Central Electricity Regulatory Commission
(Indian Electricity Grid Code) (First Amendment) Regulations, 2024
[23 October
2024]
In exercise of powers conferred
under clause (h) of subsection (1) of Section 79 read with clause (g) of
sub-section (2) of Section 178 of the Electricity Act, 2003 (36 of 2003), and
all other powers enabling it in this behalf, and after previous publication,
the Central Electricity Regulatory Commission hereby makes the following
regulations to amend the Central Electricity Regulatory Commission (Indian
Electricity Grid Code) Regulations, 2023 (hereinafter referred to as "the
Principal Regulations").
Regulation - 1. Short Title and Commencement.
(1)
These regulations may be called the
Central Electricity Regulatory Commission (Indian Electricity Grid Code) (First
Amendment) Regulations, 2024.
(2)
These regulations shall come into
force from the date of publication in the official Gazette except for Amendment
to Clause (12) of Regulations 45 of Principal Regulations.
(3) Amendment to Clause (12) of Regulation 45 shall come into force from
1.04.2024.
Regulation - 2. Amendment to Regulation 19 of the Principal Regulations.
(1) Sub-Clause (b) of Clause (2) of Regulation 19 of the Principal
Regulations shall be substituted with subclauses (b) and (c) as follows:
"(b) Injection of infirm
power shall not exceed one year from the date of first synchronization for
generating stations other than REGS and ESS (except Hydro PSP ESS).
(c) Injection of infirm power
shall not exceed 45 (forty-five) days from the date of first-time energization
and integration (FTC) approval for REGS and ESS (except Hydro PSP ESS)."
(2) A Proviso shall be inserted in Clause (3) of Regulation 19 of the
Principal Regulations as follows:
"Provided that for REGS and
ESS (except Hydro PSP ESS), extension of period for injection of infirm power
beyond the stipulated period may be allowed (a) for a period up to three months
by respective RLDC on an application(s) made by such generating station or
ESS(except Hydro PSP ESS) to respective RLDC along with detailed reasons, at
least 10 days in advance of the completion of the stipulated period, (b) for a
period beyond three months, by the Commission on an application(s) made by such
generating station or ESS(except Hydro PSP ESS) along with detailed reasons, at
least 15 days in advance of the completion of the stipulated period".
Regulation - 3. Amendment to Regulation 22 of the Principal Regulations.
(1)
Words "continuous four (4)
hours" shall be replaced with words "four (4) hours on a cumulative
basis in a single day" in sub-clause (d) of Clause (3) of Regulation 22 of
the Principal Regulations.
(2) The following proviso shall be inserted under sub-clause (f) of Clause
(3) of Regulation 22 of the Principal Regulations:
"Provided that if it is not
possible to demonstrate the design capabilities up to the rated water drawing
levels due to insufficient reservoir levels, the COD may be declared after
demonstrating the capabilities at available water drawing levels, subject to
the condition that design capabilities up to the rated water drawing levels
shall be demonstrated immediately when sufficient reservoir level is available
after COD.
Provided further that if such a
generating station is not able to demonstrate the design capabilities when sufficient
water is available, the generating company shall have the option to either go
for a repeat trial run or de-rate the capacity. If the generating company
decides to de-rate the unit capacity in terms of sub-clause (b) of Clause (2)
of Regulation 22 of these Regulations, such de-rating shall be effective from
the COD."
Regulation - 4. Amendment to Regulation 27 of the Principal Regulations.
(1) The Clause (2) of the of Regulation 27 of the Principal Regulations shall
be substituted as under:
"On declaration of
commercial operation date, scheduling of the generating station or unit
thereof, shall start from 0000 hours of D+2 (where D is the date when a
generating station intimates the commercial operation of the generating station
or unit thereof) or the commercial operation date declared by the generating
station or unit thereof, whichever is later."
Regulation - 5. Amendment of Regulation 45 of the Principal Regulations.
(1) The Third and Fourth Proviso to Clause 12 of Regulation 45 of the
Principal Regulations shall be substituted as follows:
"Provided further that the
regional entity thermal generating stations whose tariffs are adopted under
Section 63 of the Act shall be compensated for part load operation, that is,
for generation below the normative level of operation, in terms of the
provisions of the contract entered into by such generating stations with the
beneficiaries or buyers, or in the absence of such provision in the contract,
as per the mechanism already in force under the Central Electricity Regulatory
Commission (Indian Electricity Grid Code) Regulations, 2010:
Provided further that the
thermal generating stations whose tariffs are determined under Section 62 of
the Act by the Commission, shall be compensated for part load operation as per
the provisions of applicable Tariff Regulations."
Regulation - 6. Amendment to Regulation 49 of the Principal Regulations.
(1)
The words "unless the consent is
withheld by the beneficiary or buyer in writing" under sub-clause (l) of
Clause (1) of Regulation 49 of the Principal Regulations shall be substituted
with the words "without the consent of beneficiary(ies)."
(2) A new sub-clause (v-a) shall be added after sub-clause (v) of Clause
(2)(a) of Regulation 49 of the Principal Regulations as follows:
"(v-a) In case a regional entity generating station, whose tariff is
determined under Section 62 of the Act, gets a schedule below minimum turndown
level for Off-Peak hours of the day, however, gets a schedule above minimum
turndown level for Peak hours of the day, where Peak hours and Off-Peak hours
shall be as declared by the concerned RLDC under the Tariff Regulations, the
schedule below the minimum turndown level may, on the request by such
generating station to NLDC shall be adjusted as follows:
(a)
the schedule below the minimum
turndown level shall be adjusted under SCED such that the schedule in all time
blocks of the day is at least at the minimum turndown level. The schedule of
the marginal generating station (s) (A), that is, the generating station with
the highest energy charge in the stack prepared under and after completion of
step at sub-clause (iv) of this clause, shall be reduced, subject to ramp up or
ramp down rate, response time, transmission congestion and such other
parameters as stipulated in the Detailed Procedure.
(b)
In case the SCED energy charge or SCED
Compensation Charge, as applicable, of such generating station (A), which was
required to be issued SCED down, is lower than the energy charge of the
generating station (B) whose schedule was increased up to the minimum turndown
level, the difference between the SCED energy charge or the SCED Compensation
Charge (for A) and the energy charge (for B) shall be payable by the entity
which has caused the schedule of the generating station or unit thereof below minimum
turndown level.
(c)
In case the SCED energy charge or SCED
Compensation Charge, as applicable, of such generating station (A) which was
required to be issued SCED down, is higher than the energy charge of the
generating station (B) whose schedule was increased up to the minimum turndown
level, the difference between the SCED energy charge or SCED Compensation
Charge (for A) and the energy charge (for B) shall be adjusted in accordance
with sub-clauses (viii) to (x) of this clause.
(d)
The above steps shall be carried out
only after the generating station furnishes to the RLDC the efforts made by
such generating station to achieve a schedule of Minimum turndown level through
the sale of power in the Power market (under bilateral or collective
transactions).
(e)
NLDC shall submit a detailed Procedure
including the modalities of payment of charges as per subclause (b) of
Regulation 49(2)(a)(v-a), within a month of notification of these regulations,
for approval of the Commission."
(3)
The words ", and also subject to
the condition the entire drawal schedule against such generating station can be
accommodated under SCED" under sub-clause (a)(vi)(b) of Clause (2) of
Regulation 49 of the Principal Regulations shall be deleted.
(4)
The words "or partial outage as
per clause (7-a) of this Regulation" shall be added at the end of the
first proviso to sub-clause (a) to Clause (4) of Regulation 49 of the Principal
Regulations.
(5) The following proviso shall be inserted under sub-clause b(ii) of Clause
(4) of Regulation 49 of the Principal Regulations:
"Provided that downward
revision of schedules by the buyers for D day, after 1430 hrs on D-1 day in the
generating station is permissible only for beneficiaries which have scheduled
above their respective share of minimum turndown level in the generating
station:
Provided also that downward
revision by such beneficiaries, which have scheduled above their respective
share of minimum turndown level in the generating station, shall be permissible
limited to a quantum such that overall schedule of the generating station is at
least at Minimum turndown level.
The downward revision of
schedules by such beneficiaries for D day, after 1430 hrs on D-1 day shall be
permissible on a pro-rata basis of the power scheduled above the minimum
turndown level of their share at 1430 hrs of D-1 day.
Illustration for a sample
generating station for a sample time block:
State |
Sche dules given prior to 2.30 pm on D-1 (in MW) |
Sche dule for D day after down ward revision for a
sam ple day (in MW) |
Allo cation after deduc ting auxi liary consu mption
(in MW) |
55% allocation (consi dering MTL as 55%) (in MW) |
Share taken ab ove MTL (in MW) |
Ratio (in %) |
Maxi mum down perm itted after 2.30 PM on ‘D-1’/’D’
day (in MW) |
|
A |
B |
C |
D = C x 55% |
E = A-D |
F = (E/ sigma E) X 100 |
G=F X (total sched ule at 2.30 PM on ‘D- 1’ -
MTL) |
State A |
213 |
117 |
210 |
115 |
98 |
30.62% |
37 |
State B |
682 |
706 |
1245 |
685 |
0 |
|
0 |
State C |
110 |
61 |
106 |
58 |
52 |
16.16% |
19 |
State D |
354 |
195 |
335 |
184 |
170 |
53.12% |
63 |
State E |
0 |
0 |
258 |
142 |
0 |
|
0 |
State F |
0 |
0 |
30 |
17 |
0 |
|
0 |
|
1359 |
1079 |
2184 |
|
320 |
|
119 |
|
|
|
|
|
|
|
|
MTL |
1240 MW |
||||||
Schedule at 2.30 PM on ‘D-1’ - MTL |
119 MW |
(6) The following Clause (7-a) shall be inserted after Clause (7) of
Regulation 49 of the Principal Regulations:
"(7-a) Revision of Declared
Capacity and schedule of a generating station or ESS (as an injecting entity)
shall be allowed only in case of bilateral transactions and not in case of
collective transaction as per following details:
(a)
The generating station (other than
lignite, gas based thermal generating station, and hydro generating station) or
ESS (as an injecting entity) shall be allowed a maximum of 4 (four) revisions
of Declared Capacity and schedule in a day subject to a maximum of 60 (sixty)
revisions during a month, due to reasons such as a partial outage of the unit
or variation of fuel quality or any other technical reason to be recorded in
writing:
Provided that RLDC may allow upward revision of DC beyond the above limit
keeping in view grid requirements.
(b)
The generating station based on
lignite, gas, or hydro generating station shall be allowed 6(six) revisions of
Declared Capacity and schedule in a day subject to a maximum of 120 (One
hundred twenty) revisions during a month, due to reasons such as a partial
outage of the unit or water availability for hydro generating stations or fuel
quality or variations in the supply of gas for gas generating stations or any
other technical reason to be recorded in writing:
Provided that RLDC may allow upward revision of DC beyond the above limit
keeping in view grid requirements."