Pt. Girdharan Prasad Missir And Another
v.
State Of Bihar And Another
(Supreme Court Of India)
Civil Appeal No. 2310 (N) of 1969 | 06-08-1979
Gupta, J.
This appeal is directed against an order of Division Bench of the Patna High Court dismissing the writ petition filed by the appellants before us inter alia on the ground of undue delay in making the petition. By filing the writ petition, the appellants questioned the validity of acquisition of Plot Nos. 449 and 447 of Khata Number 29, Touzi No. 915 of Village Naraipur, Police Station Bagaha in the District of Champaran under the Land Acquisition Act. The High Court held that the unexplained delay in making the petition was itself a good ground for dismissing the writ petition, but also proceeded to consider the merits of the case and found that the petition was liable to be dismissed.
2. The notification under Section 4 of the Land Acquisition Act was issued in this case on May 22, 1956. The notification under Section 6 is dated December 20, 1953. The award was made on July 14, 1962 and Collector took possession of the disputed property on August 27, 1963. The writ petition was filed on March 12, 1964. The High Court found that the delay of more than 17 months from the date of the award has not been satisfactorily explained. for the appellants refers to a number of decision of this Court which deal with the question of delay and all of them agree that in such matters each case would depend upon its own facts. We find no reason why the appellants, if they were convinced that acquisition proceedings was invalid, could not file the writ petition within a reasonable time after the Section 6 notification was made, which was in 1958. Really therefore, the delay was longer than the High Court thought necessary. On these facts, we are of opinion that the High Court was right in holding that the explained delay was a good ground for dismissing the writ petition. As the view we have taken on the question of delay is sufficient to dispose of the appeal, we do not consider it necessary to go into the other question raised on behalf of the appellants.
3. The appeal is dismissed with costs.
This appeal is directed against an order of Division Bench of the Patna High Court dismissing the writ petition filed by the appellants before us inter alia on the ground of undue delay in making the petition. By filing the writ petition, the appellants questioned the validity of acquisition of Plot Nos. 449 and 447 of Khata Number 29, Touzi No. 915 of Village Naraipur, Police Station Bagaha in the District of Champaran under the Land Acquisition Act. The High Court held that the unexplained delay in making the petition was itself a good ground for dismissing the writ petition, but also proceeded to consider the merits of the case and found that the petition was liable to be dismissed.
2. The notification under Section 4 of the Land Acquisition Act was issued in this case on May 22, 1956. The notification under Section 6 is dated December 20, 1953. The award was made on July 14, 1962 and Collector took possession of the disputed property on August 27, 1963. The writ petition was filed on March 12, 1964. The High Court found that the delay of more than 17 months from the date of the award has not been satisfactorily explained. for the appellants refers to a number of decision of this Court which deal with the question of delay and all of them agree that in such matters each case would depend upon its own facts. We find no reason why the appellants, if they were convinced that acquisition proceedings was invalid, could not file the writ petition within a reasonable time after the Section 6 notification was made, which was in 1958. Really therefore, the delay was longer than the High Court thought necessary. On these facts, we are of opinion that the High Court was right in holding that the explained delay was a good ground for dismissing the writ petition. As the view we have taken on the question of delay is sufficient to dispose of the appeal, we do not consider it necessary to go into the other question raised on behalf of the appellants.
3. The appeal is dismissed with costs.
Advocates List
For
For Petitioner
- Shekhar Naphade
- Mahesh Agrawal
- Tarun Dua
For Respondent
- S. Vani
- B. Sunita Rao
- Sushil Kumar Pathak
Bench List
HON'BLE JUSTICE A. C. GUPTA
HON'BLE JUSTICE E.S.VENKATARAMIAH
Eq Citation
1979 (11) UJ 721
(1980) 2 SCC 83
LQ/SC/1979/322
HeadNote
Land Acquisition Act, 1894 — Ss. 4, 6 and 11 — Writ petition filed by appellants against acquisition of land — Held, High Court was right in holding that unexplained delay in making petition was itself a good ground for dismissing writ petition — Delay of more than 17 months from date of award was not satisfactorily explained — Hence, writ petition rightly dismissed — No need to go into other question raised on behalf of appellants — Civil Procedure Code, 1908, S. 256
Thank you for subscribing! Please check your inbox to opt-in.
Oh no, error happened! Please check the email address and/or try again.