Open iDraf
The Union Of India v. Mangaldas N. Varma Of Bombay Having His Office At Janmabhoomi Chambers, Within The Fort Of Bombay

The Union Of India
v.
Mangaldas N. Varma Of Bombay Having His Office At Janmabhoomi Chambers, Within The Fort Of Bombay

(High Court Of Judicature At Madras)

Appeal Against Order No. 76 And 275 Of 1955 | 18-11-1957


Rajagopalan, Officiating Chief Justice

Sri M. N. Varma (hereinafter referred to as the contractor) entered into a contract with the Government of India to construct but, in the Avadi camp for the use of the military authorities. It was what was known as a lump sum contract. The amount was over Rs. 20 lakhs. The works were completed in 1945. Disputes about the quantum still payable to the contractor were referred to arbitrators in accordance with Cl. 35 of the contract between the contractor and the Government. Since the two arbitrators differed they referred the questions at issue between the parties to an Umpire, The award of the Umpire Sri C. G. Modi dated 29th July 1953 ran:

The Union of India, the opponents, do pay to the claimant Shri Mangaldas N. Varma the sum of Rs. 6,05,000 (Rs. Six lakhs and five thousand only) in respect of the claim. I do further award that the opponents do pay to the claimant Rs. 20,000 (Rs. Twenty thousands only) for costs of this reference.

Though the arbitration proceedings were at Bombay, Avadi, it should be remembered, lay within the territorial jurisdiction of the District Court of Chingleput. The contractor preferred O. P. No. 38 of 1953 to the District Judge of Chingleput to file the award and pass a decree in terms thereof. The Government in its turn filed O. P. No. 48 of 1953 to set aside the award of the Umpire. The learned District Judge allowed O. P. No. 38 of 1953 and dismissed O.P. No. 43 of 195

3. Against these decisions C. M. A. Nos. 275 of 1955 and 76 of 1955 respectively were preferred by the Government.

To appreciate scope of the contentions of Mr. Rege, the learned Counsel for the Government-appellant, what preceded the Umpires award has to be set out. These facts themselves were never in dispute. The arbitration clause in the contract between the contractor and the Government provided for the settlement of disputes by the Major General (Administration) as arbitrator. It was common ground that that office was abolished and it ceased to exist even by August 194

8. In September 1951 the contractor and the Government agreed to submit the disputes between them for settlement by the two arbitrators, Mr. S. K. Patil and Brigadier Halloway. The reference to arbitration specifically provided that if there was any difference between the arbitrators the disputes should be referred to an Umpire (Ex. A-2): Ex. A-2 itself listed the points of difference between the Government and the contractor.

The arbitrators entered upon their duties. Ex. B-15 was the detailed claim presented to the arbitrators by the contractor. The total of his claim against the Government was Rs. 57,78,929-4-0. The heads of claims were marked A to E. Of these item A was a claim for Rs. 98,211-7-0 which the contractor claimed was the balance due to him under the contract itself for the work done. Items B-1 to B. 12 represented claims for compensation. The total of the claims under Items A and B. 1 to B. 12 came to Rs. 6,03,049-11-0. Item C was a claim for Rs. 3,52,855-9-9, which according to the contractor represented the interest on the said sum of Rs. 6,03049-11-0 at 9 per cent per annum from 1st April 1945 till 30th September 195

1. The contractor claimed that further interest would be payable on the total sum awarded at 9 per cent from 30th September 1951 till the date of payment. Under Item D the contractor claimed Rs. 72,366 as compensation, because he had to maintain an establishment to finalise his claims against the Government and to recover what was lawfully due to him. The basis of the claim under Item E. Rs. 47,49,658 was that if the contractor had been paid what was lawfully due to him on the dates when they fell due, he would have been in a position to invest these sums in his contract business and he would have been able to earn considerable profits. Ex. A. 12 was only a summary of these claims. In Ex. A. 13 the details of the counter claim made by the Government against the contractor amounting to Rs. 1,16,602-6-0 were set out.

The statutory allowance of four months to complete the arbitration was obviously insufficient. The parties to the arbitration as well as the arbitrators applied in O. P. No. 9 of 1952 (Ex. A. 3) to the District Judge of Chingleput and obtained time till 10th May 1952, for the arbitrators to give their award. As recited in Ex. B. 1, the arbitrators failed to agree, and on 24th April 1952 they appointed Mr. E. A. Nadir Shaw as the Umpire to decide the questions at issue between the parties. Mr. Nadir Shaw apparently entered upon his duties as Umpire, but he had to relinquish them in June 1952, because he had to go abroad. Ex. B. 14 is the letter dated 13-14th June 1952 written by Mr. Nadir Shaw to the parties. He asked them to appoint another Umpire.

On 19th June 1952 and 26th June 1952 the contractor and the Government respectively wrote to the arbitrators to appoint a fresh Umpire. Ex. A. 6 was the letter that the Government addressed to the arbitrators.

The arbitrators, Mr. Patil and Brigadier Halloway, selected Mr. C. G. Modi, a Judge of the Court of Small Causes, Bombay, and requested him in Ex. B. 1 dated 1st July, 1952 to accept the office of Umpire. Intimation of this was given to both the contractor and the Government by Ex. A. 7 dated 4th July 195

2. They were informed that Mr. Modi could enter upon his office as Umpire only after obtaining the permission of the Government of Bombay, and the parties were informed further that steps were being taken to obtain the requisite sanction. That sanction was eventually accorded on 31st July 195

2. At the request of Mr. Patil conveyed by Ex. B. 1 dated 1st July 1952, the other arbitrator Brigadier Halloway informed both the Government and the contractor by Ex. A. 9 dated 5th August 1952 that Mr. Modi had accepted the appointment of Umpire.

That was followed up by Ex. A. 10, also dated 5th August 1952, the formal reference by the two arbitrators to the Umpire, Mr. Modi. Copies of Ex. A. 10 were communicated by the arbitrators both to the Government and to the contractor.

The Umpire gave notice on 14th August 1952 both to the Government and to the contractor fixing 30th August 1952 for a preliminary meeting to enquire into the matters in dispute (Ex. A. 11). Two days earlier than that, on 12th August 1952, the Government sent Ex. B. 12 to the Umpire in effect requesting him to proceed with the inquiry.

Thus it should be clear that a new Umpire was appointed by the arbitrators at the request of both the parties, the Government and the contractor. Both of them accepted the appointment of Mr. Modi and the Government requested him to proceed with the enquiry. No one up to this stage questioned the validity of the appointment of Mr. Modi as Umpire.

Ex. A. 18 dated 23rd August 1952 showed that the Government Solicitor advised the Government that possibly the arbitrators had no authority to appoint a fresh Umpire. The Umpire, Mr. Modi, it should be remembered had fixed 30th August 1952 presumably in response to Ex. B. 12 for a preliminary enquiry. There were no proceedings that day and further proceedings were adjourned to 4th September 1952 as was shown in Ex. B. 8, the minutes of the proceedings before the Umpire. The Umpire recorded on 4th September 1952:

Mr. Jayakar (Solicitor for the Government) raised a point with regard to the legality of my appointment as also the date on which I am supposed to have entered upon the reference. The parties agreed to take the opinion of the Advocate General on the two points raised. The matter adjourned to 8th September, 1952 at 5 P. M.

The Government Solicitor, Mr. Jayakar, was certainly aware of the fact that the Advocate General was the Counsel for the contractor and yet the Solicitor was prepared to abide by the opinion of the Advocate General on the legality of the appointment of Mr. Modi as Umpire. On 8th September, 1952, the Umpire recorded:

The respective Solicitors informed me that the required opinion was taken and that the date for hearing may now be fixed to proceed with the arbitration.

The matter adjourned to 30th September, 1952, at 11-30 A. M.

It should thus be clear that the Government at this stage gave up its attempt to challenge the jurisdiction of Mr. Modi to act as Umpire. This was followed up by the Umpire by his notice, Ex. B-13, issued to the Solicitors of both the Government and the contractor, informing them in writing that 30th September, 1952, had been appointed as the date for proceeding with the arbitration. The Umpire informed them:

This long date is fired to suit the convenience of the Central Government on the understanding that the parties in the meantime will obtain extension of time from the proper Court for making the award.

On 30th September, 1952, Ex. A-15 was filed on behalf of the Government before the Umpire. It was signed by the Counsel for the Government and ran:

The respondent objects to the jurisdiction of Shri Champaklal G. Modi, B. A. LL. B., as Umpire.



2. The respondent has been advised that the appointment of Shri Champaklal G. Modi is invalid and inoperative in law and that he is not entitled to hold the office of Umpire and proceed with the above matter.



3. The respondent is advised that he should not take part in the proceedings proposed to be held by Shri Champaklal G. Modi in the above matter.



4. The respondent, therefore, says that under the circumstances the proceedings in the above matter should be adjourned pending the valid appointment of an Umpire in accordance with the provisions of the Indian Arbitration Act, 1940.

5. The respondent is appearing by Counsel in these proceedings under protest and will continue to so appear until the proceedings are adjourned.

On this the Umpire recorded (Ex. B-8):

Mr. Rege (Counsel for the Government) submits to me a statement objecting to the legality of my appointment. Mr. Rege was informed that this point was raised by Mr. Jayakar and after the opinion of the Advocate General about the validity of my appointment Mr. Jayakar consented to proceed with the arbitration and he took todays date by mutual consent for the purpose. It was also brought to the notice of Mr. Jayakar that the time for making the award was too short. A long date was given to suit the convenience of the Central Government on the understanding that the parties in the meantime will obtain extension of time from the proper Court, for making the award. As Mr. Jayakar has gone to Poona, the matter is adjourned to 7th October, 1952, at 5 p. m. to enable the Counsel for the Government to meet Mr. Jayakar to ascertain the above facts.

Exhibit B-8 showed that on 7th October, 1952, Mr. Rege, Counsel for the Government, still appeared under protest. Nothing however was done that day and the proceedings were adjourned to 8th October, 195

2. On 8th October, 1952, apparently Mr. Rege was not present but Mr. Jayakar, Solicitor for the Government, represented the Government. The Umpires note ran:

Mr. Jayakar informs me that he has communicated with the Chief Engineers Office, Southern Command and that necessary steps will be taken to have the time extended for making the award till 31st January, 1953.

Mr. Jayakar apparently ceased to act as Solicitor for the Government by the end of January 1953 and fresh Solicitors came on record as is clear from the notes of the Umpire dated 30th January, 1953, and 2nd February, 1953.

Meanwhile, on 11th November, 1952, the Government preferred O. P. No. 33 of 1952 to the District Judge of Chingleput to extend upto 31st March, 1953, the time required to complete the award. This was apparently to implement what was represented to the Umpire on 8th October, 195

2. Even the time upto 31st March, 1953 was not sufficient. On 9th March, 1953, the contractor presented O. P. No. 12 of 1953 to the District Judge, Chingleput, to extend the time upto 31st May, 1953, for the Umpire to give his award. On that application the Solicitor for the Government of India endorsed:

I hereby give my consent on behalf of the respondent to the time for the Umpire Sri C. G. Modi for making his award in the matter extended till 31th day of May 1953.

The Court granted time till 31st July 1953.

It should thus be clear that though at one stage the Counsel for the Government challenged the validity of the appointment of Mr. Modi as Umpire, that objection was apparently not persisted in. Certainly no objection was put forward in the proceedings in the District Court, Chingleput, when both parties virtually asked the District Court to extend the time to enable Mr. Modi as Umpire to give his award. Time, as we have pointed out, was granted by the District Court upto 31st July 1953.

Ex. B. 8, the minutes of the proceedings before the Umpire showed that the actual enquiry commenced on 28th February, 1953, and was concluded on 15th July, 195

3. The Umpires award was given on 29th July, 1953.

It is against this background that we have to consider the submissions of the learned Counsel for the appellant. His first contention was that the appointment of Mr. Modi as Umpire by the arbitrators was invalid and therefore the Umpire had no jurisdiction at all to proceed with the arbitration. His next set of contentions was that the award was vitiated, because the Umpire did not give his decision with reference to each head of claim and counter claim, especially when the Umpire had to decide the plea of limitation also with reference to each head of claim of the contractor.

The relevant dates with reference to the first of these contentions were as follows. On 14th June, 1952 Mr. Nadir Shaw relinquished his office. On 19th June, 1952, and 26.h June, 1952, respectively the contractor and the Government asked the arbitrators to appoint a fresh Umpire in the place of Mr. Nadirshaw. Though on 1st July, 1952, itself the arbitrators appointed Mr. Modi as Umpire, effect could be given to that appointment only on 5th August, 1952, alter the requisite sanction had been obtained from the Government of Bombay to permit Mr. Modi to take up his work as Umpire.

The learned Counsel for the appellant urged that 5th August, 1952, should be taken as the date on which Mr. Modi was appointed Umpire, and that such an appointment was in contravention of S. 8 (2) of the Arbitration Act, 1940 and was in excess of the powers of the arbitrators. The learned District Judge referred to the petitions filed in his Court for extension of time to complete the arbitration proceedings and observed that these petitions indicated that the parties accepted the Umpire and were willing to abide by his award The learned Judge concluded:

I do not consider that in these circumstances it could be said that the Umpire acted without jurisdiction or without this being as Umpire legally appointed under the Arbitration Act.

The relevant portion of S. 8(1) (c) of the Arbitration Act runs:

Where the arbitrators are required to appoint an Umpire and do not appoint him; any party may serve the other parties or the arbitrators, as the case may be, with a written notice to concur in the appointment or appointments or in supplying the vacancy.

S. 8 (2) runs:

If the appointment is not made within fifteen clear days after the service of the said notice, the Court may, on the application of the party who gave the notice and after giving the other parties an opportunity of being heard appoint anumpirewho shall have like power to act in the reference and to make an award as if he had been appointed by consent of all parties.

We are unable to discover any real basis in these statutory provisions for the contention of the learned Counsel that in the circumstances of this case the two arbitrators were divested of their powers to appoint an umpire on the expiry of the fifteenth day from the date on which the parties to the reference, the contractor and the Government, wrote to them asking for the appointment of an Umpire. In this case the obligation of the arbitrators to appoint an Umpire arose when Mr. Nadir Shaw informed them and the parties on 14th June, 1952, of his inability to function any longer as an Umpire. On 23rd June, 1952, Mr. Patil wrote Ex. A. 4 to the other arbitrator, Brigadier Holloway, suggesting certain names. Ex. A. 5 was the reply Of Brigadier Holloway dated 25th June, 1952, accepting the suggestion to appoint Mr. Modi. On 1st July 1952, both of them addressed Mr. Modi to accept the appointment: Ex. B.

1. Thus it was not a case of neglect or refusal of the arbitrators to appoint an Umpire. They did appoint the Umpire. They selected Mr. Modi for appointment even before 1-7-1952, though the formal appointment had to be deferred till 5th August, 1952, to obtain he sanction of the Government of Bombay to enable Mr. Modi to accept the officer of appointment. The parties, the contractor and the Government, were kept informed all through. It should be clear that it was not a cases where the arbitrators, who were required to appoint an Umpire, did not appoint one within the meaning of S. 8(1) (c) of the Arbitration Act. That Sub-section postulates at least a factual failure on the part of the arbitrators to appoint an Umpire before either of the parties could serve the notice on the arbitrators. The notice, for which S. 8(1)(c) provides, is a notice by the party to the arbitrators, who had already (ailed to appoint an Umpire, to concur in the appointment of an Umpire or to concur in supplying the vacancy in the office of the Umpire. Even factually the letters written by the contractor and the Government to the arbitrators on 19th June, 1952, and 26th June, 1952, respectively were not the notice for which S. 8 (1) (c) provided. S. 8 (2) comes into play only after the service of the said notice, the notice issued by the party under S. 8 (1) (c). There was no such notice. There was no occasion for any such notice.

Even assuming that the letters dated 19th June, 1952, and 26th June, 1952, could be viewed as notices under S. 8 (1)(c) of the Act, S. 8 (2) is only an enabling Section. The party whose notice was ignored is enabled by S. 8 (2) to apply to the Court for the appointment of an Umpire. The scheme underlying S. 8 is that the default of a party to the reference or even the default of an arbitrator should not normally result in the arbitration agreement itself becoming abortive. Consent, of course, is of the very essence of arbitration. Reading S. 8 (1) (c) and S. 8 (2) together, it seems to us that, even where the arbitrators were requested by the parties to appoint an Umpire, if the request was complied with and an Umpire was appointed, and that appointment was accepted by the parties, the validity of the appointment cannot be challenged on the ground that that appointment was made more than 15 days after the parties had asked the arbitrators to appoint an Umpire. If the requirements of S. 8 (2) are satisfied, and an application is made to the Court to appoint an Umpire, thereafter, of course, when the Court is seized of the matter, the arbitrators could not be permitted to appoint an Umpire. None of these factors came into play in the present case. Once again we have to point out that the arbitrators acted promptly on the receipt of the letters from the parties to the reference to arbitration, and the delay in giving effect to that appointment was one which, was specifically brought to the notice of both the contractor and the Government and they accepted that delay as inevitable.

The contention of the learned Counsel for the appellant, that the appointment of Mr. Modi as Umpire was invalid even at its inception, therefore, fails.

In the view we have taken of the validity of the appointment of the Umpire, it may not really be necessary to uphold his jurisdiction on the ground that the Government, by its conduct, was estopped from questioning the validity of the appointment in subsequent proceedings. The learned Counsel for the appellant urged that the participation of the Government in the proceedings before the Umpire subsequent to 30th September 1952, on which date the Counsel for the Government lodged Ex. A-15 with the Umpire, did not really bar the Government from attacking the validity of the proceedings before that Umpire. The learned Counsel relied on Chatandas v. Radhakisson (A.I.R. 1927 Bom. 553) [LQ/BomHC/1927/58] and Rambaksh v. Bombay Cotton Co. (A.I.R. 1931 Bom. 81) [LQ/BomHC/1930/5] . What would have been the position had the Umpire, after the protest by the Government on 30th September, 1952, completed the arbitration proceedings within the time allowed by Jaw and gave his award, we are not called upon to discuss or decide in this case. Whether in such a case, the subsequent participation in the proceedings before the Umpire after the initial protest would amount to a waiver of the Governments right to challenge the jurisdiction of the Umpire does not arise for consideration in the circumstances of this case. The Umpire could not complete the arbitration proceedings within the time allowed by law. The requisite Sanction of the Court had to be obtained to extend the time within which the Umpire could give his award. That sanction was sought first on the initiative of the Government itself when it filed O. P. No. 33 of 1952) and next on the initiative of the contractor when he filed O. P. No. 12 of 195

3. Who presented the petition may not be material in the circumstances of this case, as both parties to the reference had agreed before the Umpire to obtain the sanction of the Court to extend the time for the Umpire to give his award. O. P. No. 12 of 1953, it should be remembered, contained an express consent given by the Solicitor for the Government to extend the time. If the Government wanted to challenge the validity of the appointment of Mr. Modi, as Umpire, the proper stage was when an application was made to the District Court, Chingleput, to extend the time, and the appropriate forum to decide such an issue was that Court. The conduct of the Government in accepting the validity of the proceedings before the Umpire, on the basis of which alone the Government could have asked for extension of time or acquiesced in the subsequent request for extension of time, should be sufficient to deny them the right at this stage to impeach the validity of the appointment of Mr. Modi as Umpire.

This was the conduct of the Government after the formal protest to the Umpires jurisdiction by filing Ex. A-15 on 30th September 195

2. But this apart, we have narrated the manner in which the Government concurred in the appointment of the Umpire and the steps they took before him requesting him to proceed with the reference, (Ex. B-12). Learned Counsel urged that this might not amount to waiver or acquiescence because it was not proved that Government were aware of the precise legal point regarding invalidity when they took these steps. It is unnecessary to pronounce on the sustainability of this explanation because in the present case the Government specifically gave up this objection later on after they were aware of the supposed invalidity in the appointment of the Umpire. In saying this we are thinking of the proceedings before the Umpire dated 4th September 1952 which we have already set out. On the latter date they expressly abandoned their objections to the validity of the Umpires appointment accepting the opinion of the Advocate General in the matter. Learned Counsel for the appellant faintly suggested that the Advocate General whose opinion was sought was Counsel for the contractor but if as was admitted this fact was known to the representative of the Government when the latter agreed to abide by his opinion, it did not affect its binding character. Indeed even after an opinion adverse to Governments contention was given by the Advocate General it was in terms accepted by the Solicitor who represented the Government before the Umpire and it was on this basis that the Umpire adjourned the proceedings to 30th September 195

2. This conduct of the Government might, in our opinion, sustain a plea that the Government had precluded themselves from lodging any protest to the jurisdiction of the Umpire on 30th September 1952 when they filed Ex. A-15 before him.

But, as we have already recorded earlier, it may not be necessary to rest our decision on these features of the case; because independent of these we have found that the appointment of Mr. Modi as Umpire was valid.

There was even less basis for the second set of contentions of the learned Counsel for the appellant. It is true that the Umpire did not give any reasons in the award. But, then that by itself cannot vitiate the award. Ex. B-8 was a fairly full record of the proceedings before the Umpire, which showed that each head of claim and counter claim was separately considered by the arbitrator. It was not as if the question of limitation was not considered by the arbitrator. Ex. A-16 showed that 28 hours and 45 minutes were spent in all by the Umpire in listening to arguments on the question of limitation. Ex. A. 16 also showed that each of the claims and counter claims was considered, and the time spent by the Umpire on each of these claims was also recorded. We have referred to this only to show that every aspect of the case with reference to each head of claim was fully considered by the Umpire before he gave his award. We are not now concerned with the question whether the ultimate decision of the Umpire which might very well have been based in part on his construction of the correspondence as acknowledgment of liability on the part of the Government was right or not, all that we need say is that the apparent failure to record specific findings on the issue of limitation with reference to each head of claim did not vitiate the Umpires award. Nor can the validity of the award be impugned on the ground that each item of claim or counter claim was not specifically dealt with and the Umpires decision thereon recorded. An award of a lump sum is not invalid and the sum awarded must on the facts of the present case be taken to reflect the net result of the claims upheld or disallowed.

The appeals fail and are dismissed with costs in one, C.M. A. No. 76 of 1955.

Advocates List

For the Petitioner The Govt. Pleader, R.G. Rajan, Advocates. For the Respondent Messrs. M.S. Venkatarama Ayyar, V. Krishnan, Advocates.

For Petitioner
  • Shekhar Naphade
  • Mahesh Agrawal
  • Tarun Dua
For Respondent
  • S. Vani
  • B. Sunita Rao
  • Sushil Kumar Pathak

Bench List

HON'BLE OFFICIATING CHIEF JUSTICE MR. RAJAGOPALAN

HON'BLE MR. JUSTICE RAJAGOPALA AYYANGAR

Eq Citation

(1958) 2 MLJ 16

(1958) ILR MAD 420

AIR 1958 MAD 296

LQ/MadHC/1957/323

HeadNote

Limitation Act, 1963 — S. 14 — Extension of time — Arbitration proceedings — Extension of time for making award — When not necessary — Arbitration Act, 1940, S. 8(2)