Joint Electricity Regulatory Commission for
the State of Goa and Union Territories (Solar PV Grid Interactive System based
on Net Metering) Regulations, 2019
Joint Electricity
Regulatory Commission for the State of Goa and Union Territories (Solar PV Grid
Interactive System based on Net Metering) Regulations, 2019[1]
[24th
July, 2019]
In exercise of the powers
conferred under Sub-Section (1) of Section 181 and Clauses (zd), (ze) and (zf)
of Sub-Section (2) of Section 181, read with Sections 42, 61(h), 66, 83 and
86(1)(e) of the Electricity Act, 2003 and all other powers enabling it in this
behalf, the Joint Electricity Regulatory Commission (for the State of Goa and
Union Territories) hereby makes the following Regulations, namely:
Regulation - 1. Short Title, Commencement and extent
1.1. These Regulations
shall be called the “Joint Electricity Regulatory Commission for the State of
Goa and Union Territories (Solar PV Grid Interactive System based on Net
Metering) Regulations, 2019” (hereinafter referred to as “Net Metering
Regulations, 2019”).
1.2. These Regulations
shall come into force from the date of publication in the official gazette.
1.3. These Regulations
shall extend to the State of Goa and the Union Territories of Andaman and
Nicobar Islands, Chandigarh, Dadra & Nagar Haveli, Daman & Diu,
Lakshadweep and Puducherry.
1.4. These Regulations
shall apply only to the Grid Connected Rooftop mounted, ground mounted and
floating Solar Power Projects.
Regulation - 2. Definitions, Abbreviations and Interpretations
2.1. In these Regulations,
unless the context otherwise requires:
(1) “Act” means the
Electricity Act, 2003 (36 of 2003), and subsequent amendments thereof;
(2) “Average Power Purchase
Cost” (APPC) means the Weighted Average Pooled Price of power purchase
at Distribution Licensee's periphery, as approved by the Commission in the
Tariff Order of the respective year in which solar energy is generated, from
all the energy suppliers on long-term, medium-term and short-term basis, but
excluding energy purchased from Renewable Energy sources;
(3) “Authority” means
the Central Electricity Authority referred to in sub-section (1) of Section 70
of the Act;
(4) “Billing cycle”
means the period for which regular electricity bills as specified by the
Commission, are prepared for different categories of consumers by the Licensee;
(5) “COD” or “Commercial
Operation Date” or “Date of commercial operation” mean the date on
which generating plant is synchronised with the grid system;
(6) “Check Meter” means
a meter, which shall be connected to the same core of the current transformer
(CT) and voltage transformer (VT) to which Solar Energy Meter is connected and
shall be used for accounting and billing of electricity in case of failure of
main meter or Solar Energy Meter;
(7) “Commission” or “Joint
Electricity Regulatory Commission” or “JERC” means the Joint Electricity
Regulatory Commission for the State of Goa and Union Territories of Andaman and
Nicobar Islands, Chandigarh, Dadra & Nagar Haveli, Daman & Diu,
Puducherry and Lakshadweep referred to in sub-section (1) of Section 82 of the
Act and constituted under the Act;
(8) “Connection Agreement”
means the net-metering inter-connection Agreement entered into between the
Distribution Licensee and the Consumer;
(9) “Consumer” means any
person who is connected to the electricity distribution system of the
Distribution Licensee or any other person engaged in the business of supplying
electricity to the public, as per the Act or any other law in force as of now
and includes any person whose premises are used for receiving power;
(10) “Consumer Grievances
Redressal Forum (CGRF in brief)” means the forum for redressal of grievance
of Consumers, established under Section 42(5) of the Act;
(11) “Contracted Load” or
“Contract Demand” means the maximum demand in kW, kVA or HP, agreed to
be supplied by the Distribution Licensee and as indicated in the Agreement
executed between the Licensee and the Consumer;
(12) “Credit Note” means
number of units (kWh) as credit in the account as surplus power exported to the
grid or the banked solar units accounted at the end of financial year by the
Consumer for which the Distribution Licensee shall make the payment to the
Consumer as per these Regulations;
(13) “Distribution Licensee”
means a person granted a Licence under Section 14(b) of the Act authorizing him
to operate and maintain a distribution system and supply electricity to the
consumers in his area of supply;
(14) “Electricity Supply Code”
means the Electricity Supply Code specified by the Commission under Section 50
of the Act and subsequent amendments thereof;
(15) “Eligible Consumer”
means a consumer of electricity in the area of supply of the Distribution
Licensee, who uses a self-owned or third party owned solar power project, to
offset part or all of the consumer's own electricity requirements;
(16) “Feed-in-Tariff”
means the Generic Tariff determined by the Commission for generation from Solar
Photovoltaic projects for Gross Metering in accordance with the Joint
Electricity Regulatory Commission for the State of Goa and UTs (Terms and
Conditions for Tariff determination from Renewable Energy Sources) Regulations,
2019 or as amended from time to time;
(17) “Grid” means the low
voltage electrical network, the distribution and transmission network or the
high voltage backbone system of inter-connected transmission lines,
sub-stations and generating plants for sale of energy or wheeling of energy as
defined in these Regulations;
(18) “Group Net Metering”
means an arrangement whereby surplus energy is generated and injected from a
Renewable Energy System through Net Meter and the exported energy is adjusted
in more than one electricity service connection(s) of the same consumer either
at the same or different premise located within the same Distribution
Licensee's area of supply;
(19) “Installed Capacity”
means the summation of the name plate capacities expressed in kWp of all the
units of the Solar Project or the capacity of the Solar Project reckoned at the
output terminals, approved by the Commission;
(20) “Interconnection Point”
means the interface point of a Solar Project with the distribution network of
the Distribution Licensee at appropriate voltage level as defined in the Joint
Electricity Regulatory Commission for the State of Goa and UTs (Electricity
Supply Code) Regulations, 2018 or as amended from time to time;
(21) “Invoice” means a
periodical Bill/Supplementary Bill or an Invoice/Supplementary Invoice by the
Distribution Licensee to the Consumer;
(22) “Month” means
English calendar month starting with 1st day/date of the month
and ending with last day/date of the month. Part Month will be applicable for
number of days in proportion to total number of days in the specific month;
(23) “Net Metering” means
an arrangement under which Solar PV System installed at Eligible Consumer's
premises is delivering surplus electricity, if any, to the grid of the
Distribution Licensee after off-setting the electricity supplied by the
Distribution Licensee to such Eligible Consumer during the applicable billing
period;
(24) “Net Meter” means an
appropriate bi-directional energy meter capable of recording both import from
the grid and export of electricity generated at Solar Project;
(25) “Obligated Entity”
means the licensed Supplier of Power, Distribution Licensee(s), Captive user(s)
and Open Access Consumer(s), identified under Joint Electricity Regulatory
Commission for the State of Goa and Union Territories (Procurement of Renewable
Energy) Regulations, 2010 as amended from time to time and mandated under
clause (e) of sub-section (1) of Section 86 of the Act to fulfil the Renewable
Purchase Obligations as determined by the Commission from time to time;
(26) “Ombudsman” means
the person appointed in accordance with Section 42(6) read with Section 181 of
the Act;
(27) “Open Access Consumer”
means a person permitted to use Intra-State Transmission System and/or
Distribution System to receive supply of electricity from a person other than
the Distribution Licensee of his area of supply, and the expression includes a
Generating Company and a Licensee, who has availed of or intends to avail of
Open Access;
(28) “Project Developer”
means the developer of the Solar Project, who shall develop such a project on
his own premises or on premises taken on lease or rent;
(29) “Prosumer” means a
Consumer who is also a Producer of Solar Power;
(30) “Producer of Solar Power”
means an individual or an entity or a group of people intending to set up or
who has/have set up a Solar Project for the purpose of generation of Solar
power for own consumption and sale of surplus power to the Distribution Licensee;
(31) “Premises” means
Rooftop of a house/factory/Ware house/Government building/Panchayat
Bhavan/Community Centre/School/dispensary/hospital/parking place/Bus
Stand/Group Housing Society/Market Society/market roof top/Canals/Water
Reservoir/any such place/or vacant space and elevated area on the land,
building or the Infrastructure or part or combination thereof, or the area
taken on rent or on lease, or the area for the common facility in the premises
of any multi-storeyed building, Group Housing Society/Residential Welfare
Association/Market Welfare Association/Industrial Welfare Group and in respect
of which a separate meter or metering arrangements have been made by the
Licensee for supply of electricity. The premises exclude the structures of
historic significance (unless permission is taken from appropriate authority);
(32) “Renewable Energy
Certificate (REC)” means the certificate issued in accordance with the
Regulations and the procedures approved by the Central Electricity Regulatory
Commission;
(33) “Renewable Purchase
Obligations (RPO)” means renewable power purchase obligations;
(34) “Sanctioned Load”
means the load in kW, kVA or HP, which the Licensee has agreed to supply from
time to time subject to the governing terms and conditions in the absence of an
Agreement between the Distribution Licensee and the consumer;
(35) “Settlement Period”
means the period beginning from first day of April as per the English calendar
year and ending with the thirty first day of March of the next year;
(36) “Solar Energy Meter”
means the meter used for measuring the gross solar power units generated by the
Solar Project for the purpose of accounting and billing;
(37) “Solar Grid Inverter”
means equipment that converts the DC (direct current) power from Solar Power
modules to Grid-compatible AC (alternating current) power;
(38) “Solar Photovoltaic
Power” means a solar photo voltaic power project that uses sunlight for
direct conversion into electricity through Photo Voltaic technology based on
technologies such as crystalline Silicon or thin film, etc., as approved by the
Ministry of New & Renewable Energy (MNRE) from time to time;
(39) “Solar Project”
means a Rooftop or ground mounted or floating Photovoltaic and other small
Solar Power generating station, installed that uses sunlight for its direct
conversion into electricity;
(40) “Solar Project Developer
(SPD)” means a Consumer or an entity whose Solar Project has been granted
connectivity by the Distribution Licensee;
(41) “Solar Power Generator
(SPG)” means anyone who has started generating solar power from the
approved project;
(42) “State Nodal Agency”
means the agency in the concerned State or Union Territory as may be designated
by the Commission to act as the agency for accreditation and recommending the
renewable energy projects for registration and to undertake such functions as
may be specified under clause (e) of sub-section (1) of Section 86 of the Act;
(43) “Supplier of Power”
means a person or an entity having licence to supply electricity to the
Consumer;
(44) “Tariff Order” in
respect of a Licensee means the last retail Tariff Order issued by the
Commission for that Licensee indicating the tariff to be charged by the
Licensee from various categories of Consumers for supply of electrical energy
and services;
(45) “Third Party Owned”
means a Solar Project owned by a Solar Project Developer that is installed on
the roof or elevated structure or the Premises as defined in 1(31) above for
which a commercial lease or revenue share agreement has been entered into by
the Solar Project Developer with the owner;
(46) “Virtual Net Metering”
means an arrangement whereby entire energy generated from a Solar Project
installed at Consumer premise or any other location is injected through Solar
Energy Meter and the energy exported is adjusted in either one or more than one
electricity service connection(s) of participating Consumer(s) located within
the same Distribution Licensee's area of supply;
(47) “Year” or “Financial
Year” means a period commencing on 1st April of an English calendar year
and ending on 31st March of the subsequent calendar year.
2.2. Abbreviations: In
these Regulations the following shall be interpreted as:
(i)
“EPC”
means Engineering Procurement & Construction Contractor authorized by the
Distribution Licensee;
(ii)
“kWp”
means kilo Watt peak, term used as a rating of the Solar Plant;
(iii)
“MNRE”
means the Ministry of New and Renewable Energy of Government of India;
2.3. All other words and
expressions used in these Regulations if not specifically defined herein above,
but defined in the Act, shall have the meaning assigned to them in the Act. The
other words and expressions used herein but not specifically defined in these
Regulations or in the Act but defined under any other law passed by the
Parliament applicable to the electricity industry in the State or Union
Territory shall have the meaning assigned to them in such law.
Regulation - 3. Scope of Regulations and Extent of Application
3.1. These Regulations
shall be applicable to the grid connected solar projects subject to the
fulfilment of Eligibility Criteria specified in these Regulations.
3.2. Group Net Metering
Framework shall be applicable for all Consumers.
3.3. Virtual Net Metering
Framework shall be applicable for residential consumers, Group Housing
Societies, and establishments of Government/Local Authorities.
Regulation - 4. Eligibility Criteria
4.1. Solar Projects of
capacity up to 500 kWp at one premise based on the technologies approved by
MNRE are eligible for connecting the project with the Grid under these
Regulations. The capacity of the Solar Project to be installed under Group Net
Metering or Virtual Net Metering framework shall not be less than 5 kWp and
more than 500 kWp
Provided that the Solar
Project of rating higher than 500 kWp can be considered by the Distribution
Licensee if the distribution system remains stable with higher rating Solar
Project getting connected to the grid.
4.2. The Eligible Consumer
may install the Solar Project under these Regulations, provided the Solar
Project is:
(i)
Within
the permissible rated capacity as defined under these Regulations;
(ii)
Located
at the Consumer's Premises;
(iii)
Interconnected
and operated safely in parallel with the Distribution Licensee's network.
4.3. Consumers will
generate solar power for self-consumption and are allowed to feed the excess
solar power into the grid, which shall be adjusted under Net Metering as per
provisions of these Regulations.
4.4. The maximum Solar
Power Generation capacity to be installed at any Eligible Consumer's Premises
shall not exceed his Contract Demand (in kVA) or Sanctioned Load (in kW).
Regulation - 5. Third Party Owned Solar Project.
In the third party owned
Solar Project, the following conditions shall apply:
(i)
The
Consumer may lease out/rent the Rooftop Space/Land/Water bodies to a Solar
Project Developer on a mutual commercial arrangement for setting up Solar
Project under Net Metering framework. The Consumer will pay the Solar Project
Developer for all the energy generated by the Solar Project at a mutually
agreed tariff. The commercial arrangement between the Project Developer and the
Prosumer will be submitted to the Distribution Licensee for records and the
Distribution Licensee will not have any role in such commercial arrangement.
All the provisions of Net Metering framework shall be applicable for Solar Project
set up by a Solar Project Developer.
(ii)
Such
Solar Projects set up under these Regulations shall be exempted from Open
Access restrictions and associated charges including losses.
(iii)
The
Distribution Licensee/Nodal Agency may explore other business models that may
facilitate the proliferation of Grid connected Rooftop solar projects. For any
new business model not envisaged in these Regulations, the Commission will
approve the framework for such business model based on the specific Petition to
be filed in this regard.
Regulation - 6. Solar Power Generation Capacities
6.1. The Distribution
Licensee may undertake demand aggregation and other related activities, to
promote solar power capacity in its licensed area. The Distribution Licensee
may act EPC to undertake solar power development:
Provided that in case the
Distribution Licensee acts EPC, the income from such activity shall be
considered as “Other Income” under the provisions of the applicable Tariff
Regulations.
6.2. The Distribution
Licensee shall facilitate the Solar Project Development:
Provided that the
cumulative solar capacity allowed at a particular Distribution Transformer
shall not exceed 75 percent of the capacity of the Distribution Transformer:
Provided further that the
Distribution Licensee may allow solar power capacity connected to a particular
Distribution Transformer and feeder connected to the same exceeding 75 percent
of capacity upon consideration of a detailed load study carried out by it.
6.3. The Distribution
Licensee shall update on a yearly basis for each of the Distribution
Transformers, the Distribution Transformer capacity available for connecting
the Solar Projects and shall provide the information on its website, as well as
to the Commission.
Regulation - 7. Solar Project-Types.
For the purpose of these
Regulations, the Commission has covered the Solar Power Projects for Prosumer,
which may be roof mounted, ground mounted, floating on water bodies or
installed on Elevated structures.
Regulation - 8. Metering Arrangement
8.1. The metering system
shall be as per the Central Electricity Authority (Installation & Operation
of Meters) Regulations, 2006, as amended from time to time.
8.2. Net Meter of the same
accuracy class as the Consumer's meter existing before the commissioning of the
Solar Project, shall be installed in replacement of existing meter:
Provided that, if the
Eligible Consumer is within the ambit of Time-of-Day (‘ToD’) Tariff, the Net
Meter installed shall be capable of recording ToD consumption and generation:
Provided further that such
Meters may be provided by the Distribution Licensee or the Consumer, subject to
the same being from the approved list of the suppliers:
Provided also that if the
Meter is installed by the Distribution Licensee, its cost shall be recovered
from the Consumer before the COD of the Project.
8.3. The Solar Energy
Meter (a unidirectional meter) is to be installed as an integral part of the
Net Metering system at the point at which the electricity is generated by the
Solar Project and delivered to the main panel. The Solar Energy Meter shall
have facility for recording meter readings using Meter Reading Instrument (MRI)
or wireless equipment.
8.4. Check Meters shall be
mandatory for Solar Project having capacity more than 20 kW. For installations
having capacity less than or equal to 20 kW, the Check Meters would be
optional:
Provided that the cost of
Check Meter shall be borne by the Consumer, and such meter shall be tested and
installed by the Distribution Licensee.
8.5. The Distribution
Licensee shall be responsible for installation, testing and maintenance of the
metering equipment/system and its adherence to the applicable standards and
specifications.
8.6. The Meters installed,
if arranged by the Consumer, shall be inspected, verified for the accuracy and
sealed by the Distribution Licensee in the presence of the Consumer or its
representative (if he chooses to be present at the time of testing).
Regulation - 9. Inter-connection with the Distribution Network, Standards and Safety
9.1. The Distribution
Licensee shall ensure that the inter-connection of the Solar Project with its
distribution network conforms to the specifications, standards and other
provisions specified in the CEA (Technical Standard for Connectivity of the
Distributed Generation Resources) Regulations, 2013, CEA (Technical Standards
for Connectivity to the Grid) Regulations, 2007 including amendments thereto,
the CEA (Measures relating to Safety and Electric Supply), Regulations, 2010
including amendments thereto, the Joint Electricity Regulatory Commission for
the State of Goa and UTs (Electricity Supply Code) Regulations, 2018 including
amendments thereto, and the Joint Electricity Regulatory Commission for the
State of Goa and UTs (State Grid Code) Regulations, 2010 including amendments
thereto.
9.2. Solar Power
generation with Net metering will be allowed for all the eligible Consumers of
the Distribution Licensee under the jurisdiction of the Commission with/without
battery back-up support:
Provided that, if an
Eligible Consumer opts for connectivity with a battery back-up, the inverter
shall have a separate back-up wiring to prevent the battery/decentralized
generation (DG) power from flowing into the grid in the absence of grid supply,
and that an automatic as well as manual isolation switch shall also be
provided.
Provided further that the
Inverter shall comply with the Standards prescribed in Annexure A.
9.3. The Eligible Consumer
shall be responsible for the safe operation, maintenance and rectification of any
defect in the Solar Project up to the point of Net Meter, beyond which point
such responsibility, including in respect of the Net Meter, shall be that of
the Distribution Licensee:
Provided that the Solar
Energy Meter shall be maintained by the Distribution Licensee.
9.4. The Eligible Consumer
shall provide appropriate protection for islanding of the Solar Project from
the network of the Distribution Licensee in the event of grid or supply
failure.
9.5. The Consumer shall be
solely responsible for any accident to human being/animals whatsoever
(fatal/non-fatal/departmental/non-departmental) that may occur due to back
feeding from the Solar Project when the grid supply is off:
Provided that the
Distribution Licensee shall have the right to disconnect the Solar Project from
its distribution network at any time in the event of any threat of accident or
damage from such Project to its distribution system, for maintenance of
distribution system so as to avoid any accident or damage to it:
Provided further that the
Eligible Consumer may use his Solar Project in islanding mode for his own
consumption.
9.6. The Distribution
Licensee and Eligible Consumer shall discharge their respective duties and
responsibilities as specified in the relevant Regulations of the Central
Electricity Authority.
9.7. HT Consumers opting
for Net Metering shall not be required to provide separate connectivity for the
Solar Project at HT voltage level for consumption at LT Level.
Regulation - 10. Communication Facilities.
All grid connected Solar
Projects shall have electricity meters with features to record energy for data
storage for injection into the grid through Solar Energy Meter as provided
under these Regulations:
Provided that all projects
shall have communication port for exchanging real time information with the
Distribution Licensee:
Provided further that all
Meters shall have Advanced Metering Infrastructure (AMI) facility.
Regulation - 11. Billing, Energy Accounting and Settlement
11.1. The accounting of
electricity exported from the Solar Project and imported from the Grid by the
Eligible Consumer shall become effective from the date of connectivity of the
Solar Project with the distribution network.
11.2. For each billing
period, the Distribution Licensee shall show separately:—
(a) the quantum of electricity
Units exported by the Eligible Consumer;
(b) the quantum of electricity
Units imported by the Eligible Consumer;
(c) the net quantum of
electricity Units billed for payment by the Eligible Consumer; and
(d) the net quantum of electricity
Units carried over (if surplus) to the next billing period:
Provided that, if the
quantum of electricity exported exceeds the quantum imported during the billing
period, the excess quantum shall be carried forward to the next billing period
as credited Units of electricity;
Provided further that, if
the quantum of electricity Units imported by the Eligible Consumer during any
billing period exceeds the quantum exported, the Distribution Licensee shall
raise its invoice/bill for the net electricity consumption after adjusting the
credited Units.
11.3. The unadjusted net
credited Units of electricity as at the end of each financial year shall be
considered as units purchased by the Distribution Licensee at Average Power
Purchase cost of the concerned Distribution Licensee or Feed-in-Tariff
determined for that Year without considering subsidy and Accelerated
Depreciation, whichever is lower.
Provided that, at the
beginning of each Settlement Period, the cumulative quantum of injected
electricity carried forward will be re-set to zero.
11.4. In case the Eligible
Consumer is within the ambit of Time of Day (ToD) tariff, the electricity
consumption in any time block, i.e., peak hours, off-peak hours, etc., shall be
first compensated with the quantum of electricity injected in the same time
block:
Provided that any excess
injection over and above the consumption in any other time block in a billing
cycle shall be accounted as if the excess injection had occurred during
off-peak hours.
11.5. The Distribution
Licensee shall compute the amount payable to the Eligible Consumer, latest by
April 30th of the following year for the excess solar energy
purchased by it during the Financial year as specified in Regulation 11.3, and
shall pay the amount to the eligible consumer by May 31st of
the following year.
11.6. The Eligible Consumer
shall have recourse, in case of any dispute with the Distribution Licensee
regarding billing, to the mechanism specified by the Commission under Sections
(5) to (7) of the Act for the redressal of grievances.
11.7. In case of Group Net
Metering, the billing and energy accounting shall be dealt with as under:
(a) Where the export of units
during any billing period exceeds the import of units at the connection where
Solar Project is located, such surplus units injected into the grid shall be
adjusted against the energy consumed in the monthly bill of service
connection(s) in a sequence indicated in the priority list provided by the
Consumer. The sequence of priority for adjustment shall be deemed to have begun
with the service connection where the Solar Project is located;
(b) The priority list for
adjustment of the balance surplus energy against other electricity
connection(s) may be revised by the Consumer once at the beginning of every
financial year with an advance notice of two months;
(c) The electricity consumption
in any time block (e.g., peak hours, off-peak hours, etc.) shall be first
compensated with the electricity generation in the similar time blocks in the
same billing cycle of the Consumer where the Solar Project is located, and any
surplus units injected shall be adjusted against the energy consumed in the
monthly bill of service connection(s) in a sequence indicated in the priority
list provided by the Consumer, as if the surplus generation/Energy Credits
occurred during the off peak time block for Time of Day (ToD) Consumers and
normal time block for Non-ToD Consumer;
(d) Where during any billing
period, the export of units either in Non-ToD Tariff or ToD Tariff exceeds the
import of units by the electricity service connection(s), such surplus units
injected by the Consumer shall be carried forward to the next billing period as
energy credit and shown as energy exported by the Consumer for adjustment
against the energy consumed in subsequent billing periods within the Settlement
Period in the sequence indicated in the priority list;
(e) For unadjusted net credited
Units of electricity at the end of each financial year, the provisions of
Clause 11.3 will be applicable for the connection where Solar Project is
located.
11.8. In case of Virtual
Net Metering, the billing and energy accounting shall be dealt with as under:
(a) The energy generated from
the Solar Project shall be credited in the monthly electricity bill of each
participating consumer(s) as per the ratio of procurement from Solar Project
indicated under the agreement/MoU entered on a stamp paper by the Consumer(s)
and submitted to the Distribution Licensee;
(b) The Consumer(s) shall have
the option to change the share of credit of electricity from Solar Project by
submitting a fresh Agreement/MoU on a stamp paper subject to the ratio of
procurement from Solar Project indicated under the agreement/MoU entered by the
Consumer(s) once at the beginning of the financial year with an advance notice
of two months;
(c) Where the service
connection of any participating consumer(s) is disconnected due to any reason
under any law for the time being in force, the unadjusted units/remaining
credits of that consumer shall be paid by the Distribution Licensee at the end
of the financial year;
(d) The electricity consumption
in any time block (e.g., peak hours, off-peak hours, etc.) shall be first
compensated with the electricity generation in the similar time blocks in the
same billing cycle of the participating consumer(s). Any surplus generation
over consumption in any time block in a billing cycle shall be accounted as if
the surplus generation/Energy Credits occurred during the off-peak time block;
(e) Where the units credited
during any billing period of any participating Consumer exceeds the import of
units by that consumer, such surplus credited units shall be carried forward in
the next billing period as energy credits for adjustment against the energy
consumed in subsequent billing periods within the settlement period of each
participating Consumer(s);
(f) For unadjusted net credited
Units of electricity at the end of each financial year, the provisions of
Clause 11.3 will be applicable for each participating Consumer(s).
(g) The commercial arrangement
for setting up and operating Solar Project under Virtual net Metering between
the participating Consumer(s) will be mutually agreed and the Distribution
Licensee will not have any role in such commercial arrangement.
Regulation - 12. Penalty or Compensation - Failure in Metering System.
In case of failure of
metering system, the provisions of penalty or compensation shall be as per the
provisions of the Joint Electricity Regulatory Commission for the State of Goa
and UTs (Standards of Performance for Distribution Licensees) Regulations, 2015
for the Distribution Licensee.
Regulation - 13. Late Payment Surcharge.
In case the payment by the
Distribution Licensee under Regulation 11.3 above is delayed beyond 31st of
May of that year, a Late Payment Surcharge at the rate of 1.25% per month from
the delay beyond 31st May shall be levied on the Distribution
Licensee.
Regulation - 14. Charges for Banking of Solar Power.
The Solar Projects, whether
self-owned or third party owned installed under these Regulations, shall be
exempted from charges in respect of banking of electricity.
Regulation - 15. Renewable Purchase Obligation and Eligibility to Participate under REC Mechanism
15.1. The quantum of
electricity consumed by the Eligible Consumer from the Solar Project under the
Net Metering Arrangement shall qualify towards his compliance of Solar RPO, if
such Consumer is an Obligated Entity.
15.2. The quantum of
electricity consumed by the Eligible Consumer from the Solar Project owned and
installed under the Net Metering arrangement shall, if such Consumer is not an
Obligated Entity, qualify towards meeting the Solar RPO of the Distribution
Licensee:
Provided that the
Distribution Licensee shall, with the consent of the Eligible Consumer, make
all the necessary arrangements, including for additional metering, as may be
required for the accounting of the Solar energy generated and consumed by the
Eligible Consumer.
15.3. The unadjusted
surplus units of Solar energy purchased by the Distribution Licensee under the
provisions of Regulation 11.3 shall also qualify towards meeting its Solar RPO.
15.4. The Solar energy
generated by an Eligible Consumer in a Net Metering Arrangement under these
Regulations shall not be eligible for REC.
15.5. The Solar Energy
generated for captive use shall also qualify for meeting the RPO.
Regulation - 16. Procedure for Application and Registration
16.1. The Eligible Consumer
shall apply to the concerned Distribution Licensee for connectivity of the
Solar Project with the Licensee's distribution network along with one-time,
non-refundable registration fee for Rs. 500 (five hundred) or such other amount
as may be stipulated by the Commission from time to time; and the Distribution
Licensee shall acknowledge receipt of such application:
Provided that the Distribution
Licensee shall provide the option of making such application and payment of
fees by electronic means online within two months from the date of publication
of these Regulations.
16.2. The procedure for
application for connectivity of a Solar Project with the network of the
Distribution Licensee is set out at Annexure 1 of these
Regulations. The model Application Form, along with a checklist, for
application to be made by the Eligible Consumer to the concerned Licensee is
at Annexure 2.
16.3. Before rejecting any
application for setting up a Solar Project for connection to a particular
Distribution Transformer, the Distribution Licensee shall serve the applicant
with a notice to rectify, within 15 days or such longer period as may be
necessary, the deficiencies:
Provided that in case
approval cannot be granted due to inadequate Distribution Transformer capacity,
the application may be considered, in chronological order of date seniority and
if the Consumer so opts, after such capacity becomes available.
16.4. The Distribution
Licensee shall implement a web-based processing system for processing of the
applications for Solar Net Metering, which shall be set up within three months
of the notification of these Regulations.
16.5. Matters relating to
subsidy shall be dealt by the State Nodal Agency/Distribution Licensee or as
approved by MNRE from time to time.
16.6. The Distribution
Licensee shall annually publish on its web, information relating to the Solar
Projects added in the year, ratings of each Solar Project and other relevant
information. The information shall also be submitted to the Commission by 30th April
of the next year.
16.7. The plants with
capacity more than 500 kWp shall be checked by the concerned Chief Electrical
Inspector associated with the Distribution Licensee.
Miscellaneous
Regulation - 17. Power to relax.
The Commission may by
general or special order, for reasons to be recorded in writing, and after
giving an opportunity of hearing to the Parties likely to be affected, relax
any of the provisions of these Regulations on its own motion or on an
application made before it by an interested person.
Regulation - 18. Power to amend.
The Commission may at any
time add, vary, alter, suspend, modify, amend or repeal any of the provisions
of these Regulations.
Regulation - 19. Repeal and Savings.
Save as otherwise provided
in this Net Metering Regulations, 2019, JERC (Grid Connected Ground Mounted and
Solar Rooftop and Metering) Regulations, 2015, together with amendments made
from time to time, are hereby repealed:
Provided that for all
purposes, including review matters pertaining to the period till notification
of these Regulations, the issues relating to Net Metering shall be governed by
the provisions of the JERC (Grid Connected Ground Mounted and Solar Rooftop and
Metering) Regulations, 2015, including amendments thereto, as may be
applicable.
Regulation - 20. Power to remove difficulties.
In case of any difficulty
arising while giving effect to the provisions of these Regulations, the Commission
may either suo-motu or on a Petition, by an order, make such provisions not
inconsistent with the provisions of the Act as may appear to be necessary.
Annexure A : Voltage level Harmonics, Standards : Harmonics & Inverter
Harmonics shall be as per IEEE
519 Standards. The permissible individual harmonics level shall be less than 3%
(for both voltage and current harmonics) and Total Harmonics Distortion (THD)
for both voltage and current harmonics of the Grid system shall be less than
5%.
Inverter
Standards
Inverter should comply with
IEC 61683/IS 61683 for efficiency and Measurements and should comply IEC
60068-2 (1, 2, 14, 30)/Equivalent BIS Standard for environmental testing.
Inverter should supervise the grid condition continuously and in the event of
grid failure (or) under voltage (or) over voltage, Solar Plant should be
disconnected by the circuit Breaker/Auto switch provided in the Inverter.
Various Other Standards |
|||
Sl. |
Parameter |
Reference |
Requirements |
1. |
Overall conditions of service |
State Distribution/Supply Code |
State Distribution/Supply Code |
2. |
Overall Grid Standards |
Central Electricity Authority (Grid Standard)
Regulations, 2010 |
Central Electricity Authority (Grid Standard)
Regulations, 2010 |
3. |
Equipment |
BIS/IEC/IEEE |
BIS/IEC/IEEE |
4. |
Meters |
Central Electricity Authority (Installation &
operation of meters) Regulation, 2006 as amended time to time |
Central Electricity Authority (Installation &
operation of meters) Regulation, 2006 as amended time to time |
5. |
Safety and supply |
Central Electricity Authority (Measures relating
to Safety and Electricity Supply) Regulations, 2010 |
Central Electricity Authority (Measures relating
to Safety and Electricity Supply) Regulations, 2010 |
6. |
Harmonic Requirements Harmonic Current |
IEEE 519 CEA (Technical Standards for Connectivity of the
Distributed Generation Resources) Regulations, 2013. |
IEEE 519 CEA (Technical Standards for Connectivity of the
Distributed Generation Resources) Regulations, 2013. |
7. |
Synchronization |
IEEE 519 CEA (Technical Standards for Connectivity of the
Distributed Generation Resources) Regulations, 2013 |
Solar Plant must be equipped with a grid
frequency synchronization device. Every time the generating station is
synchronized to the electricity system. It shall not cause voltage
fluctuation greater than +/- 5% at the point of connection. |
8. |
Voltage |
IEEE 519 CEA (Technical Standards for Connectivity of the
Distributed Generation Resources) Regulations, 2013 |
The voltage-operating window should minimize
nuisance tripping and should be under operating range of 80% to 110% of the
nominal connected voltage. Beyond a clearing time of 2 second, the Solar
Plant must isolate itself from the grid. |
9. |
Flicker |
IEEE 519 CEA (Technical Standards for Connectivity of the
Distributed Generation Resources) Regulations, 2013 |
Operation of Solar Plant should not cause voltage
flicker in excess of the limits stated in IEC 61000 standards or other
equivalent Indian standards, if any. |
10. |
Frequency |
IEEE 519 CEA (Technical Standards for Connectivity of the
Distributed Generation Resources) Regulations, 2013 |
When the Distribution system frequency deviates
outside the specified conditions (50.5 Hz on upper side and 47.5 Hz on lower
side), There should be over and under frequency trip functions with a clearing
time of 0.2 seconds. |
11. |
DC injection |
IEEE 519 CEA (Technical Standards for Connectivity of the
Distributed Generation Resources) Regulations, 2013 |
Should not in]ect DC power more than 0.5% of full
rated output at the interconnection point or 1% of rated inverter output current into
distribution system under any operating condition. |
12. |
Power Factor |
IEEE 519 CEA (Technical Standards for Connectivity of the
Distributed Generation Resources) Regulations, 2013 |
While the output of the inverter is greater than
50%, a lagging power factor of greater than 0.9 should operate. |
13. |
Islanding and Disconnection |
IEEE 519 CEA (Technical Standards for Connectivity of the
Distributed Generation Resources) Regulations, 2013 |
The Solar Project in the event of fault, voltage
or frequency variations must island/disconnect itself within IEC standard on
stipulated period. |
14. |
Overload and Overheat |
IEEE 519 CEA (Technical Standards for Connectivity of the
Distributed Generation Resources) Regulations, 2013 |
The inverter should have the facility to
automatically switch off in case of overload or overheating and should
restart when normal conditions are restored. |
15. |
Paralleling Device |
IEEE 519 CEA (Technical Standards for Connectivity of the
Distributed Generation Resources) Regulations, 2013 |
Paralleling device of Solar System shall be
capable of withstanding 220% of the normal voltage at the interconnection
point. |
16. |
Note: The standards/specifications shall be
subject to amendments/revisions from time to time by the Distribution
Licensee and the State Agency on respective websites. |
ANNEXURE-1
Procedure for Application for connectivity of Solar Project with Distribution
Licensee's Network
(a) A Consumer intending to set
up a Solar Project or who has already installed such a system may download the
Application Form from the concerned Distribution Licensee's website and submit
it, duly filled, along with technical details of the Project to the concerned
office of the Distribution Licensee along with registration fee, or apply and
pay the fee online.
(b) The Distribution Licensee
shall register the Application and acknowledge its receipt within three working
days; or intimate the Applicant within that period of any deficiency or incompleteness.
(c) The Distribution Licensee
shall conduct a technical feasibility study within 15 working days from the
registration of the Application considering the following aspects:
(i)
AC
Voltage level at which connectivity is sought;
(ii)
Sanctioned
Load/Contract Demand of the Applicant;
(iii)
Rated
Output AC Voltage of the proposed Solar Project;
(iv)
Available
cumulative capacity of relevant Distribution Transformer;
(d) Before rejecting any
application for setting up a Solar Project at a particular Distribution
Transformer, the Distribution Licensee shall serve the Applicant with a notice
to rectify, within 15 days or such longer period as may be necessary, the
deficiencies.
(e) If found technically
feasible, the Distribution Licensee shall, within 7 working days of the
completion of the feasibility study, convey its approval for installing the
Solar Project. The approval shall indicate the maximum permissible capacity of
the Project, and shall be valid for a period of 4 months from the date of
approval, or such extended period as may be agreed to by the Distribution
Licensee.
(f) The Applicant shall, within
the period of validity of such approval, submit the work completion report,
along with relevant details (such as technical specifications, test reports
received from manufacturer/system provider, etc.), with a request to the
Distribution Licensee for the testing and commissioning of the Solar Project.
(g) The Distribution Licensee
shall complete the testing and commissioning of the Project within 10 working
days from receipt of such request, and shall install the Net Metering equipment
and synchronize the Roof-top Solar PV System within 10 working days thereafter.
(h) The Eligible Consumer and
Distribution Licensee shall enter into a Net Metering Connection Agreement in
the prescribed format (Annexure-3) after the Solar Project is installed but
before it is synchronized with the distribution network.
ANNEXURE-2
Model Application Form for installation of Solar Project under Net Metering
arrangement
Name of Distribution Licensee
[]
Name of Administrative
Office []
(To be filled by the
Applicant in Block Letters)
1. |
Applicant's Full Name |
: |
2. |
Address of the premises at which
Solar Project is to be installed. |
: |
3. |
Telephone/Mobile No. |
: |
4. |
E-mail ID (if available) |
: |
5. |
Alternate Address for communication
(if any) |
: |
6. |
Category of existing electricity
connection |
: |
7. |
Consumer No. |
: |
8. |
Sanctioned Load/Contract Demand (in
kW/kVA/HP) |
: |
9. |
Voltage at which existing supply has
been given (in volts). |
: |
10. |
Proposed AC capacity of Roof-top
Solar PV System to be installed (in kW). |
: |
11. |
Voltage at the output of Solar
inverter (in volts). |
: |
12. |
Details of Registration Fee paid |
: |
(Rs. 500/-).
Date :
_______________________________ Signature of Applicant.
Application No. ___________________________
Date of Receipt
_________________________
List
of documents attached with Application Form
(1) Copy of the latest paid
electricity bill.
(2) General Power of Attorney
in favour of signatory in case of Partnership Firms; certified true copy of the
Resolution, authorizing the signatory to deal with the concerned Distribution
Licensee, passed by the Board of Directors in case of Companies (as
applicable).
(3) Technical details of PV modules,
Inverter and other equipment of system proposed to be installed.
(4) Proof of payment of
Registration Fee.
………………………………………………………………………………………………………
ACKNOWLEDGEMENT
Received an Application
from …………………………………. for connectivity/installation of Solar Project of capacity
of ………………. kW as per details below:—
Date of Receipt |
Applicant's Name |
Application Number |
Existing Consumer No. |
Capacity of Rooftop Solar PV System |
(1) |
(2) |
(3) |
(4) |
(5) |
|
|
|
|
|
Date : (Signature and
Designation of Authorized Officer).
ANNEXURE
- 3 Model Net Metering Connection Agreement
This Agreement is made and
entered into at (location) ____________ on this (date) ___________ day of
(month) _______ (year) __________ between the Eligible Consumer (Name)
________________________ having premises at (address) ____________ and Consumer
No. ___________________ as the first Party,
AND
The Distribution Licensee
_________________(hereinafter referred to as ‘the Licensee’) and having its
Registered Office at (address) ________________ as second Party of this
Agreement;
Whereas, the Eligible
Consumer has applied to the Licensee for approval of a Net Metering Arrangement
under the provisions of the Joint Electricity Regulatory Commission (Solar PV
Grid Interactive System based on Net Metering) Regulations, 2019 (herein after
referred to as ‘the Net Metering Regulations’) and sought its connectivity to
the Licensee's Distribution Network;
And whereas, the Licensee
has agreed to provide Network connectivity to the Eligible Consumer for
injection of electricity generated from its Solar Project of _____________
kilowatt;
Both Parties hereby agree
as follows:—
(1) Eligibility
The Solar Project meets the
applicable norms for being integrated into the Distribution Network, and that
the Eligible Consumer shall maintain the Project accordingly for the duration
of this Agreement.
(2) Technical and
Inter-connection Requirements
2.1. The metering
arrangement and the inter-connection of the Solar Project with the network of
the Licensee shall be as per the provisions of the Net Metering Regulations and
the technical standards and norms specified by the Central Electricity
Authority for connectivity of distributed generation resources and for the
installation and operation of meters.
2.2. The Eligible Consumer
agrees, that he shall install, prior to connection of the Solar Project to the
network of the Licensee, an isolation device (both automatic and in built
within inverter and external manual relays); and the Licensee shall have access
to it if required for the repair and maintenance of the Distribution Network.
2.3. The Licensee shall
specify the interface/inter-connection point and metering point.
2.4. The Eligible Consumer
shall furnish all relevant data, such as voltage, frequency, circuit breaker,
isolator position in his System, as and when required by the Licensee.
(3) Safety
3.1. The equipment
connected to the Licensee's Distribution System shall be compliant with
relevant International (IEEE/IEC) or Indian Standards (BIS), as the case may
be, and the installation of electrical equipment shall comply with the
requirements specified by the Central Electricity Authority regarding safety
and electricity supply.
3.2. The design,
installation, maintenance and operation of the Solar Project shall be undertaken
in a manner conducive to the safety of the Roof-top Solar PV System as well as
the Licensee's Network.
3.3. If, at any time, the
Licensee determines that the Eligible Consumer's Solar Project is causing or
may cause damage to and/or results in the Licensee's other Consumers or its
assets, the Eligible Consumer shall disconnect the Solar Project from the
distribution network upon direction from the Licensee, and shall undertake
corrective measures at his own expense prior to re-connection.
3.4. The Licensee shall
not be responsible for any accident resulting in injury to human beings or
animals or damage to property that may occur due to back-feeding from the Solar
Project when the grid supply is off. The Licensee may disconnect the
installation at any time in the event of such exigencies to prevent such
accident.
(4) Other Clearances and
Approvals
The Eligible Consumer shall
obtain any statutory approvals and clearances that may be required, such as
from the Electrical Inspector or the municipal or other authorities, before
connecting the Solar Project to the distribution Network.
(5) Period of Agreement, and
Termination
This Agreement shall be for
a period for 25 years, but may be terminated prematurely
(a) By mutual consent; or
(b) By the Eligible Consumer,
by giving 30 days' notice to the Licensee;
(c) By the Licensee, by giving
30 days' notice, if the Eligible Consumer breaches any terms of this Agreement
or the provisions of the Net Metering Regulations and does not remedy such
breach within 30 days, or such other reasonable period as may be provided, of
receiving notice of such breach, or for any other valid reason communicated by
the Licensee in writing.
(6) Access and Disconnection
6.1. The Eligible Consumer
shall provide access to the Licensee to the metering equipment and
disconnecting devices of Solar Project, both automatic and manual, by the
Eligible Consumer.
6.2. If, in an emergent or
outage situation, the Licensee cannot access the disconnecting devices of the
Solar Project, both automatic and manual, it may disconnect power supply to the
premises.
6.3. Upon termination of
this Agreement under Clause 5, the Eligible Consumer shall disconnect the Solar
Project forthwith from the Network of the Licensee.
(7) Liabilities
7.1. The Parties shall
indemnify each other for damages or adverse effects of either Party's
negligence or misconduct during the installation of the Solar Project,
connectivity with the distribution network and operation of the System.
7.2. The Parties shall not
be liable to each other for any loss of profits or revenues, business
interruption losses, loss of contract or goodwill, or for indirect,
consequential, incidental or special damages including, but not limited to,
punitive or exemplary damages, whether any of these liabilities, losses or damages
arise in contract, or otherwise.
(8) Commercial Settlement
8.1. The commercial
settlements under this Agreement shall be in accordance with the Net Metering
Regulations.
8.2. The Licensee shall
not be liable to compensate the Eligible Consumer if his Solar Project is
unable to inject surplus power generated into the Licensee's Network on account
of failure of power supply in the grid/Network.
8.3. The existing metering
System, if not in accordance with the Net Metering Regulations, shall be
replaced by a bidirectional meter (whole current/CT operated), and a separate
generation meter may be provided to measure Solar power generation. The
bi-directional meter (whole current/CT operated) shall be installed at the
inter-connection point to the Licensee's Network for recording export and
import of energy.
8.4. The uni-directional
and bi-directional meters shall be fixed in separate meter boxes in the same
proximity.
8.5. The Licensee shall
issue monthly electricity bill for the net metered energy on the scheduled date
of meter reading. If the exported energy exceeds the imported energy, the
Licensee shall show the net energy exported as credited Units of electricity as
specified in the Net Metering Regulations, 2019. If the exported energy is less
than the imported energy, the Eligible Consumer shall pay the Distribution
Licensee for the net energy imported at the prevailing tariff approved by the
Commission for the Consumer category to which he belongs.
(9) Connection Costs
The Eligible Consumer shall
bear all costs related to the setting up of the Solar Project, excluding the
Net Metering Arrangement cost beyond the Net Meter.
(10) Dispute Resolution
10.1. Any dispute arising
under this Agreement shall be resolved promptly, in good faith and in an
equitable manner by both the Parties.
10.2. Disputes pertaining
to billing/payments and metering shall be referred to the Consumer Grievances
Redressal Forum (CGRF) and then to the Ombudsman appointed under sub-section 6
of Section 42 of the Act for settlement in case the same is not resolved at
CGRF.
In the witness, where of
(Name) _______________________________ for and on behalf of
Eligible Consumer and
(Name) ________________________________ for and on behalf of
(Licensee) agree to this
agreement.
[1] Vide Noti. No.
JERC-24/2019, Extra., Part III, S. 4, dated 24-7-2019, published in the Gazette
of India, No. 263, dated 25-7-2019.