Delhi Electricity Regulatory Commission
(Terms And Conditions For Green Energy Open Access) Regulations, 2024
[12th November 2024]
PREAMBLE
In exercise of powers conferred under Section 181 read with
Sections 42, 61(h), 66 and 86(1)(e) of the Electricity Act, 2003, the Delhi
Electricity Regulatory Commission hereby makes the following Regulations,
namely Delhi Electricity Regulatory Commission (Terms and Conditions for Green
Energy Open Access) Regulations, 2024 for implementation in the National
Capital Territory of Delhi.
Regulation 1. Short Title, Extent and Commencement.
(a) These Regulations
shall be called the Delhi Electricity Regulatory Commission (Terms and
Conditions for Green Energy Open Access) Regulations, 2024.
(b) These Regulations shall
extend to the whole of National Capital Territory of Delhi.
(c)
These Regulations shall come into force on the date of its
publication in the official gazette.
Regulation 2. Definitions.
In these Regulations, unless the context otherwise requires,
(a) "Act" means
the Electricity Act, 2003 (36 of 2003);
(b) "Applicant"
means an entity, trading licensee, distribution licensee or a Generator who has
applied for seeking Green Energy Open Access, as the case may be;
(c) "Appropriate
Commission" means the Central Regulatory Commission referred to in
sub-Section (1) of Section 76 or State Regulatory Commission referred to in
Section 82 or Joint Commission referred to in Section 83 of the Act, as the
case may be;
(d) "Banking"
means the surplus green energy injected in the grid and credited with the
distribution licensee by the Green Energy Open Access consumers and that shall
be drawn along with charges to compensate additional costs, if any;
(e) "Captive
Generating Plant" (CGP) means a power plant set up under Section 9 of the
Electricity Act, 2003 by any person to generate the electricity primarily for
its own use and includes a power plant set by any co-operative society or
association of persons for generating electricity primarily for use of members
of such co-operative society or association, which fulfills the conditions laid
down in the Electricity Act, 2003 and Rules framed thereunder;
(f) "Central
Commission" means the Central Electricity Regulatory Commission referred
to in subsection (1) of Section 76 of the Act;
(g) "Central Nodal
Agency" means a Central Nodal Agency as notified by the Central Government
to set up and operate a single window Green Energy Open Access system for Green
Energy (Renewable Energy) as specified by the Ministry of Power, GoI, in the
Electricity (Promoting Renewable Energy through Green Energy Open Access)
Rules, 2022;
(h) "Commission"
means the Delhi Electricity Regulatory Commission constituted under the Act;
(i) "Consumer"
means any person who is supplied with electricity for his own use by a licensee
or the Government or by any other person engaged in the business of supplying
electricity to the public under the Electricity Act, 2003 or any other law for
the time being in force and includes any person whose premises are for the time
being connected for the purpose of receiving electricity with the works of a
licensee, the Government or such other person, as the case may be;
(j) "Developer"
means the generating company which generates electrical energy from renewable
sources of energy;
(k) "Day Ahead Market
(DAM)" means a market where Day Ahead Contracts are transacted on the
Power Exchange(s);
(l)
"Entity" means any consumer who has contracted demand or
sanctioned load of Hundred (100) KW or more either through single connection or
through multiple connections aggregating Hundred (100) KW or more, connected at
11kV or above, located in the area of a same distribution licensee, except for
captive consumers.
Provided that there shall not be any load limitation for
setting up of Green energy projects for captive use with respect to the
consumers contract demand/sanctioned load (kW/MW, KVA/MVA) with Discoms;
(m) "Existing Open
Access Consumer/Customer" means a person already availing open access for
sourcing/supplying renewable (green) energy from/to the transmission system
and/or distribution system of the licensees in the State under an existing
agreement or Commissions Regulations/Orders on the date of coming into force of
these Regulations;
(n) "Fossil
Fuel" means fuels such as coal, lignite, gas, liquid fuel, or combination
of these as its primary source of energy, which are used in Thermal Generating
Station for generating electricity;
(o) "Green
Energy" means the electrical energy from renewable sources of energy
including hydro and storage (if the storage uses renewable energy) or any other
technology as may be notified by the Government of India from time to time and
shall also include any mechanism that utilizes green energy to replace fossil
fuels including production of green hydrogen or green ammonia and any other
sources as may be determined by the Central Government as per the provision of
Clause G of sub-rule (2) of rule 4 of Electricity (Promoting Renewable Energy
Through Green Energy Open Access), Rules 2022;
(p)
"Green Energy Open Access Consumer" means any person who
has contract demand or sanctioned load of Hundred (100) kW or more, either
through single connection or through multiple connections aggregating Hundred
(100) kW or more, connected at 11kV or above, located in electricity area of a
same distribution licensee, who is supplied with electricity from green energy
sources for his own use by a licensee or the Government or from its own Captive
Generation Plant or by any other person engaged in the business of supplying
electricity to the public under the Electricity Act, 2003 or any other law for
the time being in force and includes any person whose premises are for the time
being connected for the purpose of receiving green energy with the works of a
licensee, the Government or such person, as the case may be.
Provided that there shall not be any load limitation for
setting up of Green energy projects for captive use with respect to the
consumers contract demand/sanctioned load (kW/MW, KVA/MVA) with Discoms
availing power under Green Energy Open Access;
(q) "Open
Access" means the non-discriminatory provisions for use of transmission
lines and/or distribution system or associated facilities with such lines or
system by any licensees or consumers or a person engaged in generation in
accordance with the Regulations specified by the Appropriate Commission;
(r) "Person"
shall include any company or body corporate or association or body of
individuals, whether incorporated or not or artificial juridical person;
(s) "Premises"
includes any land, building or structure;
(t) "Renewable
Energy Sources" means Renewable Sources such as large hydro as specified
under Regulation 4(2)(a), small hydro, wind, solar including its integration
with combined cycle, biomass, bio fuel cogeneration, urban or municipal waste
and/or such other source(s) recognized by Ministry of New and Renewable Energy
(MNRE) or any other agency as notified by Government of India or the
Commission;
(u) "Rules"
means Rules made under the Electricity Act, 2003 including Electricity
(Promoting Renewable Energy Through Green Energy Open Access) Rules, 2022, as
amended from time to time;
(v) "State"
means the National Capital Territory of Delhi (NCTD);
(w) "State
Transmission Utility" means the Board or the Government company specified
as such by the State Government under sub-Section (1) of Section 39 of the Act;
(x)
"State Nodal Agency" (SNA) means the Nodal Agency for
grant of open access in the National Capital Territory of Delhi; Delhi State
Load Dispatch Centre shall operate as the State Nodal Agency for grant of
Short-Term Open Access to Intra-State Transmission System in conjunction with
or without Distribution Network of Distribution Licensee of the State.
The State Transmission Utility (STU) shall operate as a
State Nodal Agency for grant of MediumTerm and Long-Term Open Access to the
Intra-State Transmission Network in conjunction with or without Distribution
Network of Distribution Licensee of the State.
The Distribution Licensee shall operate as a Nodal Agency in
co-ordination with the SNA for grant of Open Access for the cases wherein the
inter-se location of drawl and injection points fall on the Distribution
Network of the concerned Distribution Licensee;
(y) "State Load
Dispatch Centre" means State Load Dispatch the Centre established under
sub-Section (1) of Section 31 of the Act;
(z)
"Standby Arrangement" means Standby Arrangement provided
by the distribution licensee in case the Green Energy Open Access consumer is
unable to procure / schedule power from the generating sources with which they
have the arrangement to avail the supply due to outages of such generators,
transmission assets and the like;
(aa) "Standby
Charges" means the charges applicable to green energy open access
consumers against the standby arrangement provided by the distribution licensee,
in case such green energy open access consumer is unable to procure/schedule
power from the generating sources with which they have the agreements to
procure, power due to outages of generator, transmission systems and the like;
(bb)
"Wheeling" means the operation whereby the distribution system and
associated facilities of transmission licensee or distribution licensee, as the
case may be, are used by another person for the conveyance of electricity on
payment of charges to be determined under Section 62 of the Act;
Regulation 3. Interpretation of Regulations.
In the interpretation of these Regulations, unless the
context otherwise requires:
(a) Words and expressions
used and not defined in these regulations but defined in the Act or Rules, the
IEGC or State Grid Code or State Distribution Code or State Electricity Supply
Code shall have the meaning assigned to them under the Act or Rules, IEGC or
any other Regulations notified by the Commission as the case may be.
(b) The General Clauses
Act, 1897 (10 of 1897) as amended from time to time, shall apply for the
interpretation of these regulations as it applies for interpretation of an Act
of Parliament.
(c) Words in the singular
or plural term, as the case may be, shall also be deemed to include the plural
or the singular term, respectively.
(d) The terms
"include" or "including" shall be deemed to be followed by
"without limitation" or "but not limited to" regardless of
whether such terms are followed by such phrases or words of like import.
(e) References herein to the
"Regulations" shall be construed as a reference to these Regulations
as amended or modified by the Commission from time to time in accordance with
the applicable laws in force.
(f) The headings are
inserted for convenience and may not be taken into account for the purpose of
interpretation of these Regulations.
(g) References to the
Statutes, Regulations or Guidelines shall be construed as including all
statutory provisions consolidating, amending, or replacing such Statutes,
Regulations or Guidelines, as the case may be, referred to.
(h)
In case of inconsistency between any provisions of these
Regulations and any other Regulations or order passed by the Commission, the
principle of harmonious interpretation shall be applied. Even thereafter, if
inconsistency persist, the provisions of these Regulations shall prevail.
Regulation 4. Scope.
These Regulations shall be applicable for allowing Open
Access to electricity generated from green energy sources, as defined herein
above, and also to the energy from non-fossil fuel based Municipal Solid
Waste-toEnergy or Refuse-Derived Fuel (RDF) plants for use of Intra-State
Transmission System (InSTS) or distribution system or both in the State
including Intra-State Transmission System(s) (InSTS) and/or Distribution System
(s) which are incidental to Inter- State Transmission of electricity.
Regulation 5. Criteria for Allowing Green Energy Open Access.
(a) The Long-Term Green
Energy Open Access shall be allowed in accordance with the transmission
planning criteria and distribution business plan.
(b) The
Short-Term/Medium-Term Green Energy Open Access shall be allowed, if the
request can be accommodated, by utilizing:
(i) Inherent design
margins;
(ii) Margins available due
to variation in power flows and;
(iii) Margins available due
to in-built spare transmission system capacity and/or distribution system
capacity created to cater to future load growth;
(c) Installation of
energy meter i.e., ABT compliant meter at generator end as well as at consumer
end seeking open access for 1 MW and above. While in case of consumer seeking
open access below 1 MW, installation of Special Energy Meter capable of energy
recording on 15 minutes time block basis.
(d)
No dues of concerned licensee and/or SNA.
Regulation 6. Categorization of Green Energy Open Access.
The Green Energy Open Access consumers shall be classified
into the following categories based on the duration of use of the Intra- State
transmission and/or distribution system:
(a) " Long-term
Green Energy Open Access" means the right to use the intra-State
transmission system and/or distribution system for a period exceeding five
years but not exceeding 25 years.
(b) " Medium-term
Green Energy Open Access" means the right to use the intra-State
transmission system and/or distribution system for a period exceeding eleven
months but not exceeding five years.
(c)
" Short-Term Green Energy Open Access" means open access
for a period up to eleven months.
Provided that on expiry of Short-term Green Open Access,
irrespective of the period for which the same was granted, if such consumer
desires to avail the Short-Term Green Energy Open Access for a further period,
it shall be required to file a fresh application and the priority shall be
fixed on the basis of date of submission of such fresh application.
Regulation 7. Application procedure for Green Energy Open Access.
(a)
All applications for Green Energy Open Access shall be made in the
prescribed Form along with necessary documents, details, and fee if any, to be
submitted to the Central Nodal agency in accordance with these Regulations. The
applications shall be forwarded to the State Nodal Agency (SNA) by the Central
Nodal Agency.
The State Nodal Agency (SNA) shall forward the Application
to the concerned Distribution Licensee for the cases wherein the inter-se
points of drawl and injection falls on the Distribution Network of the
respective Distribution Licensee and concerned Distribution Licensee shall
process the application in accordance with these Regulations.
Provided that, till such time, the procedures and formats
are devised by Central Nodal Agency, the existing procedures / formats laid
down by the respective State Nodal Agency for granting open access may be
followed in the matter.
(b)
All applicants seeking Green Energy Open Access shall submit an
undertaking of not having entered into Power Purchase Agreement (PPA) or any
other bilateral agreement with more than one person for the capacity (quantum
of power) for which Green Energy Open Access is sought.
Notwithstanding anything contained in Regulation 7(b) above,
a drawee entity (consumer/distribution licensee) shall be eligible to enter
into Power Purchase Agreement (PPA) or any other bilateral agreement with more
than one person within the quantum of Green Energy Open Access granted or
sought by it.
(c)
The State Nodal Agency shall coordinate with transmission
licensees including STU and the Distribution Licensees to make available all
relevant information regarding green energy open access to the public on the
portal of the Central Nodal Agency.
Regulation 8. Eligibility Criteria for applying Green Energy Open Access.
(a)
The Consumer who has contracted demand or sanctioned load of
Hundred (100) KW or more, connected at 11kV or above, either through single
connection or through multiple connections aggregating Hundred (100) kW or more
located in area of a same distribution licensee, shall be eligible for Open
Access for sourcing Green Energy (RE) under these Regulations.
Provided that in case of a consumer having Captive
Generating Plant, there shall not be any load limitation in terms of contract
demand/sanctioned load (kW/MW, KVA/MVA) with Discoms.
(b) For a minimum number
of 12 time blocks, the consumer shall not change the quantum of power consumed
through Green Energy Open Access so as to avoid high variations in demand to be
met by the distribution licensee.
(c)
Subject to the provisions of these Regulations and system
availability, consumers, licensees and/or generating company shall be eligible
for Green Energy Open Access to the Intra-State Transmission System of the
State Transmission Utility or any Transmission Licensee(s) and/or Distribution
System(s) of the Distribution Licensee within the State on payment of
transmission, wheeling charges and other charges as may be determined by the
Commission from time to time. The Green energy open access consumer shall have
to install ABT Compliant meters/Special Energy Meter at their place for energy
accounting and Remote Terminal Unit (RTU) to facilitate SLDC in real time
monitoring, which shall be duly certified by the licensee concerned.
Provided that Green Energy Open Access consumer seeking open
access below 1 MW, shall be allowed based on installation of Special Energy
Meter capable of energy recording on 15 minutes time block basis.
Provided that notwithstanding anything contained in these
Regulations, any Green Energy (RE) Generating Company having subsisting Power
Purchase Agreement (PPA) with the Distribution Licensee, shall not be entitled
to Green Energy Open Access for the Green Energy (RE) capacity, for which PPA
is entered into as well as for any capacity (quantum of power) for which Open
Access is already granted, except in accordance with the terms of such PPA.
(d) Every person, who has
constructed a Captive Generating Plant (CGP) shall have the right to open
access as per the provisions of Section 9 and other provisions of the Act read
with Rules and Regulations framed under the Act and Order(s) of the Commission
on the subject matter.
(e)
The consumer seeking Green Energy Open Access shall submit the application
to the Central Nodal Agency.
Regulation 9. Allotment Priority.
(a) Distribution licensee
shall have the highest priority over other Green Energy Open Access consumers.
(b) Green Energy Open
Access consumers shall have preference (priority) over normal Open Access
consumers in the same category of open access.
(c)
Amongst the Green Energy Open Access consumers, Long-Term Green
Energy Open Access consumers shall have preference (priority) followed by
Medium-Term Green Energy Open Access consumers and subsequently Short-Term
Green Energy Open Access consumers, at any given time, subject to availability
of spare transmission/distribution system capacity margins.
Provided that the Green Energy Open Access shall be granted
on a first-come, first-serve basis.
Regulation 10. Procedure for grant of Green Energy Open Access.
(a)
Once the application is forwarded to the concerned State Nodal
Agency by the Central Nodal Agency for further verification, the same shall be
decided by the State Nodal Agency within 15 days from the date on which the
application is received by State Nodal Agency from Central Nodal Agency.
The following time schedules shall be followed for
processing the Application:
Sr. No. |
Particulars |
Time-Line |
Remarks |
1 |
Date on
which application is received by State Nodal Agency from Central Nodal
Agency. |
T0 =
Zero Date |
|
2 |
Acknowledgement
of receipt of Application. |
T0
= Zero Date |
The
acknowledgement shall be provided immediately by electronic mode. |
3 |
Acceptance
of application by State Nodal Agency after confirming that all the relevant
documents are furnished by the applicant including processing fees and BG. |
T0
+ 1 working day |
In
case the application is incomplete, the State Nodal Agency shall inform the
same to the applicant in writing and reject the application furnishing the
details of the defects. After rectifying the defects, a fresh application
shall be required to be made. |
4 |
Forwarding
of application to STU / concerned DISCOMs. |
T0
+ 3 working days |
On
acceptance of the application, the same shall be forwarded to STU/concerned
DISCOMs for ensuring the system availability, metering infrastructure, no
pending dues and that there is no subsisting PPA for the capacity for which
the Green Energy Open Access is sought. |
5 |
Intimation
from STU/ DISCOMs. |
T0
+ 7 working days |
Upon
the receipt of application STU/DISCOMs shall carry out the system study, to
assess availability of all necessary infrastructure and other infrastructure,
if required, and confirmation of no pending dues. |
In
case margin is available in the network and also availability of necessary
infrastructure then STU/DISCOMs shall intimate to the State Nodal Agency
about validity of the application. |
|||
In
case of Long Term Open Access LTOA), if system strengthening is required, STU/DISCOM
shall intimate to the Applicant and State Nodal Agency regarding the work
involved for system strengthening. |
|||
In
case system strengthening is required, probable date of granting Green Energy
Open Access shall be intimated to State Nodal Agency within the same time. |
|||
In
case intimation is not received within the specified time from STU/DISCOM, as
the case may be, the State Nodal Agency shall deem it to be a valid
application. |
|||
Provided
that the system studies at the drawl point to ascertain the availability of
necessary infrastructure is not required for a consumer of the licensee
availing Open Access, subject to the applicant furnishing an undertaking
that, he would not exceed the contract demand specified in his supply
agreement with the licensee even after opting for green energy Open Access. |
|||
Provided
that there shall not be any load limitation for setting up of Green energy
projects for captive use with respect to the consumers contract
demand/sanctioned load (kW/MW, KVA/MVA) with Discoms availing power under
Green Energy Open Access. |
|||
6 |
Intimation
by State Nodal Agency to the Applicant. |
T0
+8 working days |
The
State Nodal Agency shall intimate the Applicant, regarding the validity of
the Application for grant of Green Energy Open Access within the time
specified. |
In
case Green Energy Open Access cannot be granted, the same shall be intimated
by the State Nodal Agency to the Applicant within the above time furnishing
the reasons in writing for non-grant of Green Energy Open Access sought. |
|||
In
case, State Nodal Agency fails to intimate the grant of Green Energy Open
Access or otherwise, within the above specified time, the same shall be
deemed to have been granted, to be subject to system availability. |
|||
7 |
Submission
of signed Agreement by the applicant for MediumTerm and Long-Term Green
Energy Open Access. |
T0
+ 10 working days |
The
applicant shall submit signed Transmission and/or Wheeling Agreement to the
licensee to be executed and obtain due acknowledgment of the designated
authority notified by the concerned licensee for such submission. |
In
case the Applicant fails to submit the Transmission and/or Wheeling Agreement
within the specified time, the Open Access granted shall be deemed to have
been cancelled. |
|||
8 |
Execution
of agreement by STU/ DISCOMs and return of the executed agreement to the
applicant. |
T0
+ 13 working days |
The
concerned authority will ensure execution of Agreement with the Applicant
within three days and shall also provide the copy of such executed Agreement
and obtain due acknowledgment of the applicant. |
The
time limit for signing of Transmission Agreement by STU and Wheeling
Agreement by distribution licensee shall be three days, even where it is
required to sign both the Agreements. |
|||
The
Transmission and Wheeling Agreement to be executed, shall be in the standard
format, which shall be prepared by State Nodal Agency. Agency
/ licensee(s) as approved by the commission. The
existing wheeling/transmission agreement as modified and as approved from the
commission for RES and nonREC route projects om accordance with these
regulations shall be adopted. |
|||
9 |
Submission
of signed copies of the executed agreement/Undertaking by the applicant to
SNA. |
T0
+ 15 working days |
Thereafter,
the Applicant within two days of receipt of such executed Agreement(s) shall
submit copy(ies) of signed Transmission and/or Wheeling agreement to the
State Nodal Agency and the State Nodal Agency shall provide acknowledgement
of receipt. |
In
case STU / DISCOMs fail to sign and execute the Transmission and/or Wheeling
Agreement submitted by the applicant within the specified time above, the
Transmission and/or Wheeling Agreement shall be deemed to have been executed. |
|||
In
case of deemed execution, the provisions of standard Agreement(s) approved by
the Commission shall be applicable and binding. |
|||
In
case of deemed execution of agreement(s), the applicant shall be allowed
transmission and / or wheeling of energy from the effective date subject to
filing of an ‘Undertaking’ on affidavit that it shall avail the transmission
and / or wheeling of energy and terms & conditions of the deemed approved
Agreement(s) are binding on it. |
|||
10 |
Effective
date for wheeling. |
In
case the State Nodal Agency receives from the applicant the copy(ies) of the
executed agreement(s)/ ‘Undertaking’ on Affidavit with regard to deemed
execution of agreement, as the case may be, the effective date for
commencement of Green Energy Open Access of the applicant shall be the next
date from the day of submission of Executed copy(ies) of the
agreement(s)/undertaking to the State Nodal Agency. |
The
applicant shall be allowed to wheel the energy from the effective date. |
(b) An application for
open access shall be accompanied with the proof of payment of a non-refundable
processing fee, as detailed herein below, to the State Nodal Agency:
(i)
Rupees Fifty Thousand for Long-Term Green Energy Open Access,
(ii)
Rupees Twenty-Five Thousand for Medium-Term Green Energy Open
Access, and
(iii)
Rupees Five Thousand for Short-Term Green Energy Open Access.
(c) An application for a Short-Term
Green Energy Open Access, for Green Energy Generating plant(s) or its/their
generating unit(s) which are yet to be commissioned, shall be submitted not
before two months prior to the commissioning date of such Green Energy
Generating plant(s) or its/their generating unit(s), to avoid unnecessary
blocking of corridor.
(d) An application for
Long-Term/Medium-Term Green Energy Open Access shall be accompanied by a Bank
Guarantee (BG) of Rupees Fifty thousand (Rs. 50,000/-) for Green Open Access
capacity less than 1 MW and Rupees One lakh per MW (Rs. 1,00,000/- per MW) for
1 MW & above which shall be kept valid and subsisting till the signing of
agreement for transmission and/or wheeling of electricity and such BG shall be
encashed by the State Nodal Agency, if the application is withdrawn by the
applicant prior to the signing of such agreement. On signing of the agreement for
transmission and/or wheeling of electricity, the BG shall be returned within 25
working days to the applicant by the State Nodal Agency.
(e) In case there is any
material change with regards to the location of the injection point or quantum
of power to be interchanged using the intra-State transmission and/or
distribution system, a fresh application shall be required to be submitted for
the entire capacity to ascertain the system availability and such application
shall be accompanied by relevant documents and application fees. Moreover, in
case of LongTerm and Medium-Term Green Energy Open Access, bank guarantee shall
also be required to be furnished for the additional capacity. It is also
clarified that in case the additional capacity sought for cannot be accommodated
in the existing network, the applicant shall be entitled to Green Energy Open
Access to the extent of his original allotment.
(f) The Bank Guarantee
(BG) shall be returned by the State Nodal Agency (SNA) within 25 working days; (i) from the date
of submission of signed agreement by open access consumer to the State Nodal
Agency (SNA), in case of deemed approval considered for open access; (ii) from
the date of rejection of application for open access by SNA on ground of
non-availability of margin in the network and; (iii) from the date of rejection
of application by SNA due to any deficiency or defect. In case of rejection of
application on a ground of any deficiency or defect a fresh application to the
Central Nodal portal shall be required to be submitted by the applicant after
curing the deficiency or defect.
(g) The State Nodal
Agency shall communicate to the applicant through a recognized mode of communication regarding the grant
of Green Energy Open Access or otherwise.
(h) Further, during the
pendency of application for grant of Green Energy Open Access, the applicant shall not inject any
energy to the licensees network and the licensee shall not be liable to pay any
charges for the energy injected during such period if any.
(i) The Transmission
Licensee(s), Distribution Licensee(s), SLDC and STU shall ensure proper
coordination while arranging for Green Energy Open Access.
(j)
New Green Energy (RE) generating plant(s) or generating Unit(s) or
generating company(ies) which has/have obtained connectivity on its name, shall
apply for seeking Long-Term Green Energy Open Access and enter into agreement
for wheeling and/or transmission on its name, and shall commission such
plant(s) or unit(s) within twenty-four months from the date of Green Energy
Open Access Application, or the schedule date of commencement of open
access/COD of the plant as specified in the respective PPA/transmission
agreement/wheeling agreement, whichever is earlier, as case may be, failing
which, the Green Energy Open Access granted shall be deemed to have been
cancelled, to avoid unnecessary blocking of the corridor.
Provided that in case
the project developer is ready for commissioning of the project but such
projects are unable to commission due to non-availability of transmission/distribution
network on account of failure of licensee, such generator or generating company
shall have the liberty to approach the Commission, with supporting documentary
evidence, for extension of COD, preferably, prior to three (3) months from the
date of the completion of timelines as specified above.
(k) A Green Energy Open
Access consumer shall enter into commercial agreements with generators or
generating company, trading licensee, distribution licensee, as may be
applicable, and such agreements shall include provisions pertaining to payment
security mechanism.
(l) The State Nodal
Agency shall host on its website the details of every application received from
the Central Nodal Agency and update the status of such application on a
continuous basis, which shall be made available to the public.
(m)
The State Nodal Agency/Distribution Licensee shall prepare
procedure for grant of Green Energy Open Access consisting of documents,
formats etc. required to be submitted for Green Energy Open Access in line with the
provisions of the Act, Rules, Regulations, Orders and Procedure followed by
Central Nodal Agency, for smooth implementation of the Green Energy Open Access
in the State and get the same approved from the Commission within 90 days from
the date of Notification of these Regulations.
Regulation 11. Procedure for applying for Day Ahead Green Energy Open Access Transactions.
(a)
The applicant shall apply to the Central Portal for Day Ahead
Green Energy Open Access Transactions in the standard application format. For
the applications received by the State Nodal Agency from the Central Nodal
Agency, before 13:00 hours of the day immediately preceding the day of
scheduling for day-ahead Green Energy Open Access transaction, the State Nodal
Agency shall check for congestion in the system and convey grant of approval or
otherwise to the applicant through e-mail or fax, not later than 15:00 hours of
the day immediately preceding the day of scheduling for day-ahead transaction,
after ensuring that there is no subsisting PPA for the capacity sought under
Green Energy Open Access.
Provided that where
Green Energy Open Access is denied, the State Nodal Agency shall furnish
reasons thereof to the applicant.
(b)
Non-refundable processing fee of Five Thousand Rupees for each
transaction shall be paid by the applicant, in the manner as prescribed by the
State Nodal Agency like by way of a demand draft or payment through electronic
transfer in favour of the State Nodal Agency.
Provided that the
actual operationalization of Green Energy Open Access shall be effected subject
to payment by the applicant of the charges as specified in these Regulations
and orders passed by the Commission from time to time, before 17:00 hours of
the day immediately preceding the day of scheduling for day-ahead transaction.
Provided further that
for a minimum of 12 time-blocks, the consumer shall not change the quantum of
power consumed through open access so as to avoid high variations in demand to
be met by the distribution licensee.
Regulation 12.
[***]
Regulation 13.
[***]
Regulation 14. Utilization, Non-Utilization of Service by Green Energy Open Access Consumers.
A
medium-term/long-term consumer shall not relinquish his rights and obligations
specified in the Green Energy Open Access agreement without prior approval of
the State Nodal Agency/licensee. The relinquishment of such rights and
obligations by a long-term and medium-term consumer shall be subject to payment
of compensation, as per the provisions of these Regulations.
Regulation 15. Charges for Green Energy Open Access.
The charges on Green
Energy Open Access consumers shall be as follows:
(a)
Transmission charges;
(b)
Wheeling charges;
(c)
Cross subsidy Surcharge;
(d)
Additional Surcharge;
(e)
Standby Charges wherever applicable;
(f)
Banking facility and Charges;
(g)
Other fees and charges such as SLDC fees, scheduling charges,
deviation settlement (DSM) charges as per the relevant Regulations, Orders of
the Commission, transaction charges, Regulatory Surcharge, Metering Charges,
Payment of statutory levies/taxes by Open Access Consumers and Pension Trust
Surcharge.
(h)
Relinquishment and its Charges
(i)
Any other charges as defined by Commission by separate order
Provided that all green energy open access consumer shall be
exempted from the Wheeling, Transmission, Cross Subsidy Surcharge and
Additional Surcharge to the extent of quantum of RPO compliance.
13.1 Transmission
Charges
Green Energy Open Access Consumer using transmission system shall
pay the charges as stated hereunder:
(a)
For use of inter-State transmission system:
As specified by the Central Commission from time to time.
(b)
For use of intra-State transmission system:
The Transmission Charges for Long-Term, Medium-Term and
Short-Term Green Energy Open Access shall be as per the prevailing provisions
of the Regulations and/or Orders passed by the Commission from time to time.
The applicable rate of Transmission Charge and transmission
losses payable by Green Energy Open Access Consumer shall be specified by the
Commission in its Tariff Order.
13.2 Wheeling Charges
(a)
Wheeling charges payable to distribution licensee, by the Green
Energy Open Access Consumer for usage of its system shall be as determined by
the Commission in the tariff order from time to time:
(i)
The Commission shall specify the wheeling charge of the
Distribution Licensee.
(ii)
The rate of Wheeling Charge payable by Green Energy Open Access
Consumer shall be specified by the Commission in its Tariff Order.
(iii)
Wheeling Charge for Green Energy Open Access shall be computed in
Paisa/kWh and it shall be charged on the energy wheeled.
(b)
In addition to Wheeling Charge, Wheeling loss shall be applicable
to green energy open access consumers or generator, as the case may be, seeking
Green Energy Open Access and it shall be as determined by the Commission in the
tariff order from time to time.
(c)
Wheeling charges, wheeling losses shall not be applicable in case
green energy open access consumer is connected to the transmission system directly
or using dedicated lines owned by the consumer or generating station.
13.3 Cross Subsidy
Surcharge
(a)
The Green Energy Open Access consumer shall be required to pay
cross subsidy surcharge as provided in relevant Tariff Orders issued by the
Commission from time to time, in addition to transmission and/or wheeling
charges. Cross subsidy surcharge determined by the Commission on Per Unit basis
shall be payable, on billing cycle basis, by the open access consumers based on
the energy consumed during the billing period through open access. The amount
of surcharge shall be paid to the distribution licensee in whose area of supply
such consumer is situated.
(b)
The Cross-subsidy surcharge shall be determined by the Commission
in accordance with the provisions of the Electricity Act, 2003 read with the
principles and formula stipulated in the Tariff Policy notified by the Ministry
of Power, Govt. of India.
Provided that such cross-subsidy surcharge shall not be
levied in case distribution/transmission access is provided to a person who has
established a captive generation plant for carrying the electricity to the
destination of his own use.
Provided further that the cross-subsidy surcharge for Green
Energy Open Access Consumer purchasing green energy, from a generating plant
using green energy (renewable energy) sources, shall not be increased, during
twelve years from the date of operating of the generating plant using renewable
energy sources, by more than fifty percent of the surcharge fixed for the year in
which open access is granted.
Provided also that Cross Subsidy Surcharge shall not be
applicable in case power produced from a non-fossil fuel-based Municipal Solid
Waste-to-Energy or Refuse-Derived Fuel (RDF) plant is supplied to the Green
Energy Open Access Consumer.
Provided also that Cross Subsidy Surcharge shall not be
applicable in case if green energy is utilized for production of green hydrogen
and green ammonia.
(c)
Cross-subsidy surcharge for green energy open access shall be
computed in Paisa/kWh and shall be charged on the energy consumed by the
consumer under green energy open access.
13.4 Additional
Surcharge
(a)
The Green Energy Open Access consumers are required to pay the
Additional Surcharge as determined by the Commission with consideration of
provisions of the Act, Rules, Regulations and Orders of the Commission from
time to time. The Additional Surcharge levied on Green Energy Open Access
consumer shall not be more than the per unit fixed cost of power purchase of
the distribution licensee concerned.
(b)
The Additional Surcharge shall not be applicable to the Green
Energy Open Access consumer to the extent of contract demand being maintained
with the distribution licensee.
Provided that in case the quantum of Green Energy Open
Access availed by the Green Energy Open Access consumer is more than the
contracted demand / sanctioned load with the licensee and no fixed charge or
demand charge is being paid or payable for additional quantum, in that case the
Additional Surcharge determined by the Commission from time to time as per the
Orders of the Commission shall be applicable for such additional quantum
availed over the contracted demand / sanctioned load.
Provided that for a person availing Green Energy Open
Access, the Additional Surcharge shall be linearly reduced from the value in
the year in which Green Energy Open Access was granted so that, if it is
continued to be availed by this person, the Additional Surcharge shall get
eliminated within four years from the date of grant of Green Energy Open
Access.
Provided further that such additional surcharges shall not
be levied in case distribution/transmission access is provided to a person who
has established a Captive Generation Plant for carrying the electricity to the
destination of his own use.
Provided also that Additional Surcharge shall not be
applicable in case power produced from a Municipal Solid Waste-to-Energy plant
or Refuse-Derived Fuel (RDF) is supplied to the Green Open Access Consumer.
Provided also that Additional Surcharge shall not be
applicable in case if green energy is utilized for production of green hydrogen
and green ammonia.
Provided further that additional surcharge shall not be
applicable in case of electricity produced from offshore wind projects, which
are commissioned upto December, 2032 and supplied to the Open Access Consumers.
13.5 Standby charges
for drawl of power by Green Energy Open Access consumer from distribution
licensee In case the green energy open access consumer is unable to
procure/schedule power from the generating sources with whom they have the
arrangement to procure power due to outages of generator, transmission systems
and the like, standby arrangement shall be provided to Green Energy Open Access
consumer by the distribution licensee of the area of its supply and the
licensee shall be entitled to collect Standby charges which shall be 125% of
the normal tariff of the relevant consumer category in the prevailing rates
schedule specified in Tariff Order passed by the Commission.
Provided that the standby charges shall not be applicable,
if the green energy open access consumer has given notice, at least a day in
advance before closure time of Day Ahead Market on "D - (minus) 1"
day, "D being the day of delivery of power for standby arrangement to the
distribution licensee.
Provided also that Green Energy Open Access consumers would
have the option to arrange standby power from any other source.
Standby charge for green energy open access shall be
computed in Paisa/kWh
13.6 Banking Facility
and Charges
(a)
Banking facility shall be permitted to the intra state consumers
availing Green Energy Open Access.
(b)
Banking facility shall be permitted at least on a monthly/billing
period basis on payment of charges to compensate additional cost, if any, to the
distribution licensee by the banking.
(c)
For the purpose of these Regulations, the banking means surplus
green energy injected in the grid in 15 minutes time block basis and credited
with the distribution licensee energy by the Green Energy Open Access consumers
and that shall be drawn along with charges to compensate the distribution
licensee by the open access consumer.
(d)
The banking of energy shall be evaluated for energy accounting on
15 minutes time block basis. The difference between the injected energy from
green energy generator available at consumption point and consumers consumption
in same 15 minutes time block basis shall be considered as banked energy.
(e)
The consumption of banked energy Peak Period , Off Peak Period
& Normal Hours ( as defined in Time of Day -ToD period specified in the
Tariff Orders of the Commission for respective distribution licensees from time
to time ) shall be permitted on billing cycle basis in the following manner:
(i)
In the billing cycle, the banked energy, if any, available during
peak period , shall be allowed to be utilized during the peak period, Normal
hours and the off-peak period by the Green Energy Open Access consumer.
(ii)
The banked energy available during Normal hours shall be utilized
only during Normal hours & offpeak period by the green energy open access
consumer.
(iii)
The banked energy available during off-peak period shall be
utilized only during off-peak period by the green energy open access consumer.
(f)
The permitted quantum of banked energy by the green energy open
access consumers shall be at least 30% of total consumption, only electricity
directly procured from the distribution licensee shall be considered.
Electricity obtained through Open Access arrangement either from a third-party
supplier or via captive generation utilizing the distribution network, will be
excluded from this calculation.
(g)
When the generator situated in the State or outside the State,
connected with the Inter-State Transmission System (ISTS) grid and directly
supplying power to consumer(s) situated in the State, who are only connected
with Inter-State Transmission System/Grid but not connected with State
Transmission Network and/or Distribution System of State, the provisions
related to banking facility shall be governed as per applicable CERC
Regulations read with MoP Rules.
(h)
The Banking charges shall be adjusted in terms of quantum of the
energy banked (kWh) @8% of the energy banked.
(i)
When the Green Energy generator is situated either in State of
NCTD or outside the State of NCTD and connected with Inter-State Transmission
System/Grid and supplying power to the consumer connected with Intra-State
Transmission and/or Distribution System of the State, in that case, the banking
facility shall be governed as per the applicable CERC Regulations read with MoP
Rules.
(j)
The credit for banked energy shall not be permitted to be carried
forward to subsequent billing cycles and shall be adjusted during the same
billing cycle in a manner specified under these Regulations.
Provided that the unutilized surplus banked energy shall be
considered as lapsed at the end of each billing cycle and the renewable energy
generating station shall be entitled to get Renewable Energy Certificate (REC)
to the extent of the lapsed banked energy as per applicable Regulations.
13.7 Other Charges
and Fees
(a)
Scheduling charges
The Green Energy Open Access consumers shall require to pay
scheduling charge of Rs. 2000/ day/approval for Short-Term Open Access and in
case of Long-Term Open Access and Medium-Term Open Access the same shall be as
per Tariff Order of the Commission with regard to SLDC for respective year.
(b)
Payment Security Mechanism
At the time of submissions of signed Agreement for
transmission and/or wheeling of electricity, the Green Energy Open Access
consumer seeking open access for Long-Term Open Access, Medium-Term Open
Access, shall require to provide an irrevocable Revolving Letter of Credit (LC)
or Bank Guarantee (BG) in favour of the agency responsible for collection of
various charges specified in these Regulations for the estimated amount of
various charges for a period of two months. While in case of Short-Term Open
Access, the payment security shall be provided by the Green Energy Open Access
consumer in advance for the entire period for which open access is sought. In
absence of valid payment security instrument as stated above to be provided by
the green energy open access consumer, no open access shall be granted.
Such LC/BG must be available to the State Nodal Agency
and/or licensee during the entire period of Green Energy Open Access granted by
them and availed by the open access consumer. Failure to provide above
mentioned valid financial instruments as payment security to the State Nodal
Agency, and/or licensee, the green energy open access granted shall be deemed
to be cancelled.
13.8 Relinquishment
and its Charges
Option for relinquishment of Under-Utilization or
Non-Utilization of open access capacity in intra-State transmission
system/distribution systems by Green Energy Open Access consumers shall be
subject to the following conditions and charges:
(a)
Long-term access:
A long-term Green Energy Open Access consumer may relinquish
the long-term access rights fully or partly before the expiry of the full term
of long-term access, by making payment of compensation for the Stranded
relinquishment capacity sought, as follows: -
(i)
Long-term Green Energy Open Access consumer who has availed access
rights for at least 5 years
(1)
Notice of one (1) year - If such a Green Energy Open Access
consumer submits an application to the State Transmission Utility/Transmission
Licensee and/or Distribution Licensee at least 1 (one) year prior to the date
from which such consumer desires to relinquish the access rights, there shall
be no charges.
(2)
Notice of less than one (1) year - If such a Green Energy Open
Access consumer submits an application to the State Transmission
Utility/Transmission Licensee and/or Distribution Licensee at any time less
than a period of 1 (one) year prior to the date from which such consumer desires
to relinquish the access rights, such consumer shall pay an amount equal to 66%
of the transmission charges and/or wheeling charges for the stranded
transmission capacity and/or Distribution Capacity requested for the period
falling short of a notice period of one (1) year.
(ii)
Long-term Green Energy Open Access consumer who has not availed
access rights for at least 5 (Five) years
4. Such consumer shall pay an amount equal to
66% of the estimated transmission charges and/or wheeling charges (net present
value) for the relinquishment of stranded transmission capacity and/or
distribution capacity requested for the period falling short of 5 (five) years
of access rights:
Provided that such a Green Energy Open Access consumer shall
submit an application to the State Transmission Utility/Transmission Licensee
and/or Distribution Licensee at least 1 (one) year prior to the date from which
such consumer desires to relinquish the access rights:
Provided further that in case a Green Energy Open Access consumer
submits an application for relinquishment of long-term access rights at any
time by serving a notice period of less than one year, then such consumer shall
pay an amount equal to 66% of the estimated transmission charges and/or
wheeling charges(net present value) for the period falling short of a notice
period of one (1) year, in addition to 66% of the estimated transmission
charges and/or wheeling charges(net present value) for the relinquishment
transmission capacity and/or distribution capacity requested for the period
falling short of 5 (five) years of access rights.
5. The discount rate that shall be applicable
for computing the net present value as referred to in sub- clause (a)(ii)(1) of
clause (13.8) above, shall be as per the discount rate specified for bid
evaluation in the Ministry of Powers Guidelines for Determination of Tariff by
Bidding Process for Procurement of Power by Distribution Licensees or any
related notifications issued by the Central Commission from time to time.
6. The compensation paid by the long-term Green
Energy Open Access consumer for the relinquished transmission capacity and/or
distribution capacity shall be used for reducing transmission charges payable
by other long-term Open Access consumer and medium-term Open Access consumer in
the year in which such compensation payment shall become due in the ratio of
transmission charges and/or wheeling charges payable for that year by such long-term
consumer and medium-term Green Energy Open Access consumers.
(b)
Medium-Term Green Energy Open Access consumers
A Medium-Term Green Energy Open Access consumer may
relinquish rights, fully or partly, by giving at least 30 days prior notice to
the State Nodal Agency:
Provided that the Medium-Term Green Energy Open Access
consumer relinquishing its rights shall pay applicable transmission charges
and/or wheeling charges for the period of relinquishment or 30 days whichever
is less.
(c)
Short-Term Green Energy Open Access consumer
(i)
The Short-Term Open Access schedules accepted by the State Nodal
Agency in advance or on first- come-first-serve basis may be cancelled or
revised downwards on an application to that effect made to the State Nodal
Agency by the short-term Green Energy Open Access consumer:
Provided that such cancellation or downward revision of the
Short-Term Open Access schedules shall not be effective before expiry of a
minimum period of two (2) days:
Provided further that the day on which notice for
cancellation or downward revision of schedule is served on the State Nodal
Agency and the day from which such cancellation or downward revision is to be
implemented, shall be excluded for computing the period of two (2) days.
(ii)
The person seeking cancellation or downward revision of Short-Term
Open Access schedule shall pay the transmission charges and/or wheeling charges
for the first two (2) days of the period for which the cancellation or downward
revision of schedule, as the case may be, in accordance with the schedule
originally approved by the State Nodal Agency, and thereafter in accordance
with the revised schedule prepared by the State Nodal Agency during the period
of such cancellation or downward revision.
(iii)
In case of cancellation, SLDC operating charges specified in these
Regulations shall be payable for two (2) days or the period of cancellation in
days, whichever is less.
Regulation 16. Curtailment Priority.
In case due to
transmission/distribution system constraints or otherwise, it is necessary to
curtail the service, the following priority shall be followed:
(a) The service of
short-term open access consumer (other than Green Energy Open Access consumer)
shall be curtailed first followed by short-term Green Energy Open Access
consumers.
(b) Next, the service of
Medium-Term Open Access consumer (other than Green Energy Open Access consumer)
followed by Medium-Term Green Energy Open Access consumer shall be curtailed.
(c) Next, the service of
Long-Term Open Access consumer (other than Green Energy Open Access consumer)
followed by Long-Term Green Energy Open Access consumer shall be curtailed.
Provided that within a category, the Green Energy Open
Access consumers shall have equal curtailment priority and shall be curtailed
on pro-rata basis.
Provided further that distribution licensees shall be
curtailed as the last resort.
Regulation 17. Metering.
Green Energy Open Access consumer
having contract demand of 1 MW and above shall have to provide four quadrant
ABT compliant meters at the generator end, interface points, consumption place
which shall conform to the Central Electricity Authority (Installation and
Operation of Meters) Regulations, 2006, as amended from time to time.
Provided that the open access consumer who is also consumer
of distribution licensee and demanding the green energy open access upto 1 MW
shall be permitted by the licensee to install Special Energy Meter capable of
energy recording on 15 minutes time block basis, specified by the CEA in its
Regulations for fulfillment of the purpose of billing and energy accounting for
green energy open access at consumption place as per the discretion of
consumer.
Above Meters shall always be maintained in good condition
and shall be open for inspection by any person authorized by the State
Transmission Utility, Distribution Licensee or the State Load Dispatch Centre.
All the Green Energy Open Access consumers shall abide by
the metering standards of CEA.
Regulation 18. Compliance of Grid Code, Distribution Code, Regulations, Orders etc.
Green Energy Open Access consumers
shall abide by the State Grid Code, Distribution Code and all other Codes and
Standards, DSM Regulations and other Regulations and Orders of the Commission
as applicable from time to time.
Regulation 19. Collection and Disbursement of Charges.
The charges in respect of Green Energy
Open Access consumers shall be payable directly to the State Nodal Agency and
Distribution Licensees in accordance with the terms and conditions of payment
as specified in these Regulations. The State Nodal Agency shall disburse the
amount received to the appropriate licensees.
Regulation 20. Information System.
(a)
SLDC shall post the following information in a separate web page
titled Green Energy Open Access Information and also issue a monthly and annual
report containing following information:
(i)
A status report on Long-Term/Medium-Term/Short- Term Green Energy
Open Access consumers
(ii)
Floor rate for bidding in case of congestion.
(iii)
Peak load flows on EHV.
(iv)
Information regarding average loss in the transmission system as
determined by the licensee on a monthly basis, and distribution loss as
determined by the Commission in its respective tariff order.
(b)
The information shall be updated on every change in status.
(c)
All previous reports shall be available in the web-archives.
(d)
The SLDC shall host the above information on its website within
one month from the date of notification of these Regulations.
Regulation 21. Reports.
The transmission/distribution licensee
shall submit a quarterly report to the Commission or as may be directed by the
Commission from time to time in the format prescribed in this regard.
Regulation 22. Dispute Resolution.
No application for green energy open
access shall be denied unless the applicant has been given an opportunity of
being heard in the matter and all orders denying green energy open access shall
be speaking orders by the concerned Nodal Agency.
All disputes and
complaints relating to Green Energy Open Access shall be submitted to the
concerned State Nodal Agency, i.e. SLDC/STU/Distribution Licensee, as case may
be, which shall endeavor to resolve the grievance and shall pass appropriate
orders.
Appeal against an
Order of the concerned Nodal Agency shall be preferred before the Commission,
within a period of thirty days from the date of receipt of order as provided
under sub-Rule (4) of Rule 7 of Green Energy Open Access Rules 2022 notified by
MoP, GoI.
The Commission shall dispose the Appeal
within a period of three months and the Order issued by it shall be binding
upon the parties.
Regulation 23. Issue of Orders and Directions.
Subject to the provisions of the
Electricity Act, 2003 and these Regulations, the Commission may, from time to
time, issue Orders and practice directions with regard to the implementation of
these Regulations and procedures to be followed.
Regulation 24. Power to give Directions.
The Commission shall have the power to
issue such directions and orders from time to time as considered appropriate
for implementation of these Regulations.
Regulation 25. Power to Relax, Amend and Remove Difficulties.
The Commission may, by general or
special order, for reasons to be recorded in writing, and after giving an
opportunity of hearing to the parties likely to be affected, may relax any of
the provisions of these Regulations on its own motion or on an application made
before it by an interested person.
The Commission shall
have the power to add, vary, alter, suspend, modify, amend, or repeal any
provisions of these Regulations from time to time.
If any difficulty arises in giving
effect to the provisions of these Regulations, the Commission may, by an order,
make such provisions, not inconsistent with the provisions of the Electricity
Act, 2003 and these Regulations, as may appear to be necessary for removing the
difficulty.
Regulation 26. Repeal and Saving.
All previous orders, notifications etc.
issues by the commission with respect to the subject matter of these
Regulations shall stand repealed in so far as the same are inconsistent with
the provisions contained herein. Notwithstanding anything contained hereinabove,
the existing consumer(s)/generators including green energy (RE) shall continue
to be governed under the existing granted open access and they shall avail the
Open Access for Green Energy (RE)/ customer/ licensee/ generator under existing
open access Regulations, as per the existing agreements for the period
specified in those agreements or Orders of the Commission for the period of
granted open access.