6.10. Equipment and
structural support elements should be protected in such a way that their
function and form are not adversely affected during the plant operation.
7.0 DESIGN OF LNG TRUCK
LOADING FACILITY
7.1. Description
7.1.1. The purpose of LNG
road loading system is to transfer LNG from the storage tanks to tank truck to
deliver LNG to other sites via road transportation. The LNG road loading shall
be manually operated system, where all activities shall be done in presence of
trained personnel. LNG for loading into the tank trucks shall be tapped off
from the LNG In-tank Pump discharge. LNG vapour return from the tanker shall be
routed to the BOG suction header. When no loading will be in progress the
recirculation will be maintained in the LNG filling line, through a
recirculation line for maintaining chilled condition. The loading facility to
be provided with the LNG liquid loading arm and vapour return arm. For
monitoring of uniform chilling of the LNG feed line during no-loading
situation, suitable number of skin temperature indications with alarm shall be
provided in the control room.
7.1.2. The LNG road tanker
shall be double walled vacuum insulated cryogenic vessels suitable for
transport at cryogenic conditions. The tank truck for road movement shall be
designed, constructed and tested in accordance with the Static and Mobile Pressure
Vessels (Unfired) Rules, 2016 as amended from time to time.
7.1.3. Truck Loading
facility should consist of the following:
(i) LNG filling line, Vapor
return line & a recirculation line with adequate instrumentation
(ii) Liquid/Vapour Loading arm,
Batch Flow meter & Control Valve
(iii) Weigh Bridge/Flow meter for
Custody transfer
(iv) Sick Tanker unloading
facility
7.7. Design Considerations
of LNG Loading/Unloading Facilities
7.2.1 Loading Facility
Each loading station shall
consist of the following:
(i)
Automatic
flow control valve or suitable control mechanism meeting similar functional
requirements & non return valve shall be provided in LNG loading lines.
(ii)
A
vapour return line with an isolation valve connected back to the storage
vessel/BOG line with NRV.
(iii)
The
proper tanker earthing connection shall be provided.
(iv)
Properly
designed loading arm shall be provided at the end of filling and vapour return
lines for connecting to the tank truck. The loading arm end connection type
shall be CGA LNG 300 or flanged type. The loading arms shall be provided with
breakaway couplings. These arms shall be of approved type and tested as per OEM
recommendations.
(v)
Weigh
bridges of suitable capacity for tanker weighment shall be provided.
7.2.2. Tanker Unloading
Facility
(i)
The
tanker unloading shall be done by any of the following methods:
(a) Utilising vapours from BOG
compressors discharge.
(b) Utilizing the gas from the
pressurized gas (send out) network with proper pressure control.
(c) Utilizing tanker pressure building
coil.
(d) Dedicated unloading
compressors/pumps.
(ii)
A
suitable protection shall be considered for tanker/system over-pressurization
and due considerations of impact of high temperature.
(iii)
All
drains, vents and safety valve discharges shall be routed to the closed
system/flare system. In case of non-availability of flare system, the discharge
from safety valve shall be vented to atmosphere at a safe location minimum at
an elevation of 3 meter above the nearest working platform for effective
dispersion of hydrocarbons. The dedicated drain and vent connections to be
provided for the loading and vapour arms. Operational requirement is that after
every loading operation, before disconnection, the liquid holdup in the LNG
liquid and vapor arms are required to be drained, depressurized and purged. The
provision of Drain Pipe can be considered. The liquids collected in the Drain
Pipe would gradually vaporize. Nitrogen connection can be provided to facilitate
the vaporization process.
7.3. Other Considerations
7.3.1 Safety System
(i)
The
gantry shall have gas and spill detector at potential spillage and gas emission
locations. There shall be flame detectors which shall cover the entire gantry
and detect any fire. In addition, there shall be manual call points at
appropriate locations.
(ii)
The
fire and gas detection shall be considered as follows:
(a) Fire detectors
(b) Gas detectors
(c) Low temperature (spill)
detector
(i)
The
signals generated from the detectors shall be integrated with the ESD system.
(ii)
The
shutdown valves to be provided for all the process incoming and outgoing lines
to/from loading gantry and shall be located at least 15 meters away from the
loading gantry at an easily accessible location.
(iii)
The
Emergency Shutdown (ESD) philosophy shall be designed to initiate appropriate
shutdown action on detection of any emergency situation or through detector
signal.
(iv)
Emergency
push button or hand switch shall be provided in Control room and also in field
at safe location for manual actuation of ESD system and fire water spray system
by operator in case of emergency. The field related button/switch to be
provided on either end of the gantry at easily accessible locations.
(v)
ESD
shall be caused in case of either of the following:
(a) Signals from two detectors
of different types of gas or spill or flame
(b) Initiation of manual call
points
(c) Hand switches provided in
the field as well as in the Operator Console & Control Room.
In addition, the following
logic shall also be performed to stop individual tanker filling operation
(a) Gas detection will stop
filling operation.
(b) Earth relay contact
indicating inadequate earthing of the truck will stop filling operation.
In addition to above, fire
water spray with deluge system shall also provided in the gantry which is
activated either automatically (either Flame/Fire detector or Quartzoid bulb
assembly) or manually by manual switches.
7.3.2. Safety Precautions
Following precaution should
be taken due to associated hazards during transfer of LNG to or from a tank
truck.
(i)
No
source of ignition must be allowed in the area where product transfer
operations are carried out.
(ii)
Fire
extinguishers suitable for combating LNG fires shall be placed near the tank
trucks during transfer operations.
(iii)
The
first operation after positioning the truck should be to provide proper
earthing connection of the tanker. Earthing shall be disconnected just before
the release of the truck.
(iv)
While
disconnecting arm, connections shall be loosened only slightly at first to
allow release of trapped pressure, if any.
(v)
Always
use personal protective equipment (Cryogenic suits, flame retardant overalls
etc) while making or breaking the connections to avoid cold burns.
(vi)
The
master switch shall be put off immediately after parking the truck in position.
No electrical switch on the truck shall be turned “on” or “off” during the
transfer operation.
(vii)
No
repairs shall be made on the truck while it is in the loading area.
(viii)
Availability
of wheel chokes.
(ix)
Filling/transfer
operations shall be stopped immediately in the event of—
(a) Uncontrolled leakage
occurring
(b) A fire occurring in the
vicinity
(c) Lightning and thunder storm
Provision to stop the
Filling/transfer operations shall be available from field as well as remote
location. Stop switch in field shall be located at a safe distance (minimum 15
meters away) from the source of hazard to be protected.
7.4. Drain and Vents
Drain and vents shall be
provided to meet all the requirement of draining, purging, venting etc.
Appropriate system shall be provided to handle the discharge from the TSV's
also.
7.5 Requirements for LNG
Installations using ASME Containers for stationary applications
The requirements for
installation, design, fabrication, and siting of LNG installations using
containers of 379 m3 capacity and less constructed in
accordance with the ASME Boiler and Pressure Vessel Code or Gas Cylinder
Rules for vehicle fueling and commercial and industrial applications shall
be as specified in Annexure-I.
Schedule - 1B
8.0 Electrical Systems
8.1 Design Philosophy
(i)
The
selection of electrical equipment and systems shall be governed by fitness for
purpose, safety, reliability, maintainability, during service life and
compatibility with specified future expansion, design margins, suitability for
environment, economic considerations and past service history.
(ii)
The
design and engineering of the electrical installation shall be in accordance
with established codes, specifications, sound engineering practices and shall
meet the statutory requirements of National and Local Regulations.
(iii)
Electrical
equipment and materials shall comply with their relevant Specification, Data
sheet and Project Specification and the latest edition of the following codes
and standards (including any amendments) applicable shall be followed.
(iv)
All
Electrical equipment, systems and their installation shall be designed for
operation under site conditions as required.
(v)
All
equipment and materials shall be suitable for operation in service conditions
typical of a LNG plant within a coastal environment in the tropics.
(vi)
Switchgear
Room shall be forced ventilated, VFD/UPS Room shall be Air-Conditioned, and
Battery Room shall be ventilated with Exhaust Fans. However failure of cooling
or ventilation shall not affect the operation of this equipment.
(vii)
VRLA
battery room shall be air conditioned to maintain specified temperature.
(viii)
For
the purpose of electrical grounding calculations (soil electrical resistivity)
and cable rating calculations (soil thermal resistivity), the data of the area
shall be used.
(ix)
In
areas where the soil may become contaminated due to hydrocarbon spillage
electrical cables shall not be installed underground or shall be installed in
suitable concrete duct banks.
(x)
All
areas within battery limits shall be classified for the degree and extent of
hazard from flammable materials. Classification of hazardous areas for all
locations shall be done in accordance with area classification drawing and
guidelines indicated therein.
8.2 System Design
The distribution system
shall be designed considering all possible factors affecting the choice of the
system to be adopted such as required continuity of supply, flexibility of
operation, reliability of supply from available power sources, total load and
the concentration of individual loads. The design of electrical system shall
include the following:
(i)
The
design of electrical system for LNG receipt storage and re-gasification
facility shall include the following:
(a) Site Conditions
(b) Details of power source
(c) Planning and basic power
distribution system and single line diagram
(d) Protection-metering-control
(e) Electrical substation
Design for New substation
(f) Electrical equipment design
(g) Illumination system
(h) Earthing system
(i) Lightning protection system
(j) Electrical equipment for
hazardous area
(k) Statutory approvals
(l) Cable sizing
(ii)
Cabling
system - underground and above ground including cable tray support and routing
through pipe racks
(a) Power system studies
(b) Heat tracing system as
applicable
(iii)
The
designed electrical system shall facilitate and provide:
(a) Standard products application
(b) Safety to personnel and
equipment
(c) Reliability of services
(d) Constructability access
(e) Cabling access
(f) Minimum fire risk
(g) Cost effectiveness
(h) Ease of maintenance and
convenience of operation
(iv)
Adequate
provision for changes during design development and for future expansion and
modification (as appropriate engineering margins and or space provisions)
(v)
Automatic
protection of all electrical equipment and isolation of faulty system through
selective relaying systems or intelligent control devices.
(vi)
Remote
control and monitoring facilities & interfacing for selected devices with
other discipline systems.
(vii)
Lock
out Tag out (LOTO) provisions as applicable.
(viii)
Maximum
interchangeability of equipment.
(ix)
Fail
safe features.
8.3 System Studies
Study/Calculation shall be
carried out to substantiate the selection and sizing of all electrical
facilities in the LNG receipt, storage and regasification facilities. Study
should include minimum but not limited the following:
(i)
Plant
and Unit electrical load
(ii)
Load
Flow, Fault calculation and large motor starting studies.
(iii)
Feeder
and circuit voltage drop
(iv)
Relay
settings and coordination
(v)
Earthing
(vi)
Lighting
calculation and lightning study (Protection of structures against lightning)
(vii)
Transient
stability study
(viii)
Reacceleration
and auto changeover study
(ix)
Load
shedding study
(x)
Power
factor and Harmonic study (if required).
(xi)
Control
and protection schemes
(xii)
Synchronizing
Scheme
(xiii)
Block
diagram for fire alarm system
(xiv)
Speech
diagram and block diagram for communication system
(xv)
Area
classification drawings
8.4 Power Supply
8.4.1 Main Power Sources
and Systems:
The main power source shall
be captive power generation or connected to the grid. The voltage level of
proposed primary distribution (33KV or other) and utility grid shall be as per
plant generation and respective grid supply level. The number and schemes of
indoor switchboards shall be governed both from considerations of power
distribution capacity and also from considerations of process loading under
abnormal plant operating conditions.
8.4.2 Plant Emergency Power
Sources and Systems
Emergency power supply
shall be provided from Substation up to Emergency Mcc to meet the Emergency
lighting and critical services in plant area to permit safe shutdown in the
event of main power failure.
8.5 Power Distribution
8.5.1 General
(i)
A
load summary shall be prepared for recording and calculating the electrical
loads of the LNG receipt and storage facilities. The load summary shall
indicate continuous, intermittent and standby loads.
(ii)
This
shall be used to verify the rating and numbers of transformers, switchgears
etc. The current rating of switchboard bus bars shall also be determined
accordingly.
(iii)
Where
secondary selective systems are provided, each transformer/incomer shall be
rated in accordance with the above.
8.5.2 Main Power Distribution
(i)
A
substation shall be built at the site to cater all load (e.g. the storage tank
and plant) requirement.
(ii)
It
should be provide with dual redundant power supply from, in its each Bus
sections “A” & “B”. (Rework)
(iii)
Provide
Normal and Emergency power supply of 415 V, 3ph, 4 wires to the lighting &
Small power Distribution boards in the Tank battery limit to supply power to
all lighting and convenience receptacle loads in tank area.
(iv)
All
Motor power cables from the Substation shall be provided and terminated on both
sides.
(v)
Emergency
power supply backed by Emergency Diesel Engine (EDG) shall be provided.
8.6 Sub-station Design
8.6.1 General
(i)
The
substation shall be located in a safe area and outside the risk zone.
(ii)
Consideration
shall be given to vehicular traffic or any other factor that might affect the
operation of the substation.
(iii)
Substation
buildings shall be force ventilated with filtered air and shall comprise
elevated structures permitting the use of bottom entry switchgear with cable
cellar for cable racking and trays below.
(iv)
The
cable cellar shall be 300 mm (minimum) above the approach road level and shall
be paved and cemented. The cable cellar have a minimum clear height of 2.5m and
shall house all the cable trays and their supports.
(v)
A
separate entry of 3.0m with rolling shutter shall be provided for drawing in
all equipment for installation. The main entry for operating personal shall be
preferably provided with double door system. The substation shall also have an
emergency door opening outward.
(vi)
Substation
wall adjacent to the transformer bays shall be at-least 355 mm thick in case of
brick construction or 230 mm thick in case of RCC construction.
(vii)
Push
button shall be provided in each transformer bay for tripping of the feeder
breaker.
(viii)
Substation
building shall be without any columns within the switchgear room to ensure
optimum space utilization.
(ix)
Large
batteries shall be housed in separate rooms but small batteries when enclosed
in ventilated equipment cabinets shall be permitted in the switch room.
(x)
VRLA
batteries shall be located in Battery Room ventilated using Ex-d, IIC, T3
Exhaust Fans.
(xi)
An
access door shall lead directly to the outside from each switch room. Internal
personnel doors may connect adjacent rooms.
(xii)
Ventilation
system of substation shall trip on activation of fire and gas detection signal.
Flooring to the Battery room and walls up to 1.0m height shall have
acid/alkaline resistant protective material coating/tiling.
(xiii)
Battery
Room shall also house hydrogen detectors if applicable. Luminaires and
Receptacles in Battery Room shall be Ex-d, IIC, T3 Type of protection.
(xiv)
Heat
sensitive electronic equipment like variable speed drives shall be located in a
separate room provided with air conditioning.
(xv)
The
battery room shall be provided with minimum two exhaust fans and louvered
opening in opposite wall.
(xvi)
Substation
shall have firefighting equipment, first aid boxes and other safety equipments
as per statutory requirements. Mats of required voltage rating shall be
provided around all switchboards and panels.
(xvii) The substation building
shall be sized for housing all equipment like transformers, switchgears etc.
The substation shall be sized to maintain adequate clearances between equipment
as per IE rule.
8.6.2 Transformer Bay Layout
Oil filled transformers
shall be located at grade level in fenced enclosures adjacent to the substation
building and shall be provided with oil containment pits which shall be
connected to the Common Oil soak pit is envisaged as per IS standard (NO.). This
shall be located outside transformer bay. Firewalls shall be provided where
required by codes and standards.
8.7 Hazardous Area
8.7.1 Electrical Equipment
Selection in Hazardous Area
(i)
Electrical
equipment shall meet the requirements of the Indian Standard IS: 5571 - Guide
for selection of electrical equipment for hazardous areas or the institute of
petroleum model code of safe practice: Part 15, except that IEC 60079 Part 14
shall be followed for the selection of fluorescent fitting used in Gas Group IIC
areas.
(ii)
All
the electrical equipment installed in hazardous area shall meet the
requirements of relevant IS or IEC or CENELEC standards, whichever is followed
for design for electrical systems.
(iii)
All
electrical equipment for hazardous area shall be certified by CMRI, PTB,
BASEEFA, UL or FM or equivalent independent testing agency for the service and
the area in which it is to be used. All indigenous flameproof equipments shall
have BIS license. CCOE approval shall be obtained for equipment of non-Indian
origin.
8.8 Equipment
8.8.1 Switchgear/Motor
Control Centres/LV Distribution Boards
(i)
Switchgear
panels shall be of metal clad type with circuit breakers.
(ii)
Switch
gear panels shall have successfully passed internal are test as per IEC-62271
or equivalent standards. Switch gears shall be equipped with at-least one spare
feeder of each type or 20% of each type whichever is higher shall be provided
on each bus section.
(iii)
Motor
feeders rated greater than 22 kW shall be provided with a separate core-balance
current transformer for earth fault protection.
(iv)
Where
duplicate feeds are provided in HT and 415V switchboards, an automatic transfer
scheme will be provided in order to switch to the alternative feeder if a
failure occurs in one supply feeder. Protection shall be provided to prevent
transfer in the case of a fault downstream of the circuit breaker. The
automatic transfer systems shall be independent for each switchboard and shall
include time delay such that transfer takes place at level before transfer at
LV is affected. Return to normal after main power restoration shall be manual.
Exceeding the switchgear fault rating during momentary paralleling shall be permitted
for a nominal short duration.
(v)
Lighting
and small power distribution boards shall be located in buildings and at
strategic locations outdoor around the Tank & BOP areas. The distribution
boards shall be suitable for indoor or outdoor use and the hazardous area
classification in which they are to be installed.
(vi)
Automatic
motor re-acceleration/restarting following voltage dips shall not be provided
unless specifically warranted by process requirements.
(vii)
Power
system monitoring, control and protection shall be in accordance with project
specifications and protection philosophy shall be in accordance. Emergency Shut
Down(ESD) systems and emergency stops shall be hard wired back to the
switchgear/MCC.
(viii)
In
PMCC&MCC, 20%spare feeders of each rating and type or minimum one feeder of
each rating and type having all components in each bus section. All switchgear
shall be loaded to 80%of incomer rating at the end of design completion.
(ix)
All
incoming cable to switchgear shall be suitable for the incomer current rating.
8.8.2 Protective Relays
(i)
Protective
relays for incoming feeders, bus ties and motors having rating 90kW and above
shall be numerical type. Other Auxiliary relays, lock-out relays and Timer
relays considered will be of standard Electro-mechanical type.
(ii)
Meters,
Protection relays and other components shall be as per relevant metering and
protection diagrams and designed and procured as per project specification.
(iii)
Protective
relaying philosophy shall be based on at-least a single contingency planning so
that the relay system will provide fault clearing for one of the following:
(a) Failure of either primary
or backup relay function or the related control Circuit
(b) Failure of a circuit
breaker to interrupt, including a faulty circuit breaker.
(iv)
The
protection relaying philosophy for 220 kV and 33 kV systems shall also include
suitable main and backup schemes.
8.8.3 Power &
Distribution Transformers
(i)
Power
and distribution transformers shall be designed and procured in accordance with
project specification.
(ii)
Transformer
insulating oil shall be in accordance with project specification.
(iii)
The
cooling arrangement of all power transformers shall be ONAN/ONAF with the
possible exception of the main generator step-up transformers and main
distribution transformers, which will have cooling requirements as specified on
the relevant data sheets. Where required, transformer cooling can also be of
the OFAF type. The method of cooling shall be as specified in the data sheets.
(iv)
The
distribution transformers shall be ONAN type.
(v)
Automatic
on-load tap changers (OLTCs) shall be provided on the main transformers as
required. OCTC (Off Circuit Tap Changer) shall be +/−5% in steps of 2.5%.
Lighting transformers shall be Dry type, Air cooled mounted indoor.
(vi)
For
harmonic mitigation, use of transformers with special vector groups may be
considered for supplying large non-linear loads such as VSD's and process
heaters.
8.8.4 Emergency Diesel
Generators:
(i)
The
electrical requirements for Emergency Diesel Generators shall be designed and
procured in accordance with project specification. In addition to the above,
Alternators shall be in accordance with typical Alternator data sheet.
Emergency Diesel Generator set shall form an independent package, consisting of
diesel engine, alternator, control panel and other auxiliary systems.
Alternators shall be of Permanent magnet, Brushless and self-excited type. The
stator and field winding insulation shall be uniform and Class F throughout,
but the design temperature rise of the windings shall be to Class B limit.
(ii)
All
windings shall be with copper conductors, and the insulation shall be suitable
for operation on an unearthed system. The automatic voltage regulator (AVR)
shall be of the static type and shall be high speed compounded for parallel
operation. It shall exhibit long term stability and freedom room drift.
Generators shall be capable of withstanding without damage, a sudden three
phase, a line-to-line, a line-to-earth or two-line-to-earth short-circuit, for
a period of 3 seconds when operating at rated speed and with the excitation
corresponding to 5% over voltage at no load. Emergency Diesel Generators shall
have provision for forward and reverse synchronization and no-load test runs.
The AMF panel shall be equipped with a PLC for automation and control.
8.8.5 Neutral Earthing
Resistors
(i)
The
resistor elements shall be made of unbreakable, corrosion proof, joint-less
stainless steel grid conforming to ASTM standard A240-304 or equivalent.
(ii)
Neutral
earthing resistors shall be in accordance with design specification. 6.6 KV
earthing resistors shall be rated to withstand the maximum prospective earth
fault current for duration of not less than 10 seconds with maximum temperature
limited to 790 °C for stainless steel resistor elements, while limiting the
temperature of aluminum conductor/bus bar to 350°C. Grids shall be mounted on
steel rods insulated by special heat resistant insulating materials, suitable
for the above temperature. Ceramic/porcelain insulator shall be used to
insulate the resistor elements from the enclosure. The insulators and terminal
bushings shall have adequate minimum creepage value (total and protected) for
the required voltage grade.
(iii)
The
resistor elements shall be housed in a naturally ventilated sheet steel
enclosure with minimum IP 31 degree of ingress protection and suitable for
outdoor installation. The enclosure thickness shall not be less than 3mm.
(iv)
The
terminal for neutral and earthing connections shall be housed in a separate
vermin proof, weatherproof terminal box with minimum IP-55 degree of ingress
protection. The terminal box shall be provided with a separate bolted
re-movable undrilled gland plate of non-magnetic material.
(v)
Facility
shall be provided to earth the enclosure at two points. The bottom of the
enclosure shall be provided with a drain plug to remove water that may get
collected in the enclosure.
(vi)
Two
ends of the resistor shall be brought out to suitable epoxy/porcelain bushing
type terminals of adequate rating for the neutral and earth connections. The
terminal shall be suitable for terminating the specified size of
cables/earthing strip. Suitable anti-condensation space heater shall be
provided inside the NGR enclosure to prevent condensation of moisture.
(vii)
For
the 6.6 kV system, the rating is 250 A, and for the 11 kV system (except
generation) the rating is 250 A.
8.8.6 DC Supply Units
(i)
DC
supply units shall be switch mode power supply based and designed and procured
accordingly. Redundant system using two sets of charger with two battery banks
shall be utilized. Battery shall be Nickel Cadmium/flooded electrolyte Lead
Acid/VRLA type designed as per design specifications. Each battery bank shall
be rated to give two hours back-up and shall be rated for 100% of the total
load.
(ii)
A
common DC supply Unit shall be provided in substation for HT & LT
Switchgear, PMCC, MCC, EMCC protection, Remote IO panel, EDG AMF panel, VSD MCC
and tripping supplies of Transformer marshalling panel.
8.8.7 AC UPS for F&G,
PAS and CCTV loads
Dual redundant AC UPS with
battery back-up for 6hrs shall be provided to provide no break supplies to the
Fire and gas system. UPS, ACDB, UPS batteries shall be located in DCS Control
Room Extension.
8.8.8 Alarm Annuciations
All fault, tripped, alarm
and equipment malfunction signals from the communicable relays should be
accessible via a computer connected to the communication port in each
switchgear/PMCC. In addition, certain signals shall bring up alarms/indications
on the Electrical Data Management System in a Central Control Centre (CCC) or
in the DCS.
8.8.9 Variable Speed Drives
(i)
Low
& high voltage variable speed drive (VSD) equipment shall be in accordance
with design project specification to be followed.
(ii)
The
requirement of variable speed drives shall be considered based on an economic
and technical basis subject to process requirements.
(iii)
Converter
equipment controlling plant motors shall be located inside the substation,
except the associated transformers and reactors, which shall be located outside
within a transformer/reactor bay adjacent to the substation. For specific
requirement, the transformer and rectifier may be housed within the substation.
(iv)
Temperature
of 22°C ± 2°C & approximately 50% relative humidity to be maintained in VFD
room. Converter equipment feeding air handling units for comfort
air-conditioning and similar requirements maybe located close to the motor in
the same room or may be mounted integral to the motor.
8.8.10 Motors and Motor
Control Stations
(i)
High
voltage and low voltage motors shall be in accordance with project
specification.
(ii)
Motors
generally shall be of the squirrel cage induction type and shall have a minimum
service factor as defined in the data sheet for the specific motor, with Class
F insulation and Class B temperature rise.
(iii)
LV
motors shall normally be selected to have ratings in accordance with the
preferred rated output values of the primary series as listed in IEC 60072 and
IS 325.
(iv)
The
enclosure of motor control station shall be in accordance with the hazardous
area classification. Each motor shall be provided with a start/stop local
control station (LCS) installed on suitable steel support adjacent to the
motor. There shall be exceptions for critical drives such as emergency dc lube
oil pumps. For HVAC blowers, lock-off stop push buttons shall be provided for
each blower outside the pressurization room in order to aid maintenance access.
Each element for Start/Stop in LCS shall be provided with 2NO + 2NC contacts
which shall be wired to terminals. Terminals shall be suitable to connect 2.5
sq mm cables and shall be of cage clamp (spring loaded) type. LCS shall have
stay-put stop and lock off stop features (padlocking).
(v)
All
LV motors shall be complying to IE2 Class of efficiency unless otherwise
specified in Motor Datasheet. LCS for motors rated above 30 KW and motors
driving agitators, compressors and blowers shall be provided with Ammeter.
Ammeter shall have connection to a CT (1 amp secondary) located within the
motor starter.
(vi)
Start/stop
control stations for all motors shall be located at about 1 meter above grade.
A separate lock-off stop emergency pushbutton shall be located at ground level
for each in-tank pump motor. Compressor motors shall be provided with emergency
stop control station in the LCP.
(vii)
Motors
which have automatic process control or motors which are started from more than
one location shall be provided with LCS incorporating Hand/Auto selector
switch.
(viii)
Motor
operated valves and electric cranes shall be fully equipped with integral motor
control gear.
8.8.11 EARTHING &
LIGHTNING SYSTEM
(i)
Earthing
system shall provide low impedance earth paths for earth faults, static
discharge and lightning protection. Earthing shall be as per IS: 3043.
(ii)
Power
system earthing, lightning protection and equipment bonding shall be achieved
by overall common earthing system. All units shall be bonded together to form a
single continuous earthing system. LNG system shall be connected with Plant
earthling system at least two places.
(iii)
The
earthing system of LNG receipt and storage package shall comprise a buried grid
of galvanized mild steel flat bar bonded together and sized to suit the maximum
earth fault current for 0.5 second plus a 50% corrosion allowance as per
standards. All such earthing system shall be bonded together. Each electrode
shall be installed throughout cryogenic package area to ensure that the
requisite value of resistance between equipment and the general mass of earth
is obtained. Connections from the earthing grid rising above ground shall be
galvanized mild flat steel bar. Thereon, earthing to local network and
electrical equipment shall be carried out using PVC covered aluminum cable or
galvanized mild steel
(iv)
The
metallic enclosure of all electrical equipment shall be bonded and earthed to
the common earthing grid.
(v)
In
hazardous areas or where the equipment contains a hazardous liquid, the
metallic enclosures of non-electrical equipment, vessels, tanks, structures,
pipeline, etc., shall be bonded and earthed to the common plant earthing grid.
Maximum values of resistance of equipment earthing systems to the general body
of earth shall be as under:
(a) General Earthing: 1 ohm
(b) Earthing for Lightning
Protection & Static Bonding: 10 ohms
(vi)
Lightning
protection shall be provided for all non-metallic and all metallic on
continuously welded structures over 20 meters high and for all tall plant
buildings.
(vii)
Earthing
of lighting and small power systems shall be by means of an earth conductor
integral within the cable or conduit. Power circuits shall be earthed by a
separate earth wire connected to the earthing grid.
8.8.12 LNG Tank earthing
Internal LNG tank earthing,
In-tank pump casing earthing and Instrument casing earthing within the double
wall LNG tank shall be connected to the main earthing system.
8.8.13 Instrument earthing
Separate earth bars above
ground shall be provided for Instrument earthing in Tank & BOP area.
Instrument earth may be connected to electrical earth at one point in earth pit
only.
8.8.14 Lightning Protection
Lightning protection for
cryogenic tank shall be carried out by using rolling sphere method as per
IEC-62305. Lightning protection shall be provided as per the risk index
analysis worked as per IS 2309. 50 × 6 mm Galvanized steel strip shall be
provided for Lightning down conductor.
8.9 Lighting System
Plant lighting shall be
designed and procured in accordance with project specification.
8.9.1 General Lighting
(i)
Lighting
in industrial plant hazardous and non-hazardous areas should be by means of
fluorescent luminaries mounted on the structures, directly beneath beams or on
platform mounted poles.
(ii)
Where
required general lighting for open areas with in non-hazardous areas shall be
by means of high pressure sodium floodlight luminaries mounted on adjacent
structures or on strategically located floodlight columns. High mast
floodlighting installations shall also be used where appropriate.
(iii)
Safety
showers in plant areas shall be provided with green fluorescent fixtures for
proper identification.
(iv)
The
following average intensity levels, measured 1m above the floor level in a
horizontal plane shall form the basis for the lighting design:
|
Area or Facility
|
Average Maintained Illumination Level, lux
|
|
Operating areas (Controls, Valves & Gauges)
|
100-200
|
|
Compressor houses at or near equipment
|
200
|
|
Stairways, platforms and walkways
|
60
|
|
Outdoor operational areas (Process areas, pipe
racks, heat exchanger, flare etc.)
|
60
|
|
Outdoor Non-operational areas (At grade)
|
10
|
|
Tank farms
|
20
|
|
Main/Secondary roads
|
20
|
|
Pump houses, Sheds, Switches
|
100
|
|
Switchgear Room & UPS Room
|
150-200
|
|
Cable cellar Room
|
70
|
|
Battery rooms & transformer bays
|
100-150
|
|
Toilets and locker rooms
|
150
|
|
Control Room
|
General lighting/laboratories
|
400
|
|
Rear of instrument panels, aux. and panel
|
200-300
|
|
Outside, near entrances
|
150
|
8.9.2 Tank Farm Lighting
High mast floodlighting
columns shall be located in non-hazardous locations outside tank farm bund
walls. Local lighting may be provided as necessary in areas of regular plant
operational activity.
8.9.3 Emergency Lighting
Emergency lighting of
adequate intensity shall be provided at following locations or where ever the
safety of persons or facilities may be endangered in the event of loss of
normal main lighting:
(i)
main
access points
(ii)
muster
area
(iii)
first
aid station(s)
(iv)
fire
fighting area
(v)
stairways
and landings.
8.9.4 Lighting Control
Outdoor lighting circuits
shall generally be controlled via latitude/longitude timed switches
(astronomical type). Manual override shall be provided to permit maintenance.
Indoor lighting shall be controlled locally by suitably located switches.
8.9.5 Aircraft Warning
Lighting
The type of Aircraft
warning lights shall be in accordance to International Civil Aviation
Organization and local regulations. The aircraft warning lights shall be steady
burning or flashing type with Fresnel lens type of red colour and shall be
fitted at the highest points of the platform obstacles. These lights shall have
intensity between 25 to 200 candelas and shall be installed in such a way that
at least one light can be seen by pilots.
8.9.6 Power and Convenience
Outlets
(i)
Adequate
no. of 415 V, 63 A, TP&N+E power outlets of switched socket type shall be
provided at suitable locations to ensure accessibility with a 50 meters length
of trailing cable to any point in the process area.
(ii)
240
V, 16 A, SP&N+E convenience outlets at suitable locations such that all
principal equipment locations can be reached by use of 25 meters of extension
cable.
(iii)
Convenience
outlets for hand lamp supplies with integral transformer, rating - 100 VA,
240/24 V (Centre point earthed), shall be provided near to the man holes of vessels,
tanks columns etc. Convenience outlets shall be fed through earth leakage
circuit breakers of 30 mA sensitivity.
8.9.7 Cables and Cable
Installation
8.9.7.1 Cable Types
(i)
High
voltage and low voltage cables shall be designed and procured in accordance
with project specification. All cables of all voltage grades shall have XLPE
insulation.
(ii)
Conductors
6 mm2 and greater shall generally be aluminum (Copper may be selected on
economic or technical considerations). Conductors smaller than 6 mm2 shall be
copper. Minimum size of power & motor feeder cable shall be 4 mm2 and 2.5
mm2 for lighting
(iii)
All
cables used above or below ground in industrial areas shall have non
hygroscopic fillers, wire armoring, PVC overall sheath and FRLS type.
(iv)
6.6
KV, 11KV and 33KV grade cables shall be of earthed type (e.g. 3.8/6.6KV,
6.6/11KV & 19/33KV). Unearthed cables shall be used wherever required by
specialized equipment e.g. VSD. Cables shall be provided with Conductor screen,
insulation screen, and nonmetallic copper tape.
(v)
All
cables used above or below ground in industrial areas shall have non
hygroscopic fillers, wire armoring and PVC overall sheath. Unarmored cables and
wires may be used where proper mechanical protection (e.g. metallic conduit) is
provided or where sheathed cables are installed above ceilings or below floors
in non-industrial locations. Concealed metallic conduits shall be used for
buildings where appropriate.
(vi)
All
cables shall be of FRLS type as per OISD guidelines/requirements. Cables for
conduit installation shall be FRLS, PVC insulated, multi-stranded conductor.
(vii)
Earthing
of lighting and small power systems shall be by means of an earth conductor
integral with the cable.
8.9.7.2 Cable Installation
(i)
The
default method of cable installation is to be installed above ground, laid on
trays within dedicated levels of overhead pipe racks and on the sleepers of low
level pipe ways.
(ii)
In
certain instances cables may be routed underground, these include:
(a) High voltage distribution
cables and associated control cables
(b) Cables entering or leaving
buildings
(c) Cables in areas where
ground contamination is unlikely and economic consideration precludes the
erection of special cable supports
(d) Cabling within the power
generation area
(e) Feeder cables to satellite
substations.
(f) Cables routed underground
shall be direct buried within offsite areas and installed in formed concrete
trenches within process areas.
(iii)
Power
cables shall generally be laid on trays in a single layer with 150mm spacing
for 11&6.6kV cables & bunched for 415V cables. Control cables may be
bunched together. Cables shall be secured at required intervals.
(iv)
Power
(and associated control) and instrumentation. Telecommunication cables shall be
run in their own racks. Electrical cables shall be where practical separated by
at least 600 mm from instrumentation and telecommunication cables.
(v)
In
certain instances cables may be routed underground based on the site
conditions. Cables routed underground shall be direct buried within offsite
areas and installed in formed concrete trenches within process areas.
(vi)
33
kV cables shall be laid in a single layer at 300 mm center at a depth of 1050mm
below grade.
(vii)
11/6.6
kV cables shall be laid in one or two layers at 150 mm centers and at a minimum
depth of 900 mm below grade.
(viii)
415
V cables should be laid in up to three layers touching and at a minimum depth
of 500 mm. Control cables and lightly loaded cables may be grouped together or
laid between loaded cables.
(ix)
All
cables shall be laid on a sand bed with well compacted sand around and above.
Concrete or earthenware tiles shall be laid above the cables in unpaved areas.
Tiles are not required where cables are laid in formed concrete trenches.
Trenches shall be sized to allow for a future 20% increase in cabling which
shall be segregated and clearly marked. Trench walls preferably shall be
chamfered at tee-offs to allow adequate bending radius.
(x)
Where
cables leave the main trenches and for road crossings they shall be run in duct
banks of concrete encased HDPE ducting (150mm) spaced at 200mm centers, at a
depth of 1000mm from grade level. Duct bank shall be as per Electrical
Installation Standard for Cable Duct and Road Crossing
(xi)
Where
cables rise above grade to equipment they shall be protected by HDPE ‘kick’
sleeve up to 150 mm above grade and from there shall be run on rack or tray or
secured by some other suitable means.
(xii)
Cables
shall be installed with spacing to minimize derating but consistent with the
total space available. All cables shall be fitted with aluminum engraved
identification tags at terminations, at 30m intervals over their entire length,
at all points where they enter and leave ducts and at changes in cable
direction etc.. The identification band shall show the complete cable number.
(xiii)
Suitable
route markers shall be provided to indicate trench locations and shall be
located at 50m intervals and where the trench changes direction. When the
trench is within paved areas, a red colored concrete cover shall be used to
seal and mark cable routes.
(xiv)
Cables
shall be in one length where practical but cable joints may be installed when
necessary. Cable joints shall be recorded and their locations accurately on ‘as
built’ drawings. Above ground cable joints shall not be installed in hazardous
areas. All underground through joints shall be PU filler type. Where cables
pass through a building foundation, ducts, or an opening in the foundation,
shall be used to permit entry. Cables entering a building aboveground shall
pass through fire retardant barriers. Fire retardant coating shall be applied
on cable joints. Where appropriate, particularly where cables transition
process units, cables shall be treated with fire retardant coating. All remote
operated shut-off valves within a fire zone, which are designed to limit the
duration and severity of a fire by shutting off the fuel source, shall be
powered using circuit integrity cables.
(xv)
Adequate
segregation shall be maintained between different services. In general power and
instrumentation/telecommunication cable shall not be laid in the same trench. A
separation of 600mm shall be maintained between parallel runs of instrument and
electrical cables. Within substations, PIBs and plant areas, lighting and small
power cables shall be multi-core XLPE insulated and terminated using
compression type cable glands.
(xvi)
Cables
from variable speed drives shall be run in separate cables trays and a
separation of 600 mm shall be maintained between cables operating on sinusoidal
supplies and cables connected to the output of variable speed drives. Cable
racks and trays within close proximity of the cooling towers and desalination
plants shall be UV resistant powdered coated galvanized mild steel. FRP cable
trays can be utilized in non-hazardous areas of cooling towers and marine
facilities. Above ground cables shall be supported by cable racks or trays. A
clear space of 250 mm, measured from the top of the collar of the tray, shall
be provided above cable trays to facilitate cable laying. Power cables shall
generally be laid on racks or trays in a single layer. Control cables may be
bunched together. Cables shall be secured at required intervals. Cable racks
and trays shall be fabricated from steel and hot dipped galvanized after
fabrication. Power (and associated control) and
instrumentation/telecommunication cables shall be run in their own racks.
Electrical cables shall be where practical separated by at least 600 mm from
instrumentation and telecommunication cables except at switchgear/MCC and
substations. All cables shall be terminated using an approved double
compression cable gland which shall be nickel plated brass.
(xvii) All cable entry threads
shall be BS conduit (ET) to BS 31. All Cable glands for Equipment located in
zoned area shall be provided with Ex-d, IIC, T3 protection as a minimum
requirement.
8.10 Electrical Heat
Tracing
Where necessary, electrical
trace heating shall be provided for process pipelines. Electrical heat tracing
shall be designed and procured in accordance with project specification. As far
as practical, suitably certified self-regulating heating tapes shall be
employed. Special types of heating (e.g. skin effect, impedance or induction
heating) may be employed in particular application.
Schedule - 1C
9.0 PROCESS SYSTEM
9.1 Boil off Gas (BOG)
& Reliquefication
BOG system consists of boil
- off gas recovery from the tanks, piping and to divert it into the LNG send
out system or inject it into the pipeline transmission network. BOG is also
used for vapour return to the ship tanks during unloading thereby avoiding
pressure drop in the ship tanks. If vapour return to the ship tanks is not
considered, the BOG system should be designed to handle this additional
quantity also.
(i)
During
roll-over condition, the instantaneous BOG generation is substantially high and
necessary provision shall be provided to protect the tank from overpressure as
well as to take care of the safe discharge.
(ii)
BOG
Recovery/Utilisation Options:
(a) Re-liquefaction &
Recycle to Storage: Liquefaction process used in the LNG production plant may
be used for re-liquefaction. Re-liquefaction process is less favourable
compared to other facilities due to higher energy consumption.
(b) Pressurisation & Mixing
with gas discharged from the Terminal: The boil - off gas is compressed to the
network pressure and mixed with the re-gasified product. But while mixing, low
calorific value of the boil - off gas may reduce the heating value of the
network gas.
(c) Recondensation &
incorporation into the regassified LNG: The recondensation is carried out using
LNG cold released during vaporisation. Pressurisation of boil - off gas in the
liquid phase instead of gaseous phase leads to energy savings, safer operation.
(d) As a fuel gas in power
generation process or internal use.
(iii)
The
receiving terminal shall be provided with flare system to enhance the plant
safety. The flaring of BOG should be done only as a final solution when the
normal BOG handling system is not available.
9.2 LNG Pumping
9.2.1 In-Tank Pumps
(i)
The
tanks are provided with in-tank submerged pumps, which are also known as
primary pumps. These are provided as storage tanks have nozzles only at the
top. Pumps as well as the electric motor are submerged in LNG. Lubrication and
the cooling of the pump are done by LNG itself. These pumps are installed in
wells, equipped with foot valves, which can be isolated to enable pump removal
for maintenance. Arrangement for foot valve seal purge, well purge,
well-draining and venting shall be provided.
(ii)
If
the network pressure is not too high, in tank pumps alone may be sufficient to
bring up to the network pressure through vaporisers. If the pipeline network
pressure is high, two stage pumping may be needed which also helps in BOG re
liquefaction at intermediate pressure instead of compressing BOG vapours to the
line pressure.
(iii)
The
discharge pressure of the in tank pump is usually guided by the re-condenser
pressure. The design pressure of the pump would also consider the chill down
requirements of the ship unloading line.
9.2.2 Send out Section
(i)
In
send out section, LNG is pumped and brought to a pressure slightly higher than
the network pressure through secondary pumps and vaporised & warmed to a
temperature above 0°C and metered before it is sent for distribution.
(ii)
Secondary
Pumps: These Pumps are used for pumping the LNG from the intermediate pressure
to the network pressure through vaporisers. These are generally either
horizontal or vertical, multistage turbine/submersible pumps.
9.2.3 Vaporisation
(i)
Vaporisation
is accomplished by the transfer of heat to LNG from water/ambient air/process
stream. In the vaporisation process, LNG is heated to its bubble point,
vaporised and then warmed up to the required temperature.
(ii)
LNG
vaporisers are to be designed based on the quantity of heat to be exchanged
with LNG for its vaporisation, maximum LNG flow rate, amount of heat available
in the heating medium, lowest temperature of the heating medium.
(iii)
LNG
outlet temperature should be monitored and controlled carefully in order to
avoid any LNG or cold vapour passing into the network.
(iv)
In
case of vaporisers, where water is used as a medium, water outer temperature
should be maintained higher than water freezing point.
(v)
Submerged
combustion vaporiser shall not be located in an enclosed structure/building to
avoid accumulation of hazardous products of combustion.
9.2.4 LNG Cold Recovery
(i)
LNG
cold recovery system aims at recovering the part of the potential cold energy
available in LNG so as to use it effectively in cold utilising plants.
(ii)
In
case of LNG cold recovery facility at the terminal, all the safety features
provided on the LNG vaporisers shall be applicable.
SCHEDULE - 1D
10.0 OPEARTION, MAINTENANCE
AND INSPECTION
Each facility shall have a
documented operating manual including operations, maintenance, training
procedures, cooldown, purging, and record keeping, based on experience and
conditions under which the LNG plant is operated, and a documented maintenance
manual.
Each facility shall have
written operating, maintenance, and training procedures based on experience,
knowledge of similar facilities, and conditions under which they will be
operated.
10.1 Basic Requirements
Each facility shall meet
the following requirements:
(i)
Have
written procedures covering operation, maintenance, and training.
(ii)
Keep
up-to-date drawings of plant equipment, showing all revisions made after installation.
(iii)
Revise
the plans and procedures as operating conditions or facility equipment require.
(iv)
Establish
a written emergency plan.
(v)
Establish
liaison with appropriate local authorities such as police, fire department, or
hospitals and inform them of the emergency plans and their role in emergency
situations.
(vi)
Analyze
and document all safety-related malfunctions and incidents for the purpose of
determining their causes and preventing the possibility of recurrence.
(vii)
As
per maintenance philosophy, the activities should be identified that would be
contracted to third party contractors for maintenance and support.
(viii)
The
activity supervisors shall be identified according to the level of supervision
required.
(ix)
These
supervisors are given Safe supervisor training by designated staff and then
they are put on the job.
(x)
The
contractors staff shall be engaged in toolbox talk given on relevant topics are
held with the Contract holders and owners.
(xi)
OEM
service engineers are involved in critical overhauls for better quality
assurance and for first time activities.
10.1.1 All LNG plant
components shall be operated in accordance with the operating procedures
manual.
10.1.2 The operating
procedures manual shall be accessible to all plant personnel and shall be kept
readily available in the operating control room. The operating manual shall be
updated when there are changes in equipment or procedures.
10.1.3 The operating manual
shall include procedures for the proper startup and shutdown of all components
of the plant, including those for an initial startup of the LNG plant that will
ensure that all components operate satisfactorily.
10.1.4 The operating manual
shall include procedures for purging components, making components inert, and
cooldown of components.
10.1.5 Procedures shall
ensure that the cooldown of each system of components that is subjected to
cryogenic temperatures is limited to a rate and distribution pattern that
maintains the thermal stresses within the design limits of the system during
the cooldown period.
10.1.6 The operating manual
shall include procedures to ensure that each control system is adjusted to
operate within its design limits.
10.1.7 The operating manual
of LNG plants with liquefaction facilities shall include procedures to maintain
the temperatures, levels, pressures, pressure differentials, and flow rates for
the following:
(i)
Boilers
(ii)
Turbines
and other prime movers.
(iii)
Pumps,
compressors, and expanders.
(iv)
Purification
and regeneration equipment.
(v)
Equipment
within cold boxes, within their design limits.
10.1.8 The operating manual
shall include procedures for the following:
(i)
Maintaining
the vaporization rate, temperature, and pressure so that the resultant gas is
within the design tolerance of the vaporizer and the downstream piping.
(ii)
Determining
the existence of any abnormal conditions, and the response to these conditions
in the plant.
(iii)
The
safe transfer of LNG and hazardous fluids, including prevention of overfilling
of containers.
(iv)
Security.
(v)
For
monitoring operations.
(vi)
Emergency
preparedness and handling.
10.1.9 Operation monitoring
shall be carried out by watching or listening for warning alarms from an
attended control center and by conducting inspections at least at the intervals
set out in the written operating and inspection procedures.
10.1.10 Where the bottom of
the outer tank is in contact with the soil, the heating system shall be
monitored at least once a week to ensure that the 0°C isotherm is not
penetrating the soil.
10.1.11 Any settlement in
excess of that anticipated in the design shall be investigated and corrective
action taken as required.
10.1.12 Each entity shall
ensure that components in its LNG plant that could accumulate combustible
mixtures are purged after being taken out of service and before being returned
to service.
10.1.12 The periodic
inspections and tests shall be carried out in accordance with generally
accepted engineering practice/recommendations of Original Equipment
Manufacturer to ensure that each component is in good operating condition.
10.1.13 The support system or
foundation of each component shall be inspected at least annually to ensure
that the support system or foundation is sound.
10.1.14 Each emergency power
source at the facility shall be tested monthly for operability and annually to
ensure that it is capable of performing at its intended operating capacity.
10.1.15 Each facility
operator shall ensure that when a component is served by a single safety device
only and the safety device is taken out of service for maintenance or repair,
the component is also taken out of service.
10.1.16 The facility operator
shall ensure that where the operation of a component that is taken out of
service could cause a hazardous condition, a tag bearing the words “Do Not
Operate,” or the equivalent thereto, is attached to the controls of the
component. Wherever possible, the component shall be locked out.
10.1.17 Stop valves for
isolating pressure or vacuum-relief valves shall be locked or sealed open. On
each LNG container, no more than one stop valve shall be closed at one time.
They shall not be operated except by an authorized person.
10.2 Marine Shipping and
Receiving
10.2.1 Vehicle traffic shall
be prohibited on the pier or dock within 30m of the loading and unloading
manifold while transfer operations are in progress.
10.2.2 Warning signs or
barricades shall be used to indicate that transfer operations are in progress.
10.2.3 Prior to transfer,
the officer in charge of vessel cargo transfer and the person in charge of the
shore terminal shall inspect their respective facilities to ensure that
transfer equipment is in the proper operating condition.
10.2.4 Prior to transfer,
the officer in charge of vessel cargo transfer and the person in charge of the
shore terminal shall meet and determine the transfer procedure, verify that
ship-to-shore communications exist, and review emergency procedures.
10.2.5 Where making bulk
transfers into stationary storage containers, the LNG being transferred shall
be compatible in composition or temperature and density with the LNG already in
the container.
10.2.6 Where the composition
or temperature and density are not compatible, means shall be taken to prevent
stratification and vapor evolution that could cause rollover.
10.2.7 Where a mixing nozzle
or agitation system is provided, it shall be designed to prevent rollover.
10.3 Loading or Unloading
Operations
10.3.1 At least one
qualified person shall be in constant attendance while loading or unloading is
in progress.
10.3.2 Written procedures
shall be available to cover all transfer operations and shall cover emergency
as well as normal operating procedures.
10.3.3 Written procedures
shall be kept up-to-date and available to all personnel engaged in transfer
operations.
10.3.4 Sources of ignition,
such as welding, flames, and unclassified electrical equipment, shall not be
allowed in loading or unloading areas while transfer is in progress.
10.3.5 Loading and unloading
areas shall be posted with signs that read “No Smoking.”
10.3.6 Where multiple
products are loaded or unloaded at the same location, loading arms, hoses, or
manifolds shall be identified or marked to indicate the product or products to
be handled by each system.
10.3.7 Prior to transfer,
gauge readings shall be obtained or inventory established to ensure that the
receiving vessel cannot be overfilled, and levels shall be checked during
transfer operations.
10.3.8 The transfer system
shall be checked prior to use to ensure that valves are in the correct
position, and pressure and temperature conditions shall be observed during the
transfer operation.
10.3.9 The transfer system
shall be checked prior to use to ensure that valves are in the correct position
for transfer.
10.3.10 Transfer operations
shall be commenced slowly and if any unusual variance in pressure or
temperature occurs, transfer shall be stopped until the cause has been
determined and corrected.
10.3.11 Pressure and
temperature conditions shall be monitored during the transfer operation.
10.3.12 While tank car or
tank vehicle loading or unloading operations are in progress, rail and vehicle
traffic shall be prohibited within 7.6m of LNG facilities or within 15m of
refrigerants whose vapors are heavier than air.
10.3.13 Prior to connecting a
tank car, the car shall be checked and the brakes set, the derailer or switch
properly positioned, and warning signs or lights placed as required.
10.3.14 The warning signs or
lights shall not be removed or reset until the transfer is completed and the
car disconnected.
10.3.15 Truck vehicle engines
shall be shut off if not required for transfer operations.
10.3.16 Brakes shall be set
and wheels checked prior to connecting for unloading or loading.
10.3.17 The engine shall not
be started until the truck vehicle has been disconnected and any released
vapors have dissipated.
10.3.18 Prior to loading LNG
into a tank car or tank vehicle that is not in exclusive LNG service or contain
a positive pressure, a test shall be made to determine the oxygen content in
the container. If the oxygen content exceeds 2 percent by volume, the container
shall not be loaded until it has been purged to below 2 percent oxygen by
volume.
10.3.19 Prior to loading or
unloading, a tank vehicle shall be positioned so that it can exit the area
without backing up when the transfer operation is complete.
10.3.20 Tank cars and tank
vehicles that are top-loaded through an open dome shall be bonded electrically
to the fill piping or grounded prior to opening the dome.
10.3.21 Communications shall
be provided at loading and unloading locations so that the operator can be in
contact with other remotely located personnel who are associated with the
loading or unloading operation.
10.3.22 Other Operations
(i)
The
discharge from depressurizing shall be directed to minimize exposure to
personnel or equipment.
(ii)
Taking
an LNG container out of service shall not be regarded as a normal operation.
(iii)
All
such activities shall require the preparation of detailed procedures.
10.3.23 Each operating
company shall do the following:
(i)
Keep
the grounds of its LNG plant free from rubbish, debris, and other materials
that could present a fire hazard.
(ii)
Ensure
that the presence of foreign material contaminants or ice is avoided or
controlled to maintain the operational safety of each LNG plant component.
(iii)
Maintain
the grassed area of its LNG plant so that it does not create a fire hazard.
(iv)
Ensure
that fire control access routes within its LNG plant are unobstructed and
reasonably maintained in all weather conditions.
10.4 Maintenance Manual
10.4.1 Each facility
operator shall prepare a written manual that sets out an inspection and
maintenance programme for each component that is used in its facility.
10.4.2 The maintenance
manual for facility components shall include the following:
(i)
The
manner of carrying out and the frequency of the inspections and tests as
specified.
(ii)
All
procedures to be followed during repairs on a component that is operating while
it is being repaired to ensure the safety of persons and property at the
facility
(iii)
Each
facility operator shall conduct its maintenance programme in accordance with
its written manual for facility components.
In addition, the history
card of all critical equipments, instruments and systems shall be maintained.
10.5 Maintenance Workflow
(i)
The
objective of the work flow is to provide an integrated proactive and reactive
work plan so that repair work is minimized and reliability and availability are
optimized. Maintenance execution begins with the receipt of a work request and
concludes with the close out of the work order.
(ii)
Correct
prioritization of work and proactively preparing activities through high
quality work preparation, combined with accurate scheduling, will lead to a
more stable work environment. This will reduce deferments and breakdowns,
improve integrity and safety, and provide additional job satisfaction and
ownership to technicians.
(iii)
The
management and control of day-to-day maintenance on all process units and
utilities of a site is to provide:
(a) Support for a maintenance
strategy based on doing programmemed maintenance on time.
(b) Safe, healthy and
environmentally sound execution of maintenance work.
(c) Availability of equipment.
(d) Business efficiency.
(iv)
The
designated person for issue of work permit shall verify the execution of
preparation activities before issue of the work permit.
(v)
Maintenance
work shall be undertaken in accordance with work permit requirements.
(vi)
Inspection
personnel should be notified on time at which moment witness or hold points
set.
(vii)
A
verification of the HSE requirements should be carried as the maintenance
execution includes HSE review and a toolbox talk as outlined in the work permit
or work pack.
(viii)
The
maintenance supervisor should ensure that a toolbox talk is held before work
commences.
(ix)
Upon
completion of the job, the job site should be left safe, clean and tidy. Any
excess materials should be returned to the stores and tools should be cleaned
and returned to the workshop or put away in the correct storage place.
(x)
On
a daily basis, the progress of work should be reported. If the work is not
completed, it should continue the next working day after taking requisite
permission and approval from work permit issuing personnel.
(xi)
The
work permit duly signed shall be returned to issuing authority on completion of
job, removal of all material from site and handing over of facilities to user
etc.
10.6 Maintenance Strategy
(i)
The
facilities should be designed for minimum maintenance intervention.
(ii)
These
maintenance requirements should be clearly defined and further optimized based
on maintenance strategy reviews using tools such as reliability centred
maintenance, Risk Based Inspection and Risk Assessment Matrix (RAM), after
detailed equipment specifications are known.
(iii)
The
criticality of the equipment shall be taken into account during the maintenance
strategy selection.
(iv)
Appropriate
diagnostic tools and staff competencies shall be provided to facilitate rapid
fault finding and rectification and also to provide opportunistic maintenance
during outages.
(v)
Maintenance
strategies shall maximize non-intrusive & on line data acquisition to
support planning & analysis.
(vi)
Special
Critical Equipments shall have OEM defined performance standards which shall be
periodically tested and verified.
(vii)
Structural
and pipeline survey and painting shall be done on a regular basis.
10.7 The entity shall
prepare a written plan for preventive maintenance covering the scope,
resources, periodicity etc. The corrective measures should include the
preventive maintenance, scheduling, execution and closure.
10.8 Each facility should
have well defined system for identification of spare part, rationalization and
optimization to minimize any supply chain/logistics constraints & risks.
10.9 Well defined Roles
& Responsibilities matrix should be available made for each machine as well
as activity to be carried out in the workshop. The procedure for Audits and
Review of the workshop shall be documented and adhered to.
11.0 Inspection
(i)
Each
facility shall have written inspection, testing and commissioning programme in
place. Inspection shall include before commissioning during installation as
well as during regular operation of the LNG facilities.
(ii)
All
documents related to design, installation procedure of the respective vendors
and the manufacturer's instruction for pre-commissioning and commissioning of
the equipment, systems, instruments, control systems etc. shall be properly stored
and followed.
(iii)
Inspection
shall cover the review of test protocols and acceptance criteria that these are
in accordance with the protocols and acceptance criteria specified in line with
OEM specific requirements.
(iv)
Inspection
shall cover that the equipment is installed in accordance with design, and any
deviations documented and approved.
(v)
All
safety systems are installed inspected and tested as per design/OEM
requirement.
(vi)
Inspection
shall cover that all safety devices are installed and are in working condition
as per the design/OEM requirements.
(vii)
Inspection
shall cover the verification of various safety interlocks, ESD provided in the
design.
(viii)
Inspection
shall cover the adequacy of sealing systems.
(ix)
Inspection
shall cover the pressure and vacuum protection system.
(x)
Inspection
shall cover the electrical systems, check its integrity, earthing resistance,
bonding etc.
(xi)
Inspection
shall cover the integrity of mechanical and rotating equipment.
(xii)
The
integrity and efficacy of gas detection, fire protection and fighting system,
connected equipments shall be covered in the inspection.
(xiii)
Inspection
shall cover the efficacy of corrosion system.
(xiv)
Inspections
shall cover the bunds are installed where required and have connections to the
open drainage system in accordance with the P&IDs.
(xv)
Inspection
shall cover and review the mechanical completion records that the PSVs are of
the correct type and sizing as per the P&IDs/data sheets.
(xvi)
Inspection
shall cover location of inlet pipe-work to relieving devices in relation to
potential restrictions (e.g. above liquid levels, vessel internals, etc.)
(xvii) Inspection shall cover and
review P&IDs to check the position of isolation valves for relieving
devices, their capacities. Further, no protected equipment may be isolated from
the disposal system.
(xviii)
Inspection
to confirm by review of all vent locations (atmospheric vent from drums or
equipment seals) that they vent to safe location and in the event of liquid
carry over will not discharge to areas that may cause a hazard to personnel.
(xix)
Inspection
shall review the area classification layouts and associated studies to confirm
that all possible hazards have been appropriately considered (including
possible migration), the hazardous area drawings correctly account for the
actual location of the sources of release the hazardous areas have been
appropriately defined.
(xx)
Inspection
shall cover that all ESD devices move to their safe condition on loss of system
output, hydraulic power or instrument air. All ESDVs and actuators shall remain
functional following an explosion or under fire conditions for a sufficient
time period to perform their intended function.
(xxi)
The
maximum allowable back pressure and minimum design temperature of the relief
system shall be checked for suitability for the highest identified flow rate.
(xxii) Control System shall
include all status monitoring and actions to and from the Control Rooms.
(xxiii)
Inspection
to cover the escape and evacuation passages.
(xxiv)
Inspection
shall cover the emergency communication system for its effectiveness during
emergency situations.
(xxv) Each cryogenic piping
system shall be checked during and after cooldown stabilization for leaks in
flanges, valves, and seals.
Schedule - 1E
12.0 Competence Assurance
and Assessment
12.1 Every operating
company shall develop, implement, and maintain a written training plan to
instruct all LNG plant personnel with respect to the following:
(i)
Carrying
out the emergency procedures that relate to their duties at the LNG plant as
set out in the procedure manual and providing first aid.
(ii)
Permanent
maintenance, operating, and supervisory personnel with respect to the
following:
(a) The basic operations
carried out at the LNG plant.
(b) The characteristics and
potential hazards of LNG and other hazardous fluids involved in operating and
maintaining the LNG plant, including the serious danger from frostbite that can
result upon contact with LNG or cold refrigerants.
(c) The methods of carrying out
their duties of maintaining and operating the LNG plant as set out in the
manual of operating, maintenance and transfer procedures.
(d) Fire prevention, including
familiarization with the fire control plan of the LNG plant; fire fighting; the
potential causes of fire in an LNG plant; the types, sizes, and likely
consequences of a fire at an LNG plant.
(e) Recognizing situations when
it is necessary for the person to obtain assistance in order to maintain the
security of the LNG plant.
12.2 Each operating
company shall develop, implement, and maintain a written plan to keep personnel
of its LNG plant up-to-date on the function of the systems, fire prevention,
and security at the LNG plant.
12.3 The Refresher
programmes for training of all personnel shall be conducted an interval not
exceeding 2 years to keep personnel current on the knowledge and skills.
12.4 Every operating
company shall maintain a record for each employee of its LNG plant that sets
out the training given to the employee under this section.
12.5 Each operating
company shall ensure that LNG plant personnel receive applicable training and
have experience related to their assigned duties. Any person who has not
completed the training or received experience shall be under the control of
trained personnel.
12.6 For the design and
fabrication of components, each operator shall use personnel who have
demonstrated competence by training or experience in the design of comparable
components and for fabrication who have demonstrated competence by training or
experience in the fabrication of comparable components.
12.7 Supervisors and other
personnel utilized for construction, installation, inspection, or testing must
have demonstrated their capability to perform satisfactorily the assigned
function by appropriate training in the methods and equipment to be used or
related experience and accomplishments. Further their capability shall be
assessed periodically.
12.8 Each operator shall
utilize for operation or maintenance of components only those personnel who
have demonstrated their capability to perform their assigned functions by
successful completion of the training as specified an possess experience
related to the assigned operation or maintenance function.
12.9 Corrosion control
procedures including those for the design, installation, operation, and
maintenance of cathodic protection systems, must be carried out by, or under
the direction of, a person qualified by experience and training in corrosion
control technology.
12.10 Personnel having
security duties must be qualified to perform their assigned duties by
successful completion of the training as specified.
12.11 Each operator shall
follow a written plan to verify that personnel assigned operating, maintenance,
security, or fire protection duties at the LNG plant do not have any physical
condition that would impair performance of their assigned duties. The plan must
be designed to detect both readily observable disorders, such as physical
handicaps or injury, and conditions requiring professional examination for
discovery.
12.12 i. Each entity shall
provide and implement a written plan of initial training to instruct all
permanent maintenance, operating, and supervisory personnel—
(a) About the characteristics
and hazards of LNG and other flammable fluids used or handled at the facility,
including, with regard to LNG, low temperatures, flammability of mixtures with
air, odorless vapor, boil off characteristics, and reaction to water and water
spray;
(b) About the potential hazards
involved in operating and maintenance activities; and
(c) To carry out aspects of the
operating and maintenance procedures that relate to their assigned functions;
ii. All personnel of an LNG
installation shall be trained to carry out the emergency procedures that relate
to their assigned functions; and to give first-aid;
iii. All operating and
appropriate supervisory personnel of an LNG installation shall be trained to
understand detailed instructions on the facility operations, including
controls, functions, and operating procedures; and to understand the LNG
transfer procedures.
12.13 Personnel responsible
for security at an LNG plant must be trained in accordance with a written plan
of initial instruction to:
(i)
Recognize
breaches of security;
(ii)
Carry
out the security procedures that relate to their assigned duties;
(iii)
Be
familiar with basic plant operations and emergency procedures, as necessary to
effectively perform their assigned duties; and
(iv)
Recognize
conditions where security assistance is needed.
12.14 All personnel
involved in maintenance and operations of an LNG plant, including their
immediate supervisors, must be trained in accordance with a written plan of
initial instruction, including plant fire drills, to:
(i)
Know
and follow the fire prevention procedures as specified.
(ii)
Know
the potential causes and areas of fire determined.
(iii)
Know
the types, sizes, and predictable consequences of fire determined and.
(iv)
Know
and be able to perform their assigned fire control duties according to the
procedures and by proper use of equipment provided.
(v)
Marine.
(vi)
TT
Crew.
12.15 Each entity shall
maintain a system of records which—
(i)
Provide
evidence that the training programmes required by this subpart have been
implemented; and
(ii)
Provide
evidence that personnel have undergone and satisfactorily completed the
required training programmes.
(iii)
Records
must be maintained for one year after personnel are no longer assigned duties
at the LNG plant.
Schedule - 1F
13.0 Fire Prevention, Leak
Detection, Fire Fighting Facilities
13.1 General
(i)
Fire
protection shall be provided for all LNG facilities. The extent of such
protection shall be determined by an evaluation based upon sound fire
protection engineering principles, analysis of local conditions, hazards within
the facility and exposure to or from other property. The evaluation shall
determine as a minimum:
(ii)
The
type, quantity and location of equipment necessary for the detection and
control of fires, leaks and spills of LNG, flammable refrigerants or flammable
gases all potential fires non process and electrical fires.
(iii)
The
methods necessary for protection of the equipment and structures from the
effects of the fire exposure.
(iv)
The
equipment's and process systems to be operated with the emergency shutdown
(ESD) system.
(v)
The
type and location of sensors necessary for automatic operation of the emergency
shutdown (ESD) systems or its subsystems.
(vi)
The
availability and duties of individual plant personnel and the availability of
external response personnel operating an emergency.
(vii)
The
protective equipment and special training necessary by the individual plant
personnel for their respective emergency duties.
(viii)
The
detailed procedure manual shall be prepared to cover the potential emergency
conditions. Such procedure shall include but not necessarily be limited to the
followings:
(a) Shutdown or isolation of
various equipment in full or partial and other applicable steps to ensure that
the escape of gas or liquid is promptly cut off or reduced as much as possible.
(b) Use of fire protection
facilities.
(c) Notification of public
authorities.
(d) First aid and
(e) Duties of personnel.
(f) Communication procedure in case
of emergency.
(ix)
All
personnel shall be trained in their respective duties contained in the
emergency manual. Those personnel responsible for the use of fire protection or
other prime emergency equipment shall be trained in the use of equipment.
Refresher training of personnel shall be conducted at least on annual basis.
(x)
The
planning of effective fire control measures be co-ordinated with the authority
having jurisdiction and emergency handling agencies such as fire and police
departments who are expected to respond to such emergencies.
13.2 Fire proofing
(i)
Fire
proofing shall be used to protect equipment, typically: ESD valves, safety
critical control equipment, vessels containing quantities of liquid hydrocarbon
and structural supports, which on failure would escalation the incident and/or
endanger the activities of emergency response personnel. Equipment which can
receive thermal radiation, in excess of that defined below for a sufficient
period to cause failure shall be provided with fire proofing protection. The
fire proofing shall provide protection for the duration of the hazard event but
shall as a minimum provide 90 min protection.
|
EQUIPMENT INSIDE BOUNDARY
|
MAXIMUM THERMAL RADIATION FLUX (kW/m2)
|
|
concrete outer surface of adjacent storage tanks
|
32
|
|
Metal outer surface of adjacent storage tanks
|
15
|
|
The outer surfaces of adjacent pressure storage
vessels and process facilities
|
15
|
|
control rooms, Maintenance workshops,
laboratories, warehouses etc.
|
8
|
|
Administrative buildings
|
5
|
(ii)
Fire
protection in the form of insulation or water deluge shall be provided for
pressure vessels, which can receive thermal radiation fluxes in excess of that
defined in Annex A, to prevent such vessels failing and releasing superheated
liquid, which can result in a BLEVE.
(iii)
It
shall be recognised that pressure vessels subject to radiation from a major
incident such as an LNG tank fire shall require protection for much more than
90 min. Protection for long duration incidents may not be achieved by
insulation and a water deluge system is required.
(iv)
The
calculation of water deluge, insulation for fire protection of structures, etc.
as protection against fires shall be performed for the fluid which gives rise
to the highest radiation flux.
(v)
Fire
proofing should be designed and executed in accordance with GAP 2.5.1 or API
2218 or equivalent standards.
13.3 Leak detection
(i)
Systems
shall be provided to detect possible accidental events i.e. spillage, leakage,
smoke, fire etc. which could occur in the plant.
(ii)
The
arrangement of detectors shall be such as to always provide redundancy and to
prevent false and spurious alarms. Voting technique arrangement may be used.
Events may include:
(a) Earthquake - Where
applicable seismic acceleration monitoring shall be provided, giving signals to
automatically initiate the plant shutdown when the earthquake reaches a
pre-defined level. This pre-defined level is chosen by the operator.
(b) LNG spillage, gas leakage,
flame and smoke.
These detection systems are
intended to rapidly and reliably detect any LNG spillage or flammable gas
leakage and any fire condition in the plant.
Continuously operating
detection systems shall be installed at every location, outdoors and indoors,
where leaks are credible.
(iii)
Manual
call points shall be provided in the hazardous plant areas, typically those
plant areas covered by flame and/or combustible gas detectors, and provided on
likely escape routes from these areas.
13.4 Active Protection
The active protection
includes:
(i)
fire
water system i.e. mains network with hydrants and monitors;
(ii)
spraying
systems;
(iii)
water
curtains;
(iv)
foam
generators;
(v)
fixed
dry chemical powder systems;
(vi)
fire
fighting vehicle(s);
(vii)
Portable/mobile
fire extinguishers.
13.4.1 Fire water system
(i)
Water
has particular uses on an LNG plant. However, LNG pool fires are neither
controlled nor extinguished by water. Application of water on a liquid surface
will increase the vapour formation rate thus increasing the burning rate with
negative consequences on fire control. in an LNG plant, under fire conditions,
water may be used in great quantities for cooling storage tanks, equipment and
structures which are subject to flame impingement or heat radiation due to a
fire. As a result, the risk of escalation of the fire and deterioration of equipment
can be reduced by early and concentrated cooling.
(ii)
Plant
surface water and fire water drainage systems and LNG spill collection systems
shall be designed to minimize the possibility of fire water increasing the
vaporization rate of any LNG spill. This may be achieved by plant area and fire
water systems segregation, in the event that firewater run-off is contaminated
provision shall be made to prevent the pollution of natural water-courses.
(iii)
Fire
water networks shall be provided around all sections of the plant. Water supply
systems shall be designed in independent sections so that in case of
maintenance or damage of a section the water supply to other sections is not
interrupted. Both fire pumps should not discharge to the network through a
single header.
(iv)
All
these networks, including fire hydrants shall be maintained primed under a
minimum pressure of at least 7.0 kg/cm2 at hydraulically farthest point by
means of jockey pumps or an elevated tank. Special provisions shall be taken to
avoid any damage due to freezing etc.
(v)
Water
supply systems shall be able to provide, at fire fighting system operating
pressure, a water flow not less than that required by the fire fighting systems
as per design plus an allowance of 100 l/s for hand hoses. The fire water
supply shall be sufficient to address this incident, but shall not be less than
4 hour.
(vi)
Number
of pumps, Capacity of pumps, type of drive of pumps (diesel engine or motor
driven) and stand by requirements of pumps shall be in worked out on the basis
of single major fire at LNG Terminal and Jetty each, in case of combined fire
fighting facilities, the design shall consider simultaneous major fires at
jetty and LNG terminal.
(vii)
The
fire fighting system shall be designed to handle the largest risk for 4 hours
in case of combined facilities, it shall be based on double risk i.e. one
largest risk at LNG Terminal and Jetty each.
(viii)
The
water storage capacity of 4 hours shall be based on the design discharge
capacity of fire water pumps.
(ix)
LNG
plants (particularly impounding basins) shall be equipped with drainage systems
capable of draining the volumes of water generated by these systems.
(x)
The
maximum fire water flow rate at the LNG jetty irrespective of the LNG carrier
size and LNG unloading rate, shall be calculated based on following:
(a) Two tower monitors shall be
provided @ 1500 GPM.
(b) Two Jumbo curtain nozzles
shall be provided at the front side of jetty head between LNG carrier and jetty
head having application rate of 70 lpm/meter run of the jetty.
(c) Fire Protection of jetty
manifold, drain, vessels @ of 10.2 lpm/m2.
(d) Supplementary hose
requirement of 144 M3/hr.
13.4.2 Spraying system
(i)
The
importance of cooling each equipment item and the amount of water required
shall depend on the hazard assessment.
(ii)
Where
required, spraying systems shall distribute the water flow evenly onto the
exposed surfaces. In this way equipment subjected to radiation shall not reach
unacceptably high local temperatures.
(iii)
Recirculation
of used water may be considered where practicable and shall depend on its ability
to remove the transferred heat in a fire of long duration while keeping the
integrity and working ability of the unit. Precautions should also be taken to
ensure that flammable materials are not returned with the re-circulated water.
(iv)
The
calculation of the incident water flow on each unit shall be carried out on
basis of received radiation flux for each scenario using appropriate validated
models in order to limit the surface temperature consistent with the integrity
of the structure.
(v)
For
the LNG storage tanks, water sprays shall be provided on the tank shell
including the roof and the appurtenances on the tank. For single containment
tanks, water application rate for the tank roof and walls shall be calculated
using method detailed in Appendix 5 of IP Model Code of Safe Practice Part 9 of
NFPA 15. The water application rate on the appurtenances shall be 10.2 lpm/m2
as per this code. For double/full containment tanks, the water application rate
for the tank roof/outer shell shall be 3 lpm/m2. No cooling is required for
cooling the outer shell of tanks having concrete outer tank.
(vi)
The
water densities applicable to other equipment shall be as follows:
(a) Vessels, structural members
piping & valves manifolds: 10.2 lpm/m2
(b) Pumps: 20.4 lpm/m2
(vii)
The
deluge valves on the water spray systems on the tanks as well as the pumps,
compressors, vessels etc. shall be actuated automatically through a fire
detection system installed around the facilities with provisions of manual
actuation from Control Room or locally at site.
13.4.3 Water curtains
13.4.3.1 General
(i)
Water
curtains may be used to mitigate gas releases and protect against radiant heat.
(ii)
The
aim of a water curtain system is to rapidly lower the gas concentration of an
LNG vapour cloud in order to attain the lower flammability limit of gas in air.
(iii)
Water
curtains transfer heat to the cold natural gas cloud through contact between
LNG vapours and water droplets.
(iv)
In
addition water curtains entrain large volumes of air that transfer additional
heat, dilute the LNG vapour cloud, thus enhance its buoyancy thus facilitating
its dispersion.
(v)
The
effectiveness of a water curtain is reduced as the wind speed increases, but
natural dispersion is increased at high wind velocities.
(vi)
Effective
performance of water curtains is dependent on many different conditions, i.e.
nozzle type, water pressure, nozzle location, nozzle spacing.
(vii)
Water
curtains are known to mitigate heat radiation and gas cloud dispersion
incidents. However they cannot be relied upon as the primary means of
protection.
13.4.3.2 Characteristics
and location
(i)
Water
curtains shall be positioned as per the hazard assessment.
(ii)
Water
curtains can be located as close as possible to the area of possible spill and
concentration of LNG taking into account plant requirements. The possibility of
water curtain droplets entering the impounding areas should be minimised in
order to avoid an increase in the LNG evaporation rate.
(iii)
Water
curtains may be positioned around the impounding areas. In this way they act as
a barrier for cold natural gas clouds originating from LNG leaks.
(iv)
Nozzle
spacing should follow vendors' recommendations.
13.4.4 Foam generation
(i)
Fire
fighting foams can be used to reduce the heat radiation from LNG pool fires and
aid safer gas dispersion in the event that the leak does not ignite. The extent
of their use will depend on the hazard assessment.
(ii)
Foam
generators shall be specifically designed to operate when engulfed in an LNG
fire, unless the design of the system is such that the generator is protected
from excessive heat flux. The design of the system shall prevent water in a
liquid form from entering the impounding area.
(iii)
Foam
to be used shall be dry powder compatible and proven suitable with LNG fires in
accordance with EN 12065. Typical expansion ratios should be in the order of
500:1.
(iv)
LNG
impounding basins or areas should be fitted with fixed foam generators to enable
rapid response and remote activation.
(v)
The
volume of foam flow for LNG impounding basins or areas shall be determined in
accordance with EN 12065 in order to reduce heat radiation, taking into account
the possible failure of one generator and also the destruction rate of the foam
due to fire. A foam retention device may be placed around the impounding basin
or area where there is a risk of foam loss due to wind.
(vi)
Foam
agent reserves shall be situated in a place sheltered from heat radiation (from
fire and solar). The foam agent storage capacity (Q) shall be at least equal to
the sum of the following quantities:
Q = Q 1+Q2+Q3
Where
Q1 = t×r×S
t is the foam agent
procurement time (hours), (with a ceiling at 48 h);
r is the foam agent
destruction rate (metres/hour) (for example r = 0, 11 m/h);
Q = Q 1+
Q2+Q3
Where
Q1 = t×r×S
t is the foam agent
procurement time (hours), (with a ceiling at 48 h);
r is the foam agent
destruction rate (metres/hour) (for example r = 0, 11 m/h);
S is the largest area
to be covered (square meters);
Q 2 is the quantity
necessary for periodic foam system tests. In the absence of other information,
operation of the foam agent pumps at the maximum flow rate for 15 min is to be
taken for determining this quantity;
Q3 is the quantity
necessary for first layer build-up
13.4.5 Portable foam
equipment
The requirement for
portable foam equipment shall be defined by the Hazard Assessment, when
provided, portable foam - generating equipment connected to the firewater
supply shall be equipped with enough hose to reach the most distant hazard they
are expected to protect.
13.5 LNG fire extinguishing
with dry powder
13.5.1 General
(i)
Equipment
for LNG fire fighting shall be in accordance with relevant codes and/or
standards. The recommended extinguishing medium for LNG fires is dry powder.
(ii)
To
extinguish a burning pool of LNG, dry powder shall be applied above the surface
of the liquid without allowing the powder to impinge and agitate the surface.
(iii)
Agitation
of the liquid surface will increase the burning rate due to the increase in
vapour formation instead of extinguishing the fire.
(iv)
To
achieve optimum results in extinguishing an LNG fire, the fire's total area shall
be covered immediately and all at once. Otherwise residual flames of LNG pool
sectors can rapidly re-ignite gas emanating from the extinguished sectors. In
addition, provisions shall be taken to cool any structure surfaces which could
re-ignite the gas.
(v)
Enough
quantity of powder to allow a second shot in case of a re-ignition.
13.5.2 Types of dry powder
The dry powder shall be
proven suitable for gas fire extinguishing; foam compatibility shall be in
accordance with EN 12065.
13.5.3 Location of dry powder
systems
Dry powder systems should
be installed in an LNG plant near points of possible LNG and hydrocarbon
leakage with regard to the hazard assessment and typically near the following
units:
(i)
loading/unloading
areas as per EN 1532;
(ii)
LNG
pumps;
(iii)
ESD
valves;
(iv)
tail
pipes of tank PSV (fixed systems) alternatively nitrogen stuffing systems may
be used.
13.5.4 Portable/mobile fire
extinguishers
(i)
The
following types of extinguishers are foreseen:
(a) foam type extinguishers in
area where oil may be present (compressors building, hydraulic unit of transfer
arms at the jetty);
(b) carbon dioxide type
extinguishers in electrical and instrumentation buildings;
(c) dry chemical powder
extinguishers in process areas.
(ii)
The
fire extinguishers shall comply with the requirements of the local regulations.
(iii)
These
extinguishers are installed in the critical locations along the circulation
paths and/or platforms. Their position shall be on a recognised escape path
from the identified hazard they are installed to mitigate.
13.5.5 Fire fighting
vehicle
(i)
Where
external LNG experienced assistance in case of emergency is not available the
plant shall be equipped with at least one fire fighting vehicle to give the
required response in case of emergency.
(ii)
This
fire fighting vehicle will be fitted with:
(a) foam system suitable for
the anticipated type of fire;
(b) dry chemical powder
(iii)
Fireman
protective clothing suitable for LNG service (splash and fire) shall be
provided.
(iv)
The
vehicle shall be sufficiently equipped and manned to provide emergency response
whilst waiting for off-site support.
13.6 Other requirements
13.6.1 Provisions to
minimise hazards in buildings
(i)
This
is achieved by maintaining a continuous positive pressure ventilation in the
electrical and instrumentation rooms of the buildings located inside the
process areas.
(ii)
In
case of gas detection in the process areas, the operators in the control rooms
have the possibility to shutdown remotely the HVAc of the affected buildings.
(iii)
In
case of gas detection at the building air inlet, the external fans are tripped
and the louvers closed in order to prevent any gas entrance in the electrical
and instrumentation rooms where a risk of ignition exists.
13.6.2 Fire cabinets/hoses
boxes
(i)
An
accessible supply of fire fighting equipment shall be located where hydrants
are intended for use by either plant personnel or the local fire brigade.
(ii)
Equipment
shall be stored in cabinets which are:
(a) clearly identifiable
(b) provided with means to
securely store equipment;
(c) suitably constructed and
protected for the plant local environment;
(d) naturally ventilated;
(e) located so that personnel
can gain access from a safe area.
(iii)
Where
provide cabinets and their required contents should be approved by the local
fire authority. As a minimum each cabinet should be equipped with:
(a) two adjustable mist/solid
stream nozzles:
(b) one hydrant spanner;
(c) four coupling spanners;
(d) two hose coupling gaskets;
(e) four × 15m lengths of fire
hose;
(f) a weatherproof list of
contents.
Schedule - 1G
14.0 Safety Management
System
14.1 The organization
should establish a safety management system which shall be an integral part of
the overall management system. Safety Management System (SMS) should be based
on PDCA (Plan, Do, Check and Act) cycle which comprises of:
(i) Policy setting - includes
policy, corporate acceptance of responsibility, objectives, requirements,
strategies;
(ii) Organization - includes
structure, accountability and safety culture, involvement of the workforce,
systems for performing risk assessment;
(iii) Planning and execution -
includes operational standards and procedures for controlling risks, permit to
work, competence and training, selection & control over contractors,
management of change, planning & control for emergencies and occupational
health;
(iv) Measuring and evaluating -
includes active monitoring, recording and investigation of incidents/accidents,
auditing, handling of non-conformities;
(v) Continuous improvement -
includes review and application of the lessons learnt. Safety management system
should not degenerate into a paper exercise only, conducted solely to meet
regulatory requirements.
14.2 Elements of Safety
Management system
Safety management system
should include at least the following basic elements:
(i)
Safety Organization- Leadership and Management Commitment should
be clearly visible in the SMS. Management should develop and endorse a written
description of the company's safety and environmental policies and
organizational structure that define responsibilities, authorities, and lines
of communication required to implement the management programme. Management
should review the safety and environmental management programme to determine if
it continues to be suitable, adequate and effective at predetermined frequency.
The management review should address the possible need for changes to policy,
objectives, and other elements of the programme in light of programme audit
results, changing circumstances and the commitment to continual improvement.
Observations, conclusions and recommendations of management review should be
documented.
(ii)
Safety Information- Comprehensive safety and environmental
information for the facility, which include documentation on process,
mechanical and facility design, should be developed and maintained throughout
the life of the facility.
(iii)
Process Hazard Analysis- The purpose of Process Hazard Analysis
(PHA) is to minimise the likelihood of the occurrence and the consequences of a
dangerous substance release by identifying, evaluating and controlling the
events that could lead to the release. Process hazards analysis should be
performed for any facility to identify, evaluate, and reduce the likelihood
and/or minimize the consequences of uncontrolled releases and other safety or
environmental incidents. Human factors should also be considered in this
analysis.
The process hazard analysis
should be updated and revalidated by a team, having requisite back ground, at
least every 5 years after the completion of initial process hazard analysis.
Recommendations resulting from the PHA should be completed before start-up for
a new process or facility, or modification in existing facility.
(iv)
Operating Procedures- Written down operating procedures shall be
available describing tasks to be performed, data to be recorded, operating
conditions to be maintained, samples to be collected and safety and health
precautions to be taken for safe operation. Operating procedures should be
based on process safety information so that all known hazards are taken care
of. The human factors associated with format, content, and intended use should
be considered to minimize the likelihood of procedural error.
The operating procedures
shall provide plant specific instructions on what steps to be taken or followed
while carrying out Startup, Normal operation, Temporary operation, Normal
shut-down and Emergency operation and shut-down.
Manuals of operating
procedures shall be made available to the employees. Training shall be imparted
to the operators on operating procedures and should be certified as competent.
All the documents in
operating plan shall be controlled and amended with due authorisation. Whenever
new document has been prescribed, all the old documents shall be destroyed.
When changes are made in
facilities, operating procedures should be reviewed as part of the management
of change procedure. In addition, operating procedures should be reviewed
periodically to verify that they reflect current and actual operating
practices. Operating manuals should be certified as updated by
authorized/competent person every year.
(v)
Safe Work Practices- The entity shall maintain procedures that
address safe work practices to ensure the safe conduct of operating,
maintenance, and emergency response activities and the control of materials
that impact safety. These safe work practices may apply to multiple locations
and will normally be in written form (safety manual, safety standards, work
rules, etc.) but site-specific work practices shall be prepared and followed.
In cases where an employee believes that following a procedure will cause an
unsafe condition, one shall have authority to stop work and get permission to
deviate. Deviations should be documented for future analysis.
(vi)
Training-
The training programme shall establish and implement programmes so that all
personnel are trained to work safely and are aware of environmental
considerations, in accordance with their duties and responsibilities.
Training shall address the
operating procedures, the safe work practices, and the emergency response and
control measures. Any change in facilities that requires new or modification of
existing operating procedures may require training for the safe implementation
of those procedures. Training should be provided by qualified instructors and
documented.
The training provided to
contract personnel should include applicable site-specific safety and
environmental procedures and rules pertaining to the facility and the
applicable provisions of emergency action plans.
The entity should verify
contractor training utilizing a variety of methods, which may include audits of
the contractor's environmental, health and safety training programmes; and
operator observation of contractor work performance.
(vii)
Management of Change (MOC)- There should be procedures to identify and
control hazards associated with change and to maintain the accuracy of safety
information. For each MOC, the operator shall identify the potential risks
associated with the change and any required approvals prior to the introduction
of such changes. The types of changes that a MOC procedure addresses shall
include:
(a) technical,
(b) physical,
(c) procedural, and
(d) organizational.
This procedure shall
consider permanent or temporary changes. The process shall incorporate planning
for the effects of the change for each of these situations. These procedures
should cover the following:
(a) The process and mechanical
design basis for the proposed change.
(b) An analysis of the safety,
health, and environmental considerations involved in the proposed change,
including, as appropriate, a hazards analysis.
(c) The necessary revisions of
the operating procedures, safe work practices, and training programme.
(d) Communication of the
proposed change and the consequences of that change to appropriate personnel.
(e) The necessary revisions of
the safety and environmental information.
(f) The duration of the change,
if temporary.
(g) Required authorizations to
effect the change.
(viii)
Contractors- When selecting contractors, operators should obtain and evaluate
information regarding a contractor's safety and environmental management
policies and practices, and performance thereunder, and the contractor's
procedures for selecting sub-contractors. The entity shall communicate their
safety and environmental management system expectations to contractors and
identify any specific safety or environmental management requirements they have
for contractors.
Interfacing of SMS of
various entities (operator, contractor/service provider, subcontractor and
third-party) should be ensured through a well written bridging document. Entity
shall document the clear roles and responsibilities with its contractors.
(ix)
Assurance of quality and mechanical integrity of critical
equipment-
Procedures in place should be implemented so that critical equipment for any
facility is designed, fabricated, installed, tested, inspected, monitored, and
maintained in a manner consistent with appropriate service requirements,
manufacturer's recommendations or industry standards. Entity shall maintain
inspection and testing procedures for safety-related equipment. Human factors
should be considered, particularly regarding equipment accessibility for
operation, maintenance and testing.
(x)
Pre-startup Safety Review- Before a new or modified unit is started, a
systematic check should be made to ensure that the construction and equipment
are in accordance with specifications; operating procedures have been reviewed;
hazards analysis recommendations have been considered, addressed and
implemented; and personnel have been trained. It should be ensured that
programmes to address management of change are in place.
(xi)
Permit to Work (PTW) System- PTW system is a formal written system used
to control certain types of work which are identified as potentially hazardous.
Essential features of permit-to-work systems are:
(a) clear identification of who
may authorize particular jobs (and any limits to their authority) and who is
responsible for specifying the necessary precautions;
(b) training and instruction in
the issue, use and closure of permits;
(c) monitoring and auditing to ensure
that the system works as intended;
(d) clear identification of the
types of work considered hazardous;
(e) clear and standardized
identification of tasks, risk assessments, permitted task duration and
supplemental or simultaneous activity and control measures.
(xii)
Emergency Planning and Response- A comprehensive Emergency Response and
Disaster Management Plan (ERDMP) shall be developed in accordance to the
Petroleum and Natural Gas Regulatory Board (Codes of Practices for Emergency
Response and Disaster Management Plan (ERDMP)) Regulations, 2010. The copies of
the ERDMP for the LNG facilities including jetty shall be maintained at each
installation. The emergency response planning shall have clear written
procedures for expected actions during anticipated emergencies. Emergency
response plan shall include operational and procedural requirements for various
emergency scenarios that are relevant for the installation.
The emergency procedures
shall include, at a minimum, emergencies that are anticipated from an operating
malfunction, structural collapse of part of the LNG plant, personnel error,
forces of nature, and activities carried on adjacent to the plant.
(i)
The
emergency procedures shall include but not be limited to procedures for
responding to controllable emergencies, including the following:
(a) The notifying of personnel
(b) The use of equipment that
is appropriate for handling of the emergency
(c) The shutdown or isolation
of various portions of the equipment
(d) Other steps to ensure that
the escape of gas or liquid is promptly cut off or reduced as much as possible
(ii)
The
emergency procedures shall include procedures for recognizing an uncontrollable
emergency and for taking action to achieve the following:
(a) Minimize harm to the
personnel at the LNG plant and to the public
(b) Provide prompt notification
of the emergency to the appropriate local officials, including the possible
need to evacuate persons from the vicinity of the LNG plant
(iii)
The
emergency procedures shall include procedures for coordinating with local officials
in the preparation of an emergency evacuation plan that sets forth the steps
necessary to protect the public in the event of an emergency, including the
following:
(a) Quantity and location of
fire equipment throughout the LNG plant
(b) Potential hazards at the
LNG plant
(c) Communication and
emergency-control capabilities at the LNG plant
(d) Status of each emergency
(xiii)
Incident Investigation and Analysis- Procedures for
investigation of all incidents as per the Petroleum and Natural Gas Regulatory
Board (Codes of Practices for Emergency Response and Disaster Management Plan
(ERDMP)) Regulations, 2010 shall be developed. Incident investigations should
be initiated as promptly as possible, considering the necessity of securing the
incident scene and protecting people and the environment. The intent of the
investigation should be to learn from the incident and help prevent similar
incidents. A corrective action programme should be established based on the
findings of the investigation to prevent recurrence.
(xiv)
Compliance Audit- Safety Audits are the periodic examination
of the functioning of safety system. It gives an idea about how effectively the
safety system is implemented and how they are being accomplished. It is the
feed back mechanism that provides management with the status and measurement of
effectiveness of the various safety system elements and activities and leads to
the appropriate control over these efforts.
The audit programme and
procedures should cover:
(a) The activities and areas to
be considered in audits
(b) The frequency of audits
(c) The audit team
(d) How audits will be
conducted
(e) Audit Reporting
The findings and
conclusions of the audit should be provided to the management. Management
should establish a system to determine and document the appropriate response to
the findings and to assure satisfactory resolution. The audit report should be
retained at least until the completion of the next audit.
14.3 List of Standards and
References referred to in Schedule 1 shall be as given in Annexure III.
ANNEXURE I
Requirements
for LNG Installations using ASME Containers for stationary applications
1.0 Scope
1.1 This chapter provides
requirements for the installation, design, fabrication, and siting of LNG
installations using containers of 379 m3 capacity and less constructed
in accordance with the ASME Boiler and Pressure Vessel Code or Gas
Cylinder Rules for vehicle fueling and commercial and industrial
applications.
1.2 The maximum aggregate
storage capacity shall be 1060 m3.
2.0 General Requirements.
2.1 Site preparation
shall include provisions for retention of spilled LNG, within the limits of
plant property, and for surface water drainage.
2.2 All-weather
accessibility to the site for emergency services equipment shall be provided.
2.3 Storage and transfer
equipment at unattended facilities shall be secured to prevent tampering.
2.4 Operating
instructions identifying the location and operation of emergency controls shall
be posted conspicuously in the facility area.
2.5 Designers,
fabricators, and constructors of LNG facility equipment shall be competent in
the design, fabrication, and construction of LNG containers, cryogenic
equipment, piping systems, fire protection equipment, and other components of
the facility.
2.6 Supervision shall be
provided for the fabrication, construction, and acceptance tests of facility
components necessary to ensure that facilities are in compliance with this
standard.
2.7 Facilities
transferring LNG during the night shall have adequate lighting at the transfer
area as specified in clause 8.9.1 of Schedule 1B.
2.8 The maximum allowable
working pressure shall be specified for all pressure-containing components.
3.0 Containers
3.1 All piping that is a
part of an LNG container, including piping between the inner and outer
containers, shall be in accordance with either Section VIII of the
ASME Boiler and Pressure Vessel Code, or ASME B 31.3, Process Piping.
3.2 Internal piping
between the inner tank and the outer tank and within the insulation space shall
be designed for the maximum allowable working pressure of the inner tank, with
allowance for thermal stresses.
3.3 Bellows shall not be
permitted within the insulation space.
3.4 Containers shall be
double-walled, with the inner tank holding LNG surrounded by insulation
contained within the outer tank.
3.5 The inner tank shall
be of welded construction and in accordance with the ASME Boiler and
Pressure Vessel Code, Section VIII, or Static and Mobile Pressure Vessels
Rules and shall be stamped and certified.
3.6 The inner tank
supports shall be designed for shipping, seismic, and operating loads.
3.7 The support system to
accommodate the expansion and contraction of the inner tank shall be designed
so that the resulting stresses imparted to the inner and outer tanks are within
allowable limits as per design.
3.8 The outer tank shall
be of welded construction using any of the following materials:
(i)
Any
of the carbon steels in Section VIII, Part UCS of the ASME Boiler and
Pressure Vessel Code or equivalent at temperatures at or above the minimum
allowable use temperature in Table 1A of the ASME Boiler and Pressure
Vessel Code, Section II, Part D.
(ii)
Materials
with a melting point below 1093°C where the container is buried or mounded.
3.9 Where vacuum
insulation is used, the outer tank shall be designed by either of the
following:
(i)
The
ASME Boiler and Pressure Vessel Code, Section VIII, Parts UG-28, -29, -30,
and -33 or equivalent, using an external pressure of not less than 15 psi (100
kPa).
(ii)
The
CGA 341, Standard for Insulated Cargo Tank Specification for Cryogenic
Liquids.
3.10 Heads and spherical
outer tanks that are formed in segments and assembled by welding shall be
designed in accordance with the ASME Boiler and Pressure Vessel Code,
Section VIII, Parts UG-28, -29, -30, and -33 or equivalent, using an external
pressure of 15 psi (100 kPa).
3.11 The outer tank shall
be equipped with a relief device or other device to release internal pressure.
(i)
3.11.1 The
discharge area shall be at least 0.0034 cm2/kg of the water capacity
of the inner tank, but the area shall not exceed 2000 cm2.
(ii)
3.11.2 The
relief device shall function at a pressure not exceeding the internal design
pressure of the outer tank, the external design pressure of the inner tank, or
25 psi (172 kPa), whichever is less.
3.12 Thermal barriers
shall be provided to prevent the outer tank from falling below its design
temperature.
3.13 Seismic Design.
3.13.1 Shop-built containers
designed and constructed in accordance with the ASME Boiler and Pressure
Vessel Code or equivalent, and their support systems, shall be designed for the
dynamic forces associated with horizontal and vertical accelerations as
follows:
V = Zc × W for
horizontal force
P = 2/3
× Zc × W for vertical force
where:
Zc = the seismic
coefficient equal to 0. 60 SDS
SDS = the
maximum design spectral acceleration determined in accordance with the non
building structures provisions of the NEHRP Recommended Provisions for
Seismic Regulation for New Buildings and Other Structures, using an importance
factor, I, of 1.0, for the site class most representative of the site
conditions where the LNG facility is located
W = the total weight
of the container and its contents
3.13.2 Usage.
(i)
The
method of design described in 3.13.1 shall be used only where the natural
period T of the shop-built container and its supporting system is less than
0.06 second.
(ii)
If
the natural period T is 0.6 or greater, than seismic design
provisions of IS 1893 shall apply.
3.13.3 The container and its
supports shall be designed for the resultant seismic forces in combination with
the operating loads, using the allowable stresses increase shown in the code or
standard used to design the container or its supports.
3.14 Each container shall
be identified by the attachment of a nameplate(s) in an accessible location
marked with the following:
(i)
Manufacturer's
name and date built
(ii)
Nominal
liquid capacity
(iii)
Design
pressure at the top of the container
(iv)
Maximum
permitted liquid density
(v)
Maximum
filling level
(vi)
Minimum
design temperature
3.15 All penetrations of
storage containers shall be identified.
4.0 Container Filling
Containers designed to
operate at a pressure in excess of 15 psi (100 kPa) shall be equipped with a
device(s) that prevents the container from becoming liquid full or from
covering the inlet of the relief device(s) with liquid when the pressure in the
container reaches the set pressure of the relieving device(s) under all
conditions.
5.0 Container Foundations
and Supports
5.1 LNG container
foundations shall be designed and constructed in accordance with NFPA
5000, Building Construction and Safety Code or equivalent.
5.2 The design of saddles
and legs shall including shipping loads, erection loads, wind loads, and
thermal loads.
5.3 Foundations and
supports shall have a fire resistance rating of not less than 2 hours and shall
be resistant to dislodgement by hose streams.
5.4 LNG storage
containers installed in an area subject to flooding shall be secured to prevent
the release of LNG or flotation of the container in the event of a flood.
6.0 Container Installation
6.1 LNG containers of 3.8
m3 and smaller shall be located as follows:
(i)
0.47
m3 or less, zero m from buildings and the line of adjoining
property.
(ii)
3.8
m3 or less, 3.0m from buildings and the line of adjoining
property.
6.2 Minimum Distance
6.2.1 The minimum distance
from edge of impoundment or container drainage system serving aboveground and
mounded containers larger than 3.8 m3 to buildings and property
lines that can be built upon and between containers shall be in accordance with
Table 1.
Table 1-Distances from Impoundment Areas to Property Lines
That
Can be Built Upon
|
Container Water Capacity
|
Minimum Distance from Edge of Impoundment or
Container Drainage System to Property Lines that can be Built Upon
|
Minimum Distance Between Storage Containers
|
|
m3
|
m
|
m
|
|
3.8-7.6
|
4.6
|
1.5
|
|
7.6-56.8
|
7.6
|
1.5
|
|
56.8-114
|
15
|
1.5
|
|
114-265
|
23
|
1/4 of the sum of the diameters of adjacent
|
|
>265 and upto 379
|
0.7 times the container diameter [30m minimum]
|
containers [1.5m minimum]
|
6.2.2 The distance from
edge of impoundment or container drainage system to buildings to buildings or
walls of concrete or masonry construction shall be reduced from the distance in
Table 1 with the approval of the authority having jurisdiction with a minimum of
3m.
6.3 Underground LNG tanks
shall be installed in accordance with Table 2.
Table 2 Spacing of Underground LNG Containers
|
Container Water Capacity (gal)
|
Minimum Distance from Buildings and the Adjoining
Property Line That can be Built Upon (m)
|
Distance Between Containers (m)
|
|
<57
|
4.6
|
4.6
|
|
57-≤114
|
7.6
|
4.6
|
|
>114 and upto 379
|
12
|
4.6
|
6.4 Buried and
underground containers shall be provided with means to prevent the 0°C isotherm
from penetrating the soil.
6.5 Where heating systems
are used, they shall be installed such that any heating element or temperature
sensor used for control can be replaced.
6.6 All buried or mounded
components in contact with the soil shall be constructed from material
resistant to soil corrosion or protected to minimize corrosion.
6.7 A clear space of at
least 0.9m shall be provided for access to all isolation valves serving
multiple containers.
6.8 LNG containers of
greater than 0.5 m3 capacity shall not be located in buildings.
6.9 Points of transfer
shall be located not less than 7.6m from the following:
(i)
the
nearest important building not associated with the LNG facility
(ii)
the
line of adjoining property that can be built upon
6.10 LNG tanks and their
associated equipment shall not be located where exposed to failure of overhead
electric power lines operating at over 600 volts.
7.0 Automatic Product
Retention Valves
7.1 All liquid and vapor
connections, except relief valve and instrument connections, shall be equipped
with automatic failsafe product retention valves.
7.2 Automatic valves
shall be designed to close on the occurrence of any of the following
conditions:
(i)
Fire
detection or exposure
(ii)
Uncontrolled
flow of LNG from the container
(iii)
Manual
operation from a local and remote location
7.3 Connections used only
for flow into the container shall be equipped with either two backflow valves,
in series, or a product retention valve.
7.4 Appurtenances shall
be installed as close to the container as practical so that a break resulting
from external strain shall occur on the piping side of the appurtenance while
maintaining intact the valve and piping on the container side of the
appurtenance.
8.0 LNG Spill Containment
8.1 Impoundment (dikes),
topography, or other methods to direct LNG spills to a safe location and to
prevent LNG spills from entering water drains, sewers, waterways, or any
closed-top channel shall be used.
8.2 Flammable liquid
storage tanks shall not be located within an LNG container impoundment area.
8.3 Impounding areas
serving aboveground and mounded LNG containers shall have a minimum volumetric
holding capacity including any useful holding capacity of the drainage area and
with allowance made for the displacement of snow accumulation, other
containers, and equipment, in accordance with the following:
(i)
Where
containers in the dike area are constructed or protected to prevent failure
from spilled LNG and fire in the dike, the minimum holding of the dike shall be
the volume of the largest container in the dike.
(ii)
Where
containers in the dike area not are constructed or protected to prevent failure
from spilled LNG and fire in the dike, the minimum holding of the dike shall be
the volume of the largest container in the dike.
8.4 Impounding areas
shall be designed or equipped to clear rain or other water.
8.4.1 Where automatically
controlled sump pumps are used, they shall be equipped with an automatic cutoff
device that prevents their operation when exposed to LNG temperatures.
8.4.2 Piping, valves, and
fittings whose failure could allow liquid to escape from the impounding area
shall be designed to withstand continuous exposure to the temperature of LNG.
8.4.3 Where gravity
drainage is employed for water removal, the gravity draining system shall be
designed to prevent the escape of LNG by way of the drainage system.
9.0 Inspection
9.1 Prior to initial
operation, containers shall be inspected to ensure compliance with the
engineering design and material, fabrication, assembly, and test provisions of
the chapter.
9.2 Inspectors shall be
qualified in accordance with the code or standard applicable to the container
and as specified in this standard.
10.0 Factory Testing of LNG
Containers
10.1 The outer tank shall
be leak tested.
10.2 Container piping
shall be tested in accordance with ASME B 31.3, Process Piping.
11.0 Shipment of LNG
Containers.
Containers shall be shipped under a minimum internal pressure of 10 psi (69
kPa) inert gas.
12.0 Field Testing of LNG
Containers
12.1 Containers and
associated piping shall be leak tested prior to filling with LNG.
12.2 After acceptance
tests are completed, there shall be no field welding on the LNG containers.
13.0 Welding on Containers.
13.1 Field welding shall
be done on saddle plates or brackets provided for the purpose only.
13.2 Where repairs or
modifications incorporating welding are required, they shall comply without the
code or standard under which the container was fabricated.
13.3 Retesting by a method
appropriate to the repair or modification shall be required only where the
repair or modification is of such a nature that a retest actually tests the
element affected and is necessary to demonstrate the adequacy of the repair or
modification.
14.0 Piping
14.1 All piping that is
part of an LNG container and the facility associated with the container for
handling cryogenic liquid or flammable fluid shall be in accordance with ASME B
31.3, Process Piping or equivalent, and the following:
(i)
Type
F piping, spiral welded piping, and furnace butt-welded steel products shall
not be permitted.
(ii)
All
welding or brazing shall be performed by personnel qualified to the
requirements of the ASME Boiler and Pressure Vessel Code, Section IX or
equivalent.
(iii)
Oxygen-fuel
gas welding shall not be permitted.
(iv)
Brazing
filler metal shall have a melting point exceeding 538°C.
(v)
All
piping and tubing shall be austenitic stainless steel for all services below
-29°C.
(vi)
All
piping and piping components, except gaskets, seals, and packing, shall have a
minimum melting point of 816°C.
(vii)
Aluminum
shall be used only downstream of a product retention valve in vaporiser
service.
(viii)
Compression-type
couplings used where they can be subjected to temperatures below -29°C shall
meet the requirements of ASME B 31.3, Process Piping, Section 315 or
equivalent.
(ix)
Stab-in
branch connections shall not be permitted.
(x)
Extended
bonnet valves shall be used for all cryogenic liquid service, and they shall be
installed so that the bonnet is at an angle of not more than 45 degrees from
the upright vertical position.
14.2 The level of
inspection of piping shall be specified.
15.0 Container
Instrumentation
15.1 General
Instrumentation for LNG
facilities shall be designed so that, in the event of power or instrument air
failure, the system will go into a failsafe condition that can be maintained
until the operators can take action to reactivate or secure the system.
15.2 Level Gauging
LNG containers shall be
equipped with liquid level devices as follows:
(i)
Containers
of 3.79 m3 shall be equipped with two independent liquid level
devices.
(ii)
Containers
smaller than 3.79 m3 shall be equipped with either a fixed
length dip tube or other level devices.
(iii)
Containers
of 3.79 m3 shall have one liquid level device that provides a continuous level
indication ranging from full to empty and shall be maintainable or replaceable
without taking the container out of service.
15.3 Pressure Gauging and
Control
15.3.1 Each container shall
be equipped with a pressure gauge connected to the container at a point above
the maximum liquid level that has a permanent mark indicating the maximum
allowable working pressure (MAWP) of the container.
15.3.2 Vacuum-jacketed
equipment shall be equipped with instruments or connections for checking the
pressure in the annular space.
15.3.3 Safety relief valves
shall be sized to include conditions resulting from operational upset, vapor
displacement, and flash vaporization resulting from pump recirculation and
fire.
15.4 Pressure relief
valves shall communicate directly with the atmosphere.
15.5 Pressure relief
valves shall be sized in accordance with 2.3.6 of these Regulations or CGA
S-1.3, Pressure Relief Device Standards — Part 3 — Compressed Gas Storage
Containers or as per design standard.
15.6 Inner container
pressure relief valves shall have a manual full opening stop valve to isolate
it from the container.
15.6.1 The stop valve shall
be lockable or sealable in the fully open position.
15.6.2 The installation of
pressure relief valves shall allow each relief valve to be isolated
individually for testing or maintenance while maintaining the full relief
capacities determined in 2.3.6 of these Regulations.
15.6.3 Where only one
pressure relief valve is required, either a full-port opening three-way valve
used under the pressure relief valve and its required spare or individual
valves beneath each pressure relief valve shall be installed.
15.7 Stop valves under
individual safety relief valves shall be locked or sealed when opened and shall
not be opened or closed except by an authorized person.
15.8 Safety relief valve
discharge stacks or vents shall be designed and installed to prevent an
accumulation of water, ice, snow, or other foreign matter and, if arranged to
discharge directly into the atmosphere, shall discharge vertically upward.
16.0 Fire Protection and
Safety. The requirements of Sections 1F of these Regulations shall apply.
17.0 Gas Detectors. An operating portable
flammable gas indicator shall be readily available.
18.0 Operations and
Maintenance.
Each facility shall have
written operating, maintenance, and training procedures based on experience, knowledge
of similar facilities, and conditions under which they will be operated.
18.1 Basic Operations
Requirements.
Each facility shall meet
the following requirements:
(i)
Have
written procedures covering operation, maintenance, and training
(ii)
Keep
up-to-date drawings of plant equipment, showing all revisions made after
installation
(iii)
Revise
the plans and procedures as operating conditions or facility equipment require
(iv)
Establish
a written emergency plan as part of the operations manual
(v)
Establish
liaison with appropriate local authorities such as police, fire department, or
municipal works and inform them of the emergency plans and their role in
emergency situations
(vi)
Analyze
and document all safety-related malfunctions and incidents for the purpose of
determining their causes and preventing the possibility of recurrence
18.2 Operating Procedures
Manual
18.2.1 Each facility shall
have a written manual of operating procedures, including the following:
(i)
Conducting
a proper startup and shutdown of all components of the facility, including
those for an initial startup of the LNG facility that will ensure that all
components will operate satisfactorily
(ii)
Purging
and inerting components
(iii)
Cooling
down components
(iv)
Ensuring
that each control system is properly adjusted to operate within its design
limits
(v)
Maintaining
the vaporization rate, temperature, and pressure so that the resultant gas is
within the design tolerance of the vaporiser and the downstream piping
(vi)
Determining
the existence of any abnormal conditions and indicating the response to these
conditions
(vii)
Ensuring
the safety of personnel and property while repairs are carried out whether or
not equipment is in operation
(viii)
Ensuring
the safe transfer of hazardous fluids
(ix)
Ensuring
security at the LNG plant
(x)
Monitoring
operation by watching or listening for warning alarms from an attended control
center and by conducting inspections on a planned, periodic basis
(xi)
Monitoring
the foundation heating system weekly
18.2.2 The manual shall be
accessible to operating and maintenance personnel.
18.2.3 The manual shall be
updated when changes in equipment or procedures are made.
18.2.4 The operations manual
shall contain procedures to ensure the following:
(i)
The
cooldown of each system of components that is under its control, and that is
subjected to cryogenic temperatures, is limited to a rate and distribution
pattern that maintains the thermal stresses within the design limits of the
system during the cooldown period, having regard to the performance of
expansion and contraction devices.
(ii)
Each
facility has procedures to check each cryogenic piping system that is under its
control during and after cooldown stabilization for leaks in areas where there
are flanges, valves, and seals.
18.2.5 Each operations
manual shall include purging procedures that when implemented minimize the
presence of a combustible mixture in plant piping or equipment when a system is
being placed into or taken out of operation.
18.2.6 The operations manual
shall contain procedures for loading or unloading operations applicable to all
transfers, including the following.
(i)
Written
procedures shall cover all transfer operations and shall cover emergency as
well as normal operating procedures.
(ii)
Written
procedures shall be kept up-to-date and available to all personnel engaged in
transfer operations.
(iii)
Prior
to transfer, gauge readings shall be obtained or inventory established to
ensure that the receiving vessel cannot be overfilled.
(iv)
Levels
of the receiving vessel shall be checked during transfer operations.
(v)
The
transfer system shall be checked prior to use to ensure that valves are in the
correct position.
(vi)
Pressure
and temperature conditions shall be observed during the transfer operation
18.2.7 Each operations
manual for a facility that transfers LNG from or to a cargo tank vehicle or a
tank car shall contain procedures for loading or unloading of tank car or tank
vehicles, including the following:
(i)
While
tank car or tank vehicle loading or unloading operations are in progress, rail
and vehicle traffic shall be prohibited within 25 ft. (7.6 m) of LNG facilities
or within 50 ft. (15 m) of refrigerants whose vapors are heavier than air.
(ii)
Prior
to connecting a tank car, the car shall be checked and the brakes set, the
derailer or switch properly positioned, and warning signs or lights placed as
required.
(iii)
The
warning signs or lights shall not be removed or reset until the transfer is
completed and the car disconnected.
(iv)
Unless
required for transfer operations, truck vehicle engines shall be shut off.
(v)
Brakes
shall be set and wheels checked prior to connecting for unloading or loading.
(vi)
The
engine shall not be started until the truck vehicle has been disconnected and
any released vapors have dissipated.
(vii)
Prior
to loading LNG into a tank car or tank vehicle that is not in exclusive LNG
service, a test shall be made to determine the oxygen content in the container.
(viii)
If
a tank car or tank vehicle in exclusive LNG service does not contain a positive
pressure, it shall be tested for oxygen content.
(ix)
If
the oxygen content in either case exceeds 2 percent by volume, the container
shall not be loaded until it has been purged to below 2 percent oxygen by
volume.
18.3 Emergency Procedures.
18.3.1 Each facility shall
have a written manual of emergency procedures included in the operations manual
that shall include the types of emergencies that are anticipated from an
operating malfunction, structural collapse of part of the facility, personnel
error, forces of nature, and activities carried on adjacent to the facility,
including the following:
(i)
Procedures
for responding to controllable emergencies, including notification of personnel
and the use of equipment that is appropriate for handling of the emergency and
the shutdown or isolation of various portions of the equipment and other
applicable steps to ensure
(ii)
that
the escape of gas or liquid is promptly cut off or reduced as much as possible
(iii)
Procedures
for recognizing an uncontrollable emergency and for taking action to ensure
that harm to the personnel at the facility and to the public is minimized
(iv)
Procedures
for the prompt notification of the emergency to the appropriate local
officials, including the possible need to evacuate persons from the vicinity of
the facility
(v)
Procedures
for coordinating with local officials in the preparation of an emergency
evacuation plan that sets forth the steps necessary to protect the public in
the event of an emergency
18.3.2 When local officials
are contacted in an emergency, procedures shall include the method of
notification of the following:
(i)
The
quantity and location of fire equipment throughout the facility
(ii)
Potential
hazards at the facility
(iii)
Communication
and emergency control capabilities of the facility
(iv)
The
status of each emergency
18.3.3 A comprehensive
Emergency Response and Disaster Management Plan (ERDMP) shall be developed in
accordance to the Petroleum and Natural Gas Regulatory Board (Codes of
Practices for Emergency Response and Disaster Management Plan (ERDMP))
Regulations, 2010.
18.4 Maintenance
Each facility shall have
written maintenance procedures based on experience, knowledge of similar
facilities, and conditions under which they will be maintained.
18.4.1 Each facility
operator shall carry out periodic inspection, tests, or both, as required on
every component and its support system in service in its facility, to verify
that it is maintained in accordance with the equipment manufacturer's
recommendations and the following:
(i)
The
support system or foundation of each component shall be inspected at least
annually to ensure that the support system or foundation is sound.
(ii)
Each
emergency power source at the facility shall be tested monthly to ensure that
it is operational and annually to ensure that it is capable of performing at
its intended operating capacity.
(iii)
When
a safety device serving a single component is taken out of service for
maintenance or repair, the component shall also be taken out of service, except
where the safety function is provided by an alternate means.
(iv)
Where
the operation of a component that is taken out of service could cause a
hazardous condition, a tag bearing the words “Do Not Operate,” or the
equivalent thereto, shall be attached to the controls of the component, or the
component shall be locked out.
(v)
Stop
valves for isolating pressure or vacuum-relief valves shall be locked or sealed
open and shall be operated only by an authorized person.
(vi)
No
more than one pressure or vacuum relief valve stop valve shall be closed at one
time on an LNG container.
18.4.2 Maintenance Manual
(i)
Each
facility operator shall prepare a written manual that sets out an inspection
and maintenance programme for each component that is used in its facility.
(ii)
The
maintenance manual for facility components shall include the following:
(a) The manner of carrying out
and the frequency of the inspections and tests as specified in 18.4.1.
(b) A description of any other
action in addition to those referred to in 18.4.2.ii. a) that is necessary to
maintain the facility in accordance with this standard.
(c) All procedures to be
followed during repairs on a component that is operating while it is being
repaired to ensure the safety of persons and property at the facility
(iii)
Each
facility operator shall conduct its maintenance programme in accordance with
its written manual for facility components.
18.4.3 Facility Maintenance
(i)
Each
facility operator shall keep the grounds of its facility free from rubbish,
debris, and other materials that could present a fire hazard.
(ii)
Each
facility operator shall ensure that the components of its facility are kept
free from ice and other foreign materials that could impede their performance.
(iii)
Each
facility operator shall maintain the grassed area of its facility so that it
does not create a fire hazard.
(iv)
All
fire-control access routes within an LNG facility shall be maintained and kept
unobstructed in all weather conditions.
18.4.4 Repairs that are
carried out on components of its facility shall be carried out in a manner that
ensures the following:
(i)
The
integrity of the components is maintained, in accordance with this standard.
(ii)
Components
will operate in a safe manner.
(iii)
The
safety of personnel and property during a repair activity is maintained.
18.4.5 Each facility
operator shall ensure that a control system that is out of service for 30 days
or more is tested prior to returning it to service to ensure that it is in
proper working order.
(i)
Each
facility operator shall ensure that the inspections and tests in this section
are carried out at the intervals specified.
(ii)
Control
systems that are used seasonally shall be inspected and tested before use each
season.
(iii)
Control
systems that are used as part of the fire protection system at the facility
shall be inspected and tested in accordance with the applicable fire code.
(iv)
Relief
valves shall be inspected and set point tested at least once every 2 calendar
years, with intervals not exceeding 30 months, to ensure that each valve
relieves at the proper setting.
(v)
The
external surfaces of LNG storage tanks shall be inspected and tested as set out
in the maintenance manual for the following:
(a) Inner tank leakage
(b) Soundness of insulation
(c) Tank foundation heating to
ensure that the structural integrity or safety of the tanks is not affected
(vi)
LNG
storage plants and, in particular, the storage container and its foundation
shall be externally inspected after each major meteorological disturbance to
ensure that the structural integrity of the plant is intact.
18.4.6 Maintenance Records
(i)
Each
facility operator shall maintain a record of the date and type of each
maintenance activity performed.
(ii)
Maintenance
records shall be retained for as long as the facility is in service.
18.5 Training
The requirements as given
in Schedule 1 E of these Regulations shall apply.
ANNEXURE II
Table
- Distance between Blocks/Facilities
(all
distance in metre)
|
Sr no
|
From/To
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
|
1
|
Process Units (Regasification Facilities)
|
Note-1
|
Note-2
|
30
|
90
|
45
|
60
|
60
|
15
|
|
2
|
Process Control Room (Note-2) (Main Control Room)
|
Note-2
|
X
|
Note-3
|
90
|
45
|
30
|
30
|
0
|
|
3
|
LNG Storage Tanks (T-107)
|
30
|
Note-3
|
(D1+D2)/4=42.4
|
90
|
30
|
60
|
0.7D=59.4
|
60
|
|
4
|
Flare (Note-4) (Flare for Phase-IIIA)
|
90
|
90
|
90
|
X
|
90
|
90
|
90
|
90
|
|
5
|
Bulk Loading LPG (Rail/Road) (LNG Tanker Loading Bay)
|
45
|
45
|
30
|
90
|
T6
|
90
|
30
|
30
|
|
6
|
Fire Station/First Aid Center
(Main/Supplementary)
|
60
|
30
|
60
|
90
|
90
|
X
|
12
|
0
|
|
7
|
Boundary wall around installation
|
60
|
30
|
0.7D=59.4
|
90
|
30
|
12
|
X
|
15
|
|
8
|
Electrical Sub Station (For Phase-IIIA & B)
|
15
|
0
|
60
|
90
|
30
|
0
|
15
|
X
|
General Notes to Table;
(i)
All
distances are in meters. “T” indicates the table number to be referred. “x”
means any distance suitable for constructional or operational convenience.
(ii)
All
distances shall be measured between the nearest points on the perimeter of each
facility except (i) In case of tank vehicle loading/unloading area where the
distance shall be from the center of nearest bay. (ii) The distances given in
the brackets () are from the shell of the Heater/Boiler/Furnace/Still.
Specific notes to Table:
|
Note—1:
|
This shall be 36 meters considering
the 6-meter wide road passing through the center. The edge of the road shall
not be less than 15 meters away from the edge of the unit.
|
|
Note—2:
|
Process control room to Process
units/boiler house/heaters the minimum separation distance shall be 30 m. For
a control room attached to single process unit or a boiler or a heater, the
minimum separation distance shall be 16 m. For Gas processing plants, it
shall be minimum 30 meters irrespective of whether it is for one or more
units.
|
|
Note—3:
|
Shall be 60m for non-blast
construction and 30m for blast resistant construction.
|
|
Note—4:
|
The distances specified are for the
elevated flare. For ground flare, these distances shall be 150 m. For
Exploration & Production installations, this shall be in line with Oil
Mines Regulations.
|
ANNEXURE III
LIST
OF STANDARDS AND REFERENCES
|
Standard Number
|
Title of Standard
|
|
API 620
|
Design and Construction of Large Welded Low
Pressure Storage Tanks
|
|
API 625
|
Tank Systems for Refrigerated Liquefied Gas
Storage
|
|
ASME B31.3
|
Process Piping
|
|
CGA 341
|
Specification For Insulated Cargo Tank For
Nonflammable Cryogenic Liquids
|
|
EN 14620
|
Design and manufacture of site built, vertical,
cylindrical, flat-bottomed steel tanks for the storage of refrigerated,
liquefied gases with operating temperatures between 0°C and (-)165°C
|
|
NFPA 59A
|
Standard for the Production, Storage, and
Handling of Liquefied Natural Gas (LNG)
|
|
NFPA 5000
|
Building Construction and Safety Code
|
|
IS 3043
|
Code of Practice for Earthing
|
|
IS 1893
|
Criteria for Earthquake Resistant Design of
Structures
|
|
IS 5571
|
Guide for selection and installation of
electrical equipment in hazardous areas
|
|
IS 325
|
Three-Phase Induction Motors
|
|
IS 2309
|
Protection Of Buildings And Allied Structures
Against Lightning - Code Of Practice
|
|
IEC 60072
|
Dimensions and output series for rotating
electrical machines
|
|
IEC 60079
|
Explosive Atmospheres
|
|
IEC 62271
|
High-voltage switchgear and controlgear
|
|
IEC 62305
|
Protection against lightning
|
|
BS 31
|
Specification for Steel Conduit and Fittings for
Electrical Wiring
|
|
GAP 2.5.1
|
Fireproofing for Hydrocarbon Fire Exposures
|
|
API 2218
|
Fireproofing Practices in Petroleum and
Petrochemical Processing Plants
|
|
NFPA 15
|
Standard for Water Spray Fixed Systems for Fire
Protection
|
|
EN 12065
|
Installations and Equipment for Liquefied Natural
Gas. Testing of foam concentrates designed for generation of medium and high
expansion foam and of extinguishing powders used on liquefied natural gas
fires
|
|
EN 1473
|
Installation and equipment for liquefied natural
gas. Design of onshore installations
|
|
EN 12434
|
Cryogenic vessels. Cryogenic flexible hoses
|
|
EN 1532
|
Installation and Equipment for Liquefied Natural
Gas. Ship to Shore Interface
|
|
SIGTTO
|
Society of International Gas Tankers and
Terminals Operators
|
|
IEC
|
The International Electrotechnical Commission
|
|
IE Rules
|
Indian Electricity Rules
|
|
IP Model code of Safe Practices
|
Institute of Petroleum Model code of Safe
Practices
|
|
Petroleum and Natural Gas Regulatory Board (Codes
of Practices for Emergency Response and Disaster Management Plan)
Regulations, 2010
|
|
ASME Boiler and Pressure Vessel Code
|