Are you looking for a legal research tool ?
Get Started
Do check other products like LIBIL, a legal due diligence tool to get a litigation check report and Case Management tool to monitor and collaborate on cases.

Deputy General Manager v. Patel Bababhai Keshavdas And Anr

Deputy General Manager v. Patel Bababhai Keshavdas And Anr

(High Court Of Gujarat At Ahmedabad)

First Appeal No. 397 To 403 Of 2005 | 08-12-2010

K.S. Jhaveri, J.

1. This group of appeals involve common questions on law and facts and therefore, they are disposed of by this common judgment.

2. These appeals have been filed against the judgment and award passed by the 4th Joint Civil Judge (S.D.), Mehsana in Land Acquisition Reference Case No. 3121 of 2003 dated 22nd April 2004, whereby, the references were partly allowed and the Appellant-ONGC was held liable to pay Rs. 4.30 ps. per sq. metre as annual rent to the original claimants along with interest @ 9% p.a. for the first year and thereafter, @ 15% p.a. till the entire amount is realised.

3. The facts in brief of the case are that the Land Acquisition Officer made a proposal for temporary acquisition of the lands belonging to the Respondents, original claimants. After following due procedure, the lands came to be acquired.Thereafter, awards came to be passed by the competent authority fixing the amount of compensation.

4. However, being dissatisfied with the awards, the original claimed raised disputes by way of reference before the Court below. The reference Court, after appreciating the documents on record, partly allowed the same by way of the impugned orders. Hence, these appeals.

5. The main contention raised by the Appellant-Corporation is that the reference Court has not appreciated the law governing the subject, more particularly, Section 35 of the Land Acquisition Act, in its proper perspective. It has been submitted that the reference Court has also lost sight of several other important factors while awarding additional amount of rent.

6. Heard learned Counsel for the respective parties and perused the documents on record. Similar issues arose for consideration of this Court in a group of appeals being First Appeal No. 792/2003 & allied matters. The said group of appeals came to be disposed of by this Court, vide judgment and order dated 21st March 2006, relevant portions of which are reproduced hereunder for ready reference;

5.2 On the facts of the case, it is evident that the Reference Court has also determined the further rent which issue was not before it. I am, therefore, of the opinion that the contention raised by the learned Advocate for the Appellant that the observation or direction issued by the Reference Court in the operative part of the orders require to be quashed and set aside, is required to be accepted. If the said direction is allowed to remain then it would amount to granting the rent which is over the rent fixed by the Appellant-O.N.G.C. from time to time. Moreover, the same has been fixed without considering as to what would be the future rent fixed by the Appellant- O.N.G.C, which is beyond the scope of reference. Hence if the said observation is allowed to remain then, in that event such compensation would be much more than the amount which has been found to be adequate by the Court.

5.3 It may be noted that the Reference Court was dealing with a particular acquisition and it was not open for the said Court to pass an order in respect of future rent. Such an observation on the part of the Reference Court is clearly bad in law in view of the provisions of Section 35(3) of the Act. In that view of the matter, the observations or direction issued by the Reference Court with regard to additional amount of compensation, requires to be quashed and set aside.

6.0 In the result, these appeals are allowed. The observation "over the rent fixed by O.N.G.C. from time to time with the running interest at the rate of 9% p.a. from the date of due date of running till the day of payment is made", made by the Reference Court in the operative part of the impugned judgments and awards, is quashed and set aside. These appeals are allowed to the aforesaid extent. Rule is made absolute to the aforesaid extent with no order as to costs.

7. From the above order passed by this Court, it is clear that while dealing with an application Under Section 35(3) of the said Act, the reference Court is not empowered to pass an order in respect of future rent. Hence, the impugned orders passed by the reference Court, being bad in law, deserves to be quashed and set aside and the matter requires reconsideration.

8. For the foregoing reasons, present group of appeals are partly allowed. The impugned awards passed by the reference Court are quashed and set aside. The matters are remanded to the concerned reference Court for consideration afresh on merits in view of the principle laid down by this Court in the above decision and also being uninfluenced of this order. The references, being very old, the concerned reference Court is directed to dispose of the same expeditiously preferably within a period of two years from the date of receipt of writ of this order.

9. With the above observations and directions, present group of appeals stands disposed of. No costs.

10. It is clarified that it will be open to the Appellant-Corporation to raise all the contentions before the lower Court regarding maintainability of the Reference as well as limitation.

Advocate List
  • For Petitioner : R.R. Marshall, Ld. SC
  • Adil Mirza, Adv.
  • For Respondent : A.V. Prajapati, Adv.
Bench
  • HON'BLE JUSTICE K.S. JHAVERI, J.
Eq Citations
  • LQ/GujHC/2010/1433
Head Note

Limitation Act, 1963 — S. 5 — Reference — Maintainability — Limitation — Land Acquisition Act, 1894, S. 35(3)