GOA
WATER (PREVENTION AND CONTROL OF POLLUTION) RULES, 2021
PREAMBLE
In
exercise of the powers conferred by subsections (1) and (2) of section 54 of
the Water (Prevention and Control of Pollution) Act, 1974 (Central Act 6 of
1974), and in consultation with the Goa State Pollution Control Board, conveyed
vide No. 8/25/13-PCB/Vol X/Adm./19634/Tech/7864 dated 29-07-2021, the
Government of Goa hereby makes the following rules, namely:
Rule - 1. Short title and commencement.
(1) These rules may be
called the Goa Water (Prevention and Control of Pollution) Rules, 2021.
(2) They shall come into
force on the date of their publication in the Official Gazette.
Rule - 2. Definitions.
(1) In these rules,
unless the context otherwise requires
(a) "Act" means
the Water (Prevention and Control of Pollution) Act, 1974 (Central Act 6 of
1974);
(b) "Water
pollutant" means any solid, liquid or gaseous substance [(including
noise)] present in the atmosphere in such concentration as may be or tend to be
injurious to human beings or other living creatures or plants or property or
environment;
(c) "Board"
means the Goa State Pollution Control Board constituted under section 4 of the
Water (Prevention and Control of Pollution) Act, 1974 (Central Act 6 of 1974);
(d) "Chairman"
means the Chairman of the Board;
(e) "Chimney"
includes any structure with an opening or outlet from or through which any
water pollutant may be emitted.
(f) "Conformity"
means fulfillment of a requirement to the Consent conditions or directions
issued by the Board from time to time;
(g) "Consequence"
means an outcome of an event affecting objectives;
(h) "Control
Equipments" means any apparatus, device, equipment or system to control
the quality and manner of emission of any water pollutant, an includes any
device used for securing the efficient operation of any industrial plant;
(i) "Correction"
means action to eliminate a detected nonconformity;
(j) "CPCB"
means Central Pollution Control Board constituted under section 3 of the Water
(Prevention and Control of Pollution) Act, 1974 (Central Act 6 of 1974);
(k) "CTE" means
Consent to Establish;
(l) "CTO" means
Consent to Operate;
(m) "Effluent" includes
any liquid, gaseous or solid substance which is discharged from any
organization/premises used for carrying on any activity, Industry, operation or
process, or treatment and disposal system including domestic sewage;
(n) "Emission"
means any solid or liquid or gaseous substance coming out of any chimney, duct
or flue or any other outlet;
(o) "Environment"
means the surroundings in which an organization operates, including water,
water, land, natural resources, flora, fauna, humans and their interrelationships.
(p) "Environmental
Audit" mean an audit conducted by an Empanelled Environmental Auditor of
the State Board or officials of the State Board;
(q) "Environmental
Audit Committee" (EAC) means an Expert Committee constituted by State
Board to assess the Environmental Audit reports submitted by the Environmental
Auditors and recommend action;
(r) "Environmental
Audit Conclusion" means outcome of an audit, after consideration of the
objectives and all audit findings;
(s) "Environmental
Audit Criteria" means the set of policies, procedures, supporting records
or requirements which are used as a reference against which audit evidence is
compared;
(t) "Environmental
Audit Evidence" means consists records, statements of fact, reports or
other information which are relevant to the audit criteria and are verifiable;
(u) "Environmental
Audit Findings" means results of the evaluation of the collected audit
evidence against audit criteria, indicating conformity or nonconformity and
additionally observations and scope for improvement;
(v) "Environmental
Audit Plan" means description of the activities and arrangements for an
audit;
(w) "Environmental
Audit protocol" means the checklist used by Empanelled Auditors of the
Board as the guide for conducting the Environmental audit;
(x) "Environmental
Audit Scope" means extent and boundaries of an audit;
(y) "Environmental
Audit Team" means an Audit team which shall consist of minimum 3 members
with an independent Technical/Scientific Expert, if felt required. The
qualifications of the team members should be varied to ensure a wider cover
having requisite technical and scientific expertise relevant to the
Organizations processes and related activities. The composition of the Audit
Team shall be as specified in Schedule II;
(z) "Environmental
Auditee" means the Organization/Industry and its work force (consisting of
employees and contractual or related workers), represented by an authorized
full time employee of the organization being audited, no lesser than a
representative of senior management;
(aa) "Environmental
Auditor" shall mean Goa State Pollution Control Board (GSPCB) empanelled
Environmental Auditor from Engineering colleges/Scientific
Institutions/Colleges, Universities, ISO Certified Agencies, Officials of the
State Board or any other expert the Board deems fit for conducting an
Environmental Audit;
(ab) "Environmental
Audit Report" shall mean the Environmental Audit report prepared by the
Empanelled Environmental Auditor of the State Board or the Officials of the
State Board;
(ac) "Event"
means an occurrence or change of a particular set of circumstances with or
without consequences and can sometimes be referred to as an
"incident" or "accident". An event without consequences can
also be referred to as a "near miss", "incident",
"near hit" or "close call";
(ad) "Form"
means form appended to these Rules;
(ae) "Government"
means the Government of Goa;
(af) "Likelihood"
means chance of something happening;
(ag) "Member
Secretary" means the Member- Secretary of the Board;
(ah) "Major
Non conformity" means Non operation/inefficient operation of the water
Pollution Control Equipments/Measures and/or non-fulfillment/violation of the
standard of emission prescribed in the consent or direct violation of specific
statutory environmental obligation by the Occupier or act of omission of the
occupier or negligence on his part whether by any accident or otherwise;
(ai) Minor
Non conformity means non-fulfilment of a requirement of the Consent condition
which includes non submission of reports or maintenance of records as specified
in the Consent Conditions and which is not defined as major Non conformity;
(aj) "Occupier",
in relation to any organization, operation or process, premises, means the
authorised person who has documented control over the affwaters of the factory
or the premises, and includes, in relation to any substance, the persons in
possession of the substance;
(ak) "Schedule"
means a Schedule appended to these rules;
(al) "section"
means a section of the Act;
(am) "Sewage" means effluent from
any sewerage system or sewage disposal works and includes sullage from open
drains;
(an) "State
water Laboratory" means a laboratory as referred in sub-section (a) of
section 52 of the Act;
(ao) "State
Board Laboratory" means a laboratory as referred to in sub-section (2) of
section 17 of the Act;
(ap) "Total
estimated investment" means the total estimated value of the proposed
industry, operation, process, treatment/disposal system or an
extension/addition thereto, and includes the value of land, building, plant and
machinery including the value of leasehold land, building and premises and
value of hired plant, machinery and equipment;
(aq) "Total
Investment" means the total value of the completed industry, operation,
process, treatment/disposal system or an extension/addition thereto, and
includes the value of land, building, plant and machinery including the value
of leasehold land, building, and premises and value of hired plant, machinery
and equipment;
(ar) "Year"
means the financial year commencing on the first day of April.
(2) Words and expressions
used and not defined in these rules but defined in the Act shall have the
meanings respectively assigned to them in the Act.
Rule - 3. Travelling allowance, daily allowance and other allowances for members.
(1) The member of the
Board shall be entitled to payment of travelling allowance as admissible to the
Grade I Officer of the Government from the Board's fund for the journey
performed by him for the purposes of the Board.
(2) Every member of the
Board shall be entitled to payment of sitting fee at such rate as may be
decided by the Board from time to time for each day of such sitting, in
addition to travelling allowance.
(3) A member of the Board
shall not be entitled to any travelling allowance for journey performed by him
on first occasion to take charge of post and also after relinquishment of post.
(4) The Member-Secretary
of the Board or any other Officer authorized by the Board shall decide about
the sitting fees and travelling allowances of the members.
(5) A non-official member
of the Board if he happens to be a member of the Legislative Assembly of Goa,
he shall not be eligible for payment of travelling allowance if he has claimed
travelling allowance, for the same journey and period for which such allowance
has been claimed in his bills for attending the meetings of the Legislative
Assembly or any Committee thereof.
Rule - 4. Time and place of meetings of the Board and procedure to be followed at such meetings.
(1) The meetings of the
Board shall ordinarily be held at the head-quarter of the Board on such dates
as may be fixed by the Chairman
(2) The Chairman shall at
his discretion or, upon written request of not less than five members of the
Board or upon a direction of the Government, call a special meeting of the
Board.
(3) Five clear days'
notice for an ordinary meeting and two clear days' notice for a special meeting
specifying the time and the place at which such meeting is to be held and the
business to be transacted there at, shall be given by the Member-Secretary to
the members of the Board.
(4) Notice of a meeting
of the Board may be given to the members of the Board by delivering the same by
messenger or sending it by registered post to their last known place of
residence or business or by email or in such other manner as the Chairman may,
in the circumstances of the case, deem fit.
(5) No member of the
Board shall be entitled to bring forward for the consideration of the meeting
any matter of which he has not given ten clear days' notice to the Member-Secretary,
unless the Chairman, in his discretion, permits him to do so.
(6) The Board may adjourn
the meeting from day-to-day or to any particular day, and no fresh notice shall
be required for such adjourned meeting.
(7) No proceeding shall
be invalidated merely on the ground that the provision in this rule relating to
the notice is not strictly complied with.
Rule - 5. Presiding Officer.
Every
meeting of the Board shall be presided over by the Chairman and, in his
absence, by an authority/officer as approved and notified by the Government.
Rule - 6. All questions to be decided by majority.
(1) All questions at a
meeting shall be decided by a majority of votes of the members present, and
voting shall be by raising of hands in favour of the proposal.
(2) In case of equality
of votes, the presiding officer shall have a second or casting vote.
Rule - 7. Quorum.
(1) Five members shall
form the quorum for any meeting.
(2) If at a time fixed
for any meeting or during the course of any meeting a quorum is not present,
the presiding officer shall adjourn the meeting and if a quorum is not present
on the expiration of fifteen minutes from such adjournment, the presiding
officer shall adjourn the meeting to such hours on the following or on some
other future date as he may fix.
(3) No quorum shall be
necessary for the adjourned meeting.
(4) No matter which had
not been on the agenda of the original meeting shall be discussed at such
adjourned meeting.
Rule - 8. Minutes.
(1) Record shall be kept
of the names of members who attended the meeting and of the proceedings at the
meeting to be maintained by the Member Secretary and uploaded on the official
website of the Board.
(2) The minutes of the
previous meeting shall be read at the beginning of the every succeeding
meeting, and shall be confirmed and signed by the Presiding Officer at such
meeting.
(3) The proceedings shall
be open for inspection to any member at the office of the Board during office
hours.
Rule - 9. Maintaining order at meeting.
The
Presiding Officer shall maintain order at meeting.
Rule - 10. Business to be transacted at meeting.
Except
with the permission of the Presiding Officer, no business which is not entered
in the agenda or of which notice has not been given by a member under sub-rule (5)
of rule 4, shall be transacted at any meeting.
Rule - 11. Order of business.
(1) At any meeting the
business to be transacted shall be in the order in which it is entered in the
agenda.
(2) Either at the
beginning of the meeting or after conclusion of the debate on a motion during
the meeting the Presiding Officer or a member may suggest a change in the order
of business as entered in the agenda and if the majority of the members present
agree, such a change shall take place.
Rule - 12. Procedure for transaction of business of committees constituted by the Board.
(1) The time and place of
the meetings of the Committees constituted by the Board under sub-section (1)
of section 9 of the Act shall be as specified by the Chairman and the Member
Secretary.
(2) The quorum for a
meeting of such committees shall be half of the total number of members of the
committee.
(3) The committee so
appointed by the Board shall take decisions and convey the same to the Board.
(4) The committee may
device its own procedure for transaction of its business at its meeting.
Rule - 13. Fees and allowances to be paid to members of the committee.
A
member of a committee shall be entitled to such travelling allowance and
sitting fee as admissible to a member of the Board, and, if he is a Government
Servant, he shall be entitled only to travelling allowance and dearness
allowance at the rates, admissible under the relevant rules of the Government
under which he is serving.
Rule - 14. Persons to be temporarily associated with the Board.
The
person temporarily associated with the Board shall be paid travelling allowance
and sitting fee if he is a non-official, at the rates specified in rule 3 and
if he is a Government Servant as specified in rule 13.
Rule - 15. Powers and duties to be exercised by the Chairman and the Member-Secretary of the Board and appointment of Officers and employees.
(1) Subject to the policy
approved by the Board, the general management of the of waters and business of
the Board shall be with the Chairman who shall have power to do all things
necessary or desirable for the management of affairs of the Board in carrying
out its objectives.
(2) The Chairman may,
(i) with prior approval
of the Government undertake tours within India for carrying out the functions
of the Board.
(ii) With the prior approval
of the Government, visit any foreign country for carrying out the functions of
the Board.
(3) The Chairman shall
have power to accord administrative and financial sanction to all estimates
without any financial limit in the allocation made for such purposes in the
budget of the Board.
(4) In the matter of
acceptance of tenders, the Chairman shall have full powers without any monetary
limit.
Rule - 16. Powers and duties of the Member Secretary.
The
Member Secretary shall be subordinate to the Chairman and shall, subject to the
control of the Chairman, exercise the following powers, namely:
(i) the Member Secretary
may undertake tours within India for the performance of duties entrusted to him
by the Board provided that he shall keep the Chairman informed of his tours and
obtain the previous permission from the Board for his tours outside the State
of Goa.
(ii) the Member Secretary
shall be in charge of all the confidential papers of the Board and shall be
responsible for preserving them.
(iii) the Member Secretary
shall produce such papers whenever so directed by the Chairman or by the Board.
(iv) the Member Secretary
shall make available to any member of the Board, for his perusal, any record of
the Board.
(v) the Member Secretary
shall be entitled to issue any direction to any officer or employee of the
Board, and call at any time, any file, paper and document, from any
section/department of the Board, for checking of accounts, vouchers, bills and
other records and stores pertaining to the Board or regional offices there
under.
(vi) the Member Secretary
may withhold any payment, provided that as soon as may be after such
withholding of payment the matter shall be placed before the Board for its
approval.
(vii) the Member Secretary
shall make all arrangements for holding meetings of the Board and meetings of
the committees constituted by the Board.
(viii) all orders,
instructions, directions, notices, communications, consents, authorizations or
registrations to be issued by the Board shall be under the signature of the
Member Secretary or of any other Officer authorized in this behalf by the
Chairman or the Board.
(ix) the Member Secretary
shall be authorized to sanction or pass and make all payments against estimates
sanctioned, within the allocations made for such purposes in the budget
approved by the Board.
(x) the Member Secretary
shall write and maintain confidential reports of all subordinate officers of
the Board and shall get them countersigned by the Chairman.
(xi) (a) the Member
Secretary shall sanction the annual increments of the officers of the Board
subordinate to him.
(b)
the annual increments of officers which the Member Secretary is not competent
to sanction shall be sanctioned by the Chairman.
(xii) the Member Secretary
shall have full power for according technical sanction to all estimates.
(xiii) the Member Secretary
shall exercise such other powers and perform such other functions as may be
delegated to him from time to time either by the Board or by the Chairman.
(xiv) the Member Secretary
shall have power to execute contract, deed, instrument and assurance of
property and in particular (a) all service agreements (b) security bonds (c)
conveyance, lease of immovable property and, (d) assurances required by law or
otherwise.
(xv) The Member Secretary
shall have power to engage legal advisors, Advocates, Attorneys on the terms
and conditions to be approved by the Board.
(xvi) The Member Secretary
or any other Officer authorized by the Chairman or the Board shall have power
to make and give receipts in respect of the claims of and demands on the Board.
(xvii) The Member Secretary
shall have power to purchase materials and equipments for execution of
construction works up to a limit of the allotments made from time to time.
(xviii) The Member Secretary
shall have power to sanction installation of telephones/broadband/internet
connections, etc. in the office of the Board.
Rule - 17. Appointment of Consulting Engineer.
(1) For the purpose of
assisting the Board in the performance of its functions, it may appoint a
Consultant for a specified period not exceeding one year:
Provided
that the Board may, with the prior approval of the Government extend the period
of such appointment from time to time:
Provided
further that if at the time of the initial appointment, the Board had reason to
believe that the services of the Consultant would be required for a period of
more than one year, the Board shall not make the appointment without the prior
approval of the Government.
(2) The Board may pay
such emoluments or fees to the Consulting Engineer depending on the nature of
work and his qualifications and experience:
Provided
that the Board shall not appoint any person as Consulting Engineer without the
prior approval of the Government, if the emoluments or fees payable to him
exceeds Rs. 1,00,000/(Rupees One Lakh only) per month.
Rule - 18. Power to terminate appointment.
Notwithstanding
the appointment of a Consulting Engineer for a specified period, the Board
shall have the right to terminate the services of the Consulting Engineer
before the expiry of the specified period, if in the opinion of the Board, he
is not discharging his duties to the satisfaction of the Board or if such a
course of action is necessary in the public interest.
Rule - 19. Tours by Consulting Engineer.
The
Consulting Engineer may undertake tours within the State with prior approval of
the Chairman for the performance of the duties entrusted to him by the Board
and in respect of such tours, he shall be entitled for travelling and daily
allowances as admissible to Grade I Officer of the Government.
Rule - 20. Consulting Engineer not to disclose information.
The
Consulting Engineer shall not disclose any information either given by the
Board or obtained during the performance of the duties assigned to him either
from the Board or otherwise, to any other person without the written permission
of the Board.
Rule - 21. Duties and functions of the Consulting Engineer.
The
Consulting Engineer shall discharge such duties and perform such functions as
are assigned to him, by the Board and he shall be duty bound to advise the
Board on all technical matters referred to him by the Board.
Rule - 22. Form of notice.
The
notice referred in clause (a) of sub-section (3) of section 21 shall be made in
Form I hereto.
Rule - 23. Form of Report of the Board Analyst.
The
report referred in sub-section (1) of section 22 of the Act shall be in Form II
hereto and submitted in triplicate.
Rule - 24. Form for submission of sample to State water Laboratory and report of the Government Analyst.
The
submission of the sample of water or effluent shall be sent for analysis under
sub-section (1) section 21 of the Act to the State Water Laboratory by a letter
in Form III hereto. The report referred in sub-section (1) of section 22 of the
Act shall be in Form IV hereto submitted in triplicate.
Rule - 25. Application for consent of the Board.
(1) The application
referred in sub-section (2) of section 25 shall be made online on the website
of the Board at www.goapcb.gov.in as applicable and it shall be accompanied by,
(a) a certificate from
the Chartered Accountant in Form V hereto which shall include value of
leasehold land, building and premises and value of hired plant, machinery and
equipment,
(b) land
allotment/earmarking letter or lease/sale deed;
(c) flow chart and detailed
production process;
(d) copy of Project
Report for projects costing 5 crores and above;
(e) site Plan (not
required for units to be set up in Industrial Estates);
(f) layout plan showing
the locations of Manufacturing equipment, water supply/drainage lines, position
of Chimneys, effluent/sewage treatment plant and final discharge point, sludge
solid waste disposal points and septic tank/soak pits;
(g) Detailed material
balance, water balance for Industries categorised under Red and Orange and
large scale Industries under green category;
(h) for large enterprises
covered under the Schedule of Environment Impact Assessment Notification, 2006
as amended from time to time, copy of the Environment Impact Assessment Study
Report;
(i) copy of the prior
Environment Clearance issued by the competent Authority as applicable for
projects listed in the Environment Impact Assessment Notification, 2006 as
amended from time to time.
(j) site plan showing
surrounding residential area, public places, water streams, etc, of the
proposed factory/operation/process/mine/quarry site within a radius of five
kilometers with Waste water treatment and disposal systems clearly indicating
where waste water is proposed to be disposed off after treatment (for medium
and large scale enterprises).
(k) schematic sketch of
the proposed Effluent/sewage treatment system/plant (ETP/STP) and or septic
tank or soakpits duly signed by Authorised person along with detailed design
calculation as applicable.
(l) original
Authorisation letter of the person to whom authorisation is made to sign this
application form except individual proprietary concern.
(m) any other
document/clarification as requisitioned by the Board.
(n) fees as specified in
the Table 1(A), 1(B) and 1(C) of Schedule I appended hereto as applicable, to
the respective category of industry.
(2) An application
without requisite fee shall not be entertained by the Board.
(3) The fees shall be
paid by a bank draft or NEFT/RTGS or NET Banking in favour of the Board.
(4) The Consent to
Establish issued by the Board shall be valid for a period of five years from
the date of issue.
(5) The Categorization of
Industries/establishments as Red, Orange, Green category shall be as specified
in Table 3 annexed herewith.
(6) When any industry,
operation, process, treatment/disposal system or/and extension/addition thereto
is established, an application for consent to operate/renewal of Consent to
Operate under sub-section (2) of section 25 of the Act shall be made online on
the website of the Board www.goapcb.gov.in as applicable to the respective
category of industry, operation or process at least two months prior to the
scheduled date of commencing operation, and shall be accompanied by,
(a) a certificate from
the Chartered Accountant as specified in Form V which shall also include value
of leasehold land, building and premises and value of hired plant, machinery
and equipment;
(b) copy of the previous
Consent issued by the Board.
(c) stack analysis
report/analysis report of treated effluent/sewage wherever applicable.
(d) any
changes/modifications carried out in the Industry/operation or process after
obtaining previous Consent;
(e) in case of Renewal of
Orange and Green Category Industry, application for Auto Renewal to be
accompanied by an Affidavit as specified at Annexure 'B' in SCHEDULE I hereto;
(f) Fees as specified in
the Table 2(A), 2(B) or 2(C) of Schedule I as applicable to the respective
category of industry;
(g) an application
without requisite fees shall not be entertained by the Board;
(h) the fees referred
herein shall be paid by a bank draft or NEFT/RTGS or NET Banking in favour of
the Goa State Pollution Control Board;
(i) The validity of
consent to operate and renewal of consent to operate shall normally be five
years for Red category, ten years for orange category and fifteen years for
green category industry, operation or process;
(j) An application for
renewal of consent to operate submitted upon expiry of the validity period
shall also be accompanied by late fees equivalent to 50% of the fees payable
for renewal.
Rule - 26. Manner of enquiry in respect of application for consent.
(1) On receipt of an
application for consent under section 21 of the Act, the Board may depute any
of its officers, accompanied by as many assistants as may be necessary, to
visit the premises of the applicant, to which such application relates for the
purpose of verifying the correctness or otherwise of the particulars furnished
in the application or for obtaining such further particulars or information as
the Board may consider necessary as specified under sections 23, 24 and 25 of
the Act. Such officer may, for that purpose, inspect any place where water
emissions or water pollutant are discharged by the applicant or water pollution
control equipments and measures and may require the applicant to furnish to him
any plan, specification and other data relating to such water pollution control
equipments and measures, systems or any part thereof, he considers necessary.
(2) Such officer shall
before visiting any premises of the applicant for the purpose of inspection
under sub-rule (1), give notice to the applicant of his intention to do so in
Form VI hereto. The applicant shall furnish to such officer all facilities that
such officer may legitimately require for the purpose.
(3) An officer of the
Board may, before or after carrying out an inspection under sub-rule (1), require
the applicant to furnish to him, orally or in writing such additional
information or clarification, or to produce before him such documents, as he
may consider necessary and may, for that purpose, summon the applicant or his
authorized agent to the office of the Board.
(4) The Board shall
conduct water quality monitoring of such units under sub-section (1) of section
21 of the Act and shall levy such fees as specified by the Board from time to
time.
(5) The Board shall
conduct environmental audit under sub-section (3) of section 21 of the Act
through an Environmental Auditor or Engineering/Scientific Institutions or
Officials of the Board upon submission of Environmental Statement by the
industry/Organization and shall follow such procedure as specified in SCHEDULE
II hereto.
(6) The Board shall
constitute an Environmental Audit Committee comprising of such members as
specified in SCHEDULE II hereto.
(7) The tenure of the
Environmental Audit committee shall be for a period of 5 year;
(8) For the purpose of
carrying out Environmental Audit the Board shall levy fees as per actual
expenses incurred by the Board for conducting the Environmental Audit plus 25
percent administrative charges.
(9) The Board shall
Empanel Environment Auditors by following such procedures as specified in
SCHEDULE II hereto;
(10) The
Institutions/Agencies/Professionals/Individuals eligible for Empanel-ment as
Environment Auditor with the Board shall be as specified in SCHEDULE II hereto;
(11) The Environment Audit
Committee shall review the Environment Audit Report submitted by the
Environment Auditors and recommend such actions as specified in SCHEDULE II
hereto;
(12) The Environment Audit
Committee shall meet at least once in 3 months;
(13) The Empanelled
Auditor shall conduct an Environment Audit as per the procedure and submit a
Report as specified in SCHEDULE II hereto;
(14) The fee to be paid to
Empanelled Environment Auditor shall be as specified in SCHEDULE II hereto.
Rule - 27. Form of budget.
(1) Before the last day
of the preceding financial year, the budget in respect of the ensuing year
showing the estimated receipts and expenditure of the Board shall be prepared
under section 38 of the Act in Forms VII hereto;
(2) The estimated
receipts and expenditure shall be accompanied by the revised budget estimates
for the current year;
(3) The budget shall, as
far as may be, based on the account heads specified in SCHEDULE III hereto.
Rule - 28. Submission of budget estimates to the Board.
(1) The budget estimates
shall be placed by the Member Secretary before the Board by the 5th October
each year for approval.
(2) After approval of the
budget estimates by the Board, four copies of the final budget proposals
incorporating therein such modifications as have been decided upon by the Board
shall be submitted to the Government by the 15th October each year.
Rule - 29. Estimates of establishment expenditure and fixed recurring charges.
The
estimates of expenditure on fixed establishment as well as fixed monthly
recurring charges on account of rent, allowances, etc. shall provide for the
gross amount without deductions of any kind.
Rule - 30. Re-appropriations and emergent expenditure.
No
expenditure which is not covered by a provision in the sanctioned budget
estimates or which is likely to be in excess over the amount provided under any
head, shall be incurred without the approval of the Board and by the Board
without provision being made for re-appropriation from some other head, under
which savings are firmly established and available.
Rule - 31. Power to incur expenditure.
The
Member Secretary shall have power to incur expenditure against allotments made
in the budget estimates sanctioned by the Board and against sanctioned
estimates out of the funds of the Board subject to observance of the general
financial rules for the purposes of procedure.
Rule - 32. Operation of fund of the Board.
The
fund of the Board shall be operated by the Member Secretary of the Board and in
his absence by any officer of the Board duly authorized by the Board in that
behalf. The Board shall create and maintain a Corpus Fund.
Rule - 33. Form of annual report.
The
annual report referred in sub-section (2) of section 39 of the Act shall be in
Form VIII hereto.
Rule - 34. Form of annual statement of accounts of the Board.
The
annual statement of accounts of the Board referred in sub-section (1) of
section 40 shall be in Forms IX, X XI, XII and XIII hereto.
Rule - 35. Audit of the annual statement of Account.
The
annual statement of account of the Board shall be audited by an Auditor
appointed by the Government for the purpose in consultation with the Office of
the Comptroller and Auditor General in Goa.
Rule - 36. Directions of the Government.
The
Board shall comply with the directions issued by Government from time to time.
Rule - 37. Repeal and savings.
(1) The Goa Water
(Prevention and Control of Pollution) Rules, 1989 are hereby repealed.
(2) Notwithstanding such
repeal any action taken or order issued under the provisions of the said
repealed Rules prior to the commencement of these Rules shall, in so far as it
is not inconsistent with the provisions of these Rules, be deemed to have been
taken or issued under the provisions of these Rules.
FORM I
THE GOA STATE POLLUTION CONTROL BOARD
Notice of intention to have sample
analysed
(See rule 22)
To,
Take
notice that it is intended to have analyzed the sample of water emissions/flue
gas emissions/ambient monitoring/emissions which is being taken today the ...
day of ... 20... from (?) ...
Name
and designation of the person who takes the sample.
(t)
Here specify the stream, well, plant, or place from where the sample is taken.
FORM II
Report by the Board Analyst
[See rule 23]
Report
No. ...
Dated
the ... 20...
I
hereby certify that I, (*)
... Board Analyst duly appointed under sub-section (2) of section 53 of the
Water (Prevention and Control of Pollution) Act, 1974 (Act 6 of 1974), received
on the (?)
... day of ... 20... (?)
... a sample of ... for analysis. The sample was in a condition fit for
analysis reported below:-
I
further certify that I have analysed the aforementioned sample on (§) ... and declare the result of the analysis to be as
follows-($)
...
The
condition of the seals fastening and container on receipt was as
follows:-Signed this ... day of ... 20... Address ...
(Signed)
Board
Analyst
To
???.
????.
FORM III
Form of letter for submission of samples to the State Water
Laboratory
[See rule 24]
To,
The
Government Analyst,
State
Water Laboratory
Sir,
I
am submitting sample No./Nos?. of water emissions taken from M/s......................................
on......................................according to the provisions of section
54 of the Water (Prevention and Control of Pollution) Act, 1974 (Central Act 6
of 1974).
|
Sample No.
|
Point of collection
|
Parameters to be analyzed
|
|
?????
|
?????
|
?????
|
|
?????
|
?????
|
?????
|
|
?????
|
?????
|
?????
|
Yours
faithfully,
(signature
of the officer taking sample)
Designation:-
Copy
forwarded to the Member Secretary, Goa State Pollution Control Board,
............................................................................
(Name
and signature of the officer taking sample)]
FORM IV
Report by the Government Analyst
[See rule 24]
Report
No. ...
Dated
the ... 20?
I
hereby certify that I, (*)
......................................... Government Analyst duly appointed
under subsection (2) of section 53 of the Water (Prevention and Control of
Pollution) Act, 1974 (Act 6 of 1974) received on the (?) ... day of ... 20... from (?) ... a sample of ... for analysis. The sample was in a
condition fit for analysis reported below:-
I
further certify that I have analysed the aforementioned sample on (§) .......................................... and declare
the result of the analysis to be as follows:
($) ....
....
....
Signed
this ... day of ... 20...
Address
....
(Signature)
Government
Analyst
To
???.
????
FORM V
(Form of the certificate of the
Chartered Accountant without appreciation and depreciation)
[See rule 25(1)(a)]
I,
Shri. _________________________________ Son/daughter of ______________________,
aged _____________________ years, Indian National, resident of
_____________________________, hereby solemnly declare an oath as follows.
(1) I say that I am the
Proprietor/Director Authorized Signatory of M/s. _________________ located at
______________________, Goa.
(2) I say that the Gross
Fixed Asset Value/Gross Estimated Value (in case of NOC) of our unit is as
follows (including the value of lease/hold land, building and premises and value
of hired plant, machinery and equipment)
(a) Land
_______________________
(b) Building
_______________________
(c) Plant & Machinery
______________
(d) Other fixed assets
_______________
Total
_______________________
(Rupees
_____________________________)
(3) I say that I am
filing this Certificate for the limited purpose of producing it before the
Board for obtaining Consent.
Solemnly
affirmed at _______________
Dated
___________________
Deponent
Name
& Signature
Note:
Kindly note that application form should be invariably submitted by only
authorized person on behalf of the unit"
FORM VI
THE GOA STATE POLLUTION CONTROL BOARD
NOTICE OF INSPECTION
[See rule 26(2)]
Chairman
Member
Secretary..................................................
Shri.............................................................................
No.....................................................
Dated..................................................
..........................................................................................
......................................................................................
To,
Take
Notice that for the purpose of enquiry under section 21 the following officers
of the State Board namely:
(i) Shri ??????????????
(ii) Shri ??????????????
(iii) Shri ??????????????
and
the persons authorized by the Board to assist them shall inspect-Any systems of
your Industrial Plant.
Any
other parts thereof or pertaining thereto under management/control of date (a) ????????????????between
??????????.hours when all facilities requested by them
for such inspection should be made available to them on the site. Take Notice
that refusal or denial to above stated demand made under the functions of the
State Board shall amount to obstruction punishable under section 37(1) of the
Act.
By
order of the Board
Member
Secretary
Copy
to:
(1) ?????????..
(2) ?????????..
(3) ?????????..
FORM VII
THE GOA STATE POLLUTION CONTROL BOARD
Detailed Budget Estimates for the year 20......
[See rule 27(1)]
ADMINISTRATION
(Expenditure)
|
Head of Account
|
Actuals for the past three years
|
Sanctioned Estimate for the current year
|
Actuals for last six months i.e. year
|
Actuals for last six months of the current year
|
Revised Estimate for the current year
|
Budget Estimate for the next year
|
Variations between column 5 and 8
|
Variations between column 8 and 9
|
Explanation for olumn 10-11
|
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
11
|
12
|
|
|
|
|
|
|
|
|
|
|
|
|
Accounts
Officer/Accountant
FORM VIII
THE GOA STATE POLLUTION CONTROL BOARD
Annual Report for the Financial year
April 20.... To March 20......
(See rule 33)
(1) Introductory.
(2) Constitution of the
Board including changes therein.
(3) Constitution of
Committees by Board and Meetings of the Committees constituted by it.
(4) Meetings of the
Board.
(5) Activities of the
Board including the various functions performed under Section 1 of the Act.
(6) Prosecutions launched
and convictions secured.
(7) Finance and Accounts
of the Board.
(8) Visits to the Board
by Experts, important persons etc.
(9) Any other important
matter dealt with by the Board.
FORM IX
THE GOA STATE POLLUTION CONTROL BOARD
Receipts and payments for the year ended...............
(See rule 34)
|
Previous year (1)
|
Receipts (2)
|
Previous year (3)
|
Payments (4)
|
|
Opening Balance
|
|
1. Capital expenditure
|
|
|
Grants received:
|
|
(i) Works
|
…...
|
|
(a) From Government
|
…....
|
(ii) Fixed Assets
|
…....
|
|
(b) From other agencies
|
…...
|
(iii) Other Assets:
|
…....
|
|
ii. Fees
|
…....
|
(a) Laboratory equipments
|
…....
|
|
iii. Fines and Forfeitures
|
…....
|
(b) Vehicles
|
…....
|
|
iv. Interest on Investment
|
…....
|
(c) Furniture & Fixtures
|
…....
|
|
v. Miscellaneous receipts
|
…....
|
(d) Scientific Instruments and Office appliances
|
…....
|
|
vi. Miscellaneous Advances
|
…....
|
(e) Tools and Plant
|
…....
|
|
vii. Deposits
|
…....
|
(2) Revenue Expenditure
|
|
|
|
|
A. Administrative:
|
|
|
|
|
(i) Salaries
|
…....
|
|
|
|
(ii) Travelling Allowance :
|
|
|
|
|
a) Chairman
|
…....
|
|
|
|
b) Members
|
…....
|
|
|
|
c) Others
|
…....
|
|
|
|
(iii) Leave salary and pension contributions
|
…....
|
|
|
|
(iv) Office expenditure
|
…....
|
|
|
|
B. (i) Board Laboratory
|
…....
|
|
|
|
(i) Charges to be paid to State Government Analyst Laboratory
|
…....
|
|
|
|
C. Running and Maintenance of Vehicles
|
…....
|
|
|
|
D. Maintenance and Repwaters:
|
|
|
|
|
(i) Buildings
|
…....
|
|
|
|
(ii) Works
|
…....
|
|
|
|
(iii) Furniture and Fixture
|
…....
|
|
|
|
(iv) Scientific Instruments and office appliances
|
…....
|
|
|
|
(v) Tools and plants
|
|
|
|
|
E. Fees to consultants and Specialist
|
…....
|
|
|
|
F. Law Charges
|
…....
|
|
|
|
G. Miscellaneous
|
…....
|
|
|
|
H. Fees for Audit
|
…....
|
|
|
|
3. Purchases
|
…....
|
|
|
|
4. Miscellaneous
|
…....
|
|
|
|
5. Advances
|
…....
|
|
|
|
6. Deposits
|
…....
|
|
|
|
Closing Balance
|
…....
|
|
Total
|
|
Total
|
…....
|
|
|
|
Accounts Officer/Accountant
|
Member Secretary
|
Chairman
|
|
|
|
|
|
FORM X
THE GOA STATE POLLUTION CONTROL BOARD
Expenditure on works as on 31st March 20.......
(Item I - Assets of the Balance Sheet)
(See rule 34)
|
Upto 31st March 20…..
|
During the year 20…...
|
Upto 31st March 2…...
|
|
Sr. No.
|
Name of the work
|
Direct expenditure
|
Overhead Charges
|
Total expenditure
|
Direct expenditure
|
Overhead Charges
|
Total expenditure
|
Direct expenditure
|
Overhead Charges
|
Total expenditure
|
|
Total -
|
|
Accounts Officer/Accountant
|
Member Secretary
|
Chairman
|
|
|
|
|
|
|
|
|
|
|
|
|
|
FORM XI
THE GOA STATE POLLUTION CONTROL BOARD
ANNUAL STATEMENT OF ACCOUNTS
Fixed Assets as on works as on 31st March 20.......
(Item 2 - Assets of the Balance Sheet)
Other Assets as on 31st March 20......
(Item 3 - Assets of the Balance Sheet)
(See rule 34)
|
Sr. No.
|
Particulars of Assets
|
Balance as on 31st March 20….
|
Additions during the year
|
Total
|
Depreciation during the year
|
Sales or write off during the year
|
Balance as on 31st March 20….
|
Cumulative depreciation as on 31st March 20…..
|
|
|
|
Accounts Officer/Accountant
|
Member Secretary
|
Chairman
|
|
|
|
|
|
|
|
|
|
|
|
FORM XII
THE GOA STATE POLLUTION CONTROL BOARD
ANNUAL STATEMENT OF ACCOUNT
Income and expenditure accounts for year ended 31st March
20..........
(See rule 34)
|
Expenditure
|
Income
|
|
Previous year
|
Details
|
Total of sub-head
|
Total of Major head
|
Previous year
|
Details
|
Total of sub-head
|
Total of Major head
|
|
(1)
|
(2)
|
(3)
|
|
(5)
|
(6)
|
(7)
|
(8)
|
|
|
Rs.
|
|
|
|
|
|
|
|
To
|
|
|
|
By
|
|
|
|
|
Revenue expenditure
|
|
|
|
I. Grants received
|
|
|
|
|
(A) Administrative
|
|
|
|
(a) From Government
|
|
|
|
|
(i) Salaries
|
|
|
|
(b) From other agencies
|
|
|
|
|
(ii) Travelling allowances
|
|
|
|
Total
|
|
|
|
|
(iii) Leave salary and pension contributions
|
|
|
|
Less:
|
|
|
|
|
(iv) Board's contribution to the staff provident fund.
|
|
|
|
Amount utilized for Capital expenditure. Net grant available for Revenue
expenditure.
|
|
|
|
|
(v) Contingent expenditure
|
|
|
|
|
|
|
|
|
(B) Running expenses of laboratories:
(i) Main laboratory
(ii) Payments to be made to the State Government Analyst laboratory
|
|
|
|
II Fees
III Service rental charges
IV Fines and forfeitures
V Interest on investments
|
|
|
|
|
(C) Running and maintenance of vehicles
|
|
|
|
VI Miscellaneous receipts
|
|
|
|
|
(D) maintenance and Repairs
(i) Building and Land
(ii) Drainage Works
(iii) Furniture and Fixtures
(iv) Scientific Instruments and office appliances
(v) Tools and Plant
|
|
|
|
VII Excess of expenditure over income
|
|
|
|
|
(E) Fees to consultants and specialists
|
|
|
|
|
|
|
|
|
(F) Law Charges
|
|
|
|
|
|
|
|
|
(G) Depreciation :
(i) Buildings
(ii) Laboratory equipment
(iii) Vehicles
(iv) Furniture and Fixtures
(v) Scientific instruments and office appliances
(vi) Tools and Plants
|
|
|
|
|
|
|
|
|
(H) Miscellaneous
(i) Write off losses (as per details in the statement attached).
(ii) Other Miscellaneous expenditure.
|
|
|
|
|
|
|
|
|
(I) Fees for Audit
|
|
|
|
|
|
|
|
|
(J) Excess of Income over expenditure
|
|
|
|
|
|
|
|
|
TOTAL
|
|
|
|
|
|
|
|
Accounts
Officer/Accountant
Member
Secretary
FORM XIII
THE GOA STATE POLLUTION CONTROL BOARD
ANNUAL STATEMENT OF ACCOUNTS
Balance sheet as at 31st March 20.....
(See rule 34)
|
Capital and Liabilities
|
Property and Assets
|
|
Previous year
|
Details
|
Total of sub-head
|
Total of Major head
|
Previous year
|
Details
|
Total of sub-head
|
Total of Major head
|
|
(1)
|
(2)
|
(3)
|
(4)
|
(5)
|
(6)
|
(7)
|
(8)
|
|
(A) Capital Fund
(i) Grants received from Government for Capital Expenditure
(a) Amount utilized upto 31st March 20....
(ii) Grant from other agencies for Capital expenditure
(a) Amount utilized upto 31st March 20...
(b) Unutilized balance to 31st March 20...
(iii) Value of land provided by Govt. (Per contra)
|
|
|
|
1. Works
(as per Form XI)
2. Fixed Assets (As per Form XII)
(a) Value of land provided by Govt. (at cost)
(b) Buildings-Balance as per last Balance Sheets Additions during the
year
|
|
|
|
|
(B) Capital Receipts
|
|
|
|
Total
|
|
|
|
|
(c) (i) Deposits received for works from outside bodies
Deposits
Less Expenditure
(ii) Other deposit
|
|
|
|
3. Other Assets
(As per Form XII)
(a) Laboratory Equipment as per last balance sheet additions during the
year
Total
Less depreciation during the year
Total
|
|
|
|
|
(D) Amounts due -
(i) Purchases
(ii) Others
|
|
|
|
(b) Vehicles as per last balance sheet Addition during the year
|
|
|
|
|
|
|
|
|
Total
|
|
|
|
|
|
|
|
|
Less Depreciation during the year
|
|
|
|
|
|
|
|
|
Total
|
|
|
|
|
(E) Excess of income over expenditure :
(i) Up to 31st March 20.....
(ii) Add for the year
(iii) Deduct Excess of
expenditure over income
|
|
|
|
(c) Furniture and fixtures as per last Balance Sheet Additions during
the year
|
|
|
|
|
|
|
|
|
Total
|
|
|
|
|
|
|
|
|
Less Depreciation during the year
|
|
|
|
|
|
|
|
|
Total
|
|
|
|
|
|
|
|
|
(d) Scientific
Instruments and Office Appliances -
As per last Balance Sheet
Additions during the year
Total
|
|
|
|
|
|
|
|
|
(e) Tools and Plants
As per last Balance Sheet Additions during the year
Total
Less Depreciation during the year
Total
|
|
|
|
|
|
|
|
|
4. Sundry Debtors
(i) Amounts due from out site bodies for expenditure incurred -
Expenditure
Less Amount received
(ii) Other sundry Debtors
|
|
|
|
|
|
|
|
|
5. Advances -
(a) Miscellaneous Advances
(b) Other amount recoverable Cash -
(c) Notice/Short Term Deposits
(d) Cash at Bank
(e) Cash at Hand
(f) Cash in transit
|
|
|
|
|
Total
|
|
|
|
Total
|
-
|
|
|
|
Accounts Officer/Accountant
|
Member Secretary
|
Chairman
|
|
|
|
|
|
|
|
|
|
|
|
SCHEDULE I
[See Rule 25]
(I)
An Application for CONSENT TO
ESTABLISH.-
(i)
A Green Category Industry shall be
accompanied by Fee as specified in Table 1(A) below;
(ii)
An Orange Category Industry shall be
accompanied by Fee as specified in Table 1 (B) below;
(iii)
A Red Category Industry shall be
accompanied by Fee as specified in Table 1(C) below.
(II)
An application for CONSENT TO
OPERATE.-
(i)
RED Category Industry (Large, Medium
and Small scale) shall be accompanied by Fees as specified in Table 2 (A)
below.
(ii)
ORANGE Category Industry (Large,
Medium and Small scale) shall be accompanied by Fees as specified in Table 2(B)
below.
(iii)
GREEN Category Industry (Large, Medium
and Small scale) shall be accompanied by Fee as specified in Table 2(C) below
Table 1
|
TOTAL ESTIMATED INVESTMENT (TEI) (Rs. In Lakhs)
|
FEE FOR CONSENT TO ESTABLISH (In Rupees)
|
|
Fee (5 years)
|
Fee (per year)
|
|
|
1
|
350
|
70
|
|
1-up to 2
|
700
|
140
|
|
2- up to 3
|
1000
|
200
|
|
3 - up to 4
|
1350
|
270
|
|
4 - up to 5
|
1700
|
340
|
|
5 - up to 6
|
2000
|
400
|
|
6 - up to 7
|
2350
|
470
|
|
7 - up to 8
|
2700
|
540
|
|
8 - up to 9
|
3000
|
600
|
|
9 - up to 10
|
3350
|
670
|
|
10 - up to 15
|
4000
|
800
|
|
15 - up to 20
|
4700
|
940
|
|
20 - up to 25
|
5350
|
1070
|
|
25 - up to 35
|
6700
|
1340
|
|
35 - up to 45
|
8000
|
1600
|
|
45 - up to 55
|
9350
|
1870
|
|
55 - up to 65
|
10700
|
2140
|
|
65 - up to 75
|
12000
|
2400
|
|
75 - up to 100
|
13350
|
2670
|
|
100 - up to 500
|
17350
|
3470
|
|
500 - up to 1000
|
21350
|
4270
|
|
1000 - up to 2000
|
25350
|
5070
|
|
2000 - up to 3000
|
33700
|
6740
|
|
3000 - up to 4000
|
42000
|
8400
|
|
4000 - up to 5000
|
50350
|
10070
|
|
5000-up to 10000
|
75350
|
15070
|
|
10000 - up to 20000
|
100350
|
20070
|
Note:
Also 2% increase in the above fees for every subsequent financial year.
Table 2 (A)
|
Renewal/Consent to operate
|
Red category (L)
|
Red Category (M)
|
Red Category (S)
|
|
|
Per year
|
|
|
|
1
|
500
|
500
|
200
|
|
1-up to 2
|
1000
|
1000
|
400
|
|
2- up to 3
|
1500
|
1500
|
600
|
|
3 - up to 4
|
2000
|
2000
|
800
|
|
4 - up to 5
|
2500
|
2500
|
1000
|
|
5 - up to 6
|
3000
|
3000
|
1200
|
|
6 - up to 7
|
3500
|
3500
|
1400
|
|
7 - up to 8
|
4000
|
4000
|
1600
|
|
8 - up to 9
|
4500
|
4500
|
1800
|
|
9 - up to 10
|
5000
|
5000
|
2000
|
|
10 - up to 15
|
6000
|
6000
|
2400
|
|
15 - up to 20
|
7000
|
7000
|
2800
|
|
20 - up to 25
|
8000
|
8000
|
3200
|
|
25 - up to 35
|
9500
|
9500
|
3800
|
|
35 - up to 45
|
11000
|
11000
|
4400
|
|
45 - up to 55
|
12500
|
12500
|
5000
|
|
55 - up to 65
|
14000
|
14000
|
5600
|
|
65 - up to 75
|
15500
|
15500
|
6200
|
|
75 - up to 100
|
17000
|
17000
|
6800
|
|
100 - up to 500
|
22000
|
22000
|
8800
|
|
500 - up to 1000
|
27000
|
27000
|
10800
|
|
1000 - up to 2000
|
37000
|
37000
|
14800
|
|
2000 - up to 3000
|
47000
|
47000
|
18800
|
|
3000 - up to 4000
|
57000
|
57000
|
22800
|
|
4000 - up to 5000
|
67000
|
67000
|
26800
|
|
5000-up to 10000
|
97000
|
97000
|
38800
|
|
10000 - up to 20000
|
127000
|
127000
|
50800
|
*Note:
An application for renewal of Consent submitted after expiry of the validity
shall accompany with penalty of 50% of the Consent fees in addition to the
prescribed consent fees. Also 2% increase in the above fees for every
subsequent financial year.
Table 2 (B)
|
Renewal/Consent to operate
|
Orange category (L)
|
Orange category (M)
|
Orange category (S)
|
|
|
Per year
|
|
|
|
1
|
350
|
350
|
150
|
|
1-up to 2
|
700
|
700
|
300
|
|
2- up to 3
|
1000
|
1000
|
450
|
|
3 - up to 4
|
1350
|
1350
|
600
|
|
4 - up to 5
|
1700
|
1700
|
750
|
|
5 - up to 6
|
2000
|
2000
|
900
|
|
6 - up to 7
|
2350
|
2350
|
1000
|
|
7 - up to 8
|
2700
|
2700
|
1200
|
|
8 - up to 9
|
3000
|
3000
|
1300
|
|
9 - up to 10
|
3350
|
3350
|
1450
|
|
10 - up to 15
|
4000
|
4000
|
1750
|
|
15 - up to 20
|
4700
|
4700
|
2000
|
|
20 - up to 25
|
5350
|
5350
|
2300
|
|
25 - up to 35
|
6350
|
6350
|
2800
|
|
35 - up to 45
|
7350
|
7350
|
3150
|
|
45 - up to 55
|
8350
|
8350
|
3600
|
|
55 - up to 65
|
9350
|
9350
|
4000
|
|
65 - up to 75
|
10350
|
10350
|
4450
|
|
75 - up to 100
|
11350
|
11350
|
4900
|
|
100 - up to 500
|
14700
|
14700
|
14700
|
|
500 - up to 1000
|
18000
|
18000
|
7750
|
|
1000 - up to 2000
|
24700
|
24700
|
10600
|
|
2000 - up to 3000
|
31350
|
31350
|
13450
|
|
3000 - up to 4000
|
38000
|
38000
|
16300
|
|
4000 - up to 5000
|
44700
|
44700
|
19150
|
|
5000-up to 10000
|
64700
|
64700
|
27750
|
|
10000 - up to 20000
|
84700
|
84700
|
36300
|
*Note:
An application for renewal of Consent submitted after expiry of the validity shall
accompany with penalty of 50% of the Consent fees in addition to the prescribed
consent fees. Also 2% increase in the above fees for every subsequent financial
year.
Table 2 (C)
|
Renewal/Consent to operate
|
Green category (L)
|
Green category (M)
|
Green category (S)
|
|
|
Per year
|
|
|
|
1
|
200
|
200
|
100
|
|
1 - up to 2
|
400
|
400
|
200
|
|
2 - up to 3
|
600
|
600
|
300
|
|
3 - up to 4
|
800
|
800
|
400
|
|
4 - up to 5
|
1000
|
1000
|
500
|
|
5 - up to 6
|
1200
|
1200
|
600
|
|
6 - up to 7
|
1400
|
1400
|
700
|
|
7 - up to 8
|
1600
|
1600
|
800
|
|
8 - up to 9
|
1800
|
1800
|
900
|
|
9 - up to 10
|
2000
|
2000
|
1000
|
|
10 - up to 15
|
2400
|
2400
|
1200
|
|
15 - up to 20
|
2800
|
2800
|
1400
|
|
20 - up to 25
|
3200
|
3200
|
1600
|
|
25 - up to 35
|
3800
|
3800
|
1900
|
|
35 - up to 45
|
4400
|
4400
|
2200
|
|
45 - up to 55
|
5000
|
5000
|
2500
|
|
55 - up to 65
|
5600
|
5600
|
2800
|
|
65 - up to 75
|
6200
|
6200
|
3100
|
|
75 - up to 100
|
6800
|
6800
|
3400
|
|
100 - up to 500
|
8800
|
8800
|
4400
|
|
500 - up to 1000
|
10800
|
10800
|
5400
|
|
1000 - up to 2000
|
14800
|
14800
|
7400
|
|
2000 - up to 3000
|
18800
|
18800
|
9400
|
|
3000 - up to 4000
|
22800
|
22800
|
11400
|
|
4000 - up to 5000
|
26800
|
26800
|
13400
|
|
5000-up to 10000
|
38800
|
38800
|
19400
|
|
10000 - up to 20000
|
50800
|
50800
|
25400
|
Note:
Also 2% increase in the above fees for every subsequent financial year.
ANNEXURE 'A'
Table 3
(See rule 25)
Categorization of Industries
|
RED CATEGORY
|
|
Sr. No.
|
Category
|
|
1
|
2
|
|
1
|
Airports and Commercial Air Strips with overall waste water generation
> 100 KLD
|
|
2
|
Aluminium Smelter
|
|
3
|
Asbestos and asbestos based industries
|
|
4
|
Automobile Manufacturing (integrated facilities)
|
|
5
|
Basic chemicals and electro chemicals and its derivatives including
manufacturing of acid
|
|
6
|
Building and construction projects having waste water generation
>100 KLD
|
|
7
|
Cement
|
|
8
|
Chlor Alkali
|
|
9
|
Chlorates, per-chlorates & peroxides
|
|
10
|
Chlorine, fluorine, bromine, iodine and their compounds
|
|
11
|
Coke making, liquefaction, coal tar distillation or fuel gas making
|
|
12
|
Common treatment and disposal facilities (CETP, TSDF, CBMWTF, effluent
conveyance project, incinerator, MSW sanitary landfill site)
|
|
13
|
Compressed Biogas (CBG)/Bio-CNG plants
CBG plants based on Municipal Solid Waste (MSW) WWG is more than 100
KLD
|
|
14
|
Compressed Biogas (CBG)/Bio-CNG plants
CBG plants based on process waste (industrial/process liquid effluent
& solid waste like press mud, organic sludge, molasses etc. WWG is more
than 100 KLD
|
|
15
|
Copper Smelter
|
|
16
|
DG Set of capacity > 5 MVA
|
|
17
|
Distillery (molasses/grain/yeast based)
|
|
18
|
Dyes and Dye- Intermediates
|
|
19
|
Fertilizer (basic) (excluding formulation)
|
|
20
|
Fibre glass production and processing (excluding moulding)
|
|
21
|
Fire crackers manufacturing and bulk storage facilities
|
|
22
|
Health Care establishments (as defined in Bio-Medical Management Waste
Rules, 2016 as amended from time to time) with overall waste water generation
>100 KLD
|
|
23
|
Hotel having overall wastewater generation @100 KLD and more
|
|
24
|
Industrial carbon including electrodes and graphite blocks, activated
carbon, carbon black
|
|
25
|
Industries engaged in recycling/reprocessing/recovery/reuse of
Hazardous Waste under schedule iv of Hazardous and Other Wastes (Management
and Transboundary Movement) Rules, 2016 and as amended from time to
time-Items namely-Spent catalyst containing nickel, cadmium, Zinc, copper,
arsenic, vanadium and cobalt,
|
|
26
|
Industries engaged in recycling/reprocessing/recovery/reuse of Hazardous
Waste under schedule iv of Hazardous and Other Wastes (Management and
Transboundary Movement) Rules, 2016 and as amended from time to time-Items
namely-Dismantlers Recycling Plants-Components of waste electrical and
electronic assembles comprising accumulators and other batteries included on
list A, mercury-switches, activated glass cullets from cathode-ray tubes and
other activated glass and PCB-capacitors, or any other component contaminated
with Schedule 2 constituents (e.g. cadmium, mercury, lead, polychlorinated
biphenyl) to an extent that they exhibit hazard characteristics indicated in
part C of this Schedule.
|
|
27
|
Industries engaged in recycling/reprocessing/recovery/reuse of
Hazardous Waste under schedule iv of Hazardous and Other Wastes (Management
and Transboundary Movement) Rules, 2016 and as amended from time to
time-Items namely-Integrated Recycling Plants -Components of waste electrical
and electronic assembles comprising accumulators and other batteries included
on list A, mercury- switches, activated glass cullets from cathode-ray tubes
and other activated glass and PCB-capacitors, or any other component contaminated
with Schedule 2 constituents (e.g. cadmium, mercury, lead, polychlorinated
biphenyl) to an extent that they exhibit hazard characteristics indicated in
part C of this Schedule.
|
|
28
|
Industries engaged in recycling/reprocessing/recovery/reuse of Hazardous
Waste under schedule iv of Hazardous and Other Wastes (Management and
Transboundary Movement) Rules, 2016 and as amended from time to time-Items
namely-Lead acid battery plates and other lead scrap/ashes/residues not
covered under Batteries (Management and Handling) Rules, 2001. [* Battery
scrap, namely: Lead battery plates covered by ISRI, Code word
"Rails" Battery lugs covered by ISRI, Code word "Rakes".
Scrap drained/dry while intact, lead batteries covered by ISRI, Code word
"rains".
|
|
29
|
Industries engaged in recycling/reprocessing/recovery/reuse of
Hazardous Waste under schedule iv of Hazardous and Other Wastes (Management
and Transboundary Movement) Rules, 2016 and as amended from time to
time-Items namely-Spent cleared metal catalyst containing copper, Spent
cleared metal catalyst containing zinc,,
|
|
30
|
Industry having liquid waste water generation of 100 KLD or more
including industrial and domestic waste water
|
|
31
|
Industry or process involving metal surface treatment or process such
as pickling/electroplating/paint stripping/heat treatment using cyanide
bath/phosphating or finishing and anodizing/enamellings/galvanizing
|
|
32
|
Iron & Steel (involving processing from ore/integrated steel
plants) and or Sponge Iron units
|
|
33
|
Isolated storage of hazardous chemicals (as per schedule of
manufacturing, storage of hazardous chemicals rules, 1989 as amended)
|
|
34
|
Lead acid battery manufacturing (excluding assembling and charging of
lead-acid battery in micro scale)
|
|
35
|
Manufacturing of explosives, detonators, fuses including management and
handling activities
|
|
36
|
Manufacturing of glue and gelatin
|
|
37
|
Manufacturing of lubricating oils, grease and petroleum based products
|
|
38
|
Manufacturing of paints varnishes, pigments and intermediate (excluding
blending/mixing)
|
|
39
|
Milk processes and dairy products (integrated project)
|
|
40
|
Mining and ore beneficiation
|
|
41
|
Nuclear power plant
|
|
42
|
Oil and gas extraction including CBM (offshore & on-shore
extraction through drilling wells)
|
|
43
|
Oil Refinery (mineral Oil or Petro Refineries)
|
|
44
|
Organic Chemicals manufacturing
|
|
45
|
Pesticides (technical) (excluding formulation)
|
|
46
|
Petrochemicals Manufacturing (including processing of Emulsions of oil
and water)
|
|
47
|
Pharmaceuticals
|
|
48
|
Phosphate rock processing plant
|
|
49
|
Phosphorous and its compounds
|
|
50
|
Photographic film and its chemicals
|
|
51
|
Ports and harbour, jetties and dredging operations
|
|
52
|
Power generation plant [except Wind and Solar renewable power plants of
all capacities and Mini Hydel power plant of capacity <25 MW]
|
|
53
|
Processes involving chlorinated hydrocarbons
|
|
54
|
Pulp & Paper (Large-Agro + wood), Small Pulp & Paper (agro
based-wheat straw/rice husk)
|
|
55
|
Pulp & Paper (waste paper based units with bleaching process to
manufacture writing & printing paper)
|
|
56
|
Pulp & Paper (waste paper based without bleaching process to
manufacture Kraft Paper)
|
|
57
|
Railway locomotive work shop/Integrated road transport
workshop/Authorized service centers
|
|
58
|
Railway Stations (Wastewater generation (???) 100 KLD)
|
|
59
|
Ship Breaking Industries
|
|
60
|
Slaughter house (as per notification S.O. 270(E) dated 26-03-2001) and
meat processing industries, bone mill, processing of animal horn, hoofs and
other body parts
|
|
61
|
Sugar (excluding Khandsari)
|
|
62
|
Synthetic fibers including rayon, tyre cord, polyester filament yarn
|
|
63
|
Tanneries
|
|
64
|
Thermal Power Plants
|
|
65
|
Tyre and tubes manufacturing unit >100 KLD waste water generation
|
|
66
|
Yarn/Textile processing involving any effluent/emission generating
processes including bleaching, dyeing, printing and colouring
|
|
67
|
Zinc Smelter
|
|
ORANGE CATEGORY
|
|
Sr. No.
|
Category
|
|
1
|
2
|
|
1
|
Airport and Commercial air strips with overall waste water generation
<100 KLD
|
|
2
|
Almirah, Grill Manufacturing (Dry Mechanical Process)
|
|
1
|
2
|
|
3
|
Aluminium & copper extraction from scrap using oil fired furnace
(dry process only)
|
|
4
|
Automobile servicing, repairing and painting (excluding only fuel
dispensing)
|
|
5
|
Automobile servicing, repairing and painting (excluding only fuel
dispensing)
|
|
6
|
Ayurvedic and homeopathic medicine
|
|
7
|
Bakery and confectionery units (With wood fired ovens/furnaces) and
electric/gas ovens > 1T/day
|
|
8
|
Brickfields (excluding fly ash brick manufacturing using lime process)
|
|
9
|
Building and construction projects having bult-up area more than 20000
sq.mt and waste water generation (???) 50 KLD
|
|
10
|
Cashew nut processing
|
|
11
|
Ceramics and Refractories
|
|
12
|
Chanachur and ladoo from puffed and beaten rice (muri and shira) using
husk fired oven
|
|
13
|
Coal washeries
|
|
14
|
Coated electrode manufacturing
|
|
15
|
Coffee seed processing
|
|
16
|
Compact disc computer floppy and cassette manufacturing/Reel
manufacturing
|
|
17
|
Compressed/Refined Bio-gas production from Biodegradable waste
|
|
18
|
Compressed Biogas (CBG)/Bio-CNG plants
CBG plants based on Municipal Solid Waste (MSW) WWG is less than 100
KLD
|
|
19
|
Compressed Biogas (CBG)/Bio-CNG plants
CBG plants based on process waste (industrial/process liquid effluent
& solid waste like press mud, organic sludge, molasses etc. WWG is less
than 100 KLD
|
|
20
|
Compressed Biogas (CBG)/Bio-CNG plants
CBG plants based on crop residue (paddy straw/wheat straw/corn sweet
sorghum/napier grass etc)
|
|
21
|
Compressed Biogas (CBG)/Bio-CNG plants
CBG plants based on animal waste (dairy farms, poultry farms and other
animal) WWG is more than 100 KLD
|
|
22
|
Construction and Demolition (C & D) waste processing plants
|
|
23
|
Cotton spinning and weaving (medium and large scale)
|
|
24
|
Dairy and dairy products (small scale)
|
|
25
|
Dairy Farm having 15 animals and above where milching animals
(cows/buffaloes) are housed to produce milk for distribution and supply to
milk processing plants
|
|
26
|
DG set of capacity >1 MVA but < 5 MVA
|
|
27
|
Dismantling of rolling stocks (wagons/coaches)
|
|
28
|
Dry cell battery (excluding manufacturing of electrodes) and assembling
& charging of acid lead battery on micro scale
|
|
29
|
Dry coal processing, mineral processing, industries involving ore
sintering, pelletisating, grinding & pulverization
|
|
30
|
Fermentation industry including manufacture of yeast, beer,
distillation of alcohol (Extra Neutral Alcohol)
|
|
31
|
Ferrous and Non-ferrous metal extraction involving different furnaces
through melting, refining, re-processing, casting and alloy-making
|
|
32
|
Fertilizer (granulation/formulation/blending only)
|
|
33
|
Fish feed, poultry feed and cattle feed
|
|
34
|
Fish processing and packing (excluding chilling of fishes)
|
|
35
|
Flakes from rejected PET bottle
|
|
36
|
Foam manufacturing
|
|
37
|
Food and food processing including fruits and vegetable processing
|
|
38
|
Forging of ferrous and non-ferrous metals (using oil and gas fired
furnaces)
|
|
39
|
Formulation/pelletization of camphor tablets, naphthalene balls from
camphor/naphthalene powders.
|
|
40
|
Gaushalas where weak, sick, injured, handicapped and abandoned homeless
cattle/cows are housed for rehabilitation is 100 KLD and more.
|
|
41
|
Glass ceramics, earthen potteries and tile manufacturing using oil and
gas fired kilns, coating on glasses using cerium fluorides and magnesium
fluoride etc.
|
|
42
|
Gold Assaying & Hallmarking Centres
|
|
43
|
Gravure printing, digital printing on flex, vinyl
|
|
44
|
Health Care establishments (as defined in Bio-Medical Management Waste
Rules, 2016 as amended from time to time) with overall waste water generation
>100 KLD
|
|
45
|
Heat treatment using oil fired furnace (without cyaniding)
|
|
46
|
Hot mix plants
|
|
47
|
Hotels (< 3 star) or hotels having > 20 rooms and less than 100
rooms.
|
|
48
|
Hotels (<3 star) or hotels having>20 rooms and less than 100
rooms
|
|
49
|
Ice cream
|
|
50
|
Industries engaged in recycling/reprocessing/recovery/reuse of
Hazardous Waste under schedule iv of Hazardous and Other Wastes (Management
and Transboundary Movement) Rules, 2016 and as amended from time to
time-Items namely-Brass Dross, Copper Dross, Copper Oxide Mill Scale, Copper
Reverts, Cake & Residues, Waste Copper and copper alloys in dispersible
form, Slags from copper processing for further processing or refining,
Insulated Copper Wire, Scrap/copper with PVC sheathing including ISRI-code
material namely "Druid", Jelly filled Copper cables, Zinc Dross-Hot
dip Galvanizers SLAB,, Zinc Dross-Bottom Dross, Zinc ash/Skimming arising
from galvanizing and die casting operations, Zinc ash/Skimming/other zinc
bearing wastes arising from smelting and refining, Zinc ash and residues
including zinc alloy residues in dispersible from,
|
|
51
|
Industries engaged in recycling/reprocessing/recovery/reuse of
Hazardous Waste under schedule iv of Hazardous and Other Wastes (Management
and Transboundary Movement) Rules, 2016 and as amended from time to
time-Items namely-Paint and ink Sludge/residues
|
|
52
|
Industries engaged in recycling/reprocessing/recovery/reuse of
Hazardous Waste under schedule iv of Hazardous and Other Wastes (Management
and Transboundary Movement) Rules, 2016 and as amended from time to
time-Items namely-Used Oil-As per specifications prescribed from time to
time.
|
|
53
|
Industries engaged in recycling/reprocessing/recovery/reuse of
Hazardous Waste under schedule iv of Hazardous and Other Wastes (Management
and Transboundary Movement) Rules, 2016 and as amended from time to
time-Items namely-Waste OilAs per specifications prescribed from time to
time.
|
|
54
|
Industry or processes involving foundry operations
|
|
55
|
Jute processing without dyeing
|
|
56
|
Lime manufacturing (using lime kiln)
|
|
57
|
Liquid floor cleaner, black phenyl, liquid soap, glycerol mono-stearate
manufacturing
|
|
58
|
Manufacturing of glass
|
|
59
|
Manufacturing of iodized salt from crude/raw salt
|
|
60
|
Manufacturing of mirror from sheet glass
|
|
61
|
Manufacturing of mosquito repellent coil
|
|
62
|
Manufacturing of silica gel
|
|
63
|
Manufacturing of Starch/Sago
|
|
64
|
Manufacturing of tooth powder, toothpaste, talcum powder and other
cosmetic items
|
|
65
|
Mechanized laundry using oil fired boiler
|
|
66
|
Mechanized laundry using oil fired boiler
|
|
67
|
Modular wooden furniture from particle board, MDF< swan timber etc,
Ceiling tiles/partition board from saw dust, wood chips etc., and other
agricultural waste using synthetic adhesive resin, wooden box making (With
boiler)
|
|
68
|
New highway construction project
|
|
69
|
New highway construction project
|
|
70
|
Non-alcoholic beverages (soft drink) & bottling of alcohol/non
alcoholic products
|
|
71
|
Paint blending and mixing (Ball mill)
|
|
72
|
Paints and varnishes (mixing and blending)
|
|
73
|
Parboiled Rice Mills
|
|
74
|
Pharmaceutical formulation and for R & D purpose (For sustained
release/extended release of drugs only and not for commercial purpose)
|
|
75
|
Ply-board manufacturing (including Veneer and laminate) with oil fired
boiler/thermic fluid heater (without resin plant)
|
|
76
|
Potable alcohol (IMFL) by blending, bottling of alcohol products
|
|
77
|
Powder Coating Compound manufacturing units
|
|
78
|
Printing ink manufacturing
|
|
79
|
Printing or etching of glass sheet using hydrofluoric acid
|
|
80
|
Printing press
|
|
81
|
Producer gas plant using conventional up drift coal gasification
(linked to rolling mills glass and ceramic industry refectories for dedicated
fuel supply)
|
|
82
|
Railway Stations (Wastewater generation >10 KLD but <100 KLD)
|
|
83
|
Reprocessing of waste plastic including PVC
|
|
84
|
Rolling mill (oil or coal fired) and cold rolling mill
|
|
85
|
Scrapping Centres (for End of Life of Vehicles and other scraps such as
plant and machineries, structural material, railway coaches and wagons etc.)
a. Collection, De-Pollution, Dismantling Centres
|
|
86
|
Scrapping Centres (for End of Life of Vehicles and other scraps such as
plant and machineries, structural material, railway coaches and wagons etc.)
a. Collection, De-Pollution, Dismantling Centres and Shredding Centres
|
|
87
|
Scrapping Centres (for End of Life of Vehicles and other scraps such as
plant and machineries, structural material, railway coaches and wagons etc.)
a. Shredding Centres (can include transparent goods "fother scraps also)
Note-Recycling/dismantling of transparent goods are covered under E-Waste
(Management & Handing Rules, 2016, end have already been categorised in
CPCS document-Classification of industrial Sector-(Feb. 2016)
|
|
88
|
Silk screen printing, sari printing by wooden blocks
|
|
89
|
Spray painting, paint baking, paint shipping
|
|
90
|
Steel and steel products using various furnaces like blast furnace/open
hearth furnace//induction furnace/arc furnace/submerged arc furnace/basic
oxygen furnace/hot rolling reheated furnace
|
|
91
|
Stone crushers
|
|
93
|
Stone Quarries
|
|
94
|
Surgical and medical products including prophylactics and latex
|
|
95
|
Synthetic detergents and soaps (excluding formulation)
|
|
96
|
Synthetic resins
|
|
97
|
Synthetic rubber excluding molding
|
|
98
|
Tephlon based products
|
|
99
|
Thermocol manufacturing (with boiler)
|
|
100
|
Thermometer manufacturing
|
|
101
|
Tobacco products including cigarettes and tobacco/opium processes
|
|
102
|
Transformer repairing/manufacturing (dry process only)
|
|
103
|
Tyres and tubes vulcanization/hot retreating
|
|
104
|
Vegetable oil manufacturing including solvent extraction and
refinery/hydrogenated oils
|
|
105
|
Wire drawing and wire netting
|
|
GREEN CATEGORY
|
|
Sr. No.
|
Category
|
|
1
|
2
|
|
1
|
Aluminium utensils from aluminium circles by pressing only (dry
mechanical operation)
|
|
2
|
Assembly of antenna
|
|
3
|
Ayurvedic and homeopathic medicines (without boiler)
|
|
4
|
Bakery/confectionery/sweets products (with production capacity <1
tpd (with gas or electrical oven)
|
|
5
|
Bi-axially oriented PP film along with metalizing operations
|
|
6
|
Biomass briquettes (sun drying) without using toxic hazardous wastes
|
|
7
|
Blending of melamine resins & different powder, additives by
physical mixing
|
|
8
|
Brass and bell metal utensils manufacturing from circles (dry
mechanical operation without re-rolling facility)
|
|
9
|
Building and construction projects having bult-up area less than 20000
sq.mt and waste water generation < 50 KLD
|
|
10
|
Bus body building excluding painting
|
|
11
|
Candy
|
|
12
|
Cardboard or paper gated box and paper products (excluding paper or
pulp manufacturing and without using boilers)
|
|
13
|
Carpentry & wooden furniture manufacturing (excluding saw mill)
with the help of electrical (motorized) machines such as electrical wood
planner, steel saw cutting circular blade, etc.
|
|
14
|
Catering Service other then on tiffin basis and self help groups.
|
|
15
|
Cement products (without using asbestos/boiler/steam curing) like pipe,
pillar, jafri, well ring, block/tiles etc.(should be done in closed covered
shed to control fugitive emissions)
|
|
16
|
Ceramic colour manufacturing by mixing & blending only (not using
boiler and wastewater recycling process)
|
|
17
|
Chilling plant and ice making without using ammonia
|
|
18
|
Chilling plant, cold storage and ice making
|
|
19
|
CO2 recovery
|
|
20
|
Coke briquetting (sun drying)
|
|
21
|
Compressed/Refined Bio-Gas Production from Bio-degradable Wastes. No
waste water discharge from digester and also feed slurry to digester having
Volatile Organic Fraction more than 75%.
|
|
22
|
Compressed Biogas (CBG)/Bio-CNG plants
CBG plants based on crop residue (paddy straw/wheat straw/corn sweet
sorghum/napier grass etc) WWG is less than 100 KLD
|
|
23
|
Compressed Biogas (CBG)/Bio-CNG plants
CBG plants based on animal waste (dairy farms, poultry farms and other
animal waste) WWG is less than 100 KLD
|
|
24
|
Cotton spinning and weaving (small scale)
|
|
25
|
Cutting, sizing and polishing of marble stone
|
|
26
|
Dal Mills
|
|
27
|
Decoration of ceramic cups and plates by electric furnace
|
|
28
|
Diesel generator sets (15 KVA to 1 MVA)
|
|
29
|
Digital printing on PVC clothes
|
|
30
|
Distilled water (without boiler) with electricity as source of heat
|
|
31
|
Electrical and electronic item assembling with painting activity
|
|
32
|
Emery powder (fine dust of sand) manufacturing
|
|
33
|
Facility of handling, storage and transportation of food grains in bulk
|
|
34
|
Facility of handling, storage and transportation of food grains in
bulk)
|
|
36
|
Flour mills (dry process)
|
|
37
|
Flyash export, transport & disposal facilities
|
|
38
|
Gaushalas where weak, sick, injured, handicapped and abandoned homeless
cattle/cows are housed for rehabilitation is less than 100 KLD.
|
|
39
|
Glass, ceramic, earthen potteries, tile and tile manufacturing using
electrical kiln or not involving fossil fuel kiln
|
|
40
|
Glue from starch (physical mixing) with gas/electrically operated
oven/boiler.
|
|
41
|
Gold and silver smithy (purification with acid smelting operation and
sulphuric acid polishing operation) (using less or equal to 1 litre of
sulphuric acid/nitric acid per month)
|
|
42
|
Heat treatment with any of the new technology like ultrasound probe,
induction hardening, ionization beam, gas carburizing etc.
|
|
43
|
Hotels (up to 20 rooms and without boilers) and overall waste water
generation < 100 KLD
|
|
44
|
Hotels (upto 20 rooms and without boiler)
|
|
45
|
Insulation and other coated papers (excluding paper or pipe
manufacturing)
|
|
46
|
Leather foot wear and leather products (excluding tanning and hide
processing except cottage scale)
|
|
47
|
Lubricating oil, greases or petroleum based products (only blending at
normal temperature)
|
|
48
|
Manufacture of sanitary pads
|
|
49
|
Manufacturing of optical lenses (using electrical furnace)
|
|
50
|
Manufacturing of pasted veneers using gas fired boiler or thermic fluid
heater and by sun drying
|
|
52
|
Marriage Halls
|
|
53
|
Mineral stack yard/Railway sidings
|
|
55
|
Mineralized water
|
|
56
|
Oil and gas transportation pipeline
|
|
57
|
Oil mill Ghani and extraction (no hydrogenation/refining)
|
|
58
|
Packing materials manufacturing from non asbestos fibre, vegetable
fibre yarn
|
|
59
|
Papad and Pickels manufacturing
|
|
60
|
Phenyl/toilet cleaner formulation and bottling
|
|
61
|
Polythene and plastic processed products manufacturing (virgin plastic)
|
|
62
|
Poultry, Hatchery and Piggery
|
|
63
|
Power looms (without dye and bleaching)
|
|
64
|
Puffed rice (muri) (using gas or electrical heating system)
|
|
65
|
Pulverization of bamboo and scrap wood
|
|
66
|
Railway Stations (Wastewater generation<10 KLD)
|
|
67
|
Ready mix cement concrete
|
|
68
|
Reprocessing of waste cotton
|
|
69
|
Rice mill (Rice hullers only)
|
|
70
|
Rolling mill (gas fired) and cold rolling mill
|
|
71
|
Rubber goods industry (with gas operated baby boiler)
|
|
72
|
Saw mills
|
|
73
|
Seasoning of wood in steam heated chamber
|
|
75
|
Soap manufacturing (hand made without steam boiling/boiler)
|
|
76
|
Spice grinding (20 HP motor)
|
|
77
|
Steel furniture without spray painting
|
|
78
|
Steeping and processing of grains
|
|
79
|
Surface treatment using water spray rinsing, degreasing, heating in
ovens, electrostatic powder coating and curing using oven
|
|
80
|
Synthetic detergent formulation
|
|
81
|
Tamarind powder manufacturing
|
|
82
|
Tea processing (with boiler)
|
|
83
|
Tyres and tube retreating (without boilers)
|
|
WHITE CATEGORY
|
|
Sr. No.
|
Category
|
|
1
|
2
|
|
1
|
Assembly of air coolers/conditioners, repairing and servicing
|
|
2
|
Assembly of bicycles, baby carriages and other small non motorizing
vehicles
|
|
3
|
Automobile fuel outlets (only dispensing)
|
|
4
|
Bailing (hydraulic press) of waste papers
|
|
5
|
Bio fertilizer and bio-pesticides without using inorganic chemicals
|
|
6
|
Biscuits trays etc from rolled PVC sheet (using automatic vacuum
forming machines)
|
|
7
|
Blending and packing of tea
|
|
8
|
Block making of printing without foundry (excluding wooden block
making)
|
|
9
|
Catering serving food on tiffin basis, self help groups.
|
|
10
|
Cement Godown
|
|
11
|
Chalk making from plaster of Paris (only casting without boilers etc.
(sun drying/electrical oven)
|
|
12
|
Compressed oxygen gas from crude liquid oxygen (without use of any
solvents and by maintaining pressure & temperature only for separation of
other gases)
|
|
13
|
Compressed Biogas (CBG)/Bio-CNG plants CBG plants (irrespective of the type
of feed) producing Fermented Organic manure (FOM) & Liquid Fermented
Organic Manure (LFOM) as by-products
|
|
14
|
Compressed Biogas (CBG)/Bio-CNG plants Household
bio-digesters/gobar-gas (cow-dung) plants based on biodegradable wastes etc.
|
|
15
|
Cotton and woolen hosiers making (Dry process only without any
dying/washing operation)
|
|
16
|
Cycle/motor track
|
|
17
|
Dairy Farm having less than 15 animals where milching animals
(cows/buffaloes) are housed to produce milk for distribution and supply to
milk processing plants
|
|
18
|
Diesel pump repairing and servicing (complete mechanical dry process)
|
|
19
|
Domestic bio-digestors based on cow-dung or household biodegradable
wastes (such as gobar gas plants)
|
|
20
|
Electric lamp (bulb) and CFL manufacturing by assembling only
|
|
21
|
Electrical and electronic item assembling (completely dry process)
|
|
22
|
Engineering and fabrication units (dry process without any heat
treatment/metal surface finishing operations/painting)
|
|
23
|
Fabrication carrying out metal primer application/hand painting
activity
|
|
24
|
Flavoured betel nuts production/grinding (completely dry mechanical
operations)
|
|
25
|
Fly ash bricks/block manufacturing
|
|
26
|
Fountain pen manufacturing by assembling only
|
|
27
|
Glass bottles and villas making from glass tubes
|
|
28
|
Glass putty and sealant (by mixing with machine only)
|
|
29
|
Ground nut decorticating
|
|
30
|
Handloom/carpet weaving (without dying and bleaching operation)
|
|
31
|
Leather cutting and stitching (more than 10 machine and using motor)
|
|
32
|
Manufacturing of coir items from coconut husks
|
|
33
|
Manufacturing of metal caps containers etc
|
|
34
|
Manufacturing of shoe brush and wire brush
|
|
35
|
Medical oxygen
|
|
36
|
Organic and inorganic nutrients (by physical mixing)
|
|
37
|
Organic manure (manual mixing)
|
|
38
|
Packing of powdered milk
|
|
39
|
Paper pins and u clips
|
|
40
|
Repairing of electric motors and generators (dry mechanical process)
|
|
41
|
Rope (plastic and cotton)
|
|
42
|
Scientific and mathematical instrument manufacturing
|
|
43
|
Sewage tankers
|
|
44
|
Solar module non conventional energy apparatus manufacturing unit
|
|
45
|
Solar power generation through solar photovoltaic cell, wind power and
mini hydel power (less than 25 MW)
|
|
46
|
Surgical and medical products assembling only (not involving
effluent/emission generating processes)
|
|
47
|
Stand-alone Massage Parlours, Beauty Parlour, Hair Cutting Saloon and
SPAs
|
|
48
|
Tea stall
|
|
49
|
Used Cooking Oil (UCO) collection centres
|
Note:
Any industry/industrial activity, process or trades which do not fall under any
of the above mentioned categories, the decision with regards to their
categorization/classification, will be taken by the Board, from time to time
when such need arises, either suo motto or on the specific request by the
Industrial unit. Industrial unit concerned may apply to the Goa State Pollution
Control Board in this respect for necessary action.
ACCOMPANIMENTS:
The
Following documents should invariably be attached along with the application as
follows:
(A)
Consent to Establish/Consent to
Operate
(1)
Land Allotment/earmarking letter or lease/Sale
deed/Form I & XIV.
(2)
Flow Chart and detailed production
process.
(3)
A copy of Project Report for projects
costing Five crores and above.
(4)
Site plan (not required for units to
be set up in Industrial Estates.)
(5)
Layout plan showing the location of manufacturing
equipments, water supply/drainage lines, position of chimneys, effluent
treatment plant and final discharge Point, Sludge solid waste disposal points
and septic tanks/soak pits.
(6)
For industries/activities listed in
Schedule I of the Environmental Impact Assessment (EIA) Notification 2006 copy
of the EIA report/Form/Report submitted for obtaining Environmental Clearance
and other survey, if required will have to be furnished in the prescribed time
limit.
(7)
Photocopy of the prior Environmental
Clearance (EC) issued by the Competent Authority, if applicable, for project
listed in the Environment Impact Assessment (EIA) Notification, 2006, as
amended from time to time.
(8)
Site plan showing surrounding
Residential area, public places, water stream, etc., of the factory site within
a radius of 5 kms with waste water treatment and disposal systems clearly
indicating where waste - water is proposed to be disposed off (for medium and
large scale enterprises).
(9)
Schematic sketch of the proposed
effluent/sewage treatment system/plant (ETP/STP) and/or septic tanks/soak pit,
duly signed by authorized person, along with detailed design calculation.
(10)
Certificate from Chartered Accountant
certifying the Total Estimated Investment (T.E.I). (refer sample specimen
below). In case of leased/hired premises/plant/machinery/equipment a
certificate from a Registered Valuer towards capital cost is to be submitted
without appreciation and depreciation.
(11)
Original authorization letter of the
person to whom authorization is made to sign this application form except
individual proprietary concern.
(12)
Any other documents/clarification as
requisition by the Goa State Pollution Control Board.
(B)
Renewal of Consent to Operate
(1)
Certificate from Chartered Accountant
certifying the Total Estimated Investment (T.E.I). (refer sample specimen
below). In case of leased/hired premises/plant/machinery/equipment a
certificate from a Registered Valuer towards capital cost is to be submitted
without appreciation and depreciation.
(2)
Previous Consent to Operate issued by
the Board
(3)
Stack Analysis Report/Analysis report
of Treated effluent/sewage.
(4)
Any changes/modifications in the
industry after the consent obtained.
(5)
Application for auto renewal of Orange
and Green category will be accompanied by an affidavit annexed hereto for an
individual proprietary concern.
(6)
Any other documents/clarification as
requisition by the Goa State Pollution Control Board.
ANNEXURE 'B'
[See rule 25(6) (e)]
Affidavit in support of obtaining
Auto Renewal of Consent to Establish/Operate
(1)
I..............................................................................................
S/o Shri.............................................,
aged.............................. years, Authorized
signatory........................... (Designation) of M/s.
..................................................................... (Unit ID
...............................................) am submitting this affidavit
in favour of Member Secretary, Goa State Pollution Control Board, Panaji for
obtaining auto renewal of Consent to Establish/Consent to Operate under the
provisions of Air (Prevention and Control of Pollution) Act, 1981 (Act 14 of
1981) and do, hereby take oath and state as under:-
(2)
That the Consent to Establish/Consent
to Operate under the provisions of Air (Prevention and Control of Pollution)
Act, 1981 (Act 14 of 1981) was issued vide order No dated ..............
...............................................................................
(3)
That the said Consent to
Establish/Consent to Operate is valid upto..............
(4)
That we have not carried out any
expansion/modernisation/change in process/product/raw material/fuel or change
in pollution load.
(5)
That we are complying with conditions
of previous consent and submitting requisite compliance report of earlier
consent along with supporting documents as per schedule.
(6)
That we have submitted Environmental
Statement report as prescribed under the rules.
(7)
There is no change in information provided
in the prescribed application form submitted for obtaining earlier consent to
operate.
(8)
That no directions were issued during
last five years by the State Board under the provisions of section 31 (A) of
Air (Prevention and Control of Pollution) Act, 1981 and section 5 of
Environment (Protection) Act, 1986 (Act 29 of 1986).
(9)
There are no prohibitory directions
from Courts/Appellate Authority/National Green Tribunal/other judicial/Quassi
judicial Authority.
(10)
We undertake to comply with the
conditions and standards stipulated in consent order and with any additional
condition/direction which may be stipulated by the Board in future and also to
pay additional fee/charges demanded by the Board in future.
(11)
That I have understood that any wrong,
partial, forged information/document submitted by me or any false affirmation
made by the undersigned, I shall be liable for legal action including the
prosecution under the provisions of Air (Prevention and Control of Pollution)
Act, 1981 (Act 29 of 1981) and Information Technology Act, 2000 (Act 21 of
2000) along with the provisions of Indian Penal Code, 1860 (Act 45 of 1860).
DEPONENT
Declaration
I,
the above named deponent do hereby attest and verify that the contents of para
No. 1 to 11 of this affidavit are true and correct to the best of my knowledge.
Nothing material has been concealed therein nor any part of it is false.
DEPONENT
SCHEDULE II
[see Rule 26(5), (6), (9), (10), (11), (13), (14)]
(A)
MEMBERS OF THE ENVIRONMENTAL AUDIT
COMMITTEE
|
1.
|
Retired Scientist/Engineer from a reputed Scientific
Organization/Institution to be nominated by the Chairman
|
: Chairman
|
|
2.
|
A Senior Expert on Environmental Audit to be Appointed by GSPCB from
any IRCA authorized ISO 14001:2015 Certification Authority
|
: Member
|
|
3.
|
Member of the State Expert appraisal Committee nominated by the State
Expert Committee
|
: Member
|
|
4.
|
Scientist/Engineer of Goa State Pollution Control Board as nominated by
Chairman, Goa State Pollution Control Board
|
: Convener
|
(B)
OBJECTIVES
Objectives
of Environmental Audit Scheme (EAS) is to engage deemed Scientific and
Technical experts to provide a clear indication of the Environmental
performance and compliance to Consent conditions of the Organization for the
period covered by the audit.
The
preliminary objectives of the EAS are as follows:
(a)
Provide an objective analysis of the
environmental impacts arising from the Organizations activities;
(b)
Assess and Determine that mitigation
measures including root cause analysis, corrective and preventive actions are
effective in addressing environmental aspects and minimizing or removing
environmental impacts;
(c)
Identify opportunities and make
recommendations for improvements in environmental performance of the Organization
(C)
ROLES AND RESPONSIBILITIES
The
roles and responsibilities of the various key players is provided in the
context of the Environment Audit scheme.
(I)
RESPONSIBILITIES OF THE ORGANIZATION
(a)
The occupier shall be responsible for
submitting Environmental Statement and provide all the assistance and necessary
documentation for completion of the Environmental audit.
(i)
GSPCB/CPCB Issued
Consents/Directions/Guidelines (e.g. COINDS or related)
(ii)
Complaint, if any, received by the
GSPCB/Organization and corrective and preventive action taken thereof.
(iii)
Defined and detailed Procedures of
production process, Pollution Control Equipment, finished product/services, by
products, consumption of raw materials, against finished products, measurement
and monitoring of consumption of water, electricity or other fuels and/or other
resources/material per unit finished product/service with responsibilities and
supporting records.
(iv)
Defined and detailed Procedures of
available addressing identified environmental aspects per unit product output
and the corrective-preventive measures to minimize its environmental impacts
through the use of alternative technology, pollution control equipment or any
other related technique with measurement and monitoring data, responsibilities
and supporting records.
(v)
Organizations Policy (Environment,
Health and Safety-EHS), if any.
(vi)
The Occupier of Organizations (as
mentioned in the Sr. No.4) shall carry out a documented Root cause analysis of
the Non conformances (NCf)/Non compliances (NCp) identified in the EAR once
received from the Auditor along with its corrective and preventive action plan,
and comments if any and submit the same within along with Form V Environmental
Statement with satisfactory closure of CAPA to the Board by target date agreed
upon by the Auditor and Occupier or before 30th June whichever is earlier with
copy of the stipulated receipt of scrutiny fees to GSPCB
(b)
The Organizations hereafter applying
for consent shall have to here onwards get its Environment Management System
inspected by respective auditors regarding adequacy and efficacy thereof,
through the Board.
(c)
The Organization is also responsible
for ensuring timely closures of Non conformances (NC) or Non Compliances or
Corrective Action Preventive Action Plans or related observations.
(II)
RESPONSIBILITIES OF THE GOA STATE
POLLUTION CONTROL BOARD
(a)
Appointment of auditor/s for
conducting Environmental Audit.
(b)
The list of Board Authorized Auditors
will be made publicly available on Board website.
(c)
To ensure effective conduct of the
individual audits, the following information should be provided to the audit
team leader by GSPCB
·
Organization Details
·
History of Defaults if any, and
closures or pending issues there off.
·
Contact name, No. address
(d)
Forward a copy of the final EAR to the
Organization within 15 days of receipt of the EAR.
(e)
Initiate appropriate action due to non
closure of Non conformances/Non Compliances within time frame specified.
(f)
Payment to Auditors
·
Mode of Payment: the State Board will
pay the Environmental Auditor the Audit fee as decided by the Board from time
to time within one week of submission of bills for conducting the audit.
·
In turn, GSPCB will issue directions
to Organizations covered under Audit Scheme to deposit the sum total of the
estimated expenses towards auditors fee and auditor expenses from the concerned
Organization within 15 days from the date of allocation to the auditor, interim
payment within 15 days on receiving of bills from the auditor and final payment
within 15 days from submission of final audit report based on actual and 25
percent of total cost incurred for Audit as administrative expenses incurred by
the State Board
(III)
RESPONSIBILITIES OF THE ENVIRONMENT
AUDIT COMMITTEE (EAC)
The
GSPCB constituted Environmental Audit Committee members shall not have any
conflict of interest with its present assignment. The terms of reference of
this Committee are as follows:
(i)
Define and develop audit criteria and
its supporting procedure and protocol for the recognition/empanelment/selection
of Environmental Auditors, including an assessment of the Auditors' (or
Auditor's selected). The EAC will suggest new parameters which have been
introduced by CPCB/GSPCB. The same will be recommended to GSPCB.
(ii)
Advise and create a guidance/technical
document related to the subject which will enable effective auditing including
effective auditing and laboratory functions.
(iii)
The committee member(s) will also
under take audit of Recognized Auditors., atleast once annually to ensure due
diligence of the Auditor to the and advise them in any relevant matter and will
suggest/implement the new parameters which are being introduced by the
CPCB/GSPCB. A observation report of the same will be submitted in this regard
within 15 days of visit
(iv)
After scrutiny, the EAC will submit
the final (list) of the Auditor(s) with their justifications for selection to
the Board for issue of Board Recognition.
(v)
EAC will meet atleast once in three
months.
(vi)
Conducting or arranging training
programme for capacity building of auditors, Organization Representatives and
regulators with respect to EAS.
(vii)
Shall review the audit report and
submit their comments on the NC(f)'s or NC(p)'s and their respective Root Cause
Analysis' (RCA) with corrective Action and Preventive Action (CAPA) Plans
(viii)
Assign the responsibility for
conducting the individual audit to be made in sufficient time before the
scheduled date of the audit, in order to ensure the effective planning of the
audit.
(D)
ENVIRONMENTAL AUDIT PLANNING AND
CONTROL
(I)
SELECTION OF ENVIRONMENTAL AUDITORS
(a)
The Member Secretary of the Board
shall appoint faculty of Engineering College, Science Colleges, University, or
retired or serving Engineer or Scientist from reputed Institutions, Government
Departments, or IRCA authorized ISO 14001:2015 Certification Agencies to be
Environment Auditor/s who shall be preferably located in the State of Goa and
have sufficient experience in the relevant field including relevant
qualifications with the approval of the Chairman.
(b)
The Member Secretary will constitute
Audit team for conducting the Environmental Audit for each audit with approval
of the Chairman.
(c)
The entire audit work must be carried
out by the auditor himself. In other words, the auditor shall and will not
assign the audit work to any other agency/firm/personnel other than those
recognized. Any violation in this regard shall lead to de-recognisation of the
auditor and imposition of penalty at the discretion of the EAC.
(d)
In case of change in the man power
(any member of the team), same shall be communicated to the GSPCB within one
month and the auditor shall also obtain the approval of the Board for the
replacement.
(II)
AUDIT CRITERIA
The
Member Secretary of the Board will set out the Audit Criteria for each
Environmental Audit with approval of the Chairman.
(III)
ENVIRONMENT AUDIT LABORATORY:
The
Board/Agency shall engage the services of NABL recognized Laboratories and also
having recognition of MoEF & CC whenever required.
(E)
AUDIT PROCEDURE
(I)
FUNCTIONS OF AUDITOR
The
Empanelled Auditor on receiving Board recognition shall:
(a)
Conduct audit of the GSPCB allotted
Organizations as per schedule provided
(b)
Identify opportunities and make
recommendations for improvements in environmental performance of the
Organization
(c)
Provide an objective, third-party
report that meets GSPCB's requirements.
(d)
The auditor shall thoroughly ascertain
about all the products/by products, manufactured by the Organization and its
related processes& report to the GSPCB immediately by verifying excise
registers, Invoices usage of raw materials and other production related
documents, if there are any discrepancies
(e)
Provide the information required to
develop an Environmental Management Plan (EMP) in the event of any significant
findings of negative impacts to the environment
(f)
It shall be open to the auditors to make
such recommendation as they may think fit for improvement of the existing
environmental management system in the Organization audited, but such
recommendation shall not bind the GSPCB in any manner. The recommendation of
the GSPCB will be technically and scientifically assessed and the decision of
the Board Chairman will be final and so intimated
(g)
Ensure high levels of integrity,
sincerity and ethics shall be maintained and practiced by the auditors
(h)
Ascertain & report to GSPCB about
the compliance made by Organization of the previous year's
recommendations/observations of the auditor in the EARs.
(i)
Report about % reduction in
steam/water consumption, mass balance (air, water and solid waste), power
consumption & consumption of raw materials etc. carried out by the
industries in its observations in the EARs compared to the previous year.
(j)
Pursue, emphasize and recommend about
adoption of clean technology/cleaner production, waste segregation, waste
minimization, waste reduction, waste exchange, reuse & recycling of
effluents etc. & report the same in EARs.
(k)
Guide the industry if possible if any
query is raised by the industry.
(l)
Ensuring review of timely closures of
Non conformances (NCf) or Non Compliances (NCp) or Corrective Action Preventive
Action Plans or related observations jointly with the Organization
(m)
Conduct audit in the audit period
prescribed i.e. financial year ending March and submit the EAR within 15 days
of completion of the audit, and the last, no later than by the 30th of April
every year.
(II)
ENVIRONMENTAL AUDIT REPORT SUBMISSION
(EAR)
(a)
The EARs must include observations
covering each of the seasons under audit, based on the analysis report of the
Moef approved Laboratory or Board laboratory for effluents (air + waste water +
Solid/hazardous waste + Noise + Weather data as case may be and other
pollutants as auditor feels so, etc.) from all discharge points & submit
all data of three observations in EARs, otherwise EARs shall be considered
incomplete and can be rejected.
(b)
The auditor must prepare and submit
the EAR of Organizations under audit within 15 days of completion of the audit.
(c)
The EAR shall be submitted to the
Board with a copy marked to the Organization, which will be forwarded by GSPCB
within 7 working days of receipt to the Organization to initiate necessary
closure of Root Cause Analysis-Corrective and Preventive Action Plans.
(d)
The auditor must clearly report to the
Board all critical findings about any inconsistency and malpractice being
committed/practiced by the Organization as listed in Sr. 2 (e.g. dilution of
effluents, illegal discharge, production without permission, by pass of
untreated effluent or any other activities which are likely to create
environmental pollution problems, & contrary to the directions issued through
consent orders & other orders under the different Acts, by the Board) after
every inspection within 24 hrs and important recommendations after every
inspection as immediately as possible but not later than 3 days and submit
Final EAR within 15 days of completion of the Audit.
(III)
CONTENT OF AUDIT REPORT
(a)
EAR'S and its reported findings and
conclusions should be :
·
Clear, timely, concise, easy to
understand and objective;
·
provide a fair summary of all the
relevant facts; and
·
demonstrate conformity with the
related Environmental requirements
·
Properly analyzed and concluded, and
·
Supported by adequate, reliable, and
fair audit evidence
(b)
The EAR should consist of :
(i)
A title page clearly briefly
Indicating AUDIT aim with Organization name
(ii)
Table of Contents
(iii)
Executive Summary comprising of:
·
Description of the Organization
Process and facilities (Main, ancillary (related) and Environmental control
operations)
·
Description of the environment
·
Contractors and Activity Descriptions
·
Summary of findings
(iv)
Introduction comprising of :
·
Audit Scope,
·
Audit Objectives identified, and
·
Audit Criteria identified
·
Auditors and Auditees (Organization
representatives who were key contacts for the audit and describe their roles
and responsibilities with regard to the audit.)
·
Reference Documents (include a list of
documentation reviewed prior to the audit (e.g., Consents, Directions, previous
EARs, environmental assessments, permits, complaints or any other reference
deemed relevant.).
(v)
Site Activity Report comprising of
(aa) List of Organization
Facilities
(ab) Developments if
any
(ac) Assessments of
internal controls
(ad) Assessments of
Organizations Environmental Management Systems and Management Commitment
(ae) Typical
Environmental Management Plan (that can be) evaluated as applicable
·
Air Quality Control Plan
·
Water Quality Control Plan (Waste and
wastewater management)
·
Waste Management Plan (Waste
segregation, management and disposal, Monitoring on pollution assessment and
performance evaluation of pollution control devices made by the Auditors)
·
Resources Control Plan (Material,
Production mass balance Energy, Fuels and equipment management-
(Figures
or production of products, by products, consumption of Resources like raw
materials, figures regarding use of water, fuel consumption and other material
utilization to maximize the yield with respect to National/International bench
mark mentioned in the format of Environmental Audit Reports prepared by
Auditors.)
·
Soil and Groundwater Contamination
Control Plan (Land, water and groundwater management
·
Marine Ecology Control Plan
·
Terrestrial Ecology Control Plan
·
Process Material Handling Plan
(Hazardous and Non Hazardous materials management)
·
Noise and Vibration Control Plan
(Noise engineering management)
·
Traffic Management Plan (Vehicle and
its distribution Management, Status of Pollution under Check (PUC’s) permits)
·
Erosion and Sediment Control Plan
·
Other Environmental Program.
(af) (Gathering of) Audit evidence
(ag) Interviews with Personnel/ground staff if any
(ah) Identification and assessments of Incidents and
Complaints if any
(vi)
Audit Findings of
·
Environmental Management Systems and
Management Commitment (Comments on the Organization’s procedures for
determining, setting, and communicating organization’s environmental policies
and objectives, as well as the overall commitment of senior management to
meeting environmental requirements. Supported by evidence of efforts to
monitor, measure, and report environmental performance.)
·
Previous Audit Results (comments on
the Organization’s mechanisms to determine the root causes of any identified
environmental concerns and on the effectiveness &sufficiency of the actions
taken to correct such situations and prevent their recurrence. And should
include the Management’s support of the processes for implementing and tracking
corrective and preventive actions)
·
Non-conformances, Observations and
Scope for Improvement (Tabulated based on priority based on degree of
seriousness of environmental impact)
·
Summary of Root Cause Analysis
-Corrective Action- and Preventive Action Plan Status (This section should
provide details on any new or previously identified corrective action(s) taken
and/or planned in response to non-conformances and/or the observations and/or
Scope for Improvement(s) identified, particularly those that have been
repetitive or are ongoing issues at the site or facility. In particular, the
Corrective Action Plan should include the detailed root cause analysis, type of
any required corrective and preventive action, the current status (e.g. open,
closed) of corrective and preventive action(s), the date of planned closure,
and the date of actual closure and deviation from the committed target and the
justification there off.)
·
Incidents and Complaints
·
Status of Environment Management Plans
if any
·
The EARs (Environment Audit Reports)
shall be prepared and submitted by the auditors in Performa 1: EAR must be
accompanied by efficacy & adequacy certificates in Performa 2 prescribed by
GSPCB with duly signed acknowledgement by all the team members. If such reports
will not be signed by all the team members then, the auditor will be
derecognized and punitive action against the Auditor or industries/Project as
listed in Sr. No. 2 will be taken, as the case may be.
(vii)
CONCLUSIONS AND RECOMMENDATIONS
This
section should include the conclusions of the audit with regard to
·
The status of the conformity and
compliance of the Organization’s EMS with the Legal and/or other requirements,
as well as
·
The effectiveness of the Organization’s
EMS in meeting its environmental objectives.
·
RCA-CAPA: the capability and
commitment of the Organization management to resolve the issues identified.
·
The auditor may propose to request
Organization to adopt an Environment Management Plan (EMP) if issues are
identified in the audit that are considered to be repetitive or are ongoing
issues, or problems that present significant concern for environmental impact.
The EMP is a Corrective Action Plan that must be submitted and approved by EAC
and requires formal reporting of the resolution of the issues. Guidance
regarding the requirements for developing an EMP should be provided by the
Auditor to facilitate the Organization to achieve anffecttive solution
·
The EAR should have recommendations to
address any significant non-conformances or deficiencies, including allocating
priorities for corrective action. Any recommendations should be specific and
detailed enough to allow GSPCB and Organization management the ability to
evaluate the feasibility and appropriateness of implementing the
recommendation. Types of recommendations might include further investigation of
an issue or implementation of emissions control technology or environmental
pollution control best management practices. The emphasis of recommendations
should be on removing the source of the problem rather than the use of
command-and-control (or end-of-pipe) technology.
The
recommendations should be brief and concise to allow Organization management to
address the issue and GSPCB& EAC to assess adequate resolution of the same.
(viii)
Attach Annexures:
·
Audit evidence (records, procedures,
photographs, supporting documents etc.)
·
Audit Protocol (Checklist) duly signed
by the Auditing team
·
Figures (if any)
·
Graphs (if any)
·
Tables (if any)
·
Any other detail felt relevant
The
above format is the bare minimum required to be included in the EAR and is open
for further additions by the Auditor if felt necessary.
Note:
Consult COINDS document of CPCB, BAT document of European union, USA EPA
document or any other relevant document to develop to bench mark.
(F)
POST AUDIT ACTION
(I)
ACTION/DIRECTION BY THE BOARD
(a)
The BOARD on receiving the EAR from
the Recognized Auditor will check status of compliance of the CAPA in the
audited Organization, after the stipulated post Target dates and present the
status to EAC for their necessary comments with Scientific and Technical
comments if any
(b)
Organizations failure to submit
compliance to the observations in the EAR with the requisite closures of Non
Conformances, Non compliances, Root Cause Analysis-Corrective and Preventive
Action Plan may lead to appropriate legal action by GSPCB which may also
include disconnection of water/power supply to the industry including closure
and or levy of Polluter Pay Penalty.
(c)
Where the Audit report of a particular
industry industry/operation/process/activity indicates that the industry does
not meet with the requirements as prescribed by or under the aforesaid
statutory provisions and that the industry has not complied with terms and
conditions of CTE/CTO and those contained in any general of special
circular/order of GSPCB, the industry shall be liable for appropriate
directions which include direction of closure, after verification of the status
of CAPA closures by stipulated dates.
(II)
ACCOUNTABILITY/LIABILITY OF THE
AUDITORS/INDUSTRIES
(a)
If the information provided by the
Organization is found to be incorrect or inaccurate the Organization shall be
liable to be subjected to the appropriate direct direction.
(b)
The Auditor whose report is found to
be incorrect or inaccurate of particular industry then that EAR shall be
rejected and action against the auditor will be taken accordingly.
(c)
The Organization has the right to
complain against the recognized environmental auditor if felt essential due to
misdemeanour or malpractice. In such a case the Organization can register a
written complaint against auditor to GSPCB within 15 days of the said
grievance, with supporting evidence and due justification. Complaints against
the actions or conduct of a certified auditor will be reviewed and investigated
by EAC. The EAC will investigate and if validated or substantiated, the
complaint may result in cancellation of recognition of the auditor s and
blacklisting them. However, If the complaint is found to be without merit, the
Organization will be appropriately penalized
(III)
APPEALS
(a)
Any person aggrieved by an order made
by the Board under section 16 or section 17 may within thirty days from the
date on which the order is communicated to him, prefer an appeal to Appellate Authority
constituted under section 31 of Air (Prevention and Control of Pollution) Act,
1981 (Act 14 of 1981).
(b)
On receipt of an appeal preferred
under sub-section (1), the Appellate Authority shall after giving the Appellant
and Board an opportunity of being heard, dispose of the appeal as expeditiously
as possible.
(G)
FORMAT FOR THE ENVIRONMENTAL AUDIT
REPORT
(To be submitted in triplicate)
(Period from........... to ...............)
To,
The
Member secretary
Goa
State Pollution Control Board
1ST
floor, Dempo Tower
Patto
Plaza Centre
Panjim-403001
|
A.
|
GENERAL
|
|
1.
|
Name of the Industry/operation/process/activity
|
|
|
2.
|
Location:
|
|
|
3.
|
Registered office Address:
|
|
|
4.
|
Month and year of establishment:
|
|
|
5.
|
No. of workers employed:
|
|
|
|
Male
|
|
|
|
Female
|
|
|
6.
|
No. of electrical connections with service numbers:
|
|
|
|
Total connected load
|
|
|
|
Electric consumption per tones of product manufactured:
|
|
|
|
Percentage enhancement in energy:
|
|
|
|
Saving as compared to previous year:
|
|
|
7.
|
Number of D.G. Set and their capacity:
|
|
|
8.
|
Name/Residential address of all Directors/Partners:
|
|
|
9.
|
Telephone Nos: (Residential & Industrial)
|
|
|
|
Fax No:
|
|
|
|
E-mail of Industry:
|
|
|
|
E-mail Partners/Directors:
|
|
|
10.
|
No. of shifts and timings:
|
|
|
11.
|
Name & Address of the in charge of Environment//Safety
Division/Cell/Unit:
|
|
|
12.
|
No. of days during which production activities were in operation during
the audit period covered:
|
|
|
13.
|
Has the industry obtained ISO 9000/ISO 14000//OSHAS 18000/Any other EM accreditation//Certification
|
|
|
14.
|
Whether the industry has adopted cleaner production/cleaner
technology/CDM?
|
|
|
B.
|
PRODUCT DETAILS
|
|
1.
|
Name of products (s) & capacity yield/purity per day,
|
|
|
2.
|
Efficiency of production (or production yield)
|
|
|
3.
|
Name of all by products and its quantity per day:
|
|
|
4.
|
Date of commencement of production for each product. Whether production
is as per consented quantity:
|
|
|
5.
|
All raw materials required per kg of the Products(s):
|
|
|
6.
|
Whether the manufacturing process is continuous or batch wise:
|
|
|
|
Indicate the batch capacity:
|
|
|
|
If the process is in batch operation, no. of batches/month along with
the duration of the completion of each batch:
|
|
|
7.
|
Detailed manufacturing Process with schematic flow diagram:-
|
|
|
|
List of unit operation and processes and with all chemical reactions
along with the time required (in hrs.) for
|
|
|
(C)
|
WATER
|
|
1.
|
The quantity of water consumed per day as per tones of product
manufactured:
(Attach water balance diagram)*over the last three years:
|
|
|
2.
|
The quantity of waste water (trade effluent) generated per tones of
each product per day, as well as per batch*over the last three years.
|
|
|
3.
|
The particulars of effluent treatment plant (Attach separate sheets)
|
|
|
|
Name and size of each unit
|
|
|
|
Capacity of ETP
|
|
|
|
Flow diagram and Hydraulic diagram, of ETP to be submitted:
|
|
|
|
Whether lighting arrangement around ETP is provided:
|
|
|
|
Whether separate energy meter is installed for effluent treatment
plant. If Yes -readings of the meter for consumption every month:
|
|
|
|
Calibration status and validity of energy meter
|
|
|
|
Whether flow meters are provided at the inlet and outlet of ETP. Please
indicate the type of the flow meter and calibration status if valid
|
|
|
4.
|
The method of disposal of final treated effluent and the point of
disposal (please attach sketch): Is it in line with the valid Consent
Requirements?
|
|
|
5.
|
The quantity of trade effluent at the inlet and outlet of ETP and at
various stages of treatment (Attach separate sheets):
|
|
|
6.
|
The quantity and quality of sewage and its method of treatment and
disposal (Attach separate sheets):
|
|
|
|
a) As per norms:
|
|
|
|
b) Total pollution load*:
|
|
|
7.
|
The open area available for disposal of the effluent
|
|
|
8.
|
Whether the quality of treated effluent meets the specified norms:
|
|
|
|
If no, the extent of deviation and reason thereof:
|
|
|
9.
|
Improvement in effluent quality and quantity since previous
environmental audit based on performance evaluation of effluent management
system:
|
|
|
|
If yes, provide details (Attach separate sheets):
|
|
|
10.
|
Retrofitting undertaking to improve performance of ETP:
|
|
|
|
If yes, provide details:
|
|
|
11.
|
Major problems encountered during operation of effluent treatment
facilities, if any and reasons thereof:
|
|
|
12.
|
The details about the Operator/Chemist responsible for operation and
maintenance of effluent treatment plant:
|
|
|
|
Name of the operators/employees:
|
|
|
|
Qualification & Experience of each Operator//employee whether
trained in such operation or not:
|
|
|
|
Salary of operators/employees.
|
|
|
|
Operator using PPE, pls specify type
|
|
|
|
Maintenance and downtime Register maintained and updated, Response time
for rectification
|
|
|
13
|
The current status of consent under the Water Act-1974:
|
|
|
D.
|
AIR
|
|
1.
|
No. of the flue gas stacks, their height (from ground level) nature and
consumption of fuel:
|
|
|
2.
|
The details pertaining to the stack monitoring facilities:
|
|
|
3.
|
Number of process stacks, their height (from ground level) source,
expected pollutants and the details pertaining to the provisions of stack
monitoring facilities:
|
|
|
4.
|
The quality of emission from each flue gas stack and the process stack
and the extent of deviation from them:
|
|
|
|
Pollution Load determination
|
|
|
5.
|
The ambient air quality within the factory premises, along with the
number of ambient air quality monitoring stations outside the industry:
|
|
|
6.
|
The status of consent under the Air Act-1981:
|
|
|
7.
|
The details of air pollution control measures for all process and flue
gas stacks
|
|
|
8.
|
Improvement in emission quality since previous environmental audit
based on performance evaluation of air pollution management system:
|
|
|
|
If yes, Provide details. (Attach separate sheets):
|
|
|
9.
|
Retrofitting undertaken to improve emission quality. If yes, provide
details:
|
|
|
10.
|
Major problems encountered during operation of control device, if any
and reasons there of:
|
|
|
11
|
equipment status
|
|
|
* Whether production is as per consented quantity
|
|
NOTE: Total pollution load each for air, water and hazardous waste
should have mentioned along with the quality of effluent, emission or solid
waste as the case maybe. Whether measures taken for reduction of pollution
load.
|
|
E.
|
HAZARDOUS (SOLID) WASTE
|
|
1.
|
The quantity, sources and composition of hazardous waste/solid waste
from each process/sources over the last three years. (Total sludge generation
per tonne of product):
|
|
|
2.
|
(a) The method of storage, treatment and disposal of hazardous/solid
waste:
|
|
|
|
The details should include area of storage and disposal and whether
storage and disposal system is covered and made impervious (pucca):
|
|
|
|
The quantity of Hazardous waste sent to TSDF.
|
|
|
|
Please also indicate how the quantity of hazardous/solid shall be
reduced in next three months:
|
|
|
|
(b) The data/information about leachate generation, quantity and
characteristics and treatment facility
|
|
|
3.
|
The status of authorization under the EPA-86 for solid waste
|
|
|
4.
|
Plan, if any to reduce hazardous waste generation or its recycling.
|
|
|
F.
|
SITE PLAN
|
|
1.
|
The site plan showing the location of effluent treatment plant, final
point of disposal of effluent, sampling point, drainage line, stacks, solid
waste storage, disposal area and green belt (its width).
|
|
|
(G)
|
RESOURCE RECOVERY
|
|
1.
|
The details regarding resource recovery including treated effluent for
recycle/reuse from environmental pollution control system including effluent
treatment plant:
|
|
|
|
The details regarding resource recovery/by product recovery from
manufacturing process by using cleaner production technology:
|
|
|
|
Energy/Fuel consumption/unit production
|
|
|
(H)
|
ACCIDENTS
|
|
1.
|
The details of accidents in the factory if any and remedial measures
taken
|
|
|
(I)
|
SAFETY MEASURES
|
|
1.
|
General Environment of the factory. Please tick (V) the appropriate
column
|
|
|
a.
|
Housekeeping
|
Good
|
Fair
|
Poor
|
|
|
b.
|
Dustiness
|
High
|
Medium
|
Low
|
|
|
c.
|
Lighting
|
Good
|
Fair
|
Poor
|
|
|
d.
|
Ventilation
|
Good
|
Fair
|
Poor
|
|
2.
|
Whether the following personal protective equipment PPC are provided to
all the workforce (employees & Contract Workers)
|
|
|
|
|
Is yes, How many?
|
|
|
Goggles
|
Yes/No (utilization level)
|
|
|
|
Gloves
|
Yes/No (utilization level)
|
|
|
|
Gumboot
|
Yes/No (utilization level)
|
|
|
|
Helmet
|
Yes/No (utilization level)
|
|
|
|
Skin cream
|
Yes/No (utilization level)
|
|
|
|
Soap
|
Yes/No (utilization level)
|
|
|
|
Ear plug
|
Yes/No (utilization level)
|
|
|
|
Face masks
|
Yes/No (utilization level)
|
|
|
|
Clothing
|
Yes/No (utilization level)
|
|
|
3.
|
The details of facilities for disaster management/gas leakage.
|
|
|
4.
|
Whether on site/off site emergency plans are prepared and are being
implemented/upgraded regularly; please give details
|
|
|
5.
|
Whether records of occupational hazards are maintained?
|
|
|
6.
|
Health checks conducted?
|
|
|
7.
|
Preventive measures adopted to minimize occupational hazard.
|
|
|
8.
|
Compliance with work exposure
|
|
|
9.
|
Noise level status
|
|
|
(J)
|
REMEDIAL MEASURES
|
|
1.
|
The details of sources; monitoring and measures taken for control of
noise pollution in and around the industrial premises:
|
|
|
2.
|
The measures taken for prevention treatment and control of odour
nuisance in and around the industrial premises:
|
|
|
3.
|
The details in respect of cases/complaints under the Water Act-1974,
the Air Act-1981 and the Environment (P) Act, 1986:
|
|
|
4.
|
The compliance report with respect to all the conditions of NOC/Consent
(Under all the Acts):
|
|
|
5.
|
Incidents of spillages, leakages etc. and remedial measures thereof
|
|
|
6.
|
Whether insurance policy obtained under PLI Act. Yes/No
|
|
|
(K)
|
WATER CESS
|
|
1.
|
The details regarding payment of the Water cess for the previous and
current year:
|
|
|
(L)
|
The name and address of the Consultant engaged by the Company/Industry
|
|
|
|
|
|
|
|
|
|
|
|
Note,
if No, reason thereof
|
It is hereby declared that all the information submitted in and with
respect to this format correct and we will be responsible for any lapse
regarding incorrect or incomplete information.
The Root Cause Analysis along with CAPA is attached here with.
|
|
A.
|
|
|
B.
|
|
|
|
Name and signature of the responsible persons industry/organization/Institute/CETP/TSDF
with the stamp
|
Name and signature of all the members of the Audit Team
|
|
Sr.
|
Name
|
Sign
|
Sr.
|
Name
|
Sign
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(H)
ADEQUACY CERTIFICATE OF ORGANISATION'S
ENVIRONMENTAL MANAGEMENT SYSTEM
Mr./Mrs./M/s._________________________________of___________________________is
recognized by the Goa State Pollution Control Board vide order
No.________________________ dated _________as an Environmental Auditor for the
purpose of the auditing, having carried Environmental audit of:
M/s
_______________________________________________
Located
at _____________________________________
Manufacturing
products:
Product
(s) ________________________________
Capacity
______________________________
Having
completed the environmental audit based on personal monitoring, and audit
report, prepared as per the notification via order no. _________ dated.
_________ . It is certified that the Environmental Management System (EMS)
provided by this industry for the products manufactured and capacity as stated
above is * ______________________ to achieve the quality of effluents (Air +
Waste Water + Solid Waste) as specified in Consent/Notifications by GSPCB,
Panjim for the following quantity of waste generation:
|
Liquid effluent
|
_________ m3/day
|
|
Solid/Hazardous waste
|
_________ m3/day
|
|
Air emissions (flue gas stacks as well as process stacks
|
Adequate/Not adequate.
Efficacious/Not efficacious
(pl. strike which is not applicable)
|
This
certificate is valid for the Audit report only. However, it is subject to
automatic cancellation in case of any change in product profile/capacity,
quality and quantity of effluent emission (Air + Waste Water + Solid/Hazardous)
and efficiency of EMS equipments.
This
Certificate forms part of Environmental Audit Report
Name
and address of the Environmental Auditor
Signature
of the Environmental Auditor
Date:
Place:
*here
write, whether adequate and efficient or inadequate and inefficient as
applicable
(I)
CERTIFICATE FOR SAMPLING AND ANALYSIS
This
is to certify that the following samples of emissions (air, water, waste water,
solid and hazardous wastes) have been collected and analysed as per the
following details:
|
Sample details
|
Sampling location
|
Collected by
|
Sample collection
|
Method of sample collection
|
Std. Analysis method
|
|
Date
|
Time
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.
|
Parameters analysed on site
|
|
|
2.
|
Parameters analysed off site
|
|
|
3.
|
Whether samples were preserved as per standard procedure for offsite
analysis: Yes/No
|
|
|
4.
|
Parameters analysed by auditors team:
|
|
|
5.
|
Parameters analysed by third party:
|
|
|
|
Name & Address of laboratory:
|
|
|
|
Whether the laboratory is classified under Schedule I of the GSPCB
|
|
|
6.
|
Method followed for analysis:
|
|
|
|
Air emission :
|
|
|
|
Water/Waste Water :
|
|
|
|
Solid Waste :
|
|
|
|
Hazardous Waste:
|
|
This
is to certify that the third party laboratory in which the analysis has been
done is approved under EPA/Accredited by NABL/recognised under GSPCB.
Name
and address of the Laboratory
Signature
of Authorised Signatory of the Laboratory
SCHEDULE
III
BUDGET AND ACCOUNT HEADS
[See rule 27(3)]
ADMINISTRATION
Head of Accounts (Expenditure)
(1) Salaries
(2) Wages
(3) Travel Expenses
(4) Office Expenses
(a) Furniture
(b) Postage
(c) Office
Machine/Equipment
(d) Liveries
(e) Telephones
(f) Electricity and Water
Charges
(g) Stationary
(h) Printing
(i) Staff car and other
vehicles
(j) Other items
(5) Fee and Honoraria
(6) Payment for
professional and special services
(7) Rents, rates and
Taxes/Royalty
(8) Publication
(9) Advertising, Sales
and Publicity Expenses
(10) Grants in
aid/Contribution/Subsidies
(11) Hospitality
Expenses/Sumptuary/Subsides
(12) Pensions/Gratuities
(13) Write off/Losses
(14) Suspenses
(15) Expenses in
connection with the setting up and maintenance of the Board Laboratory.
(16) Other charges (A
residuary head, this will also include rewards and prizes)
Head of Accounts (Receipts)
(1) Payments by
Government
(2) Fees
(3) Fines and other
Receipts.