PREAMBLE
In exercise of the powers under sub-section (2) of
Section 9 and Section 19 of the Uttar Pradesh Industrial Area Development Act,
1976 (U.P. Act No. VI of 1976) the Bhadohi Industrial Development Authority
with the previous approval of the State Government hereby makes the following
regulations to regulate erection of building in the Industrial Development area
of the Bhadohi Industrial Development Authority.
Regulation - 1. Short title, commencement and application.
(1) These regulations may be called
the Bhadohi Industrial Development Area Building Regulations, 2014.
(2) They shall come into force with
effect from the date of their publication in the Gazette.
(3) Chapter I to IV shall apply to
the building activity within the urbanisable area and Chapter V shall apply to
the area designated for agricultural use by the Authority.
(4) They shall not apply to village
abadis (registered in revenue record) or to the areas declared by the Authority
for village abadi expansion. The authority shall decide the
specifications/standards to be followed by such building.
(5) Nothing in these regulations
shall apply or effect any map already sanctioned or building constructed or
under construction as per the sanctioned map.
Regulation - 2. Definitions.
(1) In these regulations, unless the
context otherwise requires
(i) 'Act' means Uttar Pradesh
Industrial Area Development Act, 1976 (U.P. Act No. VI of 1976).
(ii) 'Agricultural use' means use of
land for the purpose of the agriculture, horticultural, sericulture, animal
husbandry, poultry farming, plant nursery, piggery, dairy fanning, vegetable
farming, any activity related to agriculture or milk chilling plant.
(iii) 'Applicant' means the person who
has legal title to land or building and includes,
(i) An agent or trustee who receives
the rent on behalf of the owner;
(ii) An agent or trustee who receives
the rent of or is entrusted with or is concerned with any building devoted to
religious or charitable purposes;
(iii) A receiver, executor or
administrator or a manager appointed by any Court of competent jurisdiction to
have the charge, or to exercise the rights of the owner; and
(iv) A mortgagee in possession.
(v) 'Approved' means approved by the
Bhadohi Industrial Development Authority.
(vi) 'Area' means the Bhadohi
Industrial Development Area.
(vii) 'Authorised Officer' means an
officer authorized by the Chief Executive Officer.
(viii) 'Atrium' A sky lighted central
area, often containing plants, in some modern buildings especially for public
of commercial nature.
(ix) 'Building' means any structure
for whatsoever purpose and of whatsoever materials constructed and every party
thereof whether used as human habitation or not and includes foundation,
plinth, walls, floors, roofs, chimneys, plumbing and building services, fixed
platforms, verandah, balcony, cornice or projection, part of a building or
anything affixed thereto or any wall enclosing or intended to enclose any land
or space but does not include illumination board, outdoor display structure,
tent, shamiana, tarpaulin shelter or any other structure erected for temporary
purpose or ceremonial occasion with the permission of the Authority.
(x) 'Building activity' means
erection, re-erection, making material alteration, or demolition of any
building.
(xi) 'Building height' means the
vertical distance measured in the case of the flat roofs from the top level of
the adjoining drain to the highest point of the building and in the case of
sloping roof the mid point between the eaves level and the ridge. Architectural
features serving no other functions except that of the decoration shall be
excluded for the purpose of taking heights.
(xii) 'Building line or envelope' means
a line up to which the plinth of a building may be lawfully extended. It
includes lines specifically indicated or to be indicated in any scheme or
layout plan or in these regulations.
(xiii) 'Canopy' means a projection over
any entrance and if provided in setbacks shall be either cantilevered or
supported on columns (maximum diameter 30.0 centimeters in case of circular and
maximum 30.0 centimeters X 30.0 centimeters in case of rectangular columns).
(xiv) 'Chajja' means a slopping or
horizontal structure overhung usually provided for protection from sun and rain
or for Architectural considerations.
(xv) 'Direction' means the direction
issued by the Authority under Section 8 of the Act, and would include, unless
the context otherwise indicates, any executive instructions issued here under.
(xvi) 'Drain' means a conduit or
channel for the carriage of storm water or other used water.
(xvii) 'Drainage' means the removal of
any liquid by a system constructed for this purpose.
(xviii) 'Dwelling Unit' means an
independent housing unit with separate facilities for living, cooking and
sanitary requirements.
(xix) 'Evergreen tree' means tree that
remains green most part of the year and sheds leaves slowly throughout the
year.
(xx) 'Existing building or use' means
building structure or its use as sanctioned/approved by the competent
authority, existing before the commencement of these regulations.
(xxi) 'Farm House' means a plot of land
including construction thereon in the area designated for agricultural use by
the Authority.
(xxii) 'Floor' means the lower surface
in the storey on which one normally walks in building.
(xxiii) 'Floor Area Ratio (FAR)' means
the quotient obtained by dividing the total covered area (plinth area) on all
floors by the area of plot.
(xxiv) 'Hazardous building' means a
building or part of a building which is used for the storage, handling,
manufacturing or processing of highly combustible or explosive materials or
products which are liable to burn with extreme rapidity or which may produce
poisonous fumes or explosions, or the storage or handling or manufacturing or
processing of highly corrosive, toxic or noxious alkalis, acids or other liquids
or chemicals producing flame, fumes or explosive, poisonous, irritant or
corrosive gases and the storage, handling or processing of any material
producing explosive mixtures of dust or which result in the division of matter
into the fine particles subject to spontaneous ignition.
(xxv)'Hedge' means number of shrubs or
trees (often similar species) planted closely together in the line. A hedge may
be pruned to shape or allowed to grow to assume its natural shape.
(xxvi) 'Layout Plan' means a plan of the
entire site showing location of plots/building blocks, roads, open spaces,
entry/exits, parking, landscaping etc. indicating the activity for all land
parcels.
(xxvii) 'Licensed Technical person' means
a draftsman/architect/civil engineer/town planner recognized or licensed by the
Authority.
(xxviii) 'Master Plan' means the master
plan of the Authority in respect of the area.
(xxix) 'Mezzanine floor' means an
intermediate floor, between two floors, above ground level, accessible only
from the lower floor.
(xxx)'Mumty or Stair cover' means a structure
with a covering roof over staircase and its landing built to enclose only the
stairs for the purpose of providing protection from weather and not used for
human habitation.
(xxxi) 'Occupancy' means the main
purpose for which a building or a part of building is used or intended to be
used and classification of a building according to occupancy shall deem to
include subsidiary occupancies which are contingent upon it.
(xxxii) 'Open Space' means a space
forming an integral part of the plot left open to the sky.
(xxxiii) 'Owner' means a person, group of
persons, a company, trust, institute, registered body, State or Central
Government and its departments, undertakings and like in whose name the
property stands registered in the relevant records.
(xxxiv) 'Parking space' means a space
enclosed or unenclosed to park vehicles together with a driveway connecting the
parking space with a street permitting ingress and egress of the vehicles.
(xxxv) 'Permit' means a permission or
authorization in writing by the Authority to carry out the work regulated by
these regulations.
(xxxvi) 'Planning and Development
Directions' means Directions issued by the Authority under Section 8 of the Act
for defining architectural features, facades of the buildings, maintenance of
amenities etc. from time to time.
(xxxvii)
'Plinth'
means a portion between the surface of the surrounding ground and surfaced
floor, immediately above the ground.
(xxxviii)
'Plot'
means a piece of land enclosed by definite boundaries.
(xxxix) 'Road/Street Right of Way' means
any highway, street, lane, pathway, alley, stairway, passage way, carriage way,
footway square, bridge, whether a thorough fare or not, place on which the
public have a right of passage, access or have passed and had access
uninterruptedly for a specified period or whether existing or proposed in any
scheme, and includes all bunds, channels, ditches, storm water drains,
culverts, side walks, traffic islands, roadside trees and hedges, retaining
walls, fences barriers and railing within the street lines.
(xl) 'Road/Street Line' means the line
defining the side limits of a street.
(xli) 'Road/Street Width' means
distance between boundaries of the road measured at right angles to the course
of the road.
(xlii) 'Setback' means a line usually
parallel to the plot boundaries and laid down in each case by the Authority beyond
which nothing can be constructed towards the plot boundaries unless
specifically allowed by the Authority.
(xliii) 'Soft Landscape' means the
components of landscape design that are animate.
(xliv) 'Table' means a table annexed to
these regulations.
(xlv) 'Urbanisable Area' means the area
earmarked for any of the following uses in the Development Plan:
(a) Residential;
(b) Commercial;
(c) Industrial;
(d) Institutional;
(e) Green area;
(f) Transportation, and
(g) Special uses.
(2) Words and expressions used but
not defined in these regulations and defined in the Act, shall have the
meanings assigned to them in the Act, National Building Code, Indian Standard
Institution Code as amended from time to time. In case of any contradiction,
the provisions of the Act shall prevail.
CHAPTER II LAYOUT/BUILDING PERMIT AND OCCUPANCY
Regulation - 3. Building permit.
No person shall erect any building or a boundary
wall or fencing without obtaining a prior building permit thereof, from the
Chief Executive Officer or an Officer authorised by the Chief Executive Officer
for this purpose.
Regulation - 4. Application for building permit.
(1) Every person who intends to erect
a building within the area shall give application in the Form given at Appendix
1.
(2) The application for building
permit shall be accompanied by documents as mentioned in checklist annexed to
Appendix 1.
(3) Such application shall not be
considered until the applicant has paid the fees mentioned in Regulation No. 6.
(4) In case of objections, the fees
so paid shall not be refunded to the applicant but the applicant shall be
allowed to resubmit the plan without any additional fees after complying with
all the objections within a period of one year from the date of receipt of the
objection order.
(5) No application for building
permit shall be necessary for the following additions/alterations provided they
do not violate any of the provisions regarding general building requirements,
structure stability and fire safety requirements specified in National Building
Code:
(a) Whitewashing and painting;
(b) Plastering and patch work;
(c) Renewal of roof at the same
height;
(d) Reconstruction of portions of
building damaged by any natural calamity to the same extent as previously
approved;
(e) Internal additions/alterations
within the building envelop certified and supervised by a licensed Technical
person registered;
(f) digging or filling of earth;
An Intimation to this affect shall be submitted to
the authority in writing before commencement of construction.
Regulation -5.
5.1. Information Accompanying
Application for Layout Plan or Building Permit.
(A)
Layouts regarding sub-division of land.
(1) The site plan shall show,
(i) the boundaries of the plot and
the name and number of the properties and road abutting to the plot;
(ii) plot number of the property on
which the building is intended to be erected;
(iii) all existing building and
physical features standing on, over or under the site;
(iv) building envelope at each floor
level in relation to the site;
(v) the total plot area and the
break-up of area under different uses, roads and open space with their percentages
in terms of the total area of the plot;
(vi) total floor area ratio, ground
coverage and height of the building of each category proposed;
(vii) setbacks of total plot as well as
individual proposed plots;
(viii) details of setback, floor area
ratio, ground coverage, on each irregular shaped plots in the proposed layout
on at least 1: 500 scale;
(ix) sewerage and drainage lines up to
discharge point and water supply lines;
(x) details of boundary wall, plinth,
culvert and ramp, trees;
(xi) scale used and the direction of north
point relating to plan of proposed building;
(xii) parking plans indicating the
parking spaces for all the buildings;
(xiii) landscape plan;
(xiv) location and size of temporary
structures like stores, labour hutments, site office and such like, and
(xv) electrical load requirement.
(2) Building Plan For any proposed
structure requirement of building plan shall be as per Clause 6.1 (B), 6.1 (C)
and 6.1 (D) as the case may be.
(3) Service Plans Details of private
water supply and sewage disposal system independent of the Municipal Services,
if any and rain water harvesting system and solar passive architectures as per
Uttar Pradesh Government orders.
(4) Specification General
specification of materials to be used in different parts of the building as
given in Appendix 6.
(5) Documents as per Checklist I-C
Annexed to Appendix 1.
(B)
Residential building on plots other than group housing (flatted).
(1) The plan shall show
(i) Key Plan A key plan drawn to a
scale of not less than 1: 10,000 shall be submitted along with the application
for a development/building permit showing the boundary locations of the site
with respect to neighbourhood landmarks;
(ii) the boundaries of the plot and
the name/number of the properties and road abutting the plot;
(iii) plot number of the property on
which the building is intended to be erected;
(iv) all existing building and
physical features standing on, over or under the site;
(v) building envelope at each floor
level in relation to the site;
(vi) the total plot area and the
break-up of covered areas on each floor with their percentages in terms of the
total area of the plot;
(vii) total height of the building;
(viii) setbacks;
(ix) details of projections and
structures in setbacks;
(x) sewerage and drainage lines up to
discharge point, rain water harvesting and water supply lines;
(xi) details of boundary wall and its
plinth, culvert and ramp, trees, concealing of water tank on roof with jaali;
(xii) car parking, if applicable;
(xiii) scale used and the direction of
north point relating to plan of proposed building;
(2) Document as per Checklist 1-B
enclosed with Appendix 1.
(3) Specification: General
specification of material to be used in different parts of the building as
given in Appendix 6.
(C)
Other buildings.
(1) The site plan shall show
(i) the boundaries of the plot and
the name/number of the properties and road abutting to the plot;
(ii) plot number of the property on
which the building is intended to be erected;
(iii) all existing building and
physical features standing on, over or under the site;
(iv) building envelope at each floor
level in relation to the site;
(v) the total plot area and the
break-up of covered areas on each floor with their percentages in terms of the
total area of the plot;
(vi) total height of the building;
(vii) setbacks;
(viii) details of projections and
structures in setbacks;
(ix) sewerage and drainage lines up to
discharge point and water supply lines;
(x) details of boundary wall, plinth,
culvert and ramp, trees;
(xi) scale used and the direction of
north point relating to plan of proposed building;
(xii) parking plan indicating the
parking spaces of all the buildings;
(xiii) landscape plan;
(xiv) location and size of temporary
structures like stores, labour hutment, site office; and
(xv) electrical load requirement.
(2) Building Plan The plan of the
building, elevations and sections accompanying the application shall be drawn
to a scale not less than 1: 200
(i) the plan shall include the floor
plans of building floors together with the covered area;
(ii) the plan shall specify the use of
all parts of the building;
(iii) the plan shall show water supply,
sewerage drainage lines and the like;
(iv) the plan shall include sectional
drawing showing clearly the thickness of walls, size and spacing of framing
members and floor slabs. The section shall also indicate the height of the
rooms and the parapet. At least one cross section shall be taken through the
staircase;
(v) the plan shall show all street
elevations;
(vi) the plan shall include terrace
plan indicating the drainage and the slope of the roof;
(vii) the plan shall give dimension of
the permissible projections in setbacks;
(viii) the plan shall give direction of
the north point in relation to the plan and scale used.
(3) Building plans for all types of
multi-storeyed buildingsFor multi-storeyed building which are more 15 meters in
height, the following additional information shall be indicated in the building
plans in addition to those mentioned in clause (2)
(i) access for fire appliances and
vehicles and details of vehicular turning circle and clear motorable access way
around the building;
(ii) size (width) of main and
alternate staircase along with balcony, corridors and ventilated lobby
approach;
(iii) location and details of lift
enclosures;
(iv) location and size of fire lift;
(v) smoke stop lobby doors, if
provided;
(vi) refuse area, refuse chutes,
refuse chamber, service ducts, etc. if any;
(vii) air conditioning system, if
provided, with position of dampers, mechanical ventilation system, electrical
services, boilers, gas pipes or the like;
(viii) details of exits including
provision of ramps for hospital and special lifts;
(ix) location of generator,
transformer and switch gear room;
(x) smoke exhauster system, if any;
(xi) details of fire alarm system;
(xii) location of centralized control,
connecting all fire alarm system, built in fire protection arrangements and
public address system;
(xiii) location and dimension of static
water storage tank and pump rooms with fire fighting inlets for mobile pump and
water storage tank;
(xiv) location and details first aid
fire fighting equipment and installations;
(xv) location and details of fixed
fire protection installation such as sprinklers, wet risers, hose-reels,
drenchers, CO2 installation, etc.
(4) Service Plans Details of private
water supply and sewage disposal system independent of the Municipal Services,
if any and rain water harvesting system and solar passive architecture as per
the Government of Uttar Pradesh orders.
(5) Specification General
specification of material to be used in different parts of the building as
given in Appendix 6.
(6) Documents as per Checklist 1-B
annexed to Appendix 1.
(D)
Temporary building.
(1) The site plan shall show
(i) the boundaries of the plot and
the name/number of the properties and road abutting to the plot;
(ii) plot number of the property on
which the building is intended to be erected;
(iii) all existing building and physical
features standing on, over or under the site;
(iv) total height of the building;
(v) setbacks;
(vi) details of projections and
structures in setbacks;
(vii) sewerage and drainage lines up to
discharge point and water supply lines;
(viii) scale used and the direction of
north point relating to plan of proposed building;
(ix) location and size of temporary
structures like stores, labour hutment, site office or such like temporary
structures.
(2) Building Plan The plan shall be
submitted for building other than labour hutment. The plan of the building,
elevations and sections accompanying the application shall be drawn to a scale
not less than 1: 200
(i) the plan shall include the floor
plans of building floors together with the covered area;
(ii) the plan shall specify the use of
all parts of the building;
(iii) the plan shall show water supply,
sewerage drainage lines and the like;
(iv) the plan shall include sectional
drawing showing clearly the thickness of walls, size and spacing of framing
members and floor slabs. The section shall also indicate the height of the
rooms and the parapet.
(v) the plan shall show all street
elevations;
(vi) the plan shall give indication of
the north point in relation to the plan and scale used.
(3) Specification General
specification of materials to be used in different parts of the building as
given in Appendix 6.
(4) Documents as per Checklist 1-D
annexed to Appendix 1.
Site plan shall be drawn to a scale as follow:
Table
|
Site area
|
Scale
|
|
Up to 0.1 hectare
|
Not less than 1: 200
|
|
Up to 0.1 hectare
1 hectare
|
Not less than 1: 500
|
|
More than 1 hectare
|
Not less than 1: 1000
|
Recommended notation for colouring of plans.
The site and building plans shall be coloured as
specified in the table given below where items of work are not identified, the
colouring notation used shall indexed:
|
Sl. No.
|
Item
|
Site Plan
|
Building Plan
|
|
1.
|
Plot lines
|
Thick Green
|
Thick Green
|
|
2.
|
Existing street
|
Green
|
|
|
3.
|
Permissible building line
|
Thick dotted green
|
|
|
4.
|
Existing work (Outline)
|
Green
|
Green
|
|
5.
|
Work proposed to be demolished
|
Yellow hatched
|
Yellow hatched
|
|
6.
|
Proposed
(a) Additions/Alterations
(b) Entirely new work
|
Red
Not to be coloured
|
Red
Not to be coloured
|
|
7.
|
Drainage
|
Red dotted
|
Red dotted
|
|
8.
|
Water Supply
|
Green dotted thin
|
Green dotted thin
|
5.4. Preparation and signing of plans.
All plans shall be prepared and signed by Licensed
Technical person as per Appendix 12.
Regulation - 6. Building permit fee, completion fees, temporary structures permit fees and calculation thereof.
(1) Applicant shall deposit building
permit fees as follows:
(i) Residential building Rs. 2 per
square meter covered area on all floors.
(ii) Commercial building Rs. 10 per
square meter covered area on all floors.
(iii) For all other type of building
Rs. 5 per square meter covered area on all floors.
(iv) For layout plan Rs. 1 per square
meter for the plot area up to 10.0 acres and Rs. 0.50 per square meter for area
above 10.0 acres.
(2) If the use of the building is
changed then the fee in case of additions and alternation of building, shall be
calculated with reference to the use proposed.
(3) In case of re-erection of
existing building after demolition, fees chargeable shall be the same as
erection of new building.
(4) The fee for revised plan of a
building which has already been sanctioned, shall be one-fourth of the fee
chargeable on the sanctioned plan, subject to condition that the covered area
of the building has not increased than in the original sanctioned plan.
(5) The area covered in the basement,
as the case may be shall be counted towards the covered area for purpose of calculation
of fees.
(6) The fee is case of building with
principal and subsidiary occupancies, in which the fees leviable are different
than the fees for the total building schemes, shall be as per the rates for
individual occupancies.
(7) The revalidation fee of a
building permit shall be 10 per cent of the original building permit fee paid
with the application, if the application is made within the period of validity
of the building permit. In case the building is under construction as per the
sanctioned plans and the application is made after the validity period from the
date of sanction then the revalidation fee shall be original building permit
fee.
(8) In case of construction without
applying for building permit a penalty at the rate of Rs. 1000 per square metre
of covered area shall be levied, provided all the provisions as per Building
Regulation are complied with.
(9) In case of construction without
revalidation, a fees of Rs. 20 per square meter of covered area shall be levied
if all provisions as per byelaws are complied with.
(10) In case of revision in layout
plan, revision in layout fees shall be charged 1.25 times for portion of plot
area of which the layout is submitted for sanction or completion.
(11) Malba charges of Rs. 13.50 per
square meter shall be levied over total covered area for all building. In case
of plot size above 2000 square meter the same may be exempted if an affidavit
duly notarized, is submitted by applicant that all malba during construction
shall be kept within the plot.
(12) The applicant shall deposit
completion fees as follows
(i) Residential building
(a) Individual residential plots Rs.
200 only.
(b) Group Housing Rs. 1.0 per square
meter of covered area on all floors.
(ii) Commercial building Rs. 5 per
square meter of covered area on all floors.
(iii) For all other type of building
Rs. 2.5 per square metre of covered area on all floors.
(iv) For layout plan Rs. 0.5 per
square metre for plot area up to 10.0 acres and Rs. 0.25 per square metre for
area above 10.0 acres.
In case even after two objection letters issued by
Authority if rectification of all objection is not done then Rs. 500 shall be
levied towards site visit fees for each subsequent visit.
(13) The applicant shall deposit 25
per cent of the building permit fees for temporary structures other than labour
hutment as per individual use of the structure. For labour hutments fees shall
be Rs. 0.25 per square meter of covered area.
(14) Water, sewer and other service
connection charge shall be paid as levied by the Authority.
(15) The Authority may be empowered to
revise the fees/Charge mentioned in this clause.
Regulation - 7. Withdrawal of application.
The applicant may withdraw his application for a
building permit at any time prior to the sanction and such withdrawal shall
terminate all proceedings with respect to such applications but the fees paid
shall in no case be refunded.
Regulation - 8. Security of the building permit.
(1) The Authorized Officer shall
verify or cause to be verified the facts given in the application for permit,
and enclosures. The title of the land shall also be verified.
(2) The authorized officer shall
check the information listed in Regulation 5.1(B) for residential buildings on
plots (other than group Housing flatted).
(3) For layout plan, other buildings
and temporary structures the Licensed Technical Person shall provide the
information in Regulations 5.1(A), 5.1(C) and 5.1(D) respectively and provision
of fire safety requirement, public convenience, safety provisions and other
relevant laws. The Licensed Technical Person shall also be responsible for all
other provisions as per Building Regulations, Planning and Development
Directions, National Building Code, Indian Standard Institution standards and
such other provisions as required by the Authority from time to time.
(4) The Owner and Licensed Technical
Person shall jointly indemnify the Authority against violation of these
Regulation Planning and Development Directions and provisions of National
Building Code.
(5) The authority, however reserves
the right to perform test checks by complete scrutiny of any of the plans
submitted for approval.
(6) In case of any violation, the
Licensed Technical Person shall be black listed under intimation to concerned
registration organization from practicing in the Notified area for a period of
5 years.
(7) In case owner is found
responsible for violation, action may be taken as per provision in lease deed.
Regulation - 9. Sanction or refusal of building permit.
(1) After filing of the application
for building permit duly certified by the Licensed Technical Person as per
Appendix 4 the applicant can commence the construction in accordance with the
requirement of Zoning Regulations of Master Plan, these Regulation or Planning
and Development Directions. In case of any objections are found during scrutiny
of the plans, the same shall be got rectified by the applicant and if any
violations are found during or after the construction, the owner shall be
required to rectify the same to the satisfaction of the Authority within a
period of 15 days from the date such violations are intimated to the owner. In
case the owner fails to comply, the Authority shall ensure compliance and the
expenditure incurred on doing so shall be recovered from the owner before issue
of completion certificate.
(2) If within thirty days of the
receipt of the application, refusal or sanction is not granted, the application
with its annexures shall be deemed to have been allowed and the permit
sanctioned provided such fact is immediately brought to the notice of the Chief
Executive Officer in writing by the applicant within twenty days after the
expiry of the period of thirty days but nothing herein shall be construed to
authorize any person to do anything in contravention of these Regulations and
Planning and Development Directions prepared under Section 8 of the Uttar
Pradesh Industrial Area Development Act, 1976.
(3) In case of refusal, the
Authorized Officer shall give reasons and quote the relevant provision of the
regulation which the plan contravenes, as far as possible in the first instance
itself and ensure that no new objections are raised when they are re-submitted
after compliance of earlier objections.
(4) Once the plans have been
scrutinized and objections, if any, have been pointed out, the applicant shall
modify the plans to comply with the objections raised and re-submitted them. If
the objections remain unresolved for a period of one year, the permit shall be
refused.
Regulation - 10. Appeal against refusal or sanction with modification of a building permit.
Any applicant aggrieved by an order refusal of a
building permit or its sanctions with modification may within thirty days from
the date of communication of such order, appeal to the Authority or Officer
Authorized in this behalf. The decision of the Authority, on such appeal shall
be final, conclusive and binding.
Regulation - 11. Duration of validity of a building permit.
(1) A layout plan or building permit
sanctioned under these regulation shall remain valid for the period as
specified in the lease deed conditions and normally application for Completion
Certificate has to be submitted within this period. In special cases or
category of cases, depending on the nature of formalities remaining
unfulfilled, the Chief Executive Officer may extend this period for submission
of completion certificate as he may deem fit. The nature of such formalities
and period for extension should be specified by a general order or guidelines
issued by the Chief Executive Officer. In case part completion has been taken
on the plot, then validity of layout plan or building permit shall be for 5
years.
(2) Validity of building permit for a
temporary structure shall be 5 years or such period as specified in the lease
deed whichever is earlier. If the period specified in the lease deed is less
than 5 years then beyond such specified period any request for extension, if
any, will be granted only in extraordinary circumstances on a case to case
basis by the Chief Executive Officer subject to adequate justification and on
payment of prescribed fees. In case period specified in lease deed is more than
5 years then extension shall be granted in multiple of 2 years after approval
of the Chief Executive Officer.
(3) After lapses of validity period
the applicant shall be liable to remove all such structures and completion
certificate shall not be granted without removal of such structures.
Regulation - 12. Additional or alterations during construction.
If any external additions or alterations from the
sanctioned plans are intended to be made permission of the Chief Executive
Officer shall be obtained in writing before the proposed additions/alterations
are carried out. It shall be incumbent upon the applicant to whom a building
permit has been sanctioned to submit amended plans for such additions or
alterations. The provisions relating to an application for permit shall also
apply to such amended plans with modification that the time limit referred to
in Regulation 9(ii) shall be thirty days.
Regulation - 13. Cancellation of permit for building activity.
If any time after the permit to proceed with any
building activity has been sanctioned, the Chief Executive Officer is satisfied
that such permit was sanctioned in consequence of any material
misrepresentation or fraudulent statement contained in the application given or
the information furnished, the Chief Executive Officer may, after opportunity
of being heard, cancel such permit and any work done thereunder shall be deemed
to have been done without permit. The Licensed Technical Person found
responsible for the same shall be blacklisted and debarred for 5 years from
practicing in the notified area. If the owner is found responsible for
violations, action may be taken as per lease deed.
Regulation - 14. Work to be carried out in full accordance of Zoning Regulations, Building Regulations and Directions.
Neither granting of the permit nor the approval of
drawings and specifications, nor inspection made by the Authority during such
erection shall in any way relieve the owner of such building from full
responsibility for carrying out the work in accordance with the requirements of
Zoning Regulations of Master Plan, these Regulations or Planning and
Development Directions. In case any violations are found during construction or
after obtaining completion the owner shall be required to rectify the same to
the satisfaction of the Authority within a period of 15 days from the time such
violations are intimated to the owner. In case the owner fails to comply, the
Authority shall ensure compliance and the expenditure incurred on doing so
shall be recovered from the owner before issue of completion certificate. In
case completion certificate has already been obtained, such expenditure shall
be recovered from the owner, if not paid within stipulated time, as arrears of
land revenue.
Regulation - 15. Documents at site.
The following documents shall be kept at site
during the construction of the building and for such a period thereafter as
required by the Authority:
(i) A copy of building permit.
(ii) Copy of approved drawings.
If the above documents are found missing for two
consecutive visits by the Authorized Officer of the Authority a penalty of Rs.
1000 shall be levied for each such lapse. In case building permit has not been
granted and applicant has applied for building permit then copy of receipt of
documents shall be kept.
Regulation - 16. Notice of completion.
Every owner shall have to submit a notice of
completion of the building to the Authority regarding completion of work
described in the building permit as per Appendix 9 accompanied by the documents
as per checklist annexed with Appendix 9.
Regulation - 17. Occupancy certificate necessary for occupation.
No building erected, re-erected or altered, shall
be occupied in whole or part until the issue of occupancy certificate by the
Chief Executive Officer in the form given in Appendix 11:
Provided that if the Chief Executive Officer fails
to issue the occupancy certificate or send any intimation showing his inability
to issue such certificate within 40 days of the date of receipt of completion
certificate, the building may be occupied without waiting for such certificate.
Intimation to this effect shall have to be sent to the Authority by the owner
before occupying the same.
Regulation - 18. Issue of occupancy certificate regarding Multi Storeyed building.
In the case of building identified in Clause
5.1(C)(3) the work shall also be subjected to the inspection of the Chief Fire
Officer, Uttar Pradesh Fire Service and the occupancy certificate shall be
issued by the Authority only after the clearance from the Chief Fire Officer
regarding the completion of work from the fire protection point of view.
CHAPTER III GENERAL REQUIREMENTS
Site Requirements
Regulation - 19. Distance from electric lines.
No verandah, balcony, or like shall be allowed to
be erected or any additions or alterations made to any building within the
distance between the building and any overhead electric supply line as indicated
below.
|
|
Vertically
|
Horizontally
|
|
(a) Low and medium voltage
|
2.4 meters
|
1.2 meters
|
|
(b) High voltage lines up to and including 33000
volts
|
3.7 meters
|
1.8 meters
|
|
(c) Extra high voltage lines beyond 33000 volts
|
(+0.03 meters for every additional 33000 volts or
part thereof)
|
(+0.03 meters for every additional 33000 volts or
part thereof)
|
Regulation - 20. Site and land use pattern.
Notwithstanding anything contained in these
regulations, no building permit on any site shall be sanctioned if:
(i) The proposed land use does not
correspond to the land use in the Master Plan.
(ii) If the construction of any
building is for public worship, which in the opinion of the Authority will
affect the religious feelings of any class or persons in the vicinity thereof.
(iii) Place which will be a source of
annoyance to, or injurious to the health of the inhabitants of the
neighbourhood.
Regulation - 21. Ground coverage, Floor Area Ratio, Height and setbacks.
(A) Residential Buildings on plots
(other than flatted group housing)
(a-1) Ground coverage, Floor Area
Ratio, height and setbacks shall be as per Table 1 appended to these
regulations.
(a-2) Other provisions:
(I) The directions of side, rear set
back and gate shall be as per the Zonal Plan and directions prepared by
Authority from time to time.
(II) In case of plots being
amalgamated, the set back lines in front and abutting adjoining property are to
be followed as per Zonal Plan.
(III) Sub-division of individual
residential plot or building constructed on it shall not be allowed.
(IV) Only two dwelling units and a
servant quarter shall be allowed on a plot.
(V) No construction of any kind shall
be permitted beyond the building envelope (on set backs) except
(i) A Chajja (projection) of maximum
width of 0.75 meters at lintel or roof level. No construction of any type shall
be permitted over projections.
(ii) Underground water tanks with top
flush with the adjoining ground level.
(iii) In plots of 200 square meter and
above, if required, a temporary guard room of porta cabin 1.5 meter x 1.5 meter
shall be permitted after approval by the Authority.
(iv) Canopy projections of 4.5 meter x
2.4 meter in front or side set backs (maximum 2 numbers) in plots where front
set back is 4.5 meter or more and only one such canopy in side back where front
set back is less than 4.5 meter.
No construction of any type shall
be permitted over the canopy projection. The canopy may be supported by
circular column of maximum 30 centimeters diameter or rectangular columns of 30
centimeters x 30 centimeter size.
(v) Open Plinth steps:
(a) Open plinth steps and plinth ramp
in front and rear setback.
(b) Open plinth steps and plinth
ramps beyond a depth of 0.6 meters in side setback.
(vi) Two end walls up to 0.75 meter
from setback lines.
(vii) In case of corner plots up to 200
square meter category, load bearing columns max size 300 millimeter x 300
millimeter in side setback maximum 2 numbers may be permitted.
(viii) Other features as mentioned in
Table 3.
(ix) Open ramps for movement of
vehicles in side setback only.
(I) FAR shall also include
Mezzanine
Mumty for staircase
Cupboards
Balconies
Bay windows Pergola shall be counted towards Floor
Area Ratio calculation as per table given below:
|
Sl. No.
|
Pergola open from number of sides
|
Pergola with minimum 50 per cent voids, area to
be added towards Floor Area Ratio
|
Pergola with less than 50 per cent voids, area to
be added towards Floor Area Ratio
|
|
1.
|
Four sides
|
Nil
|
Exact area under pergola
|
|
2.
|
Three sides
|
Exact area under pergola
|
1.25 times the Exact area under pergola
|
|
3.
|
Two sides
|
1.5 times the Exact area under pergola
|
2 times the Exact area under pergola
|
|
4.
|
One sides
|
2 times the Exact area under pergola
|
Not permitted
|
(II) Floor Area Ratio shall not
include
(i) A Chajja projection (in setbacks)
of a width of 0.75 meter at lintel or roof level. No construction of any type
or any material shall be permitted over projections other than mentioned
herewith.
(ii) Canopy projections of 4.5 meter x
2.4 meter in front or side set back (maximum 2 numbers), in plots where front
set back is 4.5 meter or more and only one such canopy in side setback where
front setback is less than 4.5 meters. No construction of any type shall be
permitted over the canopy projections (in setbacks).
(iii) Basement (only single basement)
equivalent to ground coverage shall be permitted, if used for parking, services
and storage.
(iv) Stilt area of non-habitable
height proposed to be used for parking, landscaping etc.
(v) Loft up to 1.2 meter height.
(vi) Other features as mentioned in
Table 3.
(vii) In case of corner plots up to 200
square meter category load bearing columns maximum 300 millimeter x 300
millimeter in side setback maximum 2 numbers may be permitted.
(viii) Open ramps for movement of
vehicles in side setback only.
(III) (i) Basement area shall not
exceed beyond building envelope.
(ii) The height of any basement shall be maximum
1.2 meter (including slab) above the top level of the drain. The maximum height
of the basement from floor to ceiling shall be 4 meter.
(IV) Minimum requirement for
sanction/completion: 25 per cent of maximum permissible ground coverage or 40.0
square meter whichever is more with provisions of a functional toilet/bath and
kitchen subject to maximum of permissible ground coverage. Provision of
following items in building shall be mandatory for issue of completion
certificate.
(i) Flooring;
(ii) Electrical wiring whereas
electrical fittings shall not be mandatory;
(iii) Plumbing and chrome plated
fittings in at least one toilet and kitchen;
(iv) Trees as per Table No. 7 or direction
issued from time to time whichever is higher;
(v) Number plate;
(vi) Boundary wall shall not be
mandatory. Some feature to identify the plot boundary has to be provided e.g.
barded wire fencing, hedge, boundary up to plinth level etc;
(vii) Internal and external finishing
(Plastering and transparentwashing shall not be mandatory);
(viii) Mouse shall be lockable i.e. all
external doors and windows shall have to be provided. In case grill is provided
in the windows then fixing of glasses in the windows panes shall not be mandatory;
(ix) No overall violation of Building
Regulations, Zonal Plan Regulations and Master Plan should be there in the
overall building at the time of issue of occupancy certificate.
(B) Group Housing (Flatted and
cluster type)
|
b-1 Minimum Plot Area
|
2000 square meter
|
|
b-2 Maximum permissible
|
|
|
(I) Ground coverage
|
30 per cent
|
|
(II) Floor Area Ratio
|
175
|
Height for buildings above 30 meters in height
clearance from Airport Authority shall have to be taken.
Note. Total height shall be counted from drain top to
top of the building except for
Illuminated boards
Water Tanks and
Other such structures with non-usable height.
The Chief Executive Officer reserves the right to
permit additional height at focal points wherever it is considered appropriate.
b-3 Minimum permissible set backs
as per Table No. 2
b-4 Maximum permissible density
shall be as per lease deed. Maximum density variation of 50 per cent and +5 per
cent shall be allowed.
b-5 Other provisions
No construction of any kind shall be permitted beyond
the building envelope (on setbacks) except
(i) A Chajja (projection) of maximum
width of 0.75 meter at lintel or roof level. No construction of any type or any
material shall be permitted over projections other than mentioned herewith.
(ii) Underground water tanks with top
flush with the adjoining ground level.
(iii) Watchman Shelters and Watch
Towers:
No projection of watchman shelters and watch towers
shall be allowed outside the plot line.
Maximum height of watchman shelter shall be 4
meters and watch towers 15 meters. Total area, as mentioned below, under such
shelters shall be split up in desired number of watch man shelter and watch
towers:
|
Sl. No.
|
Plot size
|
Total area for watchman shelter and watch tower
|
Maximum area under each watchman shelter
|
Maximum area under each watch tower
|
|
1.
|
Up to 0.5 acres
|
15 square meter
|
15 square meter
|
5 square meter
|
|
2.
|
Above 0.5 acres up to 10 acres
|
30 square meter
|
24 square meter
|
5 square meter
|
|
3.
|
Above 10 acres up to 25 acres
|
45 square meter
|
24 square meter
|
5 square meter
|
|
4.
|
Above 25 acres up to 50 acres
|
60 square meter
|
24 square meter
|
5 square meter
|
|
5.
|
Above 50 acres for an additional 50 acres
|
An additional 10 square meter and part thereof
|
24 square meter
|
5 square meter
|
(iv) Canopy projection of area as
mentioned in Table 4. No construction of any type shall be permitted over the
canopy projections except those mentioned in Table 3.
(v) Open plinth steps and plinth
ramps within 1.0 meter from setback line in the setback area.
(vi) Two end walls up to 0.75 meter
from setback lines.
(vii) Meter room as per Clause
22(C)(b-II)(vi).
(viii) Open transformers without any
permanent enclosure keeping in view the necessary safety requirements.
(ix) In specific cases water bodies
and pools, and other landscape features may be permitted with approval from the
Chief Executive Officer provided the fire safety requirements are not affected.
(x) Other features as mentioned in
Table 3.
(xi) Rockery, well and well
structures, water pool, swimming pool (if uncovered), uncovered platform around
tree, tank, fountain, bench, chabutra with open top and unenclosed by side
walls, compound wall, gate, slide swing, culverts on drains.
(xii) Any other feature, primarily
ornamental in nature, not enclosing or covering space of commercial use may be
permitted by the Chief Executive Officer depending on case to case basis.
(xiii) No temporary structure shall be
permitted in front setback or setback towards sides abutting road.
(xiv) Open generator set, filtration
plant, Electrical distribution equipments, feeder pillars, telephone
distribution equipments shall be permitted in open setback as a service utility
provided due clearance from the Fire Departments has been taken.
(I) Floor Area Ratio shall also
include
(i) Mezzanine
(ii) Mumty for stair cover
(iii) Cupboards
(iv) Balconies
(v) Bay windows
(vi) The shafts provided for lifts
shall be taken for covered area calculations only on one floor and included in
ground coverage
(vii) Pergola shall be counted towards
Floor Area Ratio calculation as per table given below
|
Sl. No.
|
Pergola open from number of sides
|
Pergola with minimum 50 per cent voids, area to
be added towards Floor Area Ratio
|
Pergola with less than 50 per cent voids, area to
be added towards Floor Area Ratio
|
|
1.
|
Four sides
|
Nil
|
Exact area under pergola
|
|
2.
|
Three sides
|
Exact area under pergola
|
1.25 times the exact area under pergola
|
|
3.
|
Two sides
|
1.5 times the exact area under pergola
|
2 times the exact area under pergola
|
|
4.
|
One sides
|
2 times the exact area under pergola
|
Not permitted
|
(II) Floor Area Ratio shall not
include
(i) A Chajja projection (in setbacks)
of a width of 0.75 meter at lintel or roof level. No construction of any type
or any material shall be permitted over projections.
(ii) Canopy projections of area as
mentioned in Table No. 4. No construction of any type shall be permitted over
the canopy projection except those mentioned in Table 3.
(iii) Basement (up to double basement),
shall be permissible within the setback line or each floor. However maximum
permissible area under basement shall be limited up to:
(1) Basement area, if used for
services, storage etc. then maximum area under such facilities shall be
equivalent to maximum permissible ground coverage.
(2) Basement area, if used for
parking, then area equivalent to parking requirement shall be permitted.
(3) Basement, if used for any other
use, shall be permitted up to the setback line and this useable area shall be
included in the FAR of the building. Stilt area of non-habitable height 2.25
meters from beam bottom proposed to be used for parking, landscaping etc.
(iv) Loft up to 1.2 meter height.
(v) Other features as mentioned in
Table 3.
(vi) Rockery, well and well
structures, water pool, swimming pool (if uncovered), uncovered platform around
tree, tank, fountain, bench, chabutra with open top and unenclosed by side
walls, compound wall, gate, slide swing, uncovered staircase (unenclosed and uncovered
on three sides except for 0.9 meter high railing/wall and open to sky),
overhead tanks on top of buildings, open shafts, culverts on drains.
(vii) Open ramps with no are enclosed
below it of usable height of 2.1 meter.
(viii) Any other feature purely ornamental
in nature not enclosing or covering space of commercial use may be permitted by
the Chief Executive Officer depending on case to case basis.
(ix) Only in case of commercial
building, Atrium shall be kept free from FAR and ground coverage. In case any
commercial activity is proposed in Atrium or any saleable area or any other
structure which is counted in FAR and ground coverage its respective area shall
be added in total FAR and ground coverage.
(III) All the common facilities
prescribed below will have to be provided and shall be counted in the
prescribed Floor Area Ratio Group Housing.
(i) Air-conditioning plant,
electrical installation, generator room, water works, water-tanks etc.
(ii) Watchmen shelters and watch
towers,
(iii) Garbage and lift shafts,
(iv) Fire escape staircases,
(v) Toilet blocks for visitors,
drivers, guards etc.
(vi) Shops and community facilities as
per population norms as specified in the lease deed. In case of plots were
minimum population required for provision of convenient shopping is not
achieved then
(a) Area for convenient shopping
equivalent to 0.75 per cent of total plot area shall be allowed.
(b) Minimum four kiosks of 40 square
feet of carpet area and two shops of 100 square feet carpet area shall be
provided mandatory. Shops can, be amalgamated however maximum carpet area of
such shop shall not exceed 200 square feet.
(c) Maximum height of shops and
kiosks shall be 4.0 meter from floor to ceiling.
(d) Ground coverage and Floor Area
Ratio shall be as per convenient shopping norms.
(e) In case of provision of shopping
in lease deed the same shall prevail.
(vii) Mumty, machine room for lifts.
(viii) Any other utilities as decided by
Chief Executive Officer depending on its requirement.
(IV) Distance between two adjacent
building blocks shall not be less than half of the height of tallest building.
(V) The Chief Executive Officer shall
have a right to impose such restriction and limitations as to the number of
storeys and extent of height of the building as he considers fit where
protected areas, ancient or historical monuments lie within a radius of one and
half kilometre from the boundary line of such group housing.
(VI) In density calculation each
servant quarter will be reckoned as half dwelling unit.
(VII) A group housing shall conform to
the provisions of the Sector Plan and Zonal Development Plan of the area in
terms of setbacks, ground coverage, Floor Area Ratio and height restrictions,
if any.
(VIII) The provisions contained in this
clause shall not apply to housing for economically weaker sections, low income
groups, informal sector undertaken by the State Government, Authority or any
other public body approved in this behalf by the State Government.
(IX) Basement (up to double basement)
in the Group Housing shall be permitted within the setback line only i.e. area
after leaving setback. The internal height of the basement (floor to ceiling)
shall be minimum 2.4 meter and maximum 4.5 meter. Except wherever height of
equipments such as electric generator, air conditioner and fire hydrant etc. is
more than 4.5 meter additional height equivalent to height of equipments shall
be permitted, subject to a maximum of 9.0 meters.
(X) The height of any basement,
including slab, shall be maximum 1.2 meter above the top of drain level. The
height of basement shall be maximum 1.2 meters (including slabs) above the
plinth of boundary wall. In case the basement is flush with the ground level
adequate light and ventilation shall be ensured.
(XI) Toilet block for visitors,
drivers etc. comprising of a water closet, a bath and 2 urinals shall be
provided.
(XII) In case of group housing having
more than two storey, steps must be taken to ensure water at higher floors. For
this purpose booster pumps and overhead tanks must be installed.
(XIII) At least one of the lifts
provided shall be of the specification of goods lift.
(XIV)Minimum requirement for
sanction/completion: Minimum covered area required for completion shall be as
per lease deed on Memorandum of Understanding. Provision of following items in
building shall be mandatory for issue of completion certificate:
(i) Flooring;
(ii) Electrical wiring;
(iii) Plumbing and chrome plated
fittings and fixtures;
(iv) Parking and landscaping as per
Table No. 6 and Table No. 7 respectively or directions issued from time to time
whichever is higher;
(v) Number plate and illumination
board as per direction amended or direction issued from time to time;
(vi) Internal and external finishing
(Plastering may not be mandatory);
(vii) Boundary wall and gates shall be
mandatory;
(viii) Buildings shall be lockable i.e.
all external doors and windows shall be provided. In case grill is provided in
the windows the fixing of glass in the windows pane shall not be mandatory;
(ix) No overall violation should be
there in the overall building or site at the time of issue of occupancy
certificate;
(x) Any other special provision as
mentioned in the lease deed;
(xi) In case of completion of whole
project, all temporary structures to be removed.
In case if any special clause is mentioned in the
lease deed or Memorandum of Understanding then the requirement mentioned in the
same shall be applicable.
(C) All other Buildings
(a) Industrial building/film centre:
(a-1) Setbacks, Ground Coverage,
Floor Area Ratio, Height Limitations:
|
Sl. No.
|
Plot Area (square meter)
|
Maximum Ground coverage (%)
|
Maximum Floor Area Ratio
|
|
1.
|
Up to 100
|
60
|
120
|
|
2.
|
Above 100 but not exceeding 500
|
60
|
100
|
|
3.
|
Above 500 but not exceeding 1000
|
55
|
80
|
|
4.
|
Above 1000 but not exceeding 2000
|
55
|
80
|
|
5.
|
Above 2000 but not exceeding 5000
|
55
|
70
|
|
6.
|
Above 5000 but not exceeding 12000
|
55
|
70
|
|
7.
|
Above 12000 but not exceeding 20000
|
50
|
65
|
|
8.
|
Above 20000
|
50
|
60
|
Notes:(i) Setbacks as per Table No. 2.
(ii) There will be no height restriction provided
that for buildings of height 30 meter and above, necessary clearance from
Airports Authority of India shall be taken.
(iii) Total height shall be counted from top of
drain to top of the building without exemption.
(b) Building other than Group
Housing, Individual Residential Plots, Industrial, Informal Sector and
Horticultural Nursery.
(b-1) Ground coverage, Floor Area
Ratio, height and setbacks
|
Sl. No.
|
Use
|
Maximum ground coverage
|
Maximum FAR
|
Maximum height in meters
|
|
1.
|
Convenient Shopping Centre*
|
40%
|
80
|
15.0
|
|
2.
|
Sector Shopping*
|
40%
|
120
|
15.0
|
|
3.
|
Sub-District Centre, Shopping along Street and
other Master Plan level Shopping Centres*
|
30%
|
150
|
No limit**
|
|
4.
|
Hotel
|
30%
|
215
|
No limit**
|
|
5.
|
Banks*
|
30%
|
150
|
No limit**
|
|
6.
|
Cinema
|
***
|
***
|
***
|
|
7.
|
Dharam Kanta*
|
30%
|
30
|
15.0
|
|
8.
|
Petrol Pump*
|
30%
|
30
|
15.0
|
|
9.
|
Wholesale Market*
|
30%
|
130
|
No limit**
|
|
10.
|
Gas Godown*
|
30%
|
30
|
15.0
|
|
11.
|
Warehousing/Godowns
|
30%
|
130
|
No limit**
|
|
12.
|
Dharamshala/Lodge/Guest House
|
30%
|
130
|
30.0
|
|
13.
|
Community Centre, Club Building and Barat Ghar
|
30%
|
85
|
15.0
|
|
14.
|
Fire Station
|
30%
|
85
|
15.0
|
|
15.
|
Police Station
|
30%
|
100
|
15.0
|
|
16.
|
Post Office
|
30%
|
100
|
15.0
|
|
17.
|
Sport and Amusement Complex, Swimming Pool, Shooting
Range
|
20%
|
40
|
15.0
|
|
18.
|
Low Density Sports and Amusement Complex,
Recreational Club, Social Cultural Centre
|
10%
|
20
|
15.0
|
|
19.
|
Bus Terminal, Light Rail Transit Terminal, Bus
Depots/Workshop, Booking Offices, Transport Nagar
|
30%
|
130
|
No limit**
|
|
20.
|
Taxi Stand
|
10%
|
10
|
15.0
|
|
21.
|
Nursery School/Creche
|
40%
|
85
|
15.0
|
|
22.
|
All Other Educational Institutions, Research and
Training Centre, Testing Laboratory
|
30%
|
130
|
No limit**
|
|
23.
|
Religious Building
|
30%
|
60
|
15.0
|
|
24.
|
Dispensary
|
30%
|
60
|
15.0
|
|
25.
|
Hospital, Naturopathy, Specialized Health Centre,
Nursing Home
|
30%
|
130
|
No limit**
|
|
26.
|
Government, Semi-Government, Corporate
|
30%
|
150
|
No limit**
|
|
27.
|
Hostel, Boarding House
|
30%
|
130
|
30
|
|
28.
|
Museum, Art Gallery and Exhibition Center
|
30%
|
130
|
No limit**
|
|
29.
|
Other Utilities
|
30%
|
85
|
15.0
|
|
30.
|
Multiplex
|
30%
|
As per Government Order
|
No limit**
|
|
31.
|
Information Technology and Information Technology
Enabled Services
|
30%
|
187.5
|
No limit.
|
Notes:
(I) Setback shall be as per Table No.
2.
(II) *Setbacks shall be as per control
drawing, whenever such control drawings are prepared by the Authority.
(III) Total height shall be counted
from drain top to top of the building except for
Illuminated boards
Water Tanks and
Other such structures with non-usable height
(IV) In case of any activity other
than listed above, the ground coverage and FAR shall be decided by the
Authority from time to time.
(V) **There will be no height
restriction provided that for buildings of height 30 meter and above, necessary
clearance from Airport Authority of India shall be taken. Total height of the
building shall be counted from the top of the drain to top of the building
without exemption.
(VI) ***As per Cinematography Act of
Uttar Pradesh.
(c) Other Provisions
(I) Permissible structures in setback
(i) A Chajja (projection) of maximum
width of 0.75 meter at lintel or roof level. No construction of any type or any
material shall be permitted over projections other than mentioned herewith.
(ii) Underground water tanks with top
flush with the adjoining ground level.
(iii) Canopy projections of area as
mentioned in Table 4. No construction of any type shall be permitted over the
canopy projection except those mentioned in Table 3.
(iv) Open plinth steps and plinth
ramps within 1.0 meter from setback line.
(v) Watchman Shelters and Watch
Towers.
No projection of watchman shelters and watch towers
shall be allowed outside the plot line. Maximum height of watchman shelter
shall be 4 meter and watch towers 15 meters. Total area as mentioned below,
under such shelters shall be split up in desired number of watch man shelter
and watch towers.
|
Sl. No.
|
Plot size
|
Total area for watchman shelter and watch tower
|
Maximum area under each watchman shelter
|
Maximum area under each watchmen tower
|
Maximum area under each time office
|
Total area under each watch tower
|
|
1.
|
Up to 0.5 acres
|
15 square meter
|
15 square meter
|
5 square meter
|
Nil
|
Nil
|
|
2.
|
Above 0.5 acres up to 10 acres
|
30 square meter
|
24 square meter
|
5 square meter
|
Nil
|
Nil
|
|
3.
|
Above 10 acres up to 25 acres
|
45 square meter
|
24 square meter
|
5 square meter
|
12 square meter
|
24 square meter
|
|
4.
|
Above 25 acres up to 50 acres
|
60 square meter
|
24 square meter
|
5 square meter
|
12 square meter
|
24 square meter
|
|
5.
|
Above 50 acres an additional 50 acres
|
An additional 10 square meter and part thereof
|
24 square meter
|
5 square meter
|
24 square meter
|
48 square meter
|
(vi) Meter room
(vii) Other features as mentioned in
Table 3.
(viii) Open transformers without any
permanent enclosure keeping in view the necessary safety requirements.
(ix) In specific cases water bodies
and pools, and other landscape features may be permitted with approval from the
Chief Executive Officer, provided the fire safety requirement are not affected.
(x) Any other feature purely
ornamental in nature not enclosing or covering space of commercial use may be
permitted by the Chief Executive Officer depending on case to case basis.
(xi) No temporary structure shall be
permitted in front setback or in setback of sides abutting road;
(xii) Open diesel generator set,
filtration plant, electrical distribution equipments, feeder pillar, telephone
distribution equipments shall be permitted in open setback as a service
utility, provided due clearance from Fire Department, has been taken.
(II) Floor Area Ratio shall also
include
(i) Mezzanine
(ii) Mumty for staircase
(iii) Cupboards
(iv) Balconies
(v) Bay windows
(vi) Meter room of following sizes
shall be permissible within the open space in the setback of plot. This shall
be counted towards FAR.
|
33 Kilo Volt with internal arrangement
|
5.0 metres
x 5.0 metres x 3.2 metre
|
|
33 Kilo Volt with external arrangement
|
6.0 metres
x 3.5 metres x 3.2 metres
|
|
11 Kilo Volt with external arrangement
|
4.5 metres
x 4.5 metres x 3.2 metres
|
|
Low Transmission metre room
|
2.5 metres
x 2.5 metres x 3.0 metres
|
Note. In case of specific requirement of size more
than above mentioned sizes, the same shall be permitted only after verification
by Electricity Distribution Company of Bhadohi or Unnao, as the case may be.
(vii) Pergola shall be counted towards
Floor Area Ratio calculation as per Clause 22-B(1)(vii).
(viii) The shafts provided for lifts
shall be taken for covered area calculations only of one floor and included in
ground coverage.
(ix) Only in case of commercial
building, Atrium shall be kept free from Floor Area Ratio and ground coverage.
In case any commercial activity is proposed in Atrium or any sealable area or
any other structure which is counted in Floor Area Ratio and ground coverage,
its respective area shall be added in total Floor Area Ratio and ground
coverage.
(III) Floor Area Ratio shall not
include
(i) A chajja projection (in setbacks)
of a width of 0.75 metre at lintel or roof level. No construction of any type
or any material shall be permitted over projections to provide access to the
chajja.
(ii) Canopy projections of areas
mentioned in Table 4. No construction of any type shall be permitted over the
canopy projections except those mentioned in Table 3.
(iii) Basement (up to double basement),
shall be permissible within the setback line on each floor. However, only in
case of building other than commercial maximum permissible area under basement
shall be limited up to.
(1) Basement area, if used for
services, storage etc. then maximum area under such facilities shall be
equivalent to maximum permissible ground coverage.
(2) Basement area, if used for
parking, then area equivalent to parking requirement shall be permitted.
(3) Basement, if used for any other
use, shall be permitted up to the setback line and this useable area shall be
included in the Floor Area Ratio of the building.
(4) Stilt area of non-habitable
height proposed to be used for parking landscaping etc.
(iv) In buildings for Hotels,
Hospitals, Nursing Homes, Specialised Health Centre and such similar buildings
a service floor up to 100 per cent of maximum permissible ground floor
coverage. The maximum height of service floor between floor to ceilings shall
be 2.25 metres.
(v) Loft up 1.2 metre height.
(vi) Other features as mentioned in
Table 3.
(vii) Rockery, well and well
structures, water pool, swimming pool (if uncovered), uncovered platform around
tree, tank, fountain, bench, chabutra with open top and unenclosed by side
walls, compound wall, gate, slide, swing, uncovered staircase (unenclosed and
uncovered on three sides except for 0.9 metre high railing/wall and open to
sky), overhead tanks on top of buildings, open shafts, culverts on drains.
(viii) Open ramps with no area enclosed
below it of usable height of 2.1 metres.
(ix) Any other feature, primarily
ornamental in nature, not enclosing or covering space of commercial use may be
permitted by Chief Executive Officer depending on its merits on case to case
basis.
(IV) (i) Basement area shall not
exceed beyond building envelope.
(ii) The internal height of the basement (floor to
ceiling) shall be minimum 2.4 metres and maximum 4.5 metres, except wherever
height of equipments such as electric generator, air conditioner and fire
hydrant etc. is more than 4.5 metres additional height equivalent to height of
equipments shall be permitted subject to maximum 9.0 metres.
(V) 15 per cent of the prescribed
Floor Area Ratio shall be added towards common areas, which shall include.
(i) Air-conditioning plant,
electrical installation, generator room, water works, water tank etc.
(ii) Watchmen shelters and watch tower
(iii) Garbage shafts and lift shafts
(iv) Fire escape staircases
(v) Toilet blocks for visitors,
drivers, guards etc.
(vi) Mumty, machine room for lifts
(vii) Any other utilities as decided by
Chief Executive Officer depending on its merits.
(VI) In plots above 10 acres following
public utilities/facilities such as mentioned below shall be not counted in
Floor Area Ratio.
(i) Taxi stand
(ii) Bus terminal and the like
(iii) Telephone exchange
(iv) Fire station
(v) Public toilets detached from the
main building.
(VII) Minimum requirement for
sanction/completion: Minimum area required for completion shall be as per lease
deed or as mentioned in project report at time of allotment or phasing plan
approved by Chief Executive Officer. Provision of following items in building
shall be mandatory for issue of completion certificate:
(i) Flooring;
(ii) Electrical wiring;
(iii) Plumbing, chrome plating fittings
and fixtures;
(iv) Parking and landscaping as per
Tables 6 and 7 respectively;
(v) Number plate and illumination
board as per direction amended from time to time;
(vi) Boundary wall and gates shall be
mandatory;
(vii) Buildings shall be lockable i.e.
all external and windows shall be provided. In case grill is provided in the
windows the fixing of glass in the windows pane shall not be mandatory;
(viii) No overall violation should be
there in the overall building or site at the time of issue of occupancy
certificate;
(ix) Any other special provisions as
mentioned in the lease deed;
(x) In case of completion of whole
project all temporary structures have to be removed.
In case any special clause is mentioned in lease
deed or Memorandum of Understanding then the requirement mentioned in the same
shall be applicable.
(D) Layout and sub-division of Land:
(1) All provisions shall as per
sub-division regulations in master plan approved by Authority. In case of any
special provision in lease deed, the conditions of lease deed shall prevail.
(2) Setbacks Floor Area Ratio, ground
coverage and height permissible on the subdivided plot shall be as per maximum
permissible in each individual use in these regulations.
(E) Nursery
(c-1) Floor Area Ratio Ground
Coverage:
Maximum permissible ground coverage and covered
area shall be up to 5 per cent of plot area or 300 square metre whichever is
less.
(c-2) Height 6 metres
Note.1. Total height shall be counted from drain
top to top of the building except for
* Illuminated boards
* Water Tanks and
* Other such structures with non-usable height
(c-3) Floor Area Ratio; shall not
include
(i) Green house up to maximum 2.5 per
cent of plot area.
(ii) Watchman shelters as per
Regulation 21(B) b-5(iii) and also permitted in setbacks.
(iii) Meter room as per Regulation
21(C)II(b)(vii) and shall also be permitted in setbacks.
(c-4) Shops and support
facilities shall be permitted maximum up to 10 per cent of maximum permissible
Floor Area Ratio
(c-5) Setback shall be as per
Table Number 2
(F) Informal Sectors (Economical
Weaker Section)
(c-1) Plotted Development
|
|
I.
|
Plot Size
|
:
|
20-25 square metre
|
|
|
II.
|
Ground Coverage
|
:
|
80 per cent
|
|
|
III.
|
FAR
|
:
|
160
|
|
|
IV.
|
Height
|
:
|
10 metre maximum
|
|
|
V.
|
Setback
|
:
|
1.5 metre in front
|
|
|
VI.
|
Roads
|
:
|
Main Vehicular roads shall not be less than 9.0
metres and access to plots shall be provided through roads not less than 6.0
metres
|
|
|
VII
|
Open space
|
|
Can be provided in a group or cluster?
|
|
(c-2) Flatted Development
|
|
|
|
|
I.
|
Ground Coverage
|
|
40 per cent
|
|
|
II.
|
FAR
|
|
160
|
|
|
III.
|
Setback
|
|
9.0 front 3.0 metre rear and 3.0 metre side
setback
|
|
|
IV.
|
Height
|
|
15 metre maximum.........
|
|
|
V.
|
Balcony
|
|
0.9 metre wide and 50 per cent shall be included
in Floor Area Ratio
|
|
|
VI.
|
Roads
|
:
|
Main vehicular roads 9.0 metre
|
|
|
VII.
|
Other spaces
|
:
|
60 per cent (Open + Roads + Parks)
|
|
|
VIII.
|
Individuals toilets or group may be provided
|
|
(c-3) Dormitory
|
|
|
|
|
I.
|
Ground coverage/FAR
|
:
|
40 per cent/160
|
|
|
II.
|
Setback
|
:
|
9.0 in front 3.0 in side setback
|
|
|
III.
|
Height
|
:
|
15 metre (Maximum)
|
|
|
IV.
|
Balcony
|
:
|
0.9 metre wide and 50 per cent of area of balcony
will be included in Floor Area Ratio
|
(c-4) Common points for
development
Toilet blocks.
Proposed plantation on road side has to be ever
green trees planted 10 metre centre to centre.
Provisions for community facilities like Creche,
Balwadi, Health care centre etc. to be made as per population requirement.
The population size of unit shall be 2.5 person per
unit as decided by the Authority.
The number of dwelling units permissible will be
equivalent to number of members in the society as decided by the Authority with
the maximum variation of ñ10 per cent.
The Planning and Development Directions shall not
be applicable to the informal sector layout.
Regulation - 22-A.
Notwithstanding anything contained in these
regulations, the Authority may where it considers expedient to do so, having
regard to the special features of a particular zone and the width of road
abutting and the development plan, permit such ground coverage, height and
setback in relation of a building or a group of buildings as it thinks fit.
Regulation - 22-B.
In special circumstances the Authority can,
depending on merits of the case, relax any of the provisions mentioned herewith
in the regulations as it thinks fit.
Regulation - 22-C.
Provisions of minimum parking and landscaping
requirement shall be as per Table 6 and Table 7 respectively. However, the
Authority may stipulate higher provisions if required in future as it thinks
fit and issue directions in this regard with due approval.
CHAPTER IV
STRUCTURAL SAFETY, FIRE SAFETY AND SERVICE
Regulation - 23. Fire Safety and requirements.
(a) Building shall be so planned, designed and constructed so as to ensure
fire safety and this shall be done in accordance with Part IV 'Fire Protection'
of the National Building Code of India 1970 corrected up to date.
(b) In case of multi-storeyed buildings above 15 metre in height, building
which are more than three storeys and building with more than 400 square metres
ground floor coverage and all other buildings of industrial, storage, assembly
and hazardous type building scheme, provisions of Uttar Pradesh Agni Nivaran
aur Agni Suraksha Adhiniyam, 2005 (Act No. 6 of 2005) shall apply.
Regulation - 24. Structural Design.
The structural design of any item of masonry,
timber, plain concrete and steel in a building shall be carried out in
accordance with Part VI (Structural Design, Section 1, Boards, Section 2,
Section 5, Contrete, Section 6 Steel, as in the case may be) of National
Building Code of India 1970 prepared by Indian Standard Institution and as
prevalent at the time of execution of the works.
Regulation - 25. Quality of Material and Workmanship.
All materials and workmanship shall be of good
quality conforming generally to accepted standards of Public Work Department of
Uttar Pradesh, Indian Standards Specifications and Codes as included in Part V
Building Materials and Part VII Constructional Practices and Safety of National
Building Code of India 1970 revised up to date.
Regulation - 26. Building Services.
The planning design and installation of electrical
installations, air-conditioning and heating work, installation of lifts and
escalators in a building shall be carried out in accordance with Part VIII
(Building Services, Section 2, Electrical Installations, Section 3,
Air-conditioning and heating, Section 5, Installation of lifts and escalators,
as the case may be) of National Building Code of India 1970 prepared by Indian
Standard Institution and as prevalent at the time of execution of the work.
Regulation - 27. Plumbing.
The planning design, construction and installation
of water supply, drainage and sanitation and gas supply system in building
shall be in accordance with the Part IX (Plumbing Services Section 1, Water
Supply Section 2, Drainage and Sanitation, Section 3, Gas Supply as the case
may be) of National Building Code of India prepared by Indian Standard
Institution and as prevalent at the time of execution of the work.
Regulation - 28. Water supply requirements.
The requirements of water supply in a building
shall be in accordance with the provision of National Building Code as amended
from time to time.
Regulation - 29. Sanitary Fitting.
(1) Subject to the provision of any law for the time being in force, the
sanitary fittings and installations in building shall be in accordance with the
provisions of National Building Code as amended from time to time.
(2) Every factory building within the area shall be provided with such
latrines and urinals as may be prescribed by or under the provisions of the
Factories Act, 1948 as amended from time to time.
Regulation - 30. Structural Safety for Natural Hazard Protection.
For buildings more than three storeys (including
ground floor) or more than 12 meter height and important facilities like water
works, overhead tank, telephone exchange, bridges and culverts, electric
sub-station, transmission towers, the requirements specified in the Indian
Standard Code and Guidelines and other documents shall be observed for structural
safety and natural hazards protection of buildings. The details of the relevant
codes and guidelines are given in Appendix 8-A/B/C/D.
Regulation - 31. Provision for Physically Handicapped.
Provisions for physically handicapped persons shall
be made in all buildings and facilities used by public in accordance with the
provision of Part III of National Building Code (Appendix E).
Regulation - 32-A.
All the provisions made in the building which are
not specifically provided in these regulations shall be as per the provisions
of National Building Code, Indian Standard Institution Code as applicable from
time to time. The licensed technical person shall be responsible for ensuring
the same as per Appendix 4.
Regulation - 32-B.
The Owner, Licensed Technical Person shall be fully
responsible for all provisions to be made in accordance with Regulations 23,
24, 25, 26, 27, 28, 29, 30, 31 and 32-A. A certificate to this effect shall be
given as per Appendix 4.
CHAPTER V FOR CONSTRUCTION OF FARM HOUSE BUILDING IN AGRICULTURAL
USE ZONE
Regulation - 33. Minimum size of plot Maximum coverage and Floor Area Ratio.
Minimum size of a plot for farm house shall not be
less than 0.5 hectares.
|
(a)
|
Maximum permissible ground coverage for all types
of activity
|
10 per cent
|
|
(b)
|
Maximum permissible Floor Area Ratio
|
20 per cent
|
|
(c)
|
Residential accommodation of watch and
ward/maintenance staff
|
15 per cent
|
|
(d)
|
Maximum height
|
10 meters
|
|
(e)
|
Setbacks
|
Front/side abutting road 15 meter and all other
sides 9 meter.
|
Regulation - 35. Other Provision.
(a) The maximum permissible floor
area includes the area of mezzanine floor also.
(b) The height of boundary wall shall
be as specified in the Directions.
(c) Running creeper or flowering
creeper will be planted all along the wall.
(d) Minimum 50 per cent of the total
area of the farm house shall be under plantation/cultivation; At least 100
trees per hectares have to be planted out of which at least 50 per cent shall
be evergreen trees.
Regulation - 36. Water Supply, Sewerage and Drainage.
(a) In case of a plot for a farm
house having dwelling units the owner thereof shall be responsible to make
lawful arrangements for potable water in the farm house.
(b) The owner shall be responsible to
provide drains in the farm house to be used for rain water and in case of dairy
farm open or closed sanitary drains to clean sheds, as may be required by the
Authority.
(c) The owner shall be responsible to
provide septic tank with necessary dispersion trenches for disposal of human
and animal wastes in the farm house within his own premises.
Regulation - 37. Electrification.
The owner of a farm house shall obtain electric
connection directly from the appropriate authority authorised for distribution
on such terms and conditions and at his own cost as decided by the appropriate
authority.
Table No. 2
|
Sl. No.
|
Plot Size (in square meter)
|
Front (in meter)
|
Rear (in meter)
|
Side (1) (in meter)
|
Side (2) (in meter)
|
|
1.
|
Up to 150
|
3.0
|
1.5
|
0
|
0
|
|
2.
|
Above 150 up to 300
|
3.0
|
3.0
|
0
|
0
|
|
3.
|
Above 300 up to 500
|
4.5
|
3.0
|
3.0
|
0
|
|
4.
|
Above 500 up to 2000
|
6.0
|
3.0
|
3.0
|
3.0
|
|
5.
|
Above 2000 up to 4000
|
9.0
|
6.0
|
6.0
|
6.0
|
|
6.
|
Above 4000 up to 10,000
|
15.0
|
6.0
|
6.0
|
6.0
|
|
7.
|
Above 10,000 up to 20,000
|
15.0
|
9.0
|
9.0
|
9.0
|
|
8.
|
Above 20,000 up to 40,000
|
20.0
|
9.0
|
9.0
|
9.0
|
|
9.
|
Above 40,000 up to 1,00,000
|
25.0
|
9.0
|
9.0
|
9.0
|
Notes.(1) Specific setbacks shall be as per zonal
plan prepared by the Authority whenever such a plan has prepared by the
Authority.
(2) In case the permissible coverage is not
achieved within setbacks, the setbacks of the preceding category may be followed.
Table No. 3
|
Sl. No.
|
Features
|
Description
|
|
1.
|
Decorative Column
|
Columns purely decorative and not load bearing
shall be permitted in setback. Such columns of any material and number shall
be permitted but maximum size of each column shall not exceed 300 millimeter
x 300 millimeter.
|
|
2.
|
Buttresses
|
Buttresses, any number, shall be permitted in
setback up to maximum width of 750 millimeter in setback
|
|
3.
|
Moulding, Cornices and Murals
|
Murals, moulding and cornices if provided along
under any projection shall be permitted up to a maximum width of 150
millimeter over and above the maximum permissible dimensions of a projection
or a canopy.
|
|
4.
|
Planters and Sun Control Devices
|
Projection in form of planter, cantilevered fins,
egg crates and other sun control devices shall be permitted in setback up to
maximum width of 750 millimeter. Maximum depths of such planters shall not
exceed 600 millimeter.
|
|
5.
|
Jali
|
Jali of any material shall be permitted over
projections which are primarily meant to cover window Air-conditioning units
and desert cooler. Maximum width of such jalies shall not be more than 75
millimeter.
|
|
6.
|
Casing enclosing to cover Rain Water pipe
|
Casing/enclosures of any material to cover rain
water pipe shall be permitted in setback up to depth of maximum 250
millimeter and maximum width of 600 millimeter.
|
Table No. 4
Area under canopy on building
other than residential building on plots
|
Sl. No.
|
Plot size (in square meter)
|
Maximum area under canopy (in square meter)
|
|
1.
|
Up to 150
|
Nil
|
|
2.
|
Above 150 up to 500
|
12 (only in side setback)
|
|
3.
|
Above 300 up to 500
|
25
|
|
4.
|
Above 500 up to 2000
|
40
|
|
5.
|
Above 2000 up to 4000
|
55
|
|
6.
|
Above 4000 up to 10,000
|
70
|
|
7.
|
Above 10,000 up to 20,000
|
85
|
|
8.
|
Above 20,000 up to 40,000
|
100
|
|
9.
|
Above 40,000 up to 1,00,000
|
115
|
Note. Minimum width/radius of canopy shall be 1.8
meters.
Table No. 5
(1) Excess coverage beyond
permissible coverage on each floor
|
Sl. No.
|
Particular
|
For Commercial buildings
|
For all other type of building
|
|
1
|
5 per cent of the achieved coverage on each
floor*.
|
3 times of current prevailing land rate
|
Equal to current prevailing land rate
|
|
2
|
Beyond 5 per cent
|
Not permitted
|
Not permitted
|
(2) Setback infringement on each
floor
|
Sl. No.
|
Particular
|
For Commercial Buildings
|
For all other type of building
|
|
1
|
Up to 0.15 meters
|
3 times of current prevailing land rate
|
Equal to current prevailing land rate
|
|
2
|
Beyond 0.15 meter and up to 0.30 meters
|
12 times of current prevailing land rate
|
Four times of current prevailing land rate
|
|
3
|
Beyond 0.30 meters
|
Not permitted
|
Not permitted
|
Note.*Mean excess coverage permissible shall be subject
to maximum of 5 per cent of floor area ratio.
Table No. 6
Provisions of parking, loading
and unloading spaces
(a) When parking space is to be
provided for motor vehicles, it shall not be less than 20 square meter area
(under stilts: 30 square meter) and for scooters and cycles the parking spaces
provided shall not be less than 3 square meter and 1.40 square meter
respectively.
(b) For buildings of different types,
parking space for vehicles shall be provided as specified below
|
Sl. No.
|
Occupancy
|
Parking space
|
|
1.
|
(a) Group Housing
|
One parking space per 65 square meter covered
area.
|
|
2.
|
(b) Lodges, Guesthouse, Hotel Educational and
corporate office for administrative area
|
One parking for every 3 guest room. One parking
space for every 66 square meter of covered area and parking space for every
30 square meter for administrative office.
|
|
|
(a) Auditorium
|
One parking space per 15 seats
|
|
|
(b) Bus Parking
|
One bus parking per 750 square meter of covered
area.
|
|
|
(c) Off Street Parking
|
Higher Secondary School 15 feet off-street
parking depth in the entire frontage with boundary wall shifted back and
front set back will be considered from property line and in other
institutions up to 15 feet in half the width of the front of the plot would
be required for providing off-street parking.
|
|
|
(d) Hostels and Residential area parking
|
One parking space per 75 square meter of covered
area.
|
|
3.
|
Medical
|
One parking space for every 66 square meter
covered area.
One ambulance for every 375 square meter covered
area.
|
|
4.
|
Commercial
|
One parking space for 30 square meter of covered
area.
|
|
5.
|
Industrial
|
One parking space per 85 square meter of covered
area.
|
|
|
6.
|
Storage
|
One parking space for 66 square meter of covered
area.
|
|
|
7.
|
Loading/Unloading space for Industries and storage
building.
|
One parking space for every 100 square meter with
a size of 4.5 meter x 3.0 meter
|
|
|
8.
|
Hotel
|
One parking space for every 66 square meter of
covered area and one parking space of every 30 square meter for
administrative office.
|
|
|
9.
|
Cinema
|
One parking space per 5 seats
|
|
|
10.
|
Multiplex
|
One parking space per 30 square meter of covered
area.
|
|
|
11.
|
Religious
|
One parking space per 66 square meter of covered
area.
|
|
|
12.
|
Utilities (Fire Station, Police Stations, Post
Office, Taxi Stand etc.)
|
One parking space per 66 square meter of covered
area.
|
|
|
13.
|
Recreational
|
One parking space per 30 square meter of covered
area.
|
|
Note.50 per cent of the above
specified parking provision shall be made for the cycle and scooter parking
space.
Table No. 7
Provisions for Landscaping
(1) (a) Institutional, commercial,
organization/Industrial units/group housing (flatted) shall be required to
plant a minimum number of trees in their premises as follows.
|
Plot size (in square meter)
|
Number of trees required
|
Minimum open space to be kept for landscaping
|
|
Up to 2000
|
One tree per 100 square meter of open space out
of which minimum 50 per cent to be in the category of evergreen trees, having
height of 20 feet or more
|
25 per cent of open area. In case of industrial
plots no soft landscaping is required.
|
|
Above 2000 to 12000
|
One tree per 100 square meter of open space out
of which minimum 50 per cent trees to be in the category of evergreen trees,
having height of 30 feet or more
|
25 per cent of open area.
|
|
More than 12000
|
One tree per 100 square meter of open space out
of which minimum 50 per cent to be in the category of evergreen trees, having
height of 40 feet or more
|
50 per cent of open area.
|
(b) In case of plotted development in group housing
plantation provision shall be as per Landscape Master Plan and following norms
shall be followed.
(i) On 18.0 meter and 24.0 meter wide
road, alternate variety of evergreen and ornamental trees shall be planted @7.5
meter centre to centre.
(ii) On road up to 12 meter ornamental
trees will be planted @5 meter centre to centre of single variety in each
pocket.
(c) Recreational, Institutional Green: In addition
to the requirement as mentioned in clause (a) detailed landscape plan will have
to be got approved by the Authority as per specification in Landscape Master
Plan and landscape manual approved by the Authority.
(2) Residential plots other than
group housing (flatted).
There shall be
(i) one tree in every plot of size
not exceeding 120 square meters.
(ii) two trees in every plot of size
exceeding 120 square meters but not exceeding 300 square meters.
(iii) three trees in the plot of size
exceeding 300 square meters but not exceeding 500 square meters.
(iv) five trees in every plot of size
exceeding 500 square meters.
(3) Provisions of all tree plantation
shall be in accordance with letter No. 1977/74-5-07-15(2)/07, dated 26-11-2007
which shall be as follows
(i) in all schemes of urban areas and
road side plantation fruit bearing trees of 6 feet height and other varieties
of at least 8 feet height shall be planted.
(ii) at all places other than
mentioned at serial number (i) above leaving exceptions (e.g. Prosopis, Babul,
Junglejalebi etc. which cannot be kept for more than one year in the nursery
and those trees which are planted for research plantation by grafting/or clonal
method) trees of less by than 4 feet height shall not be planted.
(iii) the above terms and conditions
shall not be applicable to the trees plantations caused to be carried on by
private persons or private institution.
(iv) if the allottee does not plant
trees the map thereof shall not be passed. The allottee shall submit landscape
plan at the time of building plan approval. The proposal shall indicate such
variety of trees as per size and category of plots trees of 3.6 M to 18 M
height which are of required height and permanent nature, and 50 per cent trees
should be of evergreen variety, for example-Neem, Jamun, Pilkhan, Tamarind,
Kadamba etc. and should fulfil the nature of permanent tree. At the time of
occupation it will be ensured that the allottee shall plant healthy trees as
per approved landscape plan. An affidavit shall also be taken from the allottee
that he shall maintain the trees properly and in case he does not do so he
shall be persuaded to be punished under Forest Rules and Allotment of Building
Rules, with the punishment for felling of green trees.
(v) in constructed building Pijo
meter shall be installed for rain water harvesting as per Urban Design
Guidelines.
APPENDIX I
[See
Regulation 4(1)]
Form for
first application to erect, re-erect, demolish or to make material alteration
in a building
To,
The Chief Executive Officer,
Bhadohi Industrial Development Authority,
Uttar Pradesh
Sir,
I hereby give application that I intend to
erect/re-erect/demolish or to make material alteration in the building on Plot
No. ..............in Village ..................in Sector .................in
accordance with the Bhadohi Industrial Development Area Building Regulations
and Planning and Development Directions and I enclose herewith the documents as
per checklist 1-A/1-B/1-C/1-D annexed to this application.
I request that the construction may be approved and
permission accorded to me to execute the work.
Signature of the applicant
Name of applicant (in Block letters).
Address of the applicant:
Dated:
(i) Note. Strike out which is not applicable.
Checklist
1-A (For buildings on individual residential plots)
(i) Ownership documents; copies of allotment letter (transfer letter in case
of transfer) possession certificate, the lease deed (transfer deed in case of
transfer), and dimension plan issued by the Authority.
(ii) Form for first application to erect, re-erect, demolish or to make material
alteration in a building (Appendix I).
(iii) Certificate prescribed in Appendix 2 for undertaking the supervision by
the Licensed Technical Person. Any change of the technical personnel during
construction work shall be intimated to the Chief Executive Officer in writing.
(iv) Structural stability certificate from the Architect/Structural Engineers
as per Appendix 3.
(v) Certificate for sanction of Building Plan as per Appendix 4.
(vi) Indemnity bond as per Appendix 5 in case where basement is proposed to
be constructed on Rs. 100 stamp paper duly attested by a Notary.
(vii) Specification of proposed building as per Appendix 6.
(viii) Application for drainage of premises as per Appendix 7.
(ix) Photocopy of the registration of the Licensed Technical Person as per
Appendix 12 duly authenticated with plot number for which it is submitted.
(x) Application form for water and sewer connection.
(xi) Photocopy of receipt of fees deposited, water and sewer connection
charges, services connection and ramp charges and such other charge and such
other charges if any as required by the Authority from time to time.
(xii) Three copies of drawings (one cloth mounted) duly signed by the Licensed
Technical Person and Owner.
(xiii) Any other document as may be required by Authority from time to time.
Checklist
1-B (For buildings other than those on individual residential plots)
(i) Ownership documents; copies of allotment letter possession certificate,
the lease deed (transfer), and dimension plan issued by the Authority.
(ii) Form for first application to erect, re-erect, demolish or to make
material alteration in a building (Appendix I).
(iii) Certificate prescribed in Appendix 2 for undertaking the supervision by
the Licensed Technical Person. Any change of the technical personnel during
construction work shall be intimated to the Chief Executive Officer in writing.
(iv) Structural stability certificate from the Architect/Structural Engineers
as per Appendix 3.
(v) Certificate for sanction of Building Plan as per Appendix 4.
(vi) Indemnity bond as per Appendix 5 in case where basement is proposed to
be constructed on Rs. 100 stamp paper duly attested by a Notary.
(vii) Specification of proposed building as per Appendix 6.
(viii) Application for drainage of premises as per Appendix 7.
(ix) Photocopy of the registration of the Licensed Technical Person as per
Appendix 12 duly authenticated with plot no for which it is submitted.
(x) Application form for water and sewer connection (if applicable).
(xi) Photocopy of receipt of fees deposited, water and sewer connection
charges, service connection and ramp charges and such other charges if any as
required by the Authority from time to time.
(xii) Three copies of drawings (one cloth mounted) duly signed by the Licensed
Technical Person and owner.
(xiii) Certificate of registered structural engineer and owner regarding
earthquake resistance of the building as per Appendix 8/A/B/C if applicable.
(xiv) Two copies of the drawings giving details of provisions for fire safety,
security as per National Building Code.
(xv) Approval from the competent authority in case of hazardous buildings.
(xvi) Soft copies of the drawings in floppy/compact disc.
(xvii) Valid time extension, if applicable.
(xviii) Any other document as may be required by the Authority from time to
time.
(xix) In case of revision and revalidation original sanction plan to be
surrendered.
Checklist
1-C (For layouts and sub-division of plots)
(i) Ownership documents; copies of allotment letter (transfer letter in case
of transfer) possession certificate, lease deed (transfer deed in case of
transfer), and dimension plan issued by the Authority.
(ii) Form for first application to erect, re-erect, demolish or to make
material alteration in a building (Appendix I).
(iii) Certificate prescribed in Appendix 2 for undertaking the supervision by
the Licensed Technical Person. Any change of the technical personnel during
construction work shall be intimated to the Chief Executive Officer in writing.
(iv) Structural stability certificate from the Architect/Structural Engineers
as per Appendix 3.
(v) Certificate for sanction of Building Plan/Layout Plan as per Appendix 4.
(vi) Specification of proposed building as per Appendix 6.
(vii) Application for drainage of premises as per Appendix 7.
(viii) Photocopy of the registration of the Licensed Technical Person as per
Appendix 12 duly authenticated with plot number for which it is submitted.
(ix) Application form for water and sewer connection (if applicable).
(x) Photocopy of receipt of fees deposited, water and sewer connection
charges, service connection and ramp charges and such other charges if any as
required by the Authority from time to time.
(xi) Three copies of drawings (one cloth mounted) duly signed by the Licensed
Technical Person and owner.
(xii) Certificate of registered structural engineer and owner regarding
earthquake resistance of the building as per Appendix 8/A/B/C, if applicable.
(xiii) Three copies of the drawings giving details of provisions for fire
safety, security as per National Building Code.
(xiv) Soft copies of the drawings.
(xv) Valid time extension, if applicable.
(xvi) Any other document as may be required by the Authority from time to
time.
(xvii) In case of revision and revalidation original sanction plan to be
surrendered.
Checklist
1-D (For Temporary Structures)
(i) Ownership documents; copies of allotment letter (transfer letter in case
of transfer) possession certificate, lease deed (transfer deed in case of
transfer), and dimension plan issued by the Authority.
(ii) Form for first application to erect, re-erect, demolish or to make
material alteration in a building (Appendix I).
(iii) Certificate prescribed in Appendix 2 for undertaking the supervision by
the licensed technical person. Any change of the technical personnel during
construction work shall be intimated to the Chief Executive Officer in writing.
(iv) Certificate for sanction of Building Plan/Layout Plan as per Appendix 4.
(v) Specification of proposed building as per Appendix 6.
(vi) Photocopy of the registration of the Licensed Technical Person as per
Appendix 12 duly authenticated with plot number for which it is submitted.
(vii) Application form for water and sewer connection (if applicable).
(viii) Photocopy of receipt of fees deposited, water and sewer connection
charges, service connection and ramp charges and such other charges if any as
required by the Authority from time to time.
(ix) Three copies of drawings (one cloth mounted) duly signed by the Licensed
Technical Person and owner.
(x) Valid time extension, if applicable.
(xi) Any other document as may be required by the Authority from time to
time.
(xii) In case of revision and revalidation original sanction plan to be
surrendered.
APPENDIX 2
(See
Appendix 1 Checklist 1-A, 1-B, 1-C, 1-D)
Form for
supervision of Building Work
To,
The Chief Executive Officer,
Bhadohi Industrial Development Authority,
Uttar Pradesh
Sir,
I hereby certify that the erection/re-erection on
Plot and material alteration/demolition in/of building/site on Plot
number...............in Village..................in Sector.................Bhadohi
shall be carried out under my supervision and I certify that all the material
(type and grade) and the workmanship of the work shall be generally in
accordance with the general and detailed specification submitted along with and
that the work shall be carried out according to the sanctioned plan.
Signature of the Licensed Technical
Person.......................................
Name of Licensed Technical
Person................................................
License number of Licensed Technical
Person...................................
Address of the Licensed Technical
Person........................................
Dated
Note. Strike out which is not applicable.
APPENDIX 3
(See
Appendix 1 Checklist 1-A, 1-B, 1-C)
For Structural
Stability Certificate
To,
The Chief Executive Officer,
Bhadohi Industrial Development Authority,
Uttar Pradesh
Sir,
I hereby certify that the structural design of the
building on Plot number ..............................in Village..................in
Sector.................Bhadohi shall be done by me/us and carried out in
accordance with Part/TV structural design of National Building Code of India
corrected up to date.
Signature of the Licensed Technical
Person.......................................
Name of Licensed Technical
Person................................................
License number of Licensed Technical
Person...................................
Address of the Licensed Technical
Person........................................
Dated
Note. Strike out which is not applicable.
APPENDIX 4
(See
Regulation 32-A and 32-B)
Certificate
of Sanction of/Layout Plan Building Plan (To be given by Licensed Technical
Person as per Appendix 12)
It is certified that the plans and all other
drawing submitted for approval for building on Plot
number........................in Village ..................in
Sector................. Bhadohi prepared in accordance with Development
Directions (as amended up to date), National Building Code, Indian Standard Institution
Code and all other provisions as given in Chapter V, as applicable.
Signature of Licensed Technical
Person........................................
Name of the Licensed Technical
Person........................................
Registration Number.............................................................
Address of Licensed Technical
Person........................................
Enclosure
Attested Photocopy of the certificate of Licensed
Technical Person.
Building Plan and all prescribed documents.
Dated:
Place:
APPENDIX 5
(See
Appendix Number 1 Checklist 1-A, 1-B, 1-C)
Indemnity
Bond
In consideration of the Bhadohi Industrial
Development Authority, a body constituted under Section 3 read with clause (d)
of Section 2 of the Uttar Pradesh Industrial Area Development Act, 1976 (U.P.
Act No. 6 of 1976) (hereinafter referred to as 'the promisee' which expression
shall unless the context otherwise require, includes its successors and
assigns) having sanctioned the construction of the basement in the building
plans of the House/Factory building to be constructed on
Industrial/Residential/institutional/Commercial/Recreational Plot
Number..................Village ..................in Sector .................
Bhadohi situated in the Bhadohi Industrial Development Area in District
Bhadohi, Uttar Pradesh. On production of the bond of Indemnity by
....................son of
..................aged...........................about................years.................resident
of .........................................................................(hereinafter
called the 'promisor' which expression shall unless the context otherwise
require includes his/her heirs, executors, administrators, representatives and
permitted assigns) to implement the promises of any loss or damage caused in
respect of construction of basement referred to above the promisor hereby
agrees to execute this Bond of Indemnity.
Now therefore this deed witnesseth as follows:
In consideration of the promisee having sanctioned
the construction of the basement in the building plan of the
factory/residential building to be constructed in
Industrial/Residential/institutional/Commercial/Recreational Plot
number...........................................in
Village........................Sector....................... situated in the
Bhadohi Industrial Development Area, District
Bhadohi....................................the promisor agrees to indemnify the
Bhadohi Industrial Development Authority and at all time holds himself liable
for all damages and losses caused to the adjoining building(s) on account of
the construction of basement referred to above and further undertakes to
indemnify the promisee Bhadohi Industrial Development Authority any such amount
to the full extent which the promisee may have or to be required to pay to any
person(s) having rights in the adjoining properties on account of the
construction of the basement (said) by way of compensation or otherwise and
further to pay all costs and expenses which the promisee may have to spend in
defending any action in the Court of Law regarding thereto.
In witness whereof the promisor executed this Bond
of Indemnity at Bhadohi Industrial Development Area, District
Bhadohi.....................on................day of............................
(Promisor),
Witness:
1.
2.
APPENDIX 6
[See
Regulation 5.1(A)(4), 5.1(B)(3), 5.1(C)(5), 5.1(D)(3)]
Bhadohi
Industrial Development Authority
General
specification sheet of proposed building
(1) Total Plot Area.........................square meter/Basement
existing......................square meter/Basement
proposed........................square meter/Ground floor
existing.................square meter/Ground Floor
Proposed...........................square meter.
(2) First Floor existing.....................square meter/First Floor
Proposed......................square meter.
Second Floor existing.......................square
meter/Second Floor Proposed.....................Square meter.
(3) Mezzanine Floor existing....................square meter/Mezzanine Floor
Proposed.................square meter.
(4) The purpose for which it is intended to use the
building........................
(5) Specification to be used in the construction of the
(i) Foundation
(ii) Walls
(iii) Floors
(iv) Roofs
(6) Number of storeys of which the building will
consist..........................
(7) Approximate number of persons proposed to be
accommodated....................
(8) The number of latrines to be provided.......................
(9) Whether the site has been built upon before or not..................
(10) Source of water to be used for building purpose......................
Signature of the
Applicant...................................
Full Name (In Block
Letters).................................
Address.........................................................
APPENDIX 7
(See
Appendix 1 Checklist 1-A, 1-B and 1-C)
Bhadohi
Industrial Development Authority
(To be
submitted in duplicate)
Application
for Drainage of premises
To,
The Chief Executive Officer,
Bhadohi Industrial Development Authority,
Uttar Pradesh
Sir,
I/We the undersigned hereby apply for permission to
drain the premises on Plot number…............in Village…...............in
Sector…..............The sanitary arrangement and drains for the premises are
shown in the accompanying plans and sections in duplicate and described in the
Appendix 7 (submitted in duplicate) and the premises are open to inspection by
the Officers of Bhadohi Industrial Development Authority. I/We undertake to carry
out the work in accordance with the provisions of Bhadohi Industrial
Development Authority Building Regulations, 2013 and to pay the Authority the
cost of connection to the sewer at the rate given in the scheme of fees.
Signature of the Applicant…....................................
Full Name (In Block Letters)….............................................
Address….....................................
Name of the Licensed Technical person carrying out
work…...............................
License number…........................................
Address of the Licensed Technical Person…........................................
Dated:
APPENDIX 8(A)
(See
Regulation Number 30)
Kindly (v)
tick the relevant codes that have been followed
Structural
Safety and Natural Hazard Protection of Buildings
Requirements specified in the following Indian
Standards, Codes and Guidelines and other documents needs to be observed for
structural safety and natural hazard protection of buildings etc.
(a) For General Structural Safety
(1) IS: 1905-1987 "Code of practice for structural safety of buildings;
masonry walls" Indian Standards Institution, March, 1981
(2) IS: 1904-1978 "Code of practice for structural safety of building:
foundation" Indian Standards Institution
(3) IS: 456-2000 "Code of practice for plain and Reinforced
Concrete" Indian Standards Institution, September, 2000
(4) IS: 800-1984 "Code of practice for general construction in
steel" Indian Standards Institution, February, 1985
(5) IS: 883-1966 "Code of practice for design of structural timbers in
buildings;" Indian Standards Institution, March, 1967
Besides any other relevant Indian Standards will
need to be referred to
(b) For Earthquake protection
(1) IS: 1893-1984 "Criteria for Earthquake resistant Design of
Structures (Fourth Revision)" June 1986
(2) IS: 13920-1993 "Ductile detailing of reinforced concrete structures
subjected to Seizmic forces Code of
Practice" November 1993
(3) IS: 4326-1993 "Earthquake Resistant Design and Construction of
Buildings Code of Practice (Second
Revision)" October 1993
(4) IS: 13828-1993 "Improving Earthquake Resistance of Low Strength
Masonry Buildings Guidelines"
August 1993
(5) IS: 13827-1993 "Improving Earthquake Resistance of Earthen Building
Guidelines" October 1993
(6) IS: 13935-1993 "Repair and Seismic Strengthening of Buildings Guidelines" November 1993
(7) "Improving Earthquake Resistance of Building Guidelines" by expert group, Government
of India, Ministry of Urban Affairs and Employment, published by Building
Materials and Technology Promotion Council, 1998
(8) The National Building Code of India, 1983
For location of the building in hazard prone area
of earthquakes, cyclone or wind storms and flood, reference may be made to the
following
"Vulnerability Atlas of India" by expert
group, Government of India, Ministry of Urban Affairs and Employment, published
by Building Materials and Technology Promotion Council, 1997.
Note.1. As and when anyone of the above referred
standards and documents is revised, the design and construction of Buildings
thereafter must satisfy the latest version for approval of building plans by
the authority.
The above information is factually correct.
Signature of owner with date Signature of the
Engineer who had/will supervised the construction (with qualification and
experience as mentioned in Appendix 12)
Name (Block)................................. Name
(Block)................................./Address:
Address:.......................................
Legible Seal:
(with address)
Signature of the Licensed Technical Person who
had/will supervised the construction
Name (Block)..................................
Registration number...........................
Legible Seal with address:....................
APPENDIX
8(B)
(See Regulation Number 30)
4.1 Building Information Schedule
|
1.
|
Building Address
|
Plot Number
|
Estate
|
Sector
|
Town
|
|
2.
|
Building function and location
|
|
|
|
|
|
2.1
|
Use
|
Institutional
|
Commercial
|
|
Industrial*
|
|
2.2
|
Importance
|
Ordinary
|
Important Hazardous
|
|
IS: 1893
|
|
2.3
|
Seismic Zone (Design Intensity Used)
|
V(IX)
|
IV(VIII)
|
III(VII) II(VI)
|
IS: 1893
|
|
3.
|
Design *EQ Factor
|
a0=.........
1=...........
|
ß=
|
ah=...........
|
IS: 1893
|
|
4.
|
Foundation
|
|
|
|
|
|
4.1
|
Soil type at site
|
Rock/Stiff Medium #Soft
|
Liquefiable
|
Expensive (Bearing
|
IS: 1904
|
|
4.2
|
(Note 2)
Type of Foundation
|
Strip Indiv. Col. Footings/Raft
|
Bearing Piles
|
Capacity) Friction Piles
|
IS: 1893
|
|
5.
|
Load Bearing Wall Buildings
|
|
|
|
|
|
5.1
|
Building Category
|
A(ah<.05)
B(ah=.05 to .06)
|
C(ath. 06 to <.08)
D(ah<.08 to a<9.12)
|
E(ah>0.12)
|
IS: 4326
|
|
5.2
|
Bearing Walls Brick
|
Stone
|
Solid Block
|
Hollow Block
|
Adobe
|
|
5.3
|
Mortar (Note 4) C:S=1........
|
C:L:S=1...........
|
L:S=1 Clay Mud
|
|
|
|
5.4
|
Floors
|
Reinforce Stone slabs on joists
|
Prefab flooring elements concrete slabs
|
|
|
|
5.5
|
Roof structure
|
Flat like floors/pitched
|
Trussed/Raftered/A Frame/Slopping
|
R.C. Slab
|
|
|
5.6
|
Roof covering
|
CGI Sheeting
|
*AC Sheeting
|
Clay tiles/Slate
|
Wood shingle
|
|
5.7
|
Opening in walls
|
Control used on sizes?
Yes/No/NA
|
Control used on location?
Yes/No/NA
|
Strengthening around?
Yes/No/NA
|
IS: 4326
IS: 13828
|
|
5.8
|
Bands Provided
|
Plinth Band Lintel Band
|
Roof/Eave Band Gable Band
|
Ridge Band
|
do
|
|
5.9
|
Vertical Bars
|
At corners of rooms
|
At jambs of openings
|
|
do
|
|
5.10
|
Stiffening of Prefab
|
R.C. screed & Band
|
Peripheral band and Diagonal planks and
|
|
IS: 4326
|
|
|
Floors/Roofs
|
Connectors
|
|
All round band
|
|
|
6.
|
Steel/R.C. frame buildings
|
|
|
|
|
|
6.1
|
Building shape Both axis near symmetrical One
axis near symmetrical/Unsymmetrical (torsion considered)
|
|
6.2
|
Infills/partitions out of plane stability check?
|
Yes/No
|
In plane stiffness considered?
Yes/No
|
IS: 1893,
IS: 4326
|
|
6.3
|
Ductile Detailing of Beams?
|
Columns?
|
Beam/column Joint?
|
Sheer Walls?
|
IS: 13920
|
|
|
R.C. Frames
|
Yes/No
|
Yes/No
|
Yes/No
|
Yes/No
|
|
6.4
|
Ductile Detailing of Beams?
|
Columns?
|
Beam/column Joint?
|
SP6(6)
|
|
|
|
Steel Frames
|
Yes/No
|
Yes/No
|
Yes/No
|
|
Notes.1. Encircle the applicable Data point or
insert information.
2. Stiff N>30: Medium N=10.3: Soft. N<10:
Liquefiable, poorly graded sands with N<15 under Water Table (see Note 5 of
Table 1 in IS: 1893)
Where N: Standard Penetration (1:2131-1981)
3. *Means any other Specify.
|
C= Cement, S=Sand, L=Lime
The above information is factually correct.
Signature of owner with date
Name (Block)..............................
Address:
|
Signature of the Engineer who had/will supervised
the construction (with qualification and experience as mentioned in Appendix
12)
Name
(Block)..........................................
Address:......................................
Legible Seal: (with address)
|
Signature of the Licensed Technical Person who
had/will supervised the construction
* R.C. stands for Reinforce Concrete.
* CGI stands for Corrugated Galvanised Iron.
* B.C. stands for Bearing Capacity.
* EQ stands for Earthquake.
* AC stands for Asbestos Corrogated.
Name (Block)...............................
Registration Number.......................
Legible Seal.................................
With address.
APPENDIX
8(C)
(See Regulation Number 30)
Certificate
(The certificate to be submitted
with the application for building permission along with the building drawings
and Building Information Schedule)
(1) Certified that the building plans
submitted for approval also satisfy the safety requirements as stipulated in
the Indian Standard Codes, guidelines and documents specified in the Appendix
8-A regarding earthquake safety awareness and the information given in the
attached Building Information Schedule is factually correct to the best of my
knowledge and understanding.
(2) It is also certified that the
structural design including safety from natural hazards including earthquake
has been prepared by duly qualified civil engineer along with qualification and
experience as mentioned in Appendix 12.
(3) Location/Address of Building
Plot number......................
Estate..............................
Sector.............................
Town..............................
(4) Particulars of Building
(1) Ground Coverage (square meter)
(2) Total covered area (square meter)
(3) Maximum Numbers of Floors above
ground.
|
Signature of owner with date
Name (Block)…...........................
Address:…................................. …................................................
|
Signature of the Engineer who had/will supervised
the construction (with qualification and experience as mentioned in Appendix
12)
Name (Block)…...........................
Address:
Legible Seal:
(with address)
|
Signature of the Licensed Technical Person who
had/will supervised the construction
Name (Block)…............................
Registration Number…....................
Legible Seal…..............................
(with address)…...........................
APPENDIX
8(D)
(See Regulation Number 30)
Certificate
(To be submitted with the
application for obtaining completion certificate)
(1) Certified that the building for
which completion plan has been submitted for approval conforms to the
requirements of relevant Indian Standard Codes and National Building Code as
referred in Appendix 8-A in respect of Structural Safety in general and natural
hazards including earthquake in particular.
(2) It is also certified that the
building has been constructed as per approved foundation and structural designs
provided by the Structural Engineer and is certified to be based on relevant
Indian Standard Code and National Building Code as referred above and the
building is safe for occupancy.
(3) Location/Address of Building
Plot number......................
Estate..............................
Sector.............................
Town..............................
(4) Particulars of Building
(1) Ground Coverage (square meter)
(2) Total covered area (square meter)
(3) Maximum Numbers of Floors above
ground.
|
Signature of owner with date…........................
Name (Block)…...........................
Address:….................................... …..................................................
|
Signature of the Engineer who had supervised the
construction (with qualification and experience as mentioned in Appendix 12)
Name (Block)…...........................
Address:
Legible Seal:
(with address)
|
Signature of the Licensed Technical Person who
had/will supervised the construction
Name (Block)…............................
Registration Number…....................
Legible Seal…..............................
(with address)…...........................
APPENDIX 9
[See
Regulation No. (16)]
Form for
Completion Certificate for Building Work
To,
The Chief Executive Officer,
Bhadohi Industrial Development Authority,
Uttar Pradesh
Sir,
I hereby certify that the
erection/re-erection/material alteration/demolition in/on building on Plot
number ..............in Village ..................in Sector
.................Bhadohi has been supervised by me and the completion plan
along with the required documents are attached herewith. The plans were
sanctioned vide letter number....................dated......................and
the work has been completed to my best satisfaction. The workmanship and all
the materials which have been used are strictly in accordance with the general,
detailed specification. No provision of the regulations, directions, no
requisition made, conditions, prescribed or order issued there under have been
transferred in the course of work. The land fit for construction for which it
has been developed or redeveloped.
Signature of the Licensed Technical
Person...............................
Name and address of the Licensed Technical
Person.....................
Dated:
Note. Strike out the words which are not
applicable.
Checklist
9-A (For buildings oh individual residential plots)
(i) 3 copies of drawings (one set cloth bounded) duly signed by the Licensed
Technical Person and Owner.
(ii) Completion fees
(iii) Valid time extension certificate, if applicable
(iv) Photographs of the building from front and side setbacks
(v) Photocopy of registration of Licensed Technical Person signing the plan
and Appendixes.
(vi) Copy of receipt of payment of Water, Sewer connection charges, Meter
charges and any other charges as may be required by the Authority.
(vii) Floppies/Compact Disc of the building plan submitted
(viii) Any other document as may be required from time to time.
Checklist
9-B (For buildings on Plots other than individual residential plots)
(i) 3 copies of drawings (one set cloth bounded) duly signed by the Licensed
Technical Person and Owner.
(ii) Completion fees
(iii) Valid time extension certificate, if applicable
(iv) Photographs of the building from front and side setbacks
(v) Photocopy of registration of Licensed Technical Person signing the plan
and Appendixes.
(vi) No Objection Certificate from Chief Fire Officer, wherever applicable
(vii) No Objection Certificate from Explosive Department, wherever applicable
(viii) Certificate from owner and structural Engineer regarding earthquake
resistance of building as per Appendix 8/A/B/D, if applicable
(ix) Copy of receipt of fees deposited with Bhadohi Power Company Limited
(x) Copy of receipt of payment of Water, Sewer connection charges, Meter
charges if not submitted at the time of plan approval, and any other charges as
may be required by the Authority
(xi) Floppies/Compact Disc of the building plan submitted
(xii) Any other document as may be required from time to time.
Checklist
9-C (For buildings layouts and sub-division land)
(i) 3 copies of drawings (one set cloth bounded) duly signed by the Licensed
Technical Person and Owner.
(ii) Completion fees
(iii) Valid time extension certificate, if applicable
(iv) Photographs of the building from front and side setbacks
(v) Photocopy of registration of Licensed Technical Person signing the plan
and Appendixes
(vi) No Objection Certificate from Chief Fire Officer, wherever applicable
(vii) No Objection Certificate from Explosive Department, wherever applicable
(viii) Certificate from owner and structural Engineer regarding earthquake
resistance of building as per Appendix 8/A/B/D, if applicable
(ix) Copy of receipt of fees deposited with Bhadohi Power Company Limited
(x) Copy of receipt of payment of Water, Sewer connection charges, Meter
charges if not submitted at the time of plan approval, and any other charges as
may be required by the Authority
(xi) Floppies/Compact Disc of the building plan submitted
(xii) Any other document as may be required from time to time.
APPENDIX 10
[See
Regulation number 9(1)]
Form for
sanction or refusal of Building Permit
From,
The Chief Executive Officer,
Bhadohi Industrial Development Authority,
Uttar Pradesh
To,
.........................
.........................
Sir,
With reference to your application
number.......................dated......................for grant of permit for
the erection/re-erection/material alteration/demolition in/of building on Plot
number.......................in Village ..................in Sector
.................Bhadohi. I have to inform you that the sanction has been
granted/refused by the Authority on the following conditions
1.
2.
3.
4.
Office Stamp
Signature...............................................
Office communication number.......................
Name of the
Officer...................................
Designation of the Officer
Dated:
Note.
Strike out which is not applicable.
APPENDIX 11
[See
Regulation Number 9(1)]
Form for
Occupancy Certificate
From,
The Chief Executive Officer,
Bhadohi Industrial Development Authority,
Uttar Pradesh
To,
Sir,
I hereby certify that the erection/re-erection/alteration/demolition
of the building on Plot number ..............in Village..................in
Sector.................Bhadohi completed under supervision of Licensed
Technical Person number..........................has been inspected by the
officers of the Authority and declare that the building conforms in all respect
to the requirements of the regulations in respect of occupancy. Structural
safety based upon the structural stability certificate and the completion
certificate submitted by the concerned Licensed Technical Personnel for fire
safety, hygienic and sanitary conditions inside and the surrounding and is fit
for occupation.
Signature...............................
Name...................................
Designation............................
Dated:
Note. Strike out which is not applicable.
APPENDIX
12
Qualification of Licensed
Technical Personnel for Preparation of Schemes for Building Permit and
Supervision
(1) The qualifications of the
technical personnel and their competence to carry out different jobs for
building permit and supervision for the purpose of licensing by the Authority
shall be as hereinafter indicated.
(2) Architects
2.1 Qualification. The qualification for licensing Architect will be
the Associate Membership of the Indian Institute of Architects or such Degree
or Diploma which makes him eligible for such membership or qualification
mentioned in Schedule XIV of Architects Act, 1972 and registered with the
Council of Architecture as provided by the provisions of the Architects Act,
1972.
2.2 A licensed Architect shall be competent to carry out work related
to building permit and shall be entitled to submit the following
(i) All plans and related information
connected with building permit.
(ii) Structural details and
calculations for building on plots up to 500 square meter and up to four
storeys high, and
(iii) Certificate of supervision for
all buildings (Except building mentioned in Regulation 30).
(3) Engineers
3.1 Qualification. The qualification for licensing of the engineers
will be Associate/Corporate Membership (Civil) of the Institution of Engineers
or such degree/diploma in Civil, Municipal, Architectural or Structural
Engineering which makes him eligible for such membership or which is recognized
by the Uttar Pradesh Public Service Commission for the post of an Assistant
Engineer.
3.2 A licensed engineer shall be competent to carry out the work
related to building permit and shall be entitled to submit the following
(i) Structural details and
calculations for all buildings (Except for buildings mentioned in Regulation
30).
(ii) Certificate of supervision for
all buildings.
(iii) Structural Calculation and
details for building mentioned in Regulation 30 shall be as per following
|
Sl. No.
|
Type of Building
|
Number of years of experience for Structural
Engineer for Structural design and supervision
|
Other Details
|
|
|
|
Graduate Civil Engineer
|
Post Graduate Structural Engineer
|
|
|
1.
|
Multi-storeyed/important facility buildings as
per Regulation 30 which are up to 4 storeys or 12 meter high or 2500 square
meter covered area
|
5 Years
|
3 Years
|
|
|
2.
|
Multi-storeyed/important facility buildings as
per Regulation 30 which are up to 4 storeys or 24 meter high or 5000 square
meter covered area
|
9 Years
|
7 Years
|
|
|
3.
|
Multi-storeyed/important facility buildings as
per Regulation 30 which arc above 8 storeys or above 24 meters high or above
5000 square meter covered area
|
10 Years
|
8 Years
|
Copy of structural design to be signed by
Professor of Structural Design of Indian Institute of Technology, Roorkee
University or any other recognized technical institutes.
|
(4) Town Planner (for layout plans
5.0 acres and above)
The minimum qualification for a town planner shall
be the Associate Membership of the Institute of Town Planners of India with
post-graduate degree or diploma in town and country planning/urban planning
which makes him eligible for such membership or recognized by the Public
Service Commissions for the Post of Assistant Town Planner.
A licensed Town Planner shall be competent to carry
out work related to building permit and shall be entitled to submit the
following
(i) Layout Plans on plots above 5.0
Acres.
(5) Group or Agency When a group or
agency comprising of qualified Architect/Engineer Town Planner is practicing
then the qualification and competence of work will be the combination of the
individual qualification and competence given under Paras 2, 3 and 4 above and
the agency shall be licensed by the Authority.