Maharashtra Electricity Regulatory Commission (Demand Flexibility And
Demand Side Management - Implementation Framework, Cost effectiveness
Assessment And Evaluation, Measurement And Verification) Regulations, 2024
[19th
November 2024]
PREAMBLE
In exercise of the powers
conferred by sub-section (1) of Section 181 and clause (zp) of sub-section (2)
of Section 181 of the Electricity Act, 2003, and all other powers enabling it
in this behalf, the Maharashtra Electricity Regulatory Commission hereby makes
the following Regulations, providing for Demand Flexibility and Demand Side
Management - Implementation Framework, Cost-effectiveness Assessment; and
Evaluation, Measurement and Verification framework to be followed by
distribution licensees and for matters in connection therewith and incidental
and ancillary thereto.
Regulation 1. Short Title, Applicability, Commencement and Interpretation.
1.1.
These Regulations may be called the "Maharashtra Electricity Regulatory
Commission (Demand Flexibility and Demand Side Management - Implementation
Framework, Cost effectiveness Assessment and Evaluation, Measurement and
Verification) Regulations, 2024".
1.2.
These Regulations extend to the whole of the State of Maharashtra and
applicable to all existing and prospective distribution licensees in the State.
1.3.
These Regulations shall come into force from the date of their publication in
the Official Gazette.
1.4.
These Regulations shall be construed harmoniously with the Maharashtra
Electricity Regulatory Commission (Multi Year Tariff) Regulations, 2024 as
amended from time to time and Maharashtra Electricity Regulatory Commission
(Resource Adequacy) Regulations, 2024.
1.5.
These Regulations form three distinct components as follows: Part A:
Implementation Framework; Part B: Cost-effectiveness Assessment; and Part C:
Evaluation, Measurement and Verification. Three parts form the entire
Regulations in its stated meanings.
Regulation 2. Definitions.
2.1.
In these Regulations, unless the context otherwise requires:
(1)
"Act" means the Electricity Act,
2003 (36 of 2003) as amended from time to time;
(2)
"Ancillary Service" or
"AS" in relation to power system operation, means the service
necessary to support the grid operation in maintaining power quality,
reliability and security of the grid and includes Primary Reserve Ancillary
Service, Secondary Reserve Ancillary Service, Tertiary Reserve Ancillary
Service, active power support for load following, reactive power support, black
start and such other services as defined in the Grid Code;
(3)
"Aggregator" is an entity
registered with the Distribution Licensee to provide aggregation of one or more
of the services like demand response services under the demand flexibility
mechanism, Distributed Generation, Energy Storage etc. within a control area;
(4)
"ARR" means Aggregate Revenue
Requirement;
(5)
"Avoided Costs" means the
incremental costs avoided by the distribution licensee when it does not
purchase power because of implementation of DF / DSM programmes (also
articulated as non-wire alternatives (NWA)), or otherwise defers or avoids
distribution related costs from investment in existing/new distribution system
upgrades;
(6)
"Cost Effectiveness" means an
indicator of the relative performance or economic attractiveness of any
investment in DF/DSM programme or when compared to the costs of energy produced
and delivered in the absence of such an investment andas stipulated in the Part
B of these Regulations;
(7)
"Demand Flexibility" means the
capacity of demand-side loads that can varytheir consumption patterns hourly or
on another timescale to help integrate higher amounts of renewable energy
resulting in making electricity more affordable to consumers with the
co-benefits of reducing or deferring system costs or a end-use consumption that
can increase or decrease as a demand response measure;
(8)
"Demand Flexibility Portfolio
Obligations (DFPO)" means a trajectory of flexible demand that a
distribution licensee needs to ensure availability of on an annual basis to
provide quick ramping-up and ramping-down of the load based on the system
requirements including maximizing renewable energy integration services;
(9)
"DF/Demand-Side Resource" means a
saving in consumption (kWh) and/or demand (kW/KVA) available as a result of
implementation of DF / DSM programme (as a single or group of device at a
single or multiple locations) to be expressed in three important dimensions:
Quantum - as to how much is available (kWh and/or kW); Time - as to when is it
available (at what time of day, on what days, in what season); and the Cost -
as at what would be the cost;
(10)
"Distribution Licensee" shall have
the meaning ascribed thereto in the Act;
(11)
"DF / DSM Cell" means a specific
department to be set-up by the Distribution Licensee for targeted activities
towards implementation of the DF/DSM activities mandated under these
regulations.
(12)
"DSM" means Demand Side Management;
(13)
"DF and DSM Consultation Committee"
means a committee set up under the convenorship of Secretary MERC to facilitate
DF and DSM programme approval process for the Commission as detailed under
Regulation 7 of these Regulations;
(14)
"Energy Efficiency" means
activities or programmes that stimulate consumers to reduce energy use by
making investments in more efficient equipment or control that reduces energy
use while maintaining a comparable level of service as perceived by the
consumer;
(15)
"Evaluation, Measurement and
Verification (EM&V)" means activities included under Part C of these
Regulations, which target evaluation, monitoring, measurement and verification
of DF / DSM programmes;
(16)
"Independent Verification Agency
(IVAs)" are either individuals certified as energy auditors or energy
managers or measurement and verification professionals or organisations with
individuals certified as energy auditors or energy managers or measurement and
verification professionals;
(17)
"IPMVP" means International
Performance Measurement & Verification Protocol which provides guidelines
that can be used to estimate the savings from the DF/DSM programmes;
(18)
"Life" means an estimate of the
median number of years that the DF/ DSM measures installed under the programme
are still in place and operable; or warrantied years of service or as defined
by DF/DSM Consultation Committee should there be a need or as suggested by the
licensee;
(19)
"LRIRIM" means Lifecycle Revenue
Impact of the DF/DSM programmes on tariffs;
(20)
"Load Management" means programmes
that reduce or shift peak demand away from periods of high-cost electricity to
non-peak or lower cost time periods, with a neutral effect on or negligible
increase in electric use;
(21)
"Load Research" means an activity
embracing the measurement and study of the characteristics of electric loads to
provide a thorough and reliable knowledge of trends, and general behaviour of
the load characteristics of the consumers serviced by the distribution licensee
using a variety of metering (including data capture from smart metering
systems), surveys, detailed energy audits of consumer-end energy consumption to
capture diurnal, daily, monthly, seasonal and annual usage patterns;
(22)
"MYT" means Multi year tariff;
(23)
"NPV" means Net Present Value;
(24)
"PCT" means Participant Cost Test
which measures the quantifiable benefits and costs to an "average"
consumer for participating in a DF/DSM programme;
(25)
"RIM" means Ratepayer Impact
Measure test which checks what impact the programme implementation and costs
would have on consumers;
(26)
"SCT" or Societal Cost Test
measures the quantifiable benefits and costs of the DF/DSM programme on society
as a whole;
(27)
"TRC" means Total Resource Cost
test which measures the total quantifiable benefits and costs of a DF/DSM
programme;
2.2.
Words and expressions used herein and not defined shall have the meanings
assigned to them in the Act or the Rules or Regulations made thereunder.
PART
1 IMPLEMENTATION FRAMEWORK
Regulation 3. Basic Principles.
3.1.
DF / DSM as a key part of the licensee operations.
Every Distribution Licensee
shall make DF / DSM an integral part of their dayto-day operations, and
undertake planning, designing and implementation of appropriate DF / DSM
programmes on a sustained basis that are measurable, replicable and available
for smooth grid operations at supply and demand-side of the electricity sector
stakeholders; and also contribute to the proper functioning of the Resource
Adequacy requirements under other Regulations. The Licensees shall adequately
staff the DF / DSM departments as needed through the formation of a DSM Cell
with a clearly defined terms of reference for its activity.
3.2.
Cost recovery of DF / DSM measures.
Distribution Licensees may
recover all justifiable costs incurred by them in any DF / DSM related
activity, including conducting Load Research (LR), planning, designing,
implementing, monitoring and evaluating DF / DSM programmes, by adding these
costs in the MYT filings and annual financial reporting. All such DF / DSM
related activities/ programmes undertaken by the Distribution Licensees:
(i)
Will need to be cost effective for the
consumers of the Distribution Licensees as well as to the Distribution
Licensees themselves as stipulated under Part B of these regulations;
(ii)
Shall protect the interest of all consumers
and be implemented in an equitable manner;
(iii)
Will result in overall tariff reductions for
all the consumers of the licensees;
(iv)
Will result in embedding renewable energy on
the consumer-side of the meter or supply-side of the meter.
3.3.
Distribution Licensees shall be guided by these Regulations.
(i)
While developing a robust five-year and
one-year DF / DSM portfolio structure on a rolling basis linked to planning and
submitting load research and proposing measures to be implemented by them as
regards demand flexibility, load management, energy conservation and energy
efficiency portfolio of programmes;
(ii)
While submitting to the Commission the impact
on energy and demand, together with the cost-benefit analysis as stipulated
under Part B of these Regulations and the evaluation, measurement and
verification of the implemented programmes stipulated under Part C of these
Regulations;
(iii)
While addressing specific directions of the
Commission.
Regulation 4. DF / DSM Guiding Principles.
The duties of the
Distribution Licensees shall be as follows:
(a)
Development of DF / DSM portfolio:
Distribution Licensees shall develop a strong portfolio of DF / DSM programmes,
on the basis of comprehensive load research, that provide long-term savings and
feed into the resource adequacy requirements. The DF / DSM portfolio shall
contribute to the integrated resources planning requirements, resource adequacy
assessment and provide a market transformation trigger. The DF / DSM programme
portfolio shall include thefollowing key sections:
(i)
findings of a detailed load research activity
based on smart metering infrastructure, automated metering infrastructure and
appliance-level metering (on a sample basis or based on publicly available
information) to assess peak convergence, consumer surveys;
(ii)
consumers perspectives and willingness to
participate in the DF / DSM initiatives;
(iii)
detailed working of the possible DF
programmes to be implemented and the DFPO targets that include all components
such as DF, energy efficiency and energy conservation measures;
(iv)
portfolio and programme-specific
cost-effectiveness assessment;
(v)
DFPO (DF) and DSM evaluation, measurement and
verification procedures developed for future verifications, using online
metering and monitoring services;
(vi)
funds deployment plan to meet the yearly DF
targets and other energy efficiency and energy conservation portfolio roll-out
on an annual basis.
(b)
Timelines for submission of DF / DSM
portfolio and according approvals:
The distribution licensees
shall submit a "DF / DSM programme portfolio and implementation action
plan" (format in Annexure 1) 3 months prior to the submission of the MYT
Tariff filings. The Commission shall accord its approval with specific
suggestions or directions to be incorporated in the MYT filings within 60 days.
On an annual basis, the distribution licensees shall submit "Status report
on DF / DSM implementation" by 31 March in the ensuing year reporting on
the portfolio performance to allow the Commission to approve or disapprove
incentives or disincentives claimed by the distribution licensee. However, in
MYT submission due for filing by 30 November 2024, distribution licensees shall
submit block estimates and budgets to implement DF/DSM portfolio with the MYT
Petition and detailed DF/DSM portfolio and implementation plan submitted within
first three months of notification of these Regulations to be approved by the
Commission before 31 March 2025.
(c)
DFPO multi-year targets: Distribution
Licensees shall adhere to specific demand flexibility portfolio obligations
(DFPO) set-up with a following specific trajectory:
Year |
DFPO as percentage of peak demand
experienced in previous Financial Year |
FY 2025-26 |
1.5% |
FY 2026-27 |
1.5% |
FY 2027-28 |
2.0% |
FY 2028-29 |
2.5% |
FY 2029-30 |
3.5% |
DFPO represent maximum
flexibility available to decrease the load at a single instance at the time of
maximum expected peak demand and corresponding increase in the non-peak hours
during a 24-hours period, demonstrated for at least one hour in a year. The Licensees
are required to carry out at least one DF/DR event in a year that is
coincidental with the top 10 days of the previous years recorded peak demand.
Subsequent to the first five years of trajectory for DFPO described above, the
Distribution Licensees shall perpetually ensure 3.5% of the previous years peak
demand as DFPO till the time it is revised by the Commission.
(d)
DFPO incentives and disincentives:
Distribution Licensee shall be eligible for an incentive of INR 0.20 Crores for
every MW achieved in excess of DFPO. Similarly, Distribution Licensee shall be
subjected to a disincentive of INR 0.20 Crores for every MW underachievement of
DFPO.
(e)
DF / DSM portfolio deployment in key sectors:
Distribution Licensees shall implement programmes that add to the structures of
resource adequacy and those that include demand flexibility to provide quick
ramp-up and ramp-down services, reduce peak demand and associated costly power
purchase, specifically in the urban centres and embedding cheaper renewable
energy available within and from outside of the distribution licensee area of
supply. The Demand Flexibility programmes shall also include Demand Response
initiatives involving consumers agreeing to modulate their load shapes through
a contract with the licensee. Given the new loads that are now experienced by
the Distribution Licensees, programme basket proposed and implemented through
these Regulations shall include, but not limited to, the following:
(a)
time-based and selective pumping (based on
the cost of energy) in Lift Irrigation Schemes, Municipal Corporations, Urban
Local Bodies, Nagar parishads, drinking water schemes at villages and cluster
of villages;
(b)
smart charging of electric vehicles in the
2-wheeler, 3-wheeler, passenger cars, fleet vehicles, public transportation
buses, freight carriers, first-mile and last-mile delivery vehicles;
(c)
behind-the-meter battery energy storage
systems;
(d)
heat pumps in residential, hospitals, hotels,
industries, commercial buildings;
(e)
thermal energy storage systems in residential,
hospitals, hotels, industries, commercial buildings;
(f)
replacement of old/inefficient appliances
with efficient appliances at consumer premises;
(g)
all behavioural changes in the end-uses
facilitated through awareness programmes that do not need any specific
investments.
In addition to the above,
specific energy conservation initiatives at the consumers premises, including
lowest category of domestic consumer base, agricultural sector shall be
included in the portfolio and shall be funded through the DF portfolio budget.
All the DF programs can be implemented by the licensees directly or by
Aggregators appointed by them following due procurement processes as the costs
incurred towards the appointment of Aggregators are embedded in the programme costs.
Distribution Licensee shall satisfy themselves that the Aggregator is
technically and financially competent to undertake on their behalf the
functions and discharge the obligations specified in these regulations.
Distribution Licensee shall ensure that the Aggregators and the IVAs are
separate entities.
(f)
Public disclosure of the DF / DSM portfolio
and review documents:
Distribution Licensee shall
publish key documents such as Load Research, appliance use and saturation
reports, DF / DSM programme portfolio and implementation action plan and Status
report on DF / DSM implementation on their website for public knowledge and
consumption. On an annual basis, the adherence to the DFPO and DSM activities
shall be published on the websites of distribution licensees. DF / DSM
portfolio evaluation, measurement and verification reports shall be submitted
to the Commission as well as put out in the public domain. DF / DSM related
data shall be included in a separate sub-section of the website of the
Distribution Licensee for easy access to all stakeholders.
Regulation 5. DF / DSM Consultation Committee (DF / DSM-CC).
A separate DF / DSM
Consultation Committee shall be set up under these Regulations through a
specific notification of the Commission with a stated tenure and terms of
reference. The DF / DSM Committee shall be a group of experts working under the
direction of the Commission, set-up under a separate notification, to review
and provide suggestions and objections on the DF / DSM programme portfolio
submitted by the distribution licensees and recommend its findings on DF / DSM
Programmes to the Commission for approval. Secretary to the Commission shall
act as the Convenor of the DF / DSM Committee with participation from
distribution licensees, Maharashtra Energy Development Agency (MEDA)
representing the Bureau of Energy Efficiency (BEE), Chief Electrical Inspector,
sectoral experts including representatives of academic/research institutions
and private sector with specific knowledge of DF / DSM opportunities. The DF /
DSM Consultation Committee shall provide guidelines to conduct robust load
research activities by the licensees, evaluate the "DF / DSM Programme
Portfolio and Implementation Plan" submitted by the distribution licensees
and provide its recommendations to the Commission, and assist in the evaluation
of the "Status report on DF / DSM implementation" submitted by
licensees. The DF / DSM Committee shall also assist in creation of sectoral
expertise in the stakeholder groups to actively guide design, implementation
and evaluation of DF/DSM programmes. The DF / DSM Committee shall meet at least
once in six months. The Commission will upload the proceedings of the DF / DSM
Consultation Committee on its website periodically.
Regulation 6. DF/DSM funding.
Funding of all the DF / DSM
portfolio programmes and plans to be implemented by the Distribution Licensees
shall be included in the MYT Tariff filings with an annual funds deployment
requirement and reported as a part of annual review. Distribution Licensees
shall be allowed to recover all costs, clearing the cost-effectiveness
assessment test included in Part B of these Regulations, incurred by them in
any DF / DSM related activity, including planning, conducting load research,
designing, implementing, monitoring and evaluating DSM programmes, by adding
these costs to their ARR to enable their funding through tariff structure. All
costs incurred to conduct load research on an annual basis, setting-up of
online monitoring systems, setting-up of network operating centres, data-driven
online and real-time monitoring services, deployment of appliance-level metering
infrastructure on a sample basis, conducting energy audits at consumers
premises, awareness campaigns, targeted research activities, dissemination efforts
and all other legitimate expenses to further the cause of DF / DSM.
The Commission may direct
the Distribution Licensees to adopt other complementing DF / DSM funding
approaches such as creating a pool of funds through collection of DF-DSM Charge
at a later date through tariff; if such an approach is found beneficial.
These Regulations will be
used to assess the economic-effectiveness of a portfolio and programmes
thereunder with some of the decision variables such as, inter alia, DF/DSM
measure/programme costs and impacts (both energy - kWh and demand - kVA or
KW),discount rate, life, escalation rate and avoided cost.
PART
2 COST-EFFECTIVENESS ASSESSMENT TESTS
Regulation 7. Cost-effectiveness Criteria.
Distribution Licensees shall
share specific Cost-effectiveness Assessment test results as a part of the DF /
DSM portfolio submission. Distribution Licensees shall evaluate Total Resource
Cost (TRC) test as the main hurdle test; followed by the Ratepayer-Impact
Measure (RIM) test that confirms the fact that programme implementation and
costs incurred would not impact the tariffs adversely. The Life-cycle revenue
impact (LRIRIM) should not be more than Rs. 0.005/kWh or over 0.05% of existing
tariff as tariff increase, whichever is higher. The programme screening shall
be carried out using the following decision tree:
(a)
TRC as the main hurdle test: All DF / DSM
programmes that show positive number for the Net Present Value (NPV) of the
Benefits over the NPV of Costs should be considered for evaluation of RIM test;
(b)
RIM test: DF / DSM Programmes that show
positive number when NPV of the Benefits over the Costs for the Ratepayers are
considered should be implemented,
(c)
LRIRIM test: DF / DSM Programmes that do not
show positive number for RIM test should be implemented if the tariff impact
due to the implementation of the DF / DSM Programmes is less than Rs. 0.005/kWh
or less than 0.05% of the existing tariff, whichever is higher. All the energy
savings numbers should be corrected for power shortages, if any.
Regulation 8. Total Resources Cost test.
The main hurdle test shall be
carried out by calculating Net Present Value (NPV) of Benefits (B) and Costs
(C). NPV for a DF / DSM measure/programme shall be determined as the difference
between B and C.
Where,
B = NPV of measure/programme
benefits discounted over a specified time period
C = NPV of measure/programme
costs discounted over a specified time period
If the measure/programme
benefit in year "t" is "Bt", and discounting rate is
"r", the time period for discounting is "n" years, then B
can be expressed as:
n
B = ? [(Bt)/ (1+r)t-1 ]
(equation 1)
t=1
Similarly, if the
measure/programme cost in year "t" is "Ct", and discounting
rate is "r", the time period for discounting is "n" years,
then C can be expressed as:
C = ? [(Ct)/ (1+r)t-1 ]
(equation 2)
t=1
Cost elements for the TRC
test shall be determined considering the following:
(a)
The cost of efficient
device/equipment/appliance/ technology or practice, including the applicable
taxes, duties and levies;
(b)
Installation, trial and commissioning costs
associated with efficient device/equipment / appliance/practice/technology;
(c)
Yearly operation and maintenance costs over
the life of the measure/programme;
(d)
Old inefficient equipment removal and safe
disposal costs (if the DSM measure/programme involves replacement or
retrofitting);
(e)
Programme administration, monitoring and
evaluation costs;
(f)
Programme marketing costs.
Notes:
If there are any tax
credits, the same shall be considered as reduction in the cost. Similarly, if
there is old equipment/device / appliance / technology etc. that is being
replaced; the salvage value of this old equipment or device shall be considered
as a reduction in the cost.
Benefits of a DF / DSM
programme or a DF / DSM measure are the savings in the energy (kWh) consumed
and/or savings in the demand (kW). The kWh savings shall be calculated based on
the number of hours the energy efficient appliance/equipment is used and number
of days in a year the appliance/equipment is used. These savings usually occur
at the point of use and are experienced by the consumer installing a DF / DSM
measure or consumer participating in a DF / DSM programme. To arrive at the
avoided purchase of power by the licensee, the participant savings at the point
of use have to be suitably adjusted to account for system transmission and
distribution losses; as well as Value of Grid-connected Rooftop Systems (VGRS).
The DF projects also have the possibility of participating in the central
Ancillary Services market defined under CERC Regulations No.
RA-14026(11)/3/2019-CERC. All such additional revenues shall be included in the
benefits stream.
Thus, if sings at point of
use in year "t" are ?St expressed in kWh, and if transmission and
distribution losses expressed as percentage in the same year are TLt and DLt,
respectively, the Avoided Purchase of Power in year "t" (APPt) by the
licensee would be:
= ?St/[(1-TLt) x (1-DLt)].
If rate of power purchase in year "t" is Rt, then Avoided Power
Purchase Cost (APPCt) in year "t" would be: = APPt x Rt
Any reduction in
"intra-state transmission charges", as a result of reduction in the
average co-incident peak demand of the licensee shall be considered a
"benefit" under this test.
While calculating energy and
demand savings as benefits, year-on-year escalation rate of5% should be
considered. Tests should consider a discount rate of 10.5%.
Both benefits and costs
shall be calculated over the "Life" of the technology being deployed.
Distribution Licensee shall use the "warrantied" life of the retrofit
by the technology provider as it is important to ensure that the savings
considered are realized over the life-span of the equipment/appliances.
Alternately, "life" as may be defined by the DSM Consultation
Committee shall be used.
Regulation 9. Ratepayer Impact Measure test.
(i)
Cost elements mentioned below shall be used
in "equation 1"
(a)
The cost of efficient
device/equipment/appliance/ technology or practice, including the applicable
taxes, duties, levies, etc. paid for by the licensee or to the extent paid for
by the licensee;
(b)
Installation, trial and commissioning costs
associated with efficient device/equipment/appliance/practice/technology paid
by the licensee or to theextent paid by the licensee;
(c)
Yearly operation and maintenance costs over
the life of the measure/programme paid for by the licensee or to the extent
paid for by the licensee;
(d)
Old inefficient equipment removal and safe
disposal costs (if the DSM programmeinvolves replacement or retrofitting) paid
for by the licensee or to the extent paid for by the licensee;
(e)
Programme administration, monitoring and
evaluation costs paid for by the licensee or to the extent paid for by the
licensee;
(f)
Programme marketing costs, including
incentives, if any, paid by the licensee or to the extent paid for by the
licensee;
(g)
Decrease in licensee revenues due to the DSM
programme;
(ii)
Benefits of the DSM programme shall be
calculated as "Avoided Cost of Power Purchase". If savings due to a
DSM programme/measure at point of use in year "t" are ?St, and if
transmission and distribution losses in the same year are TLt and DLt,
expressed as a percentage respectively, the Avoided purchase of power in year
"t" (APPt) by the licensee would be: = ?St/[(1-TLt) x (1-DLt)] If
rate of power purchase in year "t", is Rt, then avoided power
purchase cost (APPCt) in year "t" would be: = APPt x Rt
(iii)
Any reduction in "intra-state
transmission charges", as a result of reduction in the average co-incident
peak demand of the licensee shall be considered as a "benefit" under
this test;
(iv)
While calculating energy and demand savings
as benefits, year-on-year escalation rate of 5% should be considered;
Note: Tests should consider
a discount rate of 10.5%.
(v)
Both benefits and costs shall be calculated
over the "Life" of the technology;
(vi)
Distribution Licensee shall use the
"warrantied" life of the retrofit by the technology provider as it is
important to ensure that the savings considered are realized over thelife-span
of the equipment/appliance. Alternately, "life" as may be defined by
the DSM Consultation Committee shall be used;
Regulation 10. Life-cycle Revenue Impact - RIM test.
(i)
LRIRIM test shall be conducted using same
data used for calculating the RIM test described in Regulation 9 of these
regulations.
(ii)
Difference between NPV of Cost and NPV of
Benefits shall be divided with total utility kWh sales to determine the rate
impact on the non-participants.
(iii)
Distribution Licensees shall also submit
results of two more test - Participants Cost Test (PCT) and Societal Cost Test
(SCT); though these are not considered in the decision-making. Methods for
carrying out the PCT and SCT are provided in Annexure 2 to these Regulations.
Regulation 11. Values of key inputs used in the tests.
The default input values to
be considered by all Distribution Licensees in the State, shall be as follows:
(a)
Avoided cost of power purchase for TRC, RIM
and PCT - Weighted Average of Highest Marginal Cost of Power Purchase related
to top 10% of energy use stack for the pastone year.
(b)
Avoided cost of power purchase for SCT - Rs.
10/kWh (prevalent ceiling rate for Day ahead market set by CERC, revised from
time to time but as valid at the time of submission of the DF/DSM portfolio)
(c)
Escalation rates for power sales, avoided
cost of purchase - 5% year-on-year.
(d)
Discount rate for TRC and RIM tests - 10.5%.
(e)
Discount rate for PCT - 13%.
(f)
Discount rate for SCT - 10.5%.
The Commission may, by
order, revise the above values annually, if necessary.
PART
3 EVALUATION, MEASUREMENT AND VERIFICATION
Regulation 12. DSM Evaluation, Measurement & Verification Guiding Principles.
Three basic types of
evaluations covered under these Regulations include:
(a)
Impact evaluation that determines the impacts
(e.g., energy and demand savings) and co-benefits (e.g., avoided emissions,
health benefits, job creation, energy security, transmission/distribution
benefits, and water savings) that directly result from a programme. Impact
evaluations support cost-effectiveness analyses aimed at identifying relative
programme costs and benefits.
(b)
Process evaluation that assesses programme
delivery, from design to implementation, in order to identify bottlenecks,
efficiencies, what worked, what did not work, constraints, and potential
improvements. Timeliness in identifying opportunities for improvement is
essential to making corrections along the way.
(c)
Market effects evaluation that estimates a
programmes influence on encouraging future DF/DSM projects because of changes
in the energy marketplace. These evaluations are primarily, but not exclusively
used for programmes with market transformation elements and objectives.
Entire Evaluation,
Measurement & Verification (EMV) process for all the demand flexibility and
demand side management projects and programmes shall be managed in a
transparent manner using online and real-time assessment tools wherever
feasible. The Distribution Licensees shall empanel Independent Verification
Agencies (IVAs), who are either individuals or organizations with expertise
defined under these Regulations. Cost of the appointment of empanelled IVAs
shall be included in the DF / DSM portfolio costs submitted by Distribution
Licensee as a part of the project costs. The Commission may choose to have an
IVA evaluate the programmes directly as well on a case-to-case basis if it
chooses to do so.
Regulation 13. Impact Evaluation.
The impact evaluation
expressed as gross energy/demand savings and the demand flexibility created
shall be determined by comparing energy use and demand after a DF / DSM
programme is implemented (i.e. the reporting period) with the energy use and demand
if the programme not been implemented (i.e. the baseline). The estimated
savings shall be determined by the following equation:
Estimated savings =
(baseline use) - (reporting period use) ± (appropriate adjustments)
The impact evaluation shall
primarily be carried out using either of the three approaches:
* Measurement &
verification approach;
* Deemed savings approach;
and
* Large-scale data analysis.
13.1.
Measurement & verification approach.
Four generic measurement
& verification methodologies A, B, C and D described in the International
Performance Measurement & Verification Protocol (IPMVP) may be used to
estimate the savings comparing baseline use and reporting period use with
appropriate adjustments thereto. The distribution licensee should propose the
evaluation process that complies with the IPMVP guidelines at the approval
stage of the new demand side management programmes. If the distribution
licensees wish to propose any other suitable methodologies, the portfolio and
programmes should include those explicitly with justifications thereto.
Annexure 3 shows the general description of the four measurement &
verification methodologies as per IMPVP.
13.2.
Deemed savings approach.
Deemed savings (also
referred to as "stipulated" savings) shall be reported on the basis
of historical savings values of typical DSM projects. Sources of deemed savings
values must be documented in the evaluation plan. The deemed savings determined
for a sample of projects shall be applied to all the projects in the DSM programme
to estimate the programme-level savings. The deemed savings approach shall be
recommended by the distribution licensee for DSM programmes that are repeated
and have fixed operating conditions (e.g. operating hours) and
well-substantiated savings values (e.g. energy consumption patterns).
Distribution licensees shall propose this approach when well documented and
systematically validated sources, such as historical evaluations, are available
for certain types of technologies.
13.3.
Large-scale data analysis.
In case of established
homogenous energy use patterns and implementation of programmes in such
categories, the savings evaluation can be carried out using time-series
comparisons of energy use before and after the implementation of demand side management
programmes. Other approach shall include comparison of energy use of
participants and non-participants.
The EM&V plan proposed
by the distribution licenses shall also include the methodology to be followed
to determine net impacts from the gross impacts calculated based on the
methodologies proposed under 13.1, 13.2 and 13.3. The Netto-Gross Ratio
proposed should include free-riders, non-participant spill-over and participant
spill-over. The distribution licensees shall use survey techniques such as
self-reporting surveys and interviews of key participants.
Regulation 14. Process evaluation.
Distribution licensees shall
also include robust process evaluations to improve the programme design and
cost-effectiveness of the proposed measures. Process evaluations shall be
structured in order to examine the efficiency and effectiveness of DF/DSM
programme implementation procedures and systems.
These evaluations shall
include interviews with those involved in the programme, analysis of their
answers, and comparing results to established best practices. The process
evaluation shall include recommendations for changing a programmes structure,
implementation approaches, or programme design, delivery, and goals supported
through the findings from the evaluation interviews. The primary instrument
used in the process evaluations shall be data collection (e.g., surveys,
questionnaires, and interviews) from administrators, designers, participants (such
as facility operators), implementation staff (including contractors,
subcontractors, and field staff), and key policy makers. Other key elements of
a process evaluation shall be workflow and productivity measurements; reviews,
assessments, and testing of records, databases, programme-related materials,
and tools; and collection and analysis of relevant data from third-party
sources (e.g., equipment vendors, trade allies).
Regulation 15. Market Effect Evaluation.
The EM&V shall also
assess Market effects as a result of the specific DF / DSM programmes. This
evaluation shall include:
* Assessment of additional
DF / DSM programmes implemented by the participants without the support from
distribution licensee.
* Additional entities
implementing the technical interventions promoted through the distribution
licensees DSM programmes.
* Assessment of pricing,
changes in predominant efficiencies and availability of efficient products in
the market.
Regulation 16. Empanelment of Independent Verification Agencies.
Distribution Licensees,
supported through these Regulations, shall empanel Independent Verification
Agencies (IVAs). The IVCs shall be selected based on the following criteria:
(a)
IVAs should be individual consultants,
consultancy organizations, academic/research institutions, civil society
organisations and/or consortia thereof;
(b)
IVAs should have at least one BEE Certified
Energy Auditor or Certified Energy Manager; or a Certified Measurement &
Verification Professional (CMVP) certified by any national or international
certification agency on their team in case of consultancy
organizations/consortia thereof; and
(c)
Shall possess experience in design,
implementation, review, measurement, verification and statistical analysis
related to large datasets. The IVAs appointed for specific projects should not
have been involved in DF / DSM programme design, implementation, review, and
any related activity.
Regulation 17. EM&V report formats.
The EM&V reports
submitted by the IVAs shall include at a minimum the following - DF/ DSM
portfolio / programme description, description of the proposed impact, process
and market evaluation methodologies, description of measurement instruments,
sampling process, reporting period, baseline period, metering/measurement
accuracies, statistical analyses carried, list of assumptions, survey
instruments used and annexes including the key raw data, list of respondents
with their contact details, and credentials of IVAs.
Regulation 18. Powers to remove difficulties.
If any difficulty arises in
giving effect to any of the provisions of these Regulations, the Commission may
by order, take suitable action, not being inconsistent with the Act, which appears
to the Commission to be necessary or expedient for the purpose of removing difficulties.
Regulation 19. Orders and Practice Directions.
Subject to the provisions of
the Act, the Commission may from time-to-time issue ordersand practice
directions in regard to the implementation of these Regulations.
Regulation 20. Power to Amend.
The Commission may, at any
time, vary, alter, modify or amend any provisions of these Regulations.