Are you looking for a legal research tool ?
Get Started
Do check other products like LIBIL, a legal due diligence tool to get a litigation check report and Case Management tool to monitor and collaborate on cases.

M/s.inox Air Product Limited v. The Tamil Nadu Electricity Regulatory Commission Represented By Its Secretary And Others

M/s.inox Air Product Limited v. The Tamil Nadu Electricity Regulatory Commission Represented By Its Secretary And Others

(High Court Of Judicature At Madras)

Writ Petition No. 476 Of 2010 And M.P. No. 1 Of 2010 | 08-01-2010

Heard the learned counsels appearing on behalf of the parties concerned.

2. Even though various averments have been made and many grounds had been raised in the affidavit filed in support of the writ petition, the main grievance of the petitioner is that the impugned demand notice/bill in respect of the peak hour penalty has been issued by the third respondent, without due notice being given to the petitioner and without affording sufficient opportunity of hearing to the petitioner.

3. The learned counsel appearing on behalf of the petitioner has stated that the third respondent has no authority, under the relevant provisions of the law, to levy the penalty, without the prior approval of the Tamil Nadu Electricity Regulatory Commission, which is the competent statutory authority, established in accordance with the Electricity Act, 2003.

4. It has been further stated that the third respondent had failed to follow the procedures laid down, under paragraph No.33 of the order, made in M.P.No.42 of 2008, dated 28.11.2008, issued by the Tamil Nadu Electricity Regulatory Commission. Therefore, the impugned demand notice/bill issued by the third respondent is liable to be set aside.

5. Mr.A.Selvendran, the learned counsel appearing on behalf of the second and the third respondents, had not refuted the claims made by the learned counsel appearing on behalf of the petitioner. However, he had submitted that if this Court deems it fit to set aside the impugned demand notice/bill of the third respondent, liberty may be granted to the third respondent to pass appropriate orders, afresh, after due notice is issued to the petitioner.

6. In view of the submissions made by the learned counsels appearing for the petitioner, as well as the respondents, and in view of the orders passed by this Court, in a number of writ petitions, wherein similar issues have been raised, the impugned demand notice/bill, issued by the third respondent, is set aside. However, it would be open to the third respondent to pass appropriate orders, afresh, including the issuing of the appropriate demand notice/bill, after giving due notice and after affording sufficient opportunity of hearing to the petitioner.

7. After due notice is issued by the third respondent, the petitioner would be at liberty to challenge the same, if it is found necessary to do so, by raising all the grounds available to the petitioner, including those which have been raised in this writ petition. It would also be open to the petitioner to raise the ground that the third respondent has no authority to levy the penalty, on the ground that it is against the dictum laid down by the Tamil Nadu Regulatory Commission, in M.P.No.42 of 2008, dated 28.11.2008.

8. In case the petitioner had already paid the bill amount it would be adjusted to the amounts that may be claimed by the Tamilnadu Electricity Board, in the future bills relating to the petitioner, in case the final decision is in favour of the petitioner. The petitioner shall fully cooperate by participating in the inquiry or hearing that may be held by the concerned authorities of the respondent Electricity Board.

The writ petition is ordered accordingly. No costs. Consequently, connected miscellaneous petition is closed.

Advocate List
  • For the Petitioner K. Seshadri, Advocate. For the Respondents R2 & R3, A. Selvendran, Advocate.
Bench
  • HON'BLE MR. JUSTICE M.JAICHANDREN
Eq Citations
  • LQ/MadHC/2010/200
Head Note

Electricity — Electricity Act, 2003 — Peak hour penalty — Imposition of — Validity of — Petitioner's main grievance that impugned demand notice/bill in respect of peak hour penalty issued by third respondent, without due notice being given to petitioner and without affording sufficient opportunity of hearing to petitioner — Held, impugned demand notice/bill set aside — However, it would be open to third respondent to pass appropriate orders, afresh, including issuing of appropriate demand notice/bill, after giving due notice and after affording sufficient opportunity of hearing to petitioner — Electricity Board — Penalty — Imposition of — Electricity Act, 2003, Ss. 62 and 63