Nitu Kumari v. M/s Ddl Infratech Pvt. Ltd

Nitu Kumari v. M/s Ddl Infratech Pvt. Ltd

(Real Estate Regulatory Authority Bihar)

Complaint Case No. RERA/CC/1165/2020 | 28-09-2022

The matter was last heard on 22-08-2022.

1. This complainant petition has been filed seeking relief to direct the respondent to provide physical possession of land with all the amenities as committed under the terms of sale deed No. 3548, dated 16-02-2013. Further the complainant also seeks to direct the respondent to compensate by paying interest @10% on the total value of land for delay in delivery of the possession of the plot and to pay compensation of Rs.25,000/- for inconvenience, harassment and mental torture. Complainant has also prayed to direct the respondent to pay Rs.25,000/- as the litigation cost.

2. In short, the case of the complainant is that the respondent has executed the Sale Deed No. 3548, dated 16-02-2013., in favor of complainant for the plot measuring 2400 sq. ft. on the consideration amount of Rs. 3.60 lakh after the payment of full consideration amount. It has been further submitted that respondent has given assurance to provide well planned society with the facilities of good drainage system, electricity etc. but when complainant approached the plot, no development found as per deed and asked for physical possession. It has been further submitted that after the lapse of more than several years and after several requests the plot has been not handed over to complainant with development. Hence, this complaint.

3. The Bench takes the notes of committee report dated 18-02-202 placed on record for kind perusal as submitted by the committee went for inspection as per the direction of the Authority by giving their findings therein.

4. The Bench observes that the Project was applied for registration but was not approved due to map not approved by the competent authority and liberty was given to apply a fresh with the map getting approved from the competent authority, hence, the project was registrable as per 1st Proviso of Section 3(1) of the. The Hon’ble Supreme Court recently in M/s Newtech Promoters & Developers Pvt. Ltd. Vs State of U.P & Ors. [2022] (1) RCR (Civil) 357 [] has observed that the is not retrospective in nature, rather it is retroactive because it affects the existing rights of the persons mentioned in the like promoter, allottee etc. The intent of legislature was to include all ongoing projects which commenced prior to the enforcement of the and this project was also an ongoing project as evident from the documents placed.

5. Further, In Lavasa Corporation Limited v/s Jitendra Jagdish Tulsiani & Others, Second Appeal (Stamp) Nos. 9717 of 2018 & 18465 of 2018, 18467 of 2018 with Civil Application Nos. 683 of 2018, 791 of 2018, 792 of 2018, the Hon’ble Bombay High court has observed that RERA is brought on Statute Book to ensure greater accountability towards the consumers and significantly reduce frauds and delays, as also the current high transaction costs. It attempts to balance the interests of consumers and promoters, by imposing certain responsibilities on both. It seeks to establish symmetry of information between the promoter and purchaser, transparency of contractual conditions and set minimum standards of accountability and a fast-track dispute resolution mechanism. The RERA, as stated in its 'Objects and Reasons', was enacted for inducting professionalism and standardization in the sector, thus, paving the way for accelerated growth and investments in the long run.

6. It has been further observed by the Hon’ble High Court that as per Clause (2) of Section 3, the RERA is made applicable even to the projects that are on-going on the date of commencement of the RERA and for which, Completion Certificate has not been issued. In respect of such projects also, Promoters are required to register the projects with the Real Estate Regulatory Authority within three months from the commencement of the RERA, with an option that they can register entire real estate project or part of it. The specific 'Explanation' to the Section 3 of the RERA provides that, where the real estate project is to be developed in phases, every such phase shall be considered as a standalone real estate project.

7. Hence, the Bench finds that the present Complaint Case is fall within the ambit of RERA Act, 2016 to entertain and therefore, maintainable against the Respondent.

8. In the light of the submissions, advanced by learned counsel for the parties and documents placed, this Bench deals the issue raised in the present complainant in the following manner:-

9. As regards the possession of plot, the Bench takes the notes of submissions of learned counsel for respondent made during the course of hearing on that possession of plot has been handed over, not countered by complainant and observes that this issue has been addressed and complied by the respondent.

10. As regard Development is concerned, the Bench takes the notes of photographs placed as well as many photographs and videos of the project indicating development shown during the course of hearings and observes that it cannot be said that no development work has been done by the respondent at the project site but yes, few more works are needed to be done at the project site to say that project is complete and developed in all respect, hence, the Bench, directs respondent to complete the work of development at the project sites required to be completed as per agreement as soon as possible, so that, complainant/allottees can stay/ live there in better environment.

11. As regard, the execution of rectification deed is concerned, the Bench takes the notes of submissions of respondent made in respect to execution of exchange deed during the course of last hearing, not countered by complainant and observes that this issue has been addressed and complied by the respondent.

12. As regards claim for compensation is concerned, the complainant is at liberty to press the same before the A.O. as per the provisions of the.

13. With these directions and observations, this complaint petition is disposed of.

Advocate List
  • Mr. Sharad Shekhar

  • Mr. Rabindra Kumar Mr. Shiv Kumar, M.D.

Bench
  • Nupur Banerjee&nbsp
  • Member
Eq Citations
  • LQ
  • LQ/RERA/2022/987
Head Note

A. Consumer Protection — Real Estate — Delivery of possession and development of plot — Delay in delivery of possession of plot — Relief — Respondent to complete the work of development at the project sites required to be completed as per agreement as soon as possible, so that, complainant/allottees can stay/ live there in better environment