The Associated Oil Mills Limited, Katpadi
v.
The Provincial Government Of Madras Represented By The Collector Of North Arcot At Vellore
(High Court Of Judicature At Madras)
Appeal Against Order No. 667 & 732 Of 1945 | 25-08-1947
(Prayer: Appeal (disposed of on 25-8-1947) against the order of the District Judge of North Arcot at Vellore dated 7-8-1945 in O.P. No. 16 of 1945.)
Govindarajachari, J.
These two appeals are directed against the judgment and decree of the District Judge of North Arcot, Vellore, acting as an arbitrator under S. 19(1)(b) of the Defence of India Act. C.M.A. No. 667 of 1945 is by the Associated Oil Mills Ltd., Katpadi hereinafter referred to as the claimant and C.M.A. No. 732 of 1945 is by the Government of the Province of Madras. It is convenient to deal with the latter appeal first.
The only point taken in this appeal on behalf of the Government is that in his award concerning the loss of income to the claimant the District Judge should have confined it to the period from 1st June 1942 to 11th September 1942 and should not have given any amount for loss of income for the period between 11th September 1942 and 15th October 194
2. About four acres and 15 cents of land belonging to the claimant in the village of Ammanur in Arkonam taluk was requisitioned by the Government for military purposes with some superstructures standing thereon. The order requisitioning those properties was passed on the 20th May 1942; but possession was actually taken three days later. The superstructures included a mill which the claimant had erected for crushing groundnuts and other oil seeds. It is common ground that the claimant would have commenced the working of the mill and would have gone on with the manufacture of oils had it not been for the requisitioning of the properties by the Government. After it received the order of requisition the claimant had to remove the mill from there and erect it at Katpadi. On behalf of the claimant it was at first claimed that it should be awarded compensation by way of loss of income from the 23rd May 1942 to the 1st November 194
2. At the time however, when evidence was adduced before the arbitrator the claim was restricted to the period between the 1st June 1942 and 24th October 194
2. There is no objection on the part of the Government to the 1st June 1942 being regarded as the commencement of the period; but it is contended by the Government that the claimant should not be awarded any compensation for loss of income after the 11th September 194
2. The District Judge awarded Rs. 63,259-12-0 under this head calculating as already stated for the period between 1st June 1942 and 15th October 194
2. It would appear that the claimant applied to the proper authorities for permission to work the factory on the 6th October 1942 and that permission was given on the 11th October 194
2. The District Judge allowed four days for the permit to reach the claimant and that is how he fixed the 15th October 1942 as the date up to which compensation should be awarded. On behalf of the Government the learned Government Pleader argued that it is for the claimant to show that it could not have started the working of the factory at Katpadi at an earlier date. The evidence on this matter is meagre; but from the evidence of the claimants director who was the only witness examined in the case it appears that soon after the requisition was received the claimant purchased another site at Katpadi on the 2nd June 1942 and that with the greatest expedition the witness constructed the buildings there and planted the machinery which he had removed from Arkonam, by the last week of October when, according to him, he actually started pressing oil after getting a permit. There was no serious challenge of this statement which was made by the witness in his examination-in-chief. He was asked in cross-examination about the purchases made by his company on the 11th September, 1942 and again on the 14th September. He admitted the purchases, but stated that they were for small amounts. He added that the company carries an advance stock of 15000 bags valued at Rs. 3,75,000. The Government called no evidence contra. The mere fact that some quantity of groundnut was purchased on the 11th September and 14th September does not indicate that the crushing of the groundnut was started on either of these dates. Assuming that it is for the claimant to establish that it could not have started the working of the mill at Katpadi earlier, the evidence given by the witness examined on behalf of the claimant, in our opinion, satisfactorily establishes that the company could not have started the working of the mill at Katpadi earlier than the date fixed by the learned District Judge. It is not denied that the mill could not be worked without a permit which was only issued on the 11th October 194
2. All that is suggested on behalf of the Government is that the claimant could have constructed the mill at Katpadi and obtained the permit earlier than that date but for reasons already stated not only has the Government not made this out, but the claimant has definitely established that it could not have started the working of the mill at Katpadi earlier than 15th October. That is the only point argued in the appeal filed by the Government. The appeal fails and is dismissed with costs.
In the appeal filed by the claimant two points were taken on its behalf. One is that interest should have been awarded by the learned District Judge on the amount which he has decreed. The second is that the learned District Judge is wrong in allowing only Rs. 100 by way of costs to the claimant, while allowing a like amount of costs to the Government though the claimant has very substantially succeeded before him.
As to the first point we do not see how interest can be awarded on an amount which is in the nature of damages. It was suggested that the Government had agreed to pay interest. The appellants Counsel took us through some of the letters which passed between the claimants solicitor and the Government in an endeavor to establish that there was an agreement between the claimant and the Government as to the amount payable to the former by way of compensation for loss of income. We are satisfied that at no stage during the correspondence was there any such agreement. In his award dated 31st January 1945 the Collector of North Arcot refers to the claims made before him on behalf of the Associated Trading Corporation Limited and the Associated Oil Mills Ltd., the latter being the claimant in this proceeding
Dealing with the claim made by the Associated Trading Corporation, he stated that it was agreed between the Government and the Corporation that Rs. 3394 should be paid by the Government by way of compensation for requisitioning certain properties of the Corporation and in referring to this amount the Collector says that the Government was pleased to sanction payment of interest at 6 per cant per annum on the amount of compensation as finally agreed upon. In a separate paragraph he refers to the claim made by the Associated Oil Mills Ltd. There he simply sets out the particulars of the amounts which the Government was prepared to pay to the claimant and expressly states that there being no agreement between the Associated Mills and the Government, there would be a reference to the arbitrator, viz., the District Judge of North Arcot. Moreover, we are not concerned with the question whether there was any agreement between the Government and the claimant as to the period for which compensation should be awarded for loss of income, the point which we have to decide being whether the Government consented to pay interest. We have not been shown any document from which it can be said that the Government agreed to pay interest on such compensation as may be awarded to the claimant.
It was then argued on behalf of the the appellant that under S. 19(1)(e)(i) of the Defence of India Act, it would be entitled to the award of interest. S. 19(1)(e)(i) runs as follows:
The arbitrator in making his award shall have regard to
(i) The provisions of Sub-S. (1) of S. 23 of the Land Acquisition Act, 1894, so far as the same can be made applicable.
Turning to Sub-S. (i) of S. 23 of the Land Acquisition Act it will be noticed that there is no provision therein for the award of interest in cases arising under the Land Acquisition Act, the appropriate provision being contained in S. 34 which, it will be observed, is not one of the provisions made applicable to by the Defence of India Act to claims made in regard to properties which are requisitioned. Reference was made on behalf of the appellant to the decision of the Judicial Committee in Inglewood Pulp & Co. v. Newbrunswick Electric Ltd. , (A.I.R. 1928 P.C. 287=28 L.W. 753). At page 290 of the report occur the following observations of the Privy Council:
It is now well established that on a contract for sale and purchase of land it is the practice to require the purchaser to pay interest on his purchase money from the date when be took possession [per Lord Cave L.C. in Swift v. The Board of Trade (1925 A.C. 820 at 832)]. The law on the point has also been extended to cases under the Lands Clauses Consolidation Act, 1845.
So far as the compulsory purchase of properties in this country is concerned, the law is statutorily laid down in the Land Acquisition Act. In the absence of any provision in the Defence of India Act or the rules framed there under making S. 34 of the Land Acquisition Act applicable and in view of the provision expressly making Sub-S. (1) of S. 23 of that Act alone applicable, we are unable to see on what general principle we can award interest to the claimant because he was kept out of the use of money which ultimately is found payable to him by way of compensation.
It is unnecessary for us to go into the question whether any interest is awardable from and after the date of the reference to the arbitrator. Assuming that there is power and jurisdiction in the arbitrator to award interest during the pendency of the arbitration in appropriate cases, it must be noticed that no claim for interest from the commencement of the arbitration proceedings was made before the arbitrator. In a careful judgment the learned District Judge deals with every one of the claims made before him and there is no reference anywhere to any claim for interest. In these circumstances we must hold that the claimant is not entitled to the award of any interest on the amount which has been decreed to him.
As regards costs it must be mentioned that by the time the reference was made to the arbitrator the claimants total demand stood so high as Rs. 1,65,275-5-6. It is only in the statement that he subsequently filed before the arbitrator that the claim in respect of loss of income was reduced to the figure of Rs. 72,957-4-
2. It is true that the District Judge has awarded Rs. 63,259-12-0 which represents a substantial portion of the amount claimed in the respondents statement but if costs are to be awarded ad valorem as the appellants Advocate claims, the Government would be entitled to costs on the amount in respect of which the claimants demand was refused by the learned District Judge. If there are to be costs ad valorem on both sides there would be very little difference indeed in the matter of the resultant costs payable by one side to the other. We are unwilling to interfere with the discretion of the learned District Judge in his award as to costs. He fixed the sum at Rs. 100 each to the Counsel appearing for the Government and the claimant. In our opinion the award must stand. The appeal filed on behalf of the claimant also fails and is dismissed with costs.
Govindarajachari, J.
These two appeals are directed against the judgment and decree of the District Judge of North Arcot, Vellore, acting as an arbitrator under S. 19(1)(b) of the Defence of India Act. C.M.A. No. 667 of 1945 is by the Associated Oil Mills Ltd., Katpadi hereinafter referred to as the claimant and C.M.A. No. 732 of 1945 is by the Government of the Province of Madras. It is convenient to deal with the latter appeal first.
The only point taken in this appeal on behalf of the Government is that in his award concerning the loss of income to the claimant the District Judge should have confined it to the period from 1st June 1942 to 11th September 1942 and should not have given any amount for loss of income for the period between 11th September 1942 and 15th October 194
2. About four acres and 15 cents of land belonging to the claimant in the village of Ammanur in Arkonam taluk was requisitioned by the Government for military purposes with some superstructures standing thereon. The order requisitioning those properties was passed on the 20th May 1942; but possession was actually taken three days later. The superstructures included a mill which the claimant had erected for crushing groundnuts and other oil seeds. It is common ground that the claimant would have commenced the working of the mill and would have gone on with the manufacture of oils had it not been for the requisitioning of the properties by the Government. After it received the order of requisition the claimant had to remove the mill from there and erect it at Katpadi. On behalf of the claimant it was at first claimed that it should be awarded compensation by way of loss of income from the 23rd May 1942 to the 1st November 194
2. At the time however, when evidence was adduced before the arbitrator the claim was restricted to the period between the 1st June 1942 and 24th October 194
2. There is no objection on the part of the Government to the 1st June 1942 being regarded as the commencement of the period; but it is contended by the Government that the claimant should not be awarded any compensation for loss of income after the 11th September 194
2. The District Judge awarded Rs. 63,259-12-0 under this head calculating as already stated for the period between 1st June 1942 and 15th October 194
2. It would appear that the claimant applied to the proper authorities for permission to work the factory on the 6th October 1942 and that permission was given on the 11th October 194
2. The District Judge allowed four days for the permit to reach the claimant and that is how he fixed the 15th October 1942 as the date up to which compensation should be awarded. On behalf of the Government the learned Government Pleader argued that it is for the claimant to show that it could not have started the working of the factory at Katpadi at an earlier date. The evidence on this matter is meagre; but from the evidence of the claimants director who was the only witness examined in the case it appears that soon after the requisition was received the claimant purchased another site at Katpadi on the 2nd June 1942 and that with the greatest expedition the witness constructed the buildings there and planted the machinery which he had removed from Arkonam, by the last week of October when, according to him, he actually started pressing oil after getting a permit. There was no serious challenge of this statement which was made by the witness in his examination-in-chief. He was asked in cross-examination about the purchases made by his company on the 11th September, 1942 and again on the 14th September. He admitted the purchases, but stated that they were for small amounts. He added that the company carries an advance stock of 15000 bags valued at Rs. 3,75,000. The Government called no evidence contra. The mere fact that some quantity of groundnut was purchased on the 11th September and 14th September does not indicate that the crushing of the groundnut was started on either of these dates. Assuming that it is for the claimant to establish that it could not have started the working of the mill at Katpadi earlier, the evidence given by the witness examined on behalf of the claimant, in our opinion, satisfactorily establishes that the company could not have started the working of the mill at Katpadi earlier than the date fixed by the learned District Judge. It is not denied that the mill could not be worked without a permit which was only issued on the 11th October 194
2. All that is suggested on behalf of the Government is that the claimant could have constructed the mill at Katpadi and obtained the permit earlier than that date but for reasons already stated not only has the Government not made this out, but the claimant has definitely established that it could not have started the working of the mill at Katpadi earlier than 15th October. That is the only point argued in the appeal filed by the Government. The appeal fails and is dismissed with costs.
In the appeal filed by the claimant two points were taken on its behalf. One is that interest should have been awarded by the learned District Judge on the amount which he has decreed. The second is that the learned District Judge is wrong in allowing only Rs. 100 by way of costs to the claimant, while allowing a like amount of costs to the Government though the claimant has very substantially succeeded before him.
As to the first point we do not see how interest can be awarded on an amount which is in the nature of damages. It was suggested that the Government had agreed to pay interest. The appellants Counsel took us through some of the letters which passed between the claimants solicitor and the Government in an endeavor to establish that there was an agreement between the claimant and the Government as to the amount payable to the former by way of compensation for loss of income. We are satisfied that at no stage during the correspondence was there any such agreement. In his award dated 31st January 1945 the Collector of North Arcot refers to the claims made before him on behalf of the Associated Trading Corporation Limited and the Associated Oil Mills Ltd., the latter being the claimant in this proceeding
Dealing with the claim made by the Associated Trading Corporation, he stated that it was agreed between the Government and the Corporation that Rs. 3394 should be paid by the Government by way of compensation for requisitioning certain properties of the Corporation and in referring to this amount the Collector says that the Government was pleased to sanction payment of interest at 6 per cant per annum on the amount of compensation as finally agreed upon. In a separate paragraph he refers to the claim made by the Associated Oil Mills Ltd. There he simply sets out the particulars of the amounts which the Government was prepared to pay to the claimant and expressly states that there being no agreement between the Associated Mills and the Government, there would be a reference to the arbitrator, viz., the District Judge of North Arcot. Moreover, we are not concerned with the question whether there was any agreement between the Government and the claimant as to the period for which compensation should be awarded for loss of income, the point which we have to decide being whether the Government consented to pay interest. We have not been shown any document from which it can be said that the Government agreed to pay interest on such compensation as may be awarded to the claimant.
It was then argued on behalf of the the appellant that under S. 19(1)(e)(i) of the Defence of India Act, it would be entitled to the award of interest. S. 19(1)(e)(i) runs as follows:
The arbitrator in making his award shall have regard to
(i) The provisions of Sub-S. (1) of S. 23 of the Land Acquisition Act, 1894, so far as the same can be made applicable.
Turning to Sub-S. (i) of S. 23 of the Land Acquisition Act it will be noticed that there is no provision therein for the award of interest in cases arising under the Land Acquisition Act, the appropriate provision being contained in S. 34 which, it will be observed, is not one of the provisions made applicable to by the Defence of India Act to claims made in regard to properties which are requisitioned. Reference was made on behalf of the appellant to the decision of the Judicial Committee in Inglewood Pulp & Co. v. Newbrunswick Electric Ltd. , (A.I.R. 1928 P.C. 287=28 L.W. 753). At page 290 of the report occur the following observations of the Privy Council:
It is now well established that on a contract for sale and purchase of land it is the practice to require the purchaser to pay interest on his purchase money from the date when be took possession [per Lord Cave L.C. in Swift v. The Board of Trade (1925 A.C. 820 at 832)]. The law on the point has also been extended to cases under the Lands Clauses Consolidation Act, 1845.
So far as the compulsory purchase of properties in this country is concerned, the law is statutorily laid down in the Land Acquisition Act. In the absence of any provision in the Defence of India Act or the rules framed there under making S. 34 of the Land Acquisition Act applicable and in view of the provision expressly making Sub-S. (1) of S. 23 of that Act alone applicable, we are unable to see on what general principle we can award interest to the claimant because he was kept out of the use of money which ultimately is found payable to him by way of compensation.
It is unnecessary for us to go into the question whether any interest is awardable from and after the date of the reference to the arbitrator. Assuming that there is power and jurisdiction in the arbitrator to award interest during the pendency of the arbitration in appropriate cases, it must be noticed that no claim for interest from the commencement of the arbitration proceedings was made before the arbitrator. In a careful judgment the learned District Judge deals with every one of the claims made before him and there is no reference anywhere to any claim for interest. In these circumstances we must hold that the claimant is not entitled to the award of any interest on the amount which has been decreed to him.
As regards costs it must be mentioned that by the time the reference was made to the arbitrator the claimants total demand stood so high as Rs. 1,65,275-5-6. It is only in the statement that he subsequently filed before the arbitrator that the claim in respect of loss of income was reduced to the figure of Rs. 72,957-4-
2. It is true that the District Judge has awarded Rs. 63,259-12-0 which represents a substantial portion of the amount claimed in the respondents statement but if costs are to be awarded ad valorem as the appellants Advocate claims, the Government would be entitled to costs on the amount in respect of which the claimants demand was refused by the learned District Judge. If there are to be costs ad valorem on both sides there would be very little difference indeed in the matter of the resultant costs payable by one side to the other. We are unwilling to interfere with the discretion of the learned District Judge in his award as to costs. He fixed the sum at Rs. 100 each to the Counsel appearing for the Government and the claimant. In our opinion the award must stand. The appeal filed on behalf of the claimant also fails and is dismissed with costs.
Advocates List
For the Appellant Messrs. C. Venugopalachari, V. Ramaswami, T.T. Srinivasan Advocates. For the Respondent The Govt. Pleader.
For Petitioner
- Shekhar Naphade
- Mahesh Agrawal
- Tarun Dua
For Respondent
- S. Vani
- B. Sunita Rao
- Sushil Kumar Pathak
Bench List
HON'BLE MR. JUSTICE BELL
HON'BLE MR. JUSTICE GOVINDARAJACHARI
Eq Citation
(1947) 2 MLJ 429
(1948) ILR MAD 567
AIR 1948 MAD 256
LQ/MadHC/1947/199
HeadNote
A. Defence — Defence of India Act, 1939 — S. 19(1)(b) — Requisition of land and buildings — Compensation for loss of income — Period of — Held, claimant could not have started working mill earlier than date fixed by arbitrator — Land Acquisition Act, 1894, Ss. 23(1) & 34 — Evidence Act, 1872 — Or. 18 R. 4 — Cross-examination — Excursions in — Cross-examination of claimant's director, who was the only witness examined in the case, about purchases made by his company on 11th and 14th September, 1942, held, did not indicate that crushing of groundnut was started on either of these dates — Evidence Act, 1872, S. 140
Thank you for subscribing! Please check your inbox to opt-in.
Oh no, error happened! Please check the email address and/or try again.