BIHAR ELECTRICITY REGULATORY
COMMISSION (TERMS AND CONDITIONS OF INTRA-STATE OPEN ACCESS) REGULATIONS, 2018
PREAMBLE
In exercise of the powers
conferred by section 181, read with section 42 of the Electricity Act, 2003 (36
of 2003), and all other powers enabling it in this behalf, and after previous
publication, the Bihar Electricity Regulatory Commission hereby makes the
following Regulations:-
CHAPTER 1
PRELIMINARY
Regulation - 1. Short Title, Extent and Commencement.-
(1) These
regulations may be called the Bihar Electricity Regulatory Commission (Terms
and Conditions of Intra-State Open Access) Regulations, 2018.
(2) These
Regulation shall extend to the whole of the State of Bihar. These regulations
shall apply to open access for use of intra-State transmission system and/or
distribution systems in the State, including when such system is used in
conjunction with inter-State transmission system.
(3) These
regulations shall come into force on the date of publication in the Official
Gazette.
Regulation - 2. Definitions.-
(1) In these
regulations, unless the context otherwise requires
(a) "Act"
means the Electricity Act, 2003 (36 of 2003);
(b) "Allotted
Capacity" means the power transfer in MW between the specified point(s) of
injection and point(s) of drawal allowed to a long-term/medium-term customer on
the intra-State transmission system and the expression "allotment of capacity"
shall be construed accordingly;
(c) "Applicant"
means a consumer, trader, distribution licensee or a Generating company who has
applied seeking connectivity or open access as the case may be
(d) "Central
Commission" means the Central Electricity Regulatory Commission referred
to in Section 76 of the Act;
(e) "Commission"
or "BERC" means the Bihar Electricity Regulatory Commission;
(f) "Consumer"
shall carry the same meaning as in the Act, but shall be restricted to such
consumers within the State of Bihar to whom these regulations will apply.
(g) "Contracted
load" or "Contracted demand" means the load in kW/HP/kVA (kilo
Watt/Horse Power/kilo Volt Ampere) which the distribution licensee has agreed
to supply from time to time subject to the governing terms and conditions;
(h) "Day"
means a day starting at 00.00 hours and ending at 24.00 hours;
(i) "Distribution
licensee" means any person licensed under Part IV of the
Act for distribution and retail supply of electricity in the State of Bihar;
(j) "IEGC"
means Indian Electricity Grid Code Specified by Central Electricity Regulatory
Commission under clause (h) of subsection (1) of section 79 of the Act, and as
amended from time to time;
(k) "Imbalance"
in a time block for a generating station means its total actual generation
minus its total scheduled generation and for a consumer or buyer means its
total drawal minus its total scheduled drawal.
(l) "Long-term
access" means the right to use the intra-State transmission system or
distribution system for a period exceeding seven (7) years.
(m) "Medium-term
open access" means the open access for a period exceeding three months but
not exceeding five (5) years.
(n) "Month"
means a calendar month as per the Gregorian calendar;
(o) "Nodal
agency" means the nodal agency defined in Regulation 11 of these
regulations;
(p) "Open
access" means the nondiscriminatory provision for the use of transmission
lines or distribution system or associated facilities with such lines or system
by any licensee or consumer or a generating company in accordance with these
regulations and includes long term, medium-term and short-term open access.
(q) "Open
access customer" means a consumer, buyer, seller trader, distribution
licensee or a generating company who has been granted open access under these
regulations.
(r) "Reserved
Capacity" means the power transfer in MW between the specified point(s) of
injection and point(s) of drawal allowed to a short-term customer on the
transmission /distribution system depending on availability of
transmission/distribution capacity and the expression "reservation of
capacity" shall be construed accordingly;
(s) "Short-term
open access" means open access for a period up to one month at a time.
(t) "SLDC"
means the State Load Despatch Centre established under sub-section (1) of
section 31 of the Act;
(u) "State
Grid Code" means the Bihar Electricity Grid Code specified by the
Commission under clause (h) of sub-section(1) of section 86 of the Act,
(v) "State
transmission Utility (STU)" means the State Electricity Board or the
Government Company notified by the State Government under sub-section (1) of
section 39 of the Act;
(w) "Transmission
licensee" means any person licensed under Part IV of the Act for
transmission of electricity.
(x) "Transmission
System Segment" means a part or whole of the transmission system from the
point of injection to the point of drawal.
(y) "Wheeling"
means the operation whereby the distribution system and associated facilities
of a transmission Licensee or distribution Licensee, as the case may be , are
used by another person for the conveyance of electricity on payment of charges
to be determined under section 62 of the Electricity Act 2003;
(2) Words and
expressions used and not defined in these regulations but defined in the Act or
IEGC or the Bihar Electricity Grid Code, Bihar Electricity Supply Code or the
Rules and other Regulations made under the Act, as the case may be, shall have
the meaning assigned to them therein.
CHAPTER 2
CONNECTIVITY
Regulation - 3. Connectivity.-
(1) A
consumer having load of 10 MW and above or a Generating Station having capacity
of 10 MW and above shall be eligible to obtain connectivity to the intra-State
transmission system, unless already connected, and shall apply for connectivity,
in accordance with the provisions in this chapter.
(2) A
Generating Station having installed capacity less than 10 MW shall be eligible
to obtain connectivity to the Distribution system and shall apply for
connectivity as per the provisions of these regulations, unless already
connected, in accordance with the provisions in this chapter
Regulation - 4. Application procedure for Connectivity to intra-State transmission system.-
(1) Applicant
shall apply to the STU for connectivity in the Form prescribed in the detailed
procedure to be laid down by the STU.
(2) The
Application shall be accompanied by a non-refundable fee of Rs. two lakh
through demand draft or any other mode in accordance with the detailed
procedure referred to in Regulation 4(1) of these Regulations.
(3) The
application for connectivity shall contain details such as proposed
geographical location of the applicant, quantum of power to be interchanged
i.e. the quantum of power to be injected in case of a generating station
including a captive generating plant and quantum of power to be drawn in case
of consumer with the intra-State transmission system and such other details as
may be laid down by the State Transmission Utility in the detailed procedure:
Provided that in cases where once
an application has been filed and thereafter there has been any material change
in the location of the applicant or change, by more than 10 percent in the
quantum of power to be interchanged with the intra-State transmission system,
the applicant shall make a fresh application.
Regulation - 5. Processing of Application and Grant of connectivity to STU.-
(1) On
receipt of the application, the STU shall, in consultation and through
coordination with other agencies involved in the intra-State transmission,
process the application and carry out the necessary interconnection study as
specified in the Central Electricity Authority (Technical Standards for
Connectivity to the Grid) Regulations, 2007 and its amendments from time to
time.
(2) While
granting connectivity, the STU shall specify the name of the substation or
pooling station or switchyard where connectivity is to be granted. In case
connectivity is to be granted by looping-in and looping-out of an existing or
proposed line, the STU shall specify the point of connection and name of the
line at which connectivity is to be granted. The STU shall indicate the broad
design features of the dedicated transmission line and the timeframe for
completion of the dedicated transmission line.
(3) The
applicant shall sign a connection agreement with the State Transmission Utility
or intra-State transmission licensee owning the sub-station or pooling station
or switchyard or the transmission line as identified by the STU where
connectivity is being granted:
Provided that in case
connectivity of a generating station, including captive generating plant or
consumer is granted to the intra-State transmission system of an intra-State
transmission licensee other than the State Transmission Utility, a tripartite
agreement as provided in the Central Electricity Authority (Technical Standards
for Connectivity to the Grid) Regulations, 2007 shall be signed between the
applicant, the State Transmission Utility and such intra-State transmission
licensee.
(4) The grant
of connectivity shall not entitle an applicant to interchange any power with
the grid unless it obtains long-term access, medium term open access or
short-term open access in accordance with the provisions of these regulations.
Provided that a generating
station, including captive generating plant which has been granted connectivity
to the grid shall be allowed to undertake testing including full load testing
by injecting its infirm power into the grid before being put into commercial
operation, even before availing any type of open access, after obtaining permission
of the State Load Despatch Centre, which shall keep grid security in view while
granting such permission.
(5) Commercial
treatment of such infirm power referred to in Regulation 5(4) of these
Regulations from a generating station or a unit thereof, the tariff of which is
determined by the Commission, will be governed by the relevant Regulations on
Terms and Conditions of Tariff notified by the Commission from time to time.
Provided further that the power
injected into the grid from other generating stations, as a result of such
testing, shall be charged at the charges for imbalance determined by the
Commission or at UI charges where charges of imbalance have not notified by the
Commission.
(6)
An applicant may be required by the State Transmission Utility to
construct a dedicated line to the point of connection to enable connectivity to
the grid, unless exempted by the Commission for reasons to be recorded in
writing.
(7) The STU
shall convey its decision on grant of connectivity or otherwise within a period
of 60 days from the date of receipt of application.
Regulation - 6. Application procedure for Connectivity to distribution system by a generating station.-
(1) All
eligible generating stations including a captive generating plant, seeking connectivity
to the distribution system, shall apply to the distribution licensee for
connectivity in the Form prescribed in the procedure to be laid down by the
Distribution Licensee.
(2) The
Application shall be accompanied by a non-refundable fee of Rs. two lakh
through demand draft or any other mode in accordance with the detailed
procedure referred to in Regulation 6(1) of these Regulations
(3) The
application for connectivity shall contain details such as, proposed
geographical location of the generating station, quantum of power to be
injected and such other details as may be laid down by the distribution
licensee concerned in the detailed procedure.
Provided that in cases where once
an application has been filed and thereafter there has been a material change
in the location of the generating stations or change by more than 10% in the
quantum of power to be injected, the Generating Company shall make a fresh
application.
Regulation - 7. Processing of Application and Grant of connectivity to distribution system by a generating station.-
(1) On
receipt of the application, the distribution licensee shall, in consultation
and through coordination with State Transmission Utility, process the
application and carry out the necessary interconnection study as specified in the
Central Electricity Authority (Technical Standards for Connectivity to the
Grid) Regulations, 2007 and its amendments from time to time.
(2) While
granting connectivity, the distribution licensee shall specify the name of the
sub-station or pooling station or switchyard where connectivity is to be
granted.
(3) The
distribution licensee shall indicate the broad design features such as
switchyard and interconnection facility upto the point of injection into the
Substation of the distribution licensee and the timeframe for completion of the
same.
(4) The
applicant shall sign a connection agreement with the distribution licensee
where connectivity is being granted.
(5) The grant
of connectivity shall not entitle an applicant to interchange any power with
the grid unless it obtains long-term access, medium term open access or
short-term open access in accordance with the provisions of these regulations.
Provided that a generating
station, including captive generating plant which has been granted connectivity
to the distribution system shall be allowed to undertake testing including full
load testing by injecting its infirm power into the grid before being put into
commercial operation, even before availing any type of open access, after
obtaining permission of the State Load Despatch Centre and the distribution
licensee, who shall keep grid security in view while granting such permission.
(6)
Commercial treatment of such infirm power referred to in
Regulation 7(5) of these Regulations from a generating station or a unit
thereof, the tariff of which is determined by the Commission, will be governed
by the relevant Regulations on Terms and Conditions of Tariff notified by the
Commission from time to time. Provided further that the power injected into the
grid from other generating stations as a result of such testing, shall be
charged at the charges for imbalance determined by the Commission or UI charges
where charges of imbalance have not notified by the Commission.
(7)
An applicant may be required by the distribution licensee to
construct the switchyard and inter-connection facility upto the point of
injection, unless exempted by the Commission for the reason to be recorded in
writing.
(8)
In cases where augmentation of the distribution licensee's
substation is involved, the generating station shall also bear the cost of bay,
breaker in the distribution licensee's substation and equipment for
inter-connection of real time data to SLDC.
(9) The
distribution licensee shall convey its decision on grant of connectivity or
otherwise within a period of 60 days from the date of receipt of application.
CHAPTER 3
GENERAL PROVISIONS FOR OPEN
ACCESS
Regulation - 8. Eligibility for Open Access and conditions to be satisfied.-
(1) The
generating companies, captive generating plants and consumers shall be eligible
for non-discriminatory open access to the intra-State transmission system or
distribution system on payment of transmission and other charges as may be
determined by the Commission in accordance with Chapter 5 of the these
regulations.
(2) Open
access shall be permissible to the consumers seeking open access for a capacity
of 1 MW and above.
Provided that the Commission may
allow open access to consumers seeking open access for capacity less than 1 MW
at such time as it may consider feasible having regard to operational
constraints and other factors.
Provided further that when a
person, who has established a captive generating plant, opts for open access
for carrying the electricity to the destination of his own use, the limitation
of 1 MW shall not be applicable.
(3) Notwithstanding
anything contained in these Regulations, a person having outstanding dues
against him for more than two months billing of distribution/transmission
licensee at the time of application shall not be eligible for open access.
Regulation - 9. Criteria for granting long-term access or medium-term open access or short term open access.-
(1) The State
Transmission Utility shall have due regard to the augmentation required for the
intra-State transmission system before awarding long-term access.
(2) Medium-term
open access or short-term open access shall be granted if the resultant power
flow can be accommodated in the existing transmission system or the transmission
system under execution:
Provided that no augmentation
shall be carried out to the transmission system for the sole purpose of
granting medium-term open access or short-term open access:
Provided further that
construction of a dedicated transmission line shall not be construed as
augmentation of the transmission system for the purpose of this regulation.
CHAPTER 4
APPLICATION PROCEDURE AND APPROVAL
Regulation - 10. Categories of Open Access Consumers.-
The eligible consumers seeking Open Access shall be categorized
based on the following criteria:
(1)
System to which connected
(a)
Intra-State transmission system
(b)
Distribution system
(2)
Inter-se location of drawal and injection
points
(a)
Both within the same distribution system
(b)
Both within the State but in different
distribution systems
(c)
Both in different States
(3)
Duration of Open Access
(a)
Long term open access
(b)
Medium-term open access
(c)
Short-term open access
Regulation - 11. Application procedure for Open Access.-
(1)
All applications for open access shall be made
in the prescribed Form and submitted to the Nodal agency in accordance with
these regulations.
(2)
Subject to the provisions of these
regulations, the Nodal agency, Application fee, Documents to be accompanied
with the application and time frame for disposal of application shall be as
specified in the following Tables:
|
Table-1 |
|||||||||
|
Consumer
connected to Distribution System |
|||||||||
|
Application fee (Rs.) |
|||||||||
|
Sl.
No |
Period |
Inter-se
location of drawal and injection point |
Nodal
agency |
For
Capacity of 10 MW and above |
For
capacity less than 10 MW |
Documents
to accompany the application |
Time
frame for disposal of application (days from the receipt of application) |
Applicable
Charges |
Applicable
Losses |
|
1 |
Short
Term Open Access (STOA) |
Both
within the same Distribution licensee |
Concerned
Distribution Licensee |
2000 |
2000 |
Proof
of payment of Application fee. |
7
working days in case STOA applied for first time. ?3 working days on subsequent STOA
applications . |
Wheeling
charge Cross
Subsidy surcharge Additional
surcharge, if any ?Imbalance and Reactive Energy Charges, as
applicable Scheduling
and System Operating charges |
Distribution
loss in kind at relevant voltage level. |
|
2 |
|
Both
within the same State but in areas of different Distribution Licensees |
SLDC |
5000 |
5000 |
Proof
of payment of Application fee, Consent
from concerned Distribution licensees. |
7
working days in case STOA applied for first time. 3
working days on subsequent STOA applications. |
Wheeling
charge Cross
Subsidy surcharge Additional
surcharge, if any Imbalance
and Reactive Energy Charges, as applicable. Scheduling
and system Operating Charges as applicable. Transmission
Charge (Intra-State) |
Distribution
loss in kind at relevant voltage level in respect of both Distribution
Licensees Transmission
loss in kind. (Intra-State) |
|
3 |
|
Injection
point in the Intra-State transmission system within the State |
SLDC |
5000 |
5000 |
Proof
of payment of Application fee. Consent
from concerned Distribution licensees. |
7
working days
in case STOA applied ?for first time. 3
working days
on subsequent STOA applications |
Wheeling
charge Cross Subsidy surcharge Additional surcharge, if any Imbalance and
Reactive Energy Charges, as applicable Scheduling and system operating
charges, as applicable. Transmission
charge (Intra-State) |
Distribution
loss in kind at relevant voltage level. Transmission
loss in kind. (Intra-State) |
|
4 |
|
In
different States |
NLDC
or RLDC of the region where consumer is located, as the case may be |
5000 |
5000 |
Proof
of payment of Application fee, ?Consent from concern ed SLDCs and
Distribution licensee s as applicable. |
As
per Central Commission's Regulation |
Wheeling
charge Cross
Subsidy surcharge Additional
surcharge, if any ?Imbalance and Reactive Energy charges, as
applicable. Scheduling
and system Operating charges, as applicable Transmission
Charge (Intra-State and Inter |
?Distribution loss in kind at relevant
voltage level . Distribution Licensee s Transmission
loss in kind. (Intra-State) |
|
5 |
Medium
Term Open Access (MTOA) |
Both
within the same Distribution licensee |
Concerned
Distribution licensee |
50000 |
25000 |
Proof
of payment of Application fee, PPA
or Sale-Purchase agreement of power, In
case of generating station not already connected to grid, documentary
evidence for completion of the connectivity showing that the same shall be
completed before intending date of MTOA. |
20
working days |
Wheeling
charge Cross
Subsidy surcharge Additional
surcharge, if any Stand-by
charges, if any Imbalance
and Reactive Energy Charges, as applicable Scheduling
and system operating charges, as applicable |
Distribution
loss in kind at relevant voltage leave. |
|
6 |
|
Both
within the same State but different Distribution Licensees |
STU |
100000 |
50000 |
Proof
of payment of Application fee, PPA
or Sale-purchase agreement of power, ?In case of generating station not already
connected to grid, documentary evidence for completion of the connectivity
showing that the same shall be completed before intending date of MTOA. Consent
from concerned distribution licensees |
40
working days |
?Wheeling charge Cross
Subsidy surcharge Additional
surcharge, if any Stand-by
Charges, if any Imbalance
and Reactive Energy Charges, as applicable Scheduling
and system Operating Charges as applicable. Transmission
charge(Intra -State) |
Distribution
loss in kind at relevant voltage level in respect of both Distribution
Licensee s Transmission
loss in kind. (Intra-State) |
|
7 |
|
Injection
point in the Intra-State transmission system within the State |
STU |
100000 |
50000 |
proof
of payment of Application fee, PPA
or Sale-purchase agreement of power, ?In case of generating station not already
connected to grid, documentary evidence for completion of the connectivity
showing that the same shall be completed before intending date of MTOA, Consent
form concerned Distribution licensees |
40
working days |
Wheeling
charge Cross
subsidy surcharge Additional
surcharge, if any ?Imbalance and Reactive Energy charges as
applicable. Scheduling
and system Operating Charges, as applicable. Transmission
Charges (Intra-State) Standby
charges if any |
Distribution
loss in kind at relevant voltage level. Transmission
loss in kind. (Intra-State) |
|
8 |
|
In
different States |
CTU |
100000 |
100000 |
?Proof of payment of Application fee, PPA
or Sale purchase agreement of power, ?In case of generating station not already
connected to grid, documentary evidence for completion of the connectivity
showing that the same shall be completed before intending date of MTOA, Consent
from concerned SLDCs and Distribution licensees, as applicable |
As
per Central Commission's Regulation |
Wheeling
Charges Cross
Subsidy surcharge Additional
surcharge, if any Stand-by
charges, if any Imbalance
and Reactive Energy charges, as applicable. ?Scheduling and system Operating Charges, as
applicable Transmission
charge (Intra-State and Inter State). |
Distribution
loss in kind at relevant voltage level Transmission
loss in kind. (Intra-State and Inter State). |
|
9 |
Longt
Term Open Access (LTOA) |
Both
within the same Distribution licensee |
Concerned
Distribution Licensee |
50000 |
25000 |
Proof
of payment of Application fee, PPA
or Sale-purchase agreement of power, ?In case of generating station not already
connected to grid, documentary evidence for completion of the connectivity
showing that the same shall be completed before intending date of LTOA |
20
working days |
Wheeling
Charge, Cross
Subsidy surcharge Additional
surcharge, if any ?Stand-by charges, if any Imbalance
and Reactive Energy Charges, as applicable. Scheduling
and system operating charges, as applicable |
Distribution
loss in kind at relevant voltage level. |
|
10 |
|
Both
within the same State but different Distribution Licensees |
STU |
100000 |
50000 |
Proof
of payment of Application fee, ?PPA or Sale-purchase agreement of power, In
case of generating station not already connected to grid, documentary
evidence for completion of the connectivity showing that the same shall be
completed before intending
date of LTOA, Consent
from concerned distribution licensees |
?120 days where augmentation of transmission
system is not required 150
days where augmentation of transmission system is required. |
Wheeling
charge Cross
subsidy surcharge Additional
surcharge, if any Stand
by Charges, if any Imbalance
and Reactive Energy charges, as applicable. Scheduling
and system Operating Charges as applicable. Transmission
charge(Intra-State) |
?Distribution loss in kind at relevant
voltage level in respect of both Distribution Licensee s. Transmission
loss in kind. (Intra-State) |
|
11 |
|
Injection
point in the intra State transmission system within the state |
STU |
100000 |
50000 |
Proof
of payment of Application fee, PPA
or Sale-purchase agreement of power, In
case of generating station not already connected to grid, documentary
evidence for completion of the connectivity showing that the same shall be
completed before intending date of LTOA, Consent
from concerned Distribution licensee |
120
days where augmentation of transmission system is not required. 150
days where augmentation of transmission system is required. |
Wheeling
charge Cross
subsidy surcharge Additional
surcharge if any Stand
by Charges, if any ?Imbalance and Reactive Energy charges, as
applicable. Scheduling
and system Operating charges as applicable. Transmission
charge (Intra-State) |
Distribution
loss in kind at relevant voltage level. Transmission
loss in kind (Intra-State) |
|
12 |
|
In
different States |
CTU |
100000 |
100000 |
Proof
of payment of Application fee, PPA
or Sale-purchase agreement of power, In case
of generating station not already connected to
grid, documentary evidence for completion of the connectivity showing that
the same shall be completed before intending date of LTOA, Consent
from concerned SLDCs and Distribution licensees, as applicable |
As
per Central Commission' s Regulation |
Wheeling
charge ?Cross subsidy surcharge Additional
surcharge if any Stand
by Charges, if any Imbalance
and Reactive Energy charges,
as applicable. Scheduling
and system Operating charges as applicable. ?Transmission charge (Intra-State and
Inter-State) |
?Distribution loss in kind at relevant
voltage level. Transmission
loss in kind (Intra-State and Inter-State) |
|
Table
2 |
|||||||||
|
Consumer
connected to intra-State Transmission System |
|||||||||
|
Application
Fee |
|||||||||
|
SL.
No |
Period |
Inter-se
location of drawal and injection |
Nodal
agency |
For
capacity of 10 MW and above |
(Rs.)
For capacity less than 10 MW |
Documents
to accompany the application |
Time
frame for disposal of application |
Applicable
Charges |
Applicable
Losses |
|
1 |
Short
Term Open Access (STOA) |
Both
within the same State(In the Intra-State transmission system) |
SLDC |
5000 |
5000 |
Proof
of payment of Application fee. |
?7 working days in case STOA applied for
first time. 3
working days on subsequent STOA applications. |
Wheeling
charge, if applicable Transmission
charge (Intra-State) Imbalance
and Reactive Energy Charges, as applicable Scheduling
and system Operating charges, as applicable Additional
surcharge, if any ?Cross-subsidy charge, as applicable |
?Transmission loss in kind (Intra-State). |
|
2 |
|
Injection
point in the distribution system within the State |
SLDC |
5000 |
5000 |
Proof
of payment of Application fee, Consent
from concerned Distribution licensees. |
7
working days in case STOA applied for first time. 3
working days on subsequent STOA applications. |
Wheeling
charges, as applicable Imbalance
and Reactive Energy Charges, as applicable Scheduling
and system Operating charges, as applicable. Transmission
Charge (Intra-State) ?Additional surcharge, if any Cross-subsidy
charge, as applicable |
Distribution
loss in kind at relevant voltage level Transmission
loss in kind. (Intra-State) |
|
3 |
|
In
different States |
NLDC
or RLDC of the region where consumer is located, as the case may be |
5000 |
5000 |
Proof
of payment of Application fee, Consent
from SLDCs and concerned Distribution licensee as applicable |
As
per Central Commission's Regulations |
Wheeling
charge, if applicable Transmission
charge (Intra-State and Inter-State) Imbalance
and Reactive Energy Charges, as applicable Scheduling
and system Operating charges, as applicable Additional
surcharge, if any Cross-subsidy
charge, as applicable |
Transmission
loss in kind. (Intra-State and Inter-State) |
|
4 |
Middle
Term Open Access (MTOA) |
Both
within the same State(in the intra- State transmission system) |
STU |
100000 |
50000 |
Proof
of payment of Application fee, PPA
or Sale-purchase agreement of power, In
case of generating station or consumer not already connected to grid,
documentary evidence for completion of the connectivity showing that the same
shall be completed before intending date of MTOA. |
20
working days |
Imbalance
and Reactive Energy Charges, as applicable. ?Scheduling and system Operating Charges, as
applicable Transmission
Charge (Intra-State). Wheeling
Charge, if applicable Standby
charges, if any Additional
surcharge, if any Cross-subsidy
charge |
Trans
mission Loss in kind. (Intra-State). |
|
5 |
|
Injection
point in the distribution system within the State |
STU |
100000 |
50000 |
?Proof of payment of Application fee, PPA
or Sale-purchase agreement of power, In
case of generating station or consumer not already connected to grid,
documentary evidence for completion of the connectivity showing that the same
shall be completed before intending date of MTOA. Consent
concerned Distribution licensee. |
20
working days |
Wheeling
Charge as applicable, Imbalance
and Reactive Energy Charges, as applicable. Scheduling
and system Operating Charges, as applicable, Transmission
Charge (Intra-State) Standby
charges, if any ?Additional surcharge, if any Cross-subsidy
charge |
Distribution
loss in kind at relevant voltage level. Trans
mission Loss in kind (Intra-State). |
|
6 |
|
In
different States |
CTU |
100000 |
100000 |
Proof
of payment of Application fee, PPA
or Sale-purchase agreement of power, ?In case of generating station or consumer
not already connected to grid, documentary evidence for completion of the
connectivity showing that the same shall be completed before intending date
of MTOA. Consent
from concerned SLDCs and Distribution licensee as applicable. |
As
per Central Commission's Regulation |
Imbalance
and Reactive Energy Charges, as applicable. Scheduling
and system Operating Charges as applicable. ?Transmission Charge (Intra-State and
Inter-State) Wheeling
Charge, if applicable Standby
charges, if any Additional
surcharge, if any Cross-subsidy
charge |
Trans
mission Loss in kind. (Intra-State and Inter-State). |
|
7 |
Long
Term Open Access (LTOA) |
Both
within the same State(in the intra- State transmission system) |
STU |
200000 |
100000 |
Proof
of payment of Application fee, Bank
Guarantee PPA
or Sale-purchase agreement of power, ?In case of generating station or consumer
not already connected to grid, documentary evidence for completion of the
connectivity showing that the same shall be completed before intending date
of LTOA. |
120
days where augmentation of transmission system is not required. 150
days, where augmentation of transmission system is required. |
Imbalance
and Reactive Energy Charges, as applicable. Scheduling
and system Operating Charges as applicable. Transmission
Charge (Intra-State) Wheeling
Charge, if applicable ?Standby charges, if any Additional
surcharge, if any Cross-subsidy
charge |
Trans
mission Loss in kind (Intra-State). |
|
8 |
|
Injection
point in the distribution system within the State |
STU |
200000 |
100000 |
Proof
of payment of Application fee, Bank
Guarantee PPA
or Sale-purchase agreement of power, In
case of generating station or consumer not already connected to grid,
documentary evidence for completion of the connectivity showing that the same
shall be completed before intending date of LTOA. Consent
from concerned Distribution licensee. |
120
days where augmentation of transmission system is not required. 150
days, where augmentation of transmission system is required. |
Wheeling
Charges, as applicable, Imbalance
and Reactive Energy Charges, as applicable. ?Scheduling and system Operating Charges, as applicable, Transmission
Charge (Intra-State). Standby
charges, if any Additional
surcharge, if any Cross-subsidy
charge |
Distribution
Loss in kind at relevant voltage level Transmission
Loss in kind. (Intra-State). |
|
9 |
|
In
different States |
CTU |
200000 |
200000 |
?Proof of payment of Application fee, Bank
Guarantee PPA
or Sale-purchase agreement of power, In
case of generating station or consumer not already connected to grid,
documentary evidence for completion of the connectivity showing that the same
shall be completed before intending date of LTA. Consent
from concerned STU and Distribution licensee as applicable. |
As
per Central Commission's Regulation |
Imbalance
and Reactive Energy Charges, as applicable. Scheduling
and system Operating Charges as applicable. Transmission
Charge (Intra-State and Inter-State) Wheeling
Charge, if applicable Standby
charges, if any Additional
surcharge, if any Cross-subsidy
charge, as applicable |
?Transmission Loss in kind. (Intra-State and
Inter-State). |
Regulation - 12. Procedure for Long Term Open Access.-
(1)
Involving inter-State transmission system:
Notwithstanding anything contained in clauses (2) and (3)
herein below, procedure for inter-State long-term Open Access shall be as per
Central Electricity Regulatory Commission (Grant of Connectivity, Long-term
Access and Medium-term Open Access in inter-State Transmission and related
matters) Regulations, 2009 or its statutory re-enactments as amended from time
to time. Provided that in respect of a consumer connected to a distribution
system seeking Inter-state Long Term Open Access, the SLDC, before giving its
consent as required under the Central Commission's regulations, shall obtain
the consent of the distribution licensee concerned.
(2)
Involving only intra-State transmission
system:
Subject to the provisions of clause (1) herein above, intra-State
long-term Open Access involving intra-State transmission system shall be in
accordance with the provisions of sub-clause (a) to (i) herein below.
(a)
The application for grant of long-term open
access shall contain details such as name of the entity or entities from whom
electricity is proposed to be procured along with the quantum of power and such
other details as may be laid down by the State Transmission Utility in the
detailed procedure.
Provided that in case where augmentation of transmission
system is required, the applicant shall also have to bear the transmission
charges for the same as per these regulations:
Provided further that in cases where there is any
material change in location of the applicant or change by more than 10 percent
in the quantum of power to be interchanged using the intra-State transmission
system, a fresh application shall be made by the applicant in accordance with
these regulations.
(b)
The applicant shall submit any other
information sought by the nodal agency including the basis for assessment of
power to be interchanged using the intra-State transmission system and power to
be transmitted to or from various entities or regions to enable the nodal
agency to plan the intra-State transmission system in a holistic manner.
(c)
The application shall be accompanied by a
non-refundable application fee and a bank guarantee of Rs. 10,000/- (ten
thousand) per MW of the total power to be transmitted. The bank guarantee shall
be in favour of the nodal agency, in the manner laid down under the detailed
procedure.
(d)
On receipt of the application, the nodal
agency shall, in consultation and through coordination with other agencies
involved in intra-State transmission system to be used, process the application
and carry out the necessary system studies as expeditiously as possible so as
to ensure the decision to grant or reject long-term open access within the
timeframe specified in these Regulations. The cost of system study done for
long term open access customer has to be borne by the long term open access
customer.
Provided that no application shall be rejected by the
nodal agency without giving opportunity of being heard to the consumer and
reasons to be recorded in writing
Provided further that if the consumer is aggrieved with
the decision of the nodal agency, may approach the Commission serving a copy of
the petition to the nodal agency concerned.
(e)
Based on the system studies, the nodal agency
shall specify the intra-State transmission system that would be required to
give long-term access. In case augmentation to the existing intra-State
transmission system is required, the same will be intimated to the applicant.
The cost of system study done for long term open access has to be borne by the
long term open access customer.
(f)
While granting long-term access, the nodal
agency shall communicate to the applicant, the date from which long-term open
access shall be granted and an estimate of the transmission charges likely to
be payable based on the prevailing costs, prices and methodology of sharing of
transmission charges specified by the Commission.
(g)
The applicant shall sign an agreement for
long-term access with the State Transmission Utility in case long-term open
access is granted by the State Transmission Utility, in accordance with the
provision as may be laid in the detailed procedure. While seeking long-term
open access to an intra-State transmission licensee, other than the State
Transmission Utility, the applicant shall sign a tripartite long-term access
agreement with the State Transmission Utility and the intra-State transmission
licensee. The long-term open access agreement shall contain the date of
commencement of long-term access, the point of injection of power into the grid
and point of drawal from the grid and the details of dedicated transmission
lines, if any, the bank guarantee required to be given by the applicant and
other details in accordance with the detailed procedure. In case augmentation
of transmission system is required, the long-term open access agreement shall
also contain the time line for construction of the facilities of the applicant.
(h)
Immediately after grant of long-term access,
the nodal agency shall inform the State Load Despatch Centre within two working
days from the date of grant of open access/ signing of the agreement. SLDC
shall inform the Open Access customer, the date from which Open Access will be
available which shall not be later than 5 days from the date of furnishing of
agreements by the Open Access Customer.
(i)
On expiry of the period of long-term open
access, the same shall stand extended on a written request by the consumer, to
the Sate Transmission Utility, submitted at least six months prior to such
expiry, mentioning the period for which extension is required.
Provided that in case no written request is received from
the consumer within the timeline specified above, the said long-term open
access shall stand terminated on the date of its expiry.
(3)
Within same distribution system:
The procedure specified in clause (2) above shall,
mutatis mutandis, apply to cases of long-term open access when the point of
injection and the point of drawal are located in the same distribution system
except that SLDC shall be understood as distribution licensee.
Regulation - 13. Procedure for medium-term open access.-
(1)
Involving inter-State transmission system:
Notwithstanding anything contained in clauses (2) and (3)
herein below, procedure for inter-State medium-term open access shall be as per
Central Electricity Regulatory Commission (Grant of Connectivity, Long-term
Open Access and Medium-term Open Access in inter-State Transmission and related
matters) Regulations, 2009 or its statutory re-enactment as amended from time
to time.
Provided that in respect of a consumer connected to a
distribution system seeking inter-State medium-term open access, the SLDC,
before giving its consent as required under the Central Commission's
regulations, shall obtain the consent of the distribution licensee concerned.
(2)
Involving only intra-State transmission
system:
Subject to the provisions of clause (1) herein above,
intra-State medium-term open access involving intra-State transmission system
shall be in accordance with the provisions of clause (a) to (h) herein below.
(a)
The application for grant of medium-term open
access shall contain such details as may be laid down under the detailed
procedure and shall, in particular, include the point of injection into the
grid, point of drawal from the grid and the quantum of power for which
medium-term open access has been applied for.
Provided that in cases where there is any material change
in location of the applicant or change by more than 10% in quantum of power to
be interchanged using intra-state transmission system, a fresh application
shall be made by the applicant in accordance with these regulations.
(b)
The start date of the medium-term open access
shall not be earlier than 5 months and not later than 1 year from the last day
of the month in which application has been made..
(c)
The application shall be accompanied by a
non-refundable application fee.
(d)
On receipt of the application, the nodal
agency shall, in consultation and through coordination with other agencies
involved in intra-State transmission, process the application and carry out the
necessary system studies as expeditiously as possible so as to ensure that the
decision to grant or reject medium-term open access within the timeframe
specified in these Regulations. The cost of system study to be done for medium
term open access customer has to be borne by medium term open access customer.
Provided that no application shall be rejected by the
nodal agency without giving opportunity of being heard to the consumer
Provided further that if the consumer is aggrieved with
the decision of the nodal agency, may approach the Commission serving a copy of
the petition to the nodal agency concerned.
(e)
The nodal agency on being satisfied that the
requirements specified under these Regulations are met, shall grant medium-term
open access for the period stated in the application. Provided that for reasons
to be recorded in writing, the nodal agency may grant medium-term open access
for a period less than that sought for by the applicant:
(f)
The applicant shall sign an agreement for
medium-term open access with the State Transmission Utility, in accordance with
the provision as may be laid in the detailed procedure. While seeking
medium-term open access to an intra-State transmission licensee, other than the
State Transmission Utility, the applicant shall sign a tripartite medium-term
open access agreement with the State Transmission Utility and the intra-State
transmission licensee. The medium-term open access agreement shall contain the
date of commencement and end of medium-term open access, the point of injection
of power into the grid and point of drawal from the grid, the details of
dedicated transmission lines required, if any, the bank guarantee required to
be given by the applicant and other details in accordance with the detailed
procedure.
(g)
Immediately after grant of medium-term open
access, the nodal agency shall inform the State Load Despatch Centre.
(h)
Before expiry of the period of medium term
open access, the same may be extended by the Nodal agency on receipt of a
written request from such customer accompanied by application fee as prescribed
at sub regulation (3) of regulation (11).
Provided that such request is submitted at least three
months prior to the date of which the existing medium term open access expires.
Provided that in case no written request is received from
the consumer within the timeline specified above, the said medium term open
access shall stand terminated on the date of its expiry.
(3)
Within same distribution system: The
procedure specified in clause (2) above shall, mutatis mutandis, apply to cases
of medium-term open access when the point of injection and the point of drawal
are located in the same distribution system except that SLDC shall be
understood as distribution licensee.
Regulation - 14. Procedure for short-term Open Access.-
(1)
Involving inter-State transmission system:
Notwithstanding anything contained in clauses (2) to (3)
herein below, procedure for inter-State short-term Open Access shall be as per
Central Electricity Regulatory Commission (Open Access in inter-State
Transmission) Regulations, 2008, or its statutory re-enactments, as amended
from time to time:
Provided that in respect of a consumer connected to a
distribution system seeking inter-State short-term open access, the SLDC,
before giving its consent as required under the Central Commission's
regulations, shall obtain the consent of the distribution licensee concerned.
(2)
Involving only intra-State transmission
system:
Subject to the provisions of clause (1) herein above,
intra-State short-term Open Access shall be in accordance with the provisions
of sub clause (a) to (f) herein below:
(a)
Open Access in advance.-
(i)
Application may be submitted to the Nodal
Agency seeking short-term open access up to the fourth month, considering the
month in which an application is made being the first month.
(ii)
Separate application shall be made for each
month and for each transaction in a month. An application for grant of open
access commencing in any month may be up to 15th day of the preceding month.
For example, application for grant of open access
commencing in the month of July shall be received up to 15th day of June.
(iii)
The application shall contain such details as
may be laid under the detailed procedure and shall, in particular include
capacity needed, generation planned or power purchase contracted, point of
injection, point of drawal, duration of availing open access, peak load,
average load and such other additional information as may be required by the
Nodal agency.
(iv)
The application shall be accompanied by a
non-refundable application fee.
(v)
A consumer of distribution licensee intending
to avail Short-term open access shall also furnish a copy of his application to
the distribution licensee of his area of supply by e-mail or fax or by any
other usually recognized mode of communication.
(vi)
All applications received under sub-clause
(ii) above shall be taken up for consideration together and processed as per
allotment priority criteria specified under Regulation 18 of these regulations
on first served basis.
Provided that the Nodal agency shall acknowledge receipt
of the application indicating time and date.
(vii)
Nodal agency shall check transaction for
congestion of any element (line and transformer) of transmission and
distribution system involved in transaction. If the nodal agency perceives
congestion of any element of transmission or distribution system involved in
the transaction or the capacity sought by consumer for open access in advance
for the following month is more than the available capacity, the allocation
shall be made through electronic bidding procedure as referred to in clause
14(2)(c) below.
(viii) Nodal agency shall convey grant of open access or otherwise
in the manner as laid down under the detailed procedure along with schedule of
payments to the consumer latest by 19th day of such preceding month.
Provided that the nodal agency shall assign specific
reasons for denial of STOA
(b)
Day-Ahead Open Access.-
(i)
An application for grant of day ahead open
access may be received by Nodal agency within three days prior to the date of
scheduling but not later than 1300 Hours of the day immediately preceding the
day of scheduling for day-ahead transaction.
For example, application for day-ahead transaction on
25th day of July shall be received on 22nd day or 23rd day or up to 1300 hours
on 24th day of that month.
(ii)
The application shall contain such details as
may be laid down under the detailed procedure and shall in particular include
quantum of power to be inter changed, point of injection, point of drawal,
duration of availing open access, Peak load ,average load and such other
information as required by the nodal agency.
(iii)
The application shall be accompanied by
non-refundable application fee.
(iv)
A consumer of distribution licensee intending
to avail day-ahead short-term open access shall also furnish a copy of his
application to the distribution licensee of his area of supply by e-mail or fax
or by any other usually recognized mode of communication.
(v)
All applications received for day-ahead
transaction on a particular date under sub-clause (ii) above shall be taken up
for consideration together and processed as per allotment priority criteria
specified under Regulation 18 of these Regulations.
Provide that the Nodal agency shall acknowledge receipt
of the application indicating time and date.
(vi)
Nodal agency shall check transaction of any
element (line and transformer) of transmission and distribution system involved
in transaction for congestion. All other provisions of application for
short-term open access shall apply.
(vii) Nodal agency shall convey grant of open access or
otherwise in the manner as may be laid down under the detailed procedure along
with schedule of payments.
Provided that the nodal agency shall assign specific
reason for denial of day-ahead STOA.
(c)
Bidding Procedure.-
(i)
If the capacity sought by the consumers for
Open Access in Advance for the following month is more than the available
capacity or SLDC perceives congestion of any element of transmission and
distribution system involved in the transaction, the allocation shall be made
through electronic bidding procedure.
(ii)
The decision of SLDC in respect of an
expected congestion shall be final and binding.
(iii) SLDC shall convey information of congestion and decision
for invitation of bidding indicating floor price to the applicants in FORMAT-1
appended to these Regulations.
(iv)
SLDC shall also display bidding information
on its website.
(v)
The floor price of transmission and wheeling
charges determined on the basis of relevant order of the Commission shall be
indicated in FORMAT-1.
(vi)
The Bids shall be accepted in FORMAT-2 up to
the "bid closing time" as indicated in bidding invitation FORMAT-1.
Modification/amendment to a bid, once submitted shall not be entertained.
(vii) If any consumer does not participate in bidding process,
his application shall be deemed to have been withdrawn and shall not be
processed.
(viii) SLDC shall not entertain any request for extension of
time/date for submission of bids.
(ix)
The bidders shall quote price (rounded-off to
whole number) in denomination in which floor price has been determined.
(x)
The quoted price shall be arranged in
descending order and allocation of available capacities shall be accorded in
such descending order until the available capacity is exhausted.
(xi)
In case of equal price quoted by two or more
consumers, the allocation from the residual available capacity at any stage
under sub-sub-clause (x) above shall be made in proportion to capacity being
sought by such consumers.
(xii) All consumers, in favour of whom full capacities have
been allotted, shall pay the highest price obtained from bids.
(xiii) The consumers, who are allotted less capacity, shall pay
the price as quoted by them.
(xiv) SLDC shall reject bid which are incomplete, vague in any
manner or not found in conformity with bidding procedure.
(xv)
The successful bidder, in favour of whom the
capacities have been allocated, shall pay transmission charges, wheeling
charges, as the case may be, determined by bidding under sub clause (xii) or
(xiii) of this clause.
(d)
The reserved capacity by a short-term open
access consumer is not transferable to others.
(e)
The capacity available as a result of surrender
or reduction or cancellation of the reserved capacity by the State Load
Dispatch Centre, may be reserved for any other short-term open access consumer
in accordance with these regulations.
(f)
On expiry of the period of the short-term
open access, the short-term consumer shall not be entitled to any overriding
preference for renewal of the term.
(3)
Within same distribution system:
The procedure specified in clause (2) above, mutatis
mutandis, shall apply to cases of short-term open access when the point of
injection and the point of drawal are located in the same distribution system
except SLDC shall be understood as distribution licensee.
Regulation - 15. Consent by STU, SLDC or Distribution Licensee.-
(1)
Inter-State open access:
(a)
STU in the case of application for grant of
long-term access and SLDC in the case of grant of medium-term open access and
short-term open access shall convey its consent or otherwise as per the
provisions of Central Electricity Regulatory Commission (Grant of Connectivity,
Long-term Access and Medium-term Open Access in inter-State Transmission and
related matters) Regulations, 2009 and Central Electricity Regulatory
Commission (Open Access in inter-State Transmission) Regulations, 2008,
respectively or their statutory re-enactments, as amended from time to time.
(b)
In case of applicant connected to the
distribution system seeking open access, the STU or SLDC, as the case may be,
before giving its consent as required in the central commission's regulations,
shall obtain the consent of the distribution licensee concerned. The
distribution licensee shall convey its consent or otherwise to SLDC or STU, as
the case may be by e-mail or fax or by any other usually recognized mode of
communication within 3 working days to enable SLDC or STU, as the case may be
to provide consent within timeline mentioned in CERC Regulations.
(2)
Intra-State Open Access:
(a)
In respect of a consumer connected to a
distribution system seeking Open access, the STU or SLDC or distribution
licensee as the case may be shall obtain the consent of the distribution
licensee concerned. The distribution licensee shall convey its consent or
otherwise to the STU or SLDC as the case may be by e-mail or fax or by any
other usually recognized mode of communication, within three (3) working days.
(b)
While processing the application from a
generating station seeking consent as required under Central Commission's
Regulations for open access, the distribution licensee shall verify the following,
namely-
(i)
Existence of infrastructure necessary for
time-block-wise energy metering and accounting in accordance with the
provisions of the State Grid Code in force, and
(ii)
Availability of capacity in the transmission/distribution
network. STU or the distribution licensee, as the case may be, shall display
its real-time transmission or distribution capacity on its website.
(c)
Where existence of necessary infrastructure
and availability of capacity in the distribution network has been established,
the distribution licensee shall convey its consent to the applicant by e-mail
or fax or by any other usually recognised mode of communication, within three (3)
working days of receipt of the application.
(d)
In case the distribution licensee as nodal
agency finds that the application for consent is incomplete or defective in any
respect, it shall communicate the deficiency or defect to the applicant by
e-mail or fax or by any other usually recognised mode of communication, within
two (2) working days of receipt of the application:
(e)
In case the distribution licensee refuses to
give consent on the grounds of nonexistence of necessary infrastructure or
unavailability of surplus capacity in the distribution network, such refusal
shall be communicated to the STU or SLDC, as the case may be, by e-mail or fax
or by any other usually recognized mode of communication, within the period of
three (3) working days from the date of receipt of the application, along with
reasons for such refusal.
(f)
Where the distribution licensee has not
communicated any deficiency or defect in the application within two (2) days
from the date of receipt of application, or refusal or consent within the
specified period of three (3) working days from the date of receipt of the
application or intimation from STU or SLDC, consent shall be deemed to have
been granted.
Regulation - 16. Consideration of applications from defaulters.-
Notwithstanding anything contained in these regulations,
the Nodal Agency shall be at liberty to summarily reject an application for
Open Access on the ground of non-compliance of the provisions of these
regulations, more specifically the provisions relating to timely payment of the
charges leviable hereunder.
Regulation - 17. Application by eligible entities other than consumers and generating stations connected to distribution system.-
The procedure for submission of the application and
processing the same as laid down in this chapter in respect of the consumers
shall, mutatis mutandis, be applicable to the electricity trading licensees,
distribution licensees and the generating companies connected to the STU as
well.
Regulation - 18. Allotment Priority.-
(1)
The priority for allotment of open access in
intra-State transmission system shall be decided on the following criteria:
(a)
A distribution Licensee shall have the
highest priority in allotment of open access capacity irrespective of whether
the open access request is for long-term, medium-term or short-term.
(b)
The long-term open access applicants shall
have the priority next to the distribution licensee.
(c)
The medium-term open access applicants shall
have the priority next to the long- term open access applicants.
(d)
The short-term open access applicants shall
have the priority next to the medium- term open access applicants.
(e)
Allotment priority for short-term open access
applicants shall be decided subject to capacity availability.
(f)
An existing open access customer shall have
the priority higher than new open access applicants under respective category
provided the former applies for its renewal within the stipulated period prior
to the expiry of existing term of open access.
(g)
When the requirement projected by an
applicant is more than the available capacity and the said applicant is not
able to limit his requirement to the available capacity, the request of
applicant having next lower priority shall be taken up for consideration.
CHAPTER 5
OPEN ACCESS CHARGES
Regulation - 19. Transmission Charges.-
Open Access customer using
transmission system shall pay the charges as stated hereunder:
(1) For use
of inter-State transmission system - As specified by the Central Electricity
Regulatory Commission from time to time.
(2) For use
of intra-State transmission system: -
(a) Transmission
charges payable to State Transmission Utility/transmission licensee by
Long-term and Medium-term open access customer for usage of their system shall
be as determined by the Bihar Electricity Regulatory Commission from time to
time in accordance with the appropriate Regulations framed by the Commission.
Provided that transmission
charges shall be payable on the basis of contracted Capacity/ Scheduled Load or
actual power flow whichever is higher.
Provided further that where a
dedicated transmission system used for open access has been constructed for
exclusive use of an open access customer, the transmission charges for such
dedicated system shall be worked out by transmission licensee for their
respective systems and got approved by the Commission and shall be borne
entirely by such open access customer till such time the surplus capacity is
allotted and used for by other persons or purposes.
Provided also that no
transmission charges shall be payable in case of transaction of renewable
energy generated from solar and wind sources of energy.
(b) Transmission
Charges payable to State Transmission Utility/transmission licensee by
Short-Term Open Access customer for usage of their system shall be determined
as under:
Transmission Charges = ATC/(PLST
X 8760) (in Rs./MWh)
Where,
ATC= Annual Transmission Charges
determined by the Commission for the State transmission system for the
concerned year.
PLST= Peak load projected to be
served by the State transmission system in concerned year.
Provided that transmission
charges for short-term open access shall be payable on the basis of the energy
actually scheduled for Short-Term transactions.
Provided further that no
transmission charges shall be payable in case of open access transaction of
renewable energy generated from solar and wind sources of energy.
Regulation - 20. Scheduling and system operation charges.-
Scheduling and system operation
charges shall be payable by the Open Access customers at the following rates:
(1) In
respect of inter-State open access-
(a) Long-term
access and Medium-term open access-
(i) Regional
Load Despatch Centre fees and charges including charges for the Unified Load
Despatch and Communication Scheme as specified by the Central Commission under
section 28(4) of the Act.
(ii) State
Load Despatch Centre charges as specified by the Commission under sub-section
(3) of section 32 of the Act.
(b) Short-term
open access-
i.
Regional Load Despatch Centre and State Load Despatch Centre
charges as specified by the Central Commission.
(2) In
respect of intra-State open access
(a) Long-term
access and medium-term open access:-
Long-term access and medium-term
open access customers shall be liable to pay SLDC charges determined by the
Commission under subsection (3) of section 32 of the Act.
(b) Short-term
open access-
A composite operating charge @
Rs. 2,000/- per day or part of the day shall be payable by a short-term open
access customer for each transaction to the SLDC or as determined by the
Commission from time to time. The operating charge includes fee for scheduling
and system operation, energy accounting, fee for affecting revisions in
schedule on bona fide grounds and collection and disbursement of charges.
Regulation - 21. Wheeling Charges.-
Wheeling charges payable to
distribution licensee, by an open access customer for usage of its distribution
system shall be as determined by the Commission in the tariff order from time
to time:
Provided that Wheeling charges
shall be payable on monthly basis, by the Open access consumer on the basis of
scheduled energy. Provided further that no wheeling charges shall be payable in
case of transaction of renewable energy generated from solar and wind sources
of energy.
Provided further that where a
dedicated distribution system used for open access has been constructed for
exclusive use of an open access customer, the wheeling charges for such
dedicated system shall be worked out by distribution licensee for their
respective systems and got approved by the commission and shall be borne
entirely by such open access customers till such time the surplus capacity is
allotted and used for by other persons or purpose.
Regulation - 22. Cross subsidy surcharge.-
(1) If open
access facility is availed of by a subsidising consumer of a distribution
licensee of the State, then such consumer, in addition to transmission and/or
wheeling charges, shall pay cross subsidy surcharge determined by the
Commission from time to time. Provided that Cross subsidy surcharge determined
on Per Unit basis shall be payable, on monthly basis, by the open access
consumers based on the actual energy drawn during the month through open
access.
Provided also that cross subsidy
surcharge shall not be levied in case distribution access is provided to a
person who has established a captive generation plant for carrying the
electricity to the destination of his own use.
(2) The Cross
subsidy surcharge shall be determined by the Commission in accordance with the
principles and formula stipulated in the Tariff Policy notified by Central
Government under section 3 of the Act.
Regulation - 23. Additional Surcharge.-
(1) An open
access consumer, receiving supply of electricity from a person other than the
distribution licensee of his area of supply, shall pay to the distribution
licensee an additional surcharge, in addition to wheeling charges and
cross-subsidy surcharge, to meet the fixed cost of such distribution licensee
arising out of his obligation to supply as provided under sub-section (4) of
section 42 of the Act. Such additional charge payable by open access consumer
to the distribution licensee shall be as determined by the Commission in the
distribution tariff order from time to time. Provided that Additional surcharge
shall be payable on monthly basis, by the open access consumers based on the
actual energy drawn during the month through open access.
Provided also that such
additional surcharges shall not be levied in case distribution access is
provided to a person who has established a captive generation plant for
carrying the electricity to the destination of his own use.
(2) The
additional surcharge shall become applicable only if the obligation of the
licensee in terms of power purchase commitments has been and continues to be
stranded or there is an unavoidable obligation and incidence to bear fixed
costs consequent to such a contract.
(Note: The fixed cost related to
network assets is recovered through wheeling charges.)
(3) The
distribution licensee shall submit to the Commission along with its ARR, a
detailed calculation statement of fixed cost which the licensee is incurring
towards his obligation to supply, mentioning the hourly stranded data with its
merit order dispatch.
Regulation - 24. Standby charges for drawal of power by open access customer from distribution licensee.-
In cases of outages of generator
supplying to open access customer under open access, standby arrangements shall
be provided by the distribution licensee for a maximum period of 42 days in a
year, subject to the load shedding as is applicable to the embedded consumer of
the licensee at a charge under Temporary connection tariff for that category of
consumer as determined by the consumer from time to time.
Provided that such charge shall
not exceed 125% of the normal tariff for that category of consumers.
Provided that in cases where
temporary rate of charge is not available for that consumer category the
distribution licensee shall charge 125% of the normal tariff for that category
of consumers.
Provided also that open access
customers would have the option to arrange stand-by power from any other
source.
Regulation - 25. Other Charges.-
In addition to the above charges,
the regulatory charges, congestion charges and any other charges imposed by
Central Commission and/or State Commission shall be payable by the open access
customers.
CHAPTER 6
SCHEDULING, METERING, REVISION
AND LOSSES
Regulation - 26. Scheduling.-
(1) Notwithstanding
anything contained in the succeeding clauses of this regulation, scheduling of
inter-State open access transactions shall be as specified by the Central
Commission.
(2) Subject
to the foregoing clause, intra-State open access transactions in respect of
consumers of load 10 MW and above and all generating stations irrespective of
the capacity shall be scheduled by SLDC in accordance with the provisions of
the State Grid Code.
(3) There
shall be no scheduling required in respect of open access consumer having load
of less than 10 MW.
Provided that the generating
station from which such consumer has contracted power shall be subjected to
scheduling requirements as per the applicable grid code.
Regulation - 27. Metering.-
(1) In case
of open access consumer including all generating stations, Special Energy
Meters shall be installed at the point of injection and point of drawal by the
State Transmission Utility or the distribution licensee as the case may be, for
and at the cost of the customer.
(2) Special
Energy Meters installed shall be capable of time-differentiated measurements
for time-block-wise active energy and voltage differentiated measurement of
reactive energy in accordance with the Indian Electricity Grid Code/Bihar Electricity
Grid Code.
(3) Special
Energy Meters shall be open for inspection by any person authorized by the
State Transmission Utility or the State Load Despatch Centre or the
Distribution licensee.
(4) Special
Energy Meters shall always be maintained in good condition by the open access
customers and shall be periodically tested and calibrated by State Transmission
Utility/Distribution licensee.
(5) All the
open access customers shall abide by the metering standards of CEA.
Regulation - 28. Revision.-
Revision of scheduled energy
shall be permitted in accordance with the provisions of IEGC or the Bihar
Electricity Grid Code as the case may be.
Regulation - 29. Losses.-
(1) Transmission
losses:
(a) Inter-State
transmission:
(i)
Long-term access and medium-term open access: The buyers shall
bear apportioned energy losses in the transmission system in accordance with
the provisions specified by the Central Commission.
(ii)
Short-term Open Access: The buyers and sellers shall absorb
apportioned energy losses in the transmission system in accordance with the
provisions specified by the Central Commission.
(b) Intra-State
transmission: The transmission losses for the intra-State system, as determined
by the Commission in their tariff orders for the applicable year, shall be
apportioned in proportion to the actual energy drawal by the open access
customers and shall be payable in kind.
(2) Distribution
loss:
The system losses for the
distribution system, as determined by the Commission for various voltage levels
in their tariff orders for the applicable year, shall be apportioned in
proportion to the actual energy drawal by the open access customers and shall
be payable in kind at relevant voltage level.
CHAPTER 7
IMBALANCE AND REACTIVE ENERGY
CHARGES
Regulation - 30. Imbalance Charge.-
(1) Scheduling
of all transactions pursuant to grant of long-term access or medium term open access
or short-term open access shall be carried out on day-ahead basis in accordance
with the relevant provisions of IEGC for inter-State transactions and in
accordance with Bihar Electricity Grid Code, Commission's applicable
Regulations and orders for intra-State transactions.
(2) In case
of deviation by open access consumers with load of less than 10 MW, the
difference between the scheduled energy and the actual drawal shall be
accounted through the Time of Day (ToD) Meters on monthly basis and settled at the
rate of the imbalance charge as determined by the Commission. In case of
under-drawal as a result of non availability of the distribution system or
unscheduled load shedding, the open access consumer shall be compensated by the
distribution licensee at the average power purchase cost of the distribution
licensee.
[Explanation.- For the purpose of
this regulation, unscheduled load shedding means, load shedding during hours
other than the hours for which load shedding has been announced by the
distribution licensee. BERC may notify the number of days before which a
distribution licensee should declare scheduled load shedding]
(3)
Deviations between the schedule and the actual injection/drawal
(net over /under drawal or injection) in respect of open access consumers with
load of 10 MW and above and the Generating Stations irrespective of the
capacity, shall be settled based on the composite accounts for imbalance
transactions issued by SLDC on a weekly cycle in accordance with the charges
specified by the Commission.
(4) Payment
of imbalance charges shall have a high priority and the concerned constituents
(licensees or the open access customers as the case may be) shall pay the
indicated amounts within 10 (ten) days of the issue of the statement, into a
State imbalance pool account operated by the SLDC. The person who has to
receive the money on account of imbalance charges would then be paid out from
the State imbalance pool account, within three (3) working days. (5) If
payments against the above imbalance charges are delayed by more than two days,
i.e., beyond twelve (12) days from the date of issue of statement, the
defaulting party shall have to pay simple interest @ 0.04% for each day of
delay. The interest so collected shall be paid to the person whose payment has
been delayed. Persistent payment defaults, if any, shall be reported by the
SLDC to the Commission, for initiating remedial action.
Regulation - 31. Reactive Energy Charge.-
(1) In
respect of open access consumer having a load of 10 MW or above, the payment
for the reactive energy charges by open access consumers shall be in accordance
with provisions stipulated in the relevant Grid Code.
(2) In
respect of open access consumers of load less than 10 MW, reactive energy
charges shall be calculated on Power Factor basis as specified by the
Commission.
CHAPTER 8
COMMERCIAL MATTERS
Regulation - 32. Billing, collection and disbursement.-
Billing in respect of the charges
payable under these regulations shall be made as per the following procedure:
(1) Inter-State
transactions:
(a) Short-term
Open Access
(i) Collection
and disbursement of transmission charges for use of CTU and STU systems and
operating charges payable to RLDCs and SLDCs towards short-term open access
shall be made by the nodal RLDC in accordance with the procedure specified by
the Central Commission.
(ii) The
short-term open access customer connected to distribution system of a
distribution licensee shall pay to such distribution licensee the charges
payable to the distribution licensee on monthly basis within 3 days from the
grant of the short-term open access by the nodal agency.
(b) Long-term
access and medium- term open access
(i) Billing,
collection and disbursement of charges payable to RLDC including Unified Load
Despatch and Communication Scheme shall be in accordance with the procedure
specified by the Central Commission.
(ii) Bills
towards the charges payable to SLDC shall be raised by the STU/SLDC directly to
the open access customer connected to STU and to the distribution licensee in
respect of the customers connected to the distribution system, before the 3rd
working day of the succeeding calendar month.
(iii) Distribution
licensee shall raise the bill with the open access customer connected to it
within 3 days of receipt of bill from SLDC.
(iv) Open access
customer connected to the distribution licensee shall pay the charges within
five days of receipt of bill from distribution licensee. The distribution
licensee shall disburse the amount payable to STU/SLDC on a monthly basis.
(v) Open
access customer connected to the STU shall pay the bills within five working
days of receipt of the bill.
(2) Intra-State
transactions:
(a) Short-term
Open Access-
(i) The
short-term open access customer shall deposit with SLDC the transmission
charges and operating charges within 3 working days of grant of the short- term
open access by SLDC.
(ii) In
addition to the above, the short-term open access customer connected to
distribution system of a distribution licensee shall also pay to SLDC, the
charges payable to the distribution licensee within 3 days from the grant of
the short-term open access by the nodal agency. Such charges would be disbursed
to the distribution licensee on a weekly basis.
(b) Long-term
and Medium-Term open access-
SLDC, transmission licensees and
distribution licensee, where applicable, shall communicate to STU, the details
of the bills due to them by the 3rd working day of the succeeding calendar
month. STU shall separately indicate the above charges and raise the bill with
the open access customer, together with the charges receivable by it, if any,
before the 5th working day of the above month. The open access customer shall
pay the charges within 7 days from the date of receipt of the bill. STU shall
disburse the charges payable to SLDC, transmission licensee and distribution
licensee on a monthly basis.
Regulation - 33. Late payment surcharge.-
In case the payment of any bill
for charges payable under these regulations is delayed by a open access
customer beyond the due date, without prejudice to any action under the Act or
any other regulation thereunder, a late payment surcharge at the rate of 1.25%
per month shall be levied.
Regulation - 34. Default in payment.-
(1) Non-payment
of any charge or sum of money payable by the open access customer under these
regulations (including imbalance charges) shall be considered non-compliance of
these regulations and shall be liable for action under section 142 of the Act
in addition to action under section 56 of the Act. The STU or any other
transmission licensee or a distribution licensee may discontinue open access
after giving customer an advance notice of fifteen days without prejudice to
its right to recover such charges by suit.
(2) In case
of default in payment of charges due to the Load Despatch Centre the Load
Despatch Centre concerned may refuse to schedule power to the defaulting open
access customer and direct the licensee concerned to disconnect such customer
from the grid.
Regulation - 35. Payment Security Mechanism.-
In case of long-term open access
and medium-term open access, the applicant for open access will open an
irrevocable Letter of Credit equivalent to the estimated amount of various
charges for a period of two months in favour of the agency responsible for
collection of various charges.
CHAPTER 9
INFORMATION SYSTEM
Regulation - 36. Information system.-
The State Load Dispatch Centre
shall post following information on its website in a separate web page titled
"Open access information" and also issue a monthly and annual report
containing such information.
(1) A status
report on long-term access or medium-term open access customers indicating:
(a) Name of
customer;
(b) Period of
open access granted (date of commencement and date of termination);
(c) Point of
injection;
(d) Point of
drawal;
(e) Transmission
system / distribution system used, and
(f) Open
access capacity used.
(2) A status
report on short-term open access customers indicating:
(a) Name of
customer;
(b) Period of
open access granted (date of commencement and date of termination);
(c) Point of
injection;
(d) Point of
drawal;
(e) Transmission
system / distribution system used, and;
(f) Open
access capacity used.
(3)
Peak load flows and capacity available including the reserve
capacity on all EHV lines and HV lines emanating from EHV substations.
(4) The
information regarding average loss in transmission and distribution system as
determined by respective licensees.
Regulation - 37. Under -Utilization or Non-Utilization of open access capacity in intra-State transmission system.-
(1) Long-term
open access: A long-term customer may relinquish the long-term access rights
fully or partly before the expiry of the full term of long-term access, by
making payment of compensation for stranded capacity as follows:-
(a) Long-term
customer who has availed access rights for at least 7(seven) years-
(i) Notice of
one (1) year - If such a customer submits an application to the State
Transmission Utility at least 1 (one) year prior to the date from which such
customer desires to relinquish the access rights, there shall be no charges.
(ii) Notice of
less than one (1) year - If such a customer submits an application to the State
Transmission Utility at any time lesser than a period of 1 (one) year prior to
the date from which such customer desires to relinquish the access rights, such
customer shall pay an amount equal to 66% of the transmission charges for the
stranded transmission capacity for the period falling short of a notice period
of one (1) year.
(b) Long-term
customer who has not availed access rights for at least 7 (seven) years -
such customer shall pay an amount
equal to 66% of the estimated transmission charges (net present value) for the
stranded transmission capacity for the period falling short of 7 (seven) years
of access rights:
Provided that such a customer
shall submit an application to the State Transmission Utility at least 1 (one)
year prior to the date from which such customer desires to relinquish the
access rights:
Provided further that in case a
customer submits an application for relinquishment of long-term access rights
at any time at a notice period of less than one year, then such customer shall
pay an amount equal to 66% of the estimated transmission charges (net present
value) for the period falling short of a notice period of one (1) year, in
addition to 66% of the estimated transmission charges (net present value) for
the stranded transmission capacity for the period falling short of 7 (seven)
years of access rights.
(c)
The discount rate applicable for computing the net present value
as referred to in sub-clause (a) and (b) of clause (1) above shall be the
discount rate to be used for bid evaluation in the Central Commission's
Notification issued from time to time in accordance with the Guidelines for
Determination of Tariff by Bidding Process for Procurement of Power by
distribution Licensees issued by the Ministry of Power.
(d) The
compensation paid by the long-term customer for the stranded transmission
capacity shall be used for reducing transmission charges payable by other
long-term customers and medium-term customers in the year in which such
compensation payment is due in the ratio of transmission charges payable for
that year by such long- term customers and medium-term customers.
(2) Medium-term
Open Access customers -A medium-term open access customer may relinquish
rights, fully or partly, by giving at least 30 days prior notice to the nodal
agency:
Provided that the medium-term
open access customer relinquishing its rights shall pay applicable transmission
charges for the period of relinquishment or 30 days whichever is lesser.
(3) Short-term
open access customer-
(a) The
short-term open access scheduled energy accepted by the nodal agency in advance
or on first-come-first-served basis may be cancelled or revised downwards on an
application to that effect made to the nodal agency by the short-term open
access customer:
Provided that such cancellation
or downward revision of the short-term open access scheduled energy shall not
be effective before expiry of a minimum period of two (2) days:
Provided further that the day on
which notice for cancellation or downward revision of schedule is served on the
nodal agency and the day from which such cancellation or downward revision is
to be implemented, shall be excluded for computing the period of two (2) days.
(b)
The person seeking cancellation or downward revision of short-term
open access scheduled energy shall pay the transmission charges for the first
two (2) days of the period for which the cancellation or downward revision of
schedule, as the case may be, has been sought, in accordance with the schedule
originally approved by the nodal agency, and thereafter in accordance with the
revised schedule prepared by the nodal agency during the period of such
cancellation or downward revision.
(c) In case
of cancellation, operating charges specified in Regulations 20 of these
regulations shall be payable for two (2) days or the period of cancellation in
days, whichever is less.
Regulation - 38. Computation of capacity availability for open access.-
(1) The
capacity available for the open access shall be computed for each transmission
segment and for every sub-station by the STU following the methodology given
below:
(a) Available
open access capacity of a transmission system segment: = (DC-(SD + AC)) + NC -
ND where, DC=Designed capacity of the transmission segment in MW, SD =
Sustained demand (peak load experienced) in MW recorded in the segment, AC =
Already allotted capacity, but not availed in MW, NC = New capacity in MW
expected to be added and ND= New Demand expected to be added.
provided that for an embedded
consumer seeking open access within the contract demand the available open
access capacity of the transmission system segment shall be computed by using
the formula (DC-(SD-AC))+NC-ND
(b) Available
open access capacity of a sub-station: = (TC - (SP + AC)) +NC - ND
where, TC= Transformer capacity
of the substation in MVA, SP= Sub-station peak in MVA, AC= Already allotted
capacity but not availed in MVA ,NC= New transformer capacity in MVA expected
to be added and ND = New Demand expected to be added.
provided that for an embedded
consumer seeking open access within the contract demand the available open
access capacity shall be computed by using (TC-(SP-AC)) +NC - ND
(c) The STU
shall update these values on monthly basis on the first calendar day of the
month and publish it in their website.
(2) The
appropriate distribution licensee shall determine the available capacity
adopting the above methodology for allotment for the portion of the
distribution system over which open access has been requested for.
Regulation - 39. Curtailment Priority.-
When, because of constraints or
otherwise, it becomes necessary to curtail the open access service of the
customers, subject to the requirements of Bihar Electricity Grid Code, the
short-term open access customers shall be curtailed first, followed by the
medium-term open access customers and thereafter followed by long-term open
access customers. The open-access to a distribution licensee and generating
company shall be the last to be curtailed.
Provided that within a category,
the open-access customers shall have equal curtailment priority and shall be
curtailed on pro-rata basis.
SLDC shall frame guidelines for
curtailment of open access customers.
Regulation - 40. Dispute Resolution Mechanism.-
(1) The
complaints regarding all grievances and disputes relating to open access shall
be made to the respective nodal agency in writing.
(2) The nodal
agency shall investigate and endeavour to resolve the grievance/disputes
through mutual agreements.
(3) If the
nodal agency is unable to redress the grievance, dispute or the open access
customer is aggrieved with the decision of the nodal agency, the matter may be
brought before the Commission by either of the parties.
Regulation - 41. Powers to Remove Difficulties.-
If any difficulty arises in
giving effect to any of the provisions of these regulations, the Commission may
by general or special order, direct the State Transmission Utility, State Load
Dispatch Centre, intra-State licensees and the open access customer, to take
such action, as may appear to the Commission to be necessary or expedient for
the purpose of removing difficulties.
Regulation - 42. Repeal and Savings.-
(1) Save as
otherwise provided in these regulations, the Bihar Electricity Regulatory
Commission (Terms and Conditions for Open Access) Regulations, 2005, shall
stand repealed from the date of commencement of these regulations.
(2) Notwithstanding
such repeal, anything done or purported to have been done under the repealed
regulations shall be deemed to have been done or purported to have been done
under these regulations.
(3) Nothing
in these regulations shall be deemed to limit or otherwise affect the power of
the Commission to make such orders as may be necessary to meet the ends of
justice.
(4) Nothing
in these regulations shall bar the Commission from adopting in conformity with provisions
of the Act, a procedure which is at variance with any of the provisions of
these regulations, if the Commission, in view of the special circumstances of a
matter or a class of matters, deems it just or expedient for deciding such
matter or class of matters.
(5) Open
access customers to the intra-State transmission system and the distribution
system in the State on the date of coming into force of these regulations under
an existing agreement / contract shall be entitled to continue to avail such
access to the transmission and distribution system on the same terms and
conditions, as stipulated under such existing agreement/contract. Such persons
are eligible to avail long-term access or medium-term open access under these
regulations on expiry of such existing agreement/contract. However such
persons, shall have to make application with the nodal agency for long-term
access or medium-term open access category as the category may be, at least
thirty days prior to the expiry of such existing agreement/contract.
Regulation - 43. Power to amend.-
The Commission may, at any time
may add, vary, alter, modify, or amend, any provision of these regulations
FORMAT-I
CONGESTION INFORMATION AND INVITATION OF BIDDING
(to be invited by SLDC)
(See regulation 14.2.c)
|
SLDC
Bidding Invitation No. __________ |
Date
________ |
|
1 |
Customer
Application No. |
<as
provided by customer on FORMAT-1> |
Date |
|
|
2 |
Period
of Transaction |
<
1 months and more / less than 1 months / day-ahead > |
||
|
3 |
Nature
of Customer* |
<
seller/buyer/captive user/trader(on behalf of seller/buyer/captive user) > |
||
|
4 |
Customer
Name |
|
||
|
5 |
Registration
Code |
|
Valid
up to |
|
<* In terms of power transfer>
6. The anticipated congestion (transformer and electric
line/link) is as follow:
|
Network
Corridor |
Congestion
Period |
Margin/ Capacity
Available |
Total
Capacity Applied
by all
the Customers |
||||
|
Sub-station
with Transformation
capacity |
Electric Line/Link with
capacity |
Date |
Hours |
MW |
MW |
||
|
|
From |
To |
From |
To |
|
|
|
|
Intra-State
Transmission System |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Intra-State
Distribution System |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Inter-State
Transmission System |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7. In view of above please submit bid on format
[FORMAT-ST 4]. The details for bidding are hereunder:
|
(a)
Bid Invitation Date |
|
Time |
|
||||
|
(b)
Bid Submission Date |
|
Time |
|
||||
|
(c)
Bid Opening Date |
|
Time |
|
||||
|
(d)
Bids Invited for |
|
Time |
|
||||
|
Intra-State
Network Corridor |
Congestion
Period |
Margin/Capacity Available
for Bidding |
Floor
Price |
||||
|
Substation |
Electric
Line/Link |
Date |
Hours |
MW |
Rs./kWh |
||
|
|
From |
To |
From |
To |
|
||
|
Name
of Transmission System |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name
of Distribution System |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8. In case of non submission of bid, application shall be
deemed to have been withdrawn and shall not be processed.
|
Place |
Signature
(with Stamp) |
|
Date |
Name & Signature |
FORMAT-II
BID PROPOSAL
(to be submitted by the customer to SLDC)
(See regulation 14.2.c)
Ref: SLDC Bidding Invitation No. ______________
Date _________
To: Dy. General Manager (SLDC),
|
1 |
Customer
Application No. |
<as
provided by customer on FORMAT-1> |
Date |
|
|
2 |
Period
of Transaction |
<
1 months and more / less than 1 months / day-ahead > |
||
|
3 |
Nature
of Customer* |
<
seller/buyer/captive user/trader(on behalf of seller/buyer/captive user) > |
||
|
4 |
Customer
Name |
|
||
|
5 |
Registration
Code |
|
Valid
up to |
|
<* In terms of power transfer>
6. In reference to above bidding invitation, I hereby
submit my bid as follows:
|
Bidding
Details as provided by SLDC |
||||||||
|
Intra-State
Network Corridor |
Congestion
Period |
Margin/
Capacity Available |
Floor
Price |
Bid
Price to be Quoted by Bidder |
||||
|
Substation |
Electric
Line/Link |
Date |
Hours |
MW |
Paise./KWh |
Paise./KWh* |
||
|
From |
To |
From |
To |
|||||
|
Name
of Transmission System |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name
of Distribution System |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
< * Bidder shall quote price (rounded-off to whole
number) in denotation of floor price >
7. I do hereby agree that determined bid price(s) shall
be transmission and/or wheeling charges.
|
Place |
Signature
(with Stamp) |
|
Date |
Name
& Signature |