Are you looking for a legal research tool ?
Get Started
Do check other products like LIBIL, a legal due diligence tool to get a litigation check report and Case Management tool to monitor and collaborate on cases.

Ambica Construction v. Union Of India (uoi)

Ambica Construction v. Union Of India (uoi)

(Supreme Court Of India)

Civil Appeal No. 410 Of 2008 | 26-04-2017

1. The only issue that arises for consideration before this Court is, whether the claimant, i.e., the Appellant before this Court - M/s. Ambica Construction, could have been awarded interest pendente lite by the arbitrator. The arbitrator by bis award dated 28.06.1999, besides awarding a sum of Rs. 9,20,694/- to the claimant, held the claimant also entitled to interest pendente lite, at the rate of 15% per annum. The operative part of the award passed by the arbitrator depicting the above position is extracted below:

I therefore award a sum of Rs. 9,20, 694.00 in favour of the claimant and against the Respondent. The claimant will also be entitled to interest pendente lite at the rate of 15% per annum and interest on award until recovery at the rate of 15% per annum.-The Union of India, namely, the Respondent before this Court, assailed the award passed by the arbitrator in the High Court of Calcutta, by preferring A.P. No. 39 of 1999. A learned single Judge of the High Court, by an order dated 3.8.2001, affirmed the award passed by the arbitrator on 28.6.1999, including the pendente lite interest, extended to the claimant. The relevant portion of the order of the learned single Judge is extracted below:

"Apart from that there is no allegation of misconduct against the Arbitrator. There is no impropriety in the matter of procedure or norms of hearing before the Arbitrator. There is hardly any reason for the court to pass an order allowing the application. This application for setting aside the award is dismissed."-2. The award dated 28.6.1999, and the order passed by the learned single Judge dated 3.8.2001 were then assailed by the Union of India, before a Division Bench of the High Court, by preferring A.P.O.T. No. 678 of 2001. While disposing of the above intra-court appeal, the High Court accepted the prayer made by the Union of India, and set aside the determination of the arbitrator in awarding interest pendente lite, by observing as under:

In respect of award of interest as payment of interest is excluded under Clause 16(2) of the agreement and as no reason was assigned by the learned Arbitrator for awarding interest till then, in our opinion, interest could not be awarded and the award is modified by excluding interest therefrom.

In above view of the findings the award stands modified by excluding the award of interest and the appeal is allowed to that extent only.

3. The impugned order passed by the High Court dated 17.06.2005, limited to the determination with reference to pendente lite interest, has been assailed by the Appellant, through the instant civil appeal. During the course of hearing, it was not disputed, that the contractual obligation between the parties expressly provided, that interest could not be claimed, either on earnest money or on the security deposit, and even on amounts payable to the claimant. The relevant clause affirming the above position is extracted hereinbelow:

"(2) Interest on amounts. No interest will be payable upon the earnest money or the security deposit or amounts payable to the contractor under the contract, but Government Securities deposited in terms of Sub-clause (1) of this clause will repayable with interest accrued thereon."-The aforesaid clause has been relied upon by the learned Counsel representing the Union of India to contend, that when interest was not payable even on the principal amount, there was no question of the same being payable during the period the matter remained pending for adjudication. It is therefore apparent, that the learned Counsel for the Respondent, relied upon the contractual obligation contained in the clause, extracted hereinabove, to counter the claim of pendente lite interest and to support the impugned order passed by the High Court.

4. The only contention advanced at the hands of the learned Counsel for the Appellant, was based on the judgment of this Court in Union of India v. Ambica Construction (2016) 6 SCC 36 [LQ/SC/2016/441 ;] ">(2016) 6 SCC 36 [LQ/SC/2016/441 ;] [LQ/SC/2016/441 ;] : (AIR 2016 SC 1441 [LQ/SC/2016/441 ;] ">AIR 2016 SC 1441 [LQ/SC/2016/441 ;] [LQ/SC/2016/441 ;] , Para 24), wherein, having examined the legal position declared by this Court, by a Constitution Bench in Irrigation Department, State of Orissa v. G.C. Roy (1992) 1 SCC 508 [LQ/SC/1991/700] : (AIR 1992 SC 732 [LQ/SC/1991/700] ), it was held as under:

34. Thus, our answer to the reference is that if the contract expressly bars the award of interest pendente lite, the same cannot be awarded by the arbitrator. We also make it clear that the bar to award interest on delayed payment by itself will not be readily inferred as express bar to award interest pendente lite by the Arbitral Tribunal, as ouster of power of the arbitrator has to be considered on various relevant aspects referred to in the decisions of this Court, it would be for the Division Bench to consider the case on merits.-A perusal of the conclusions drawn by this Court in the above judgment, rendered by a three Judge Division Bench, leaves no room for any doubt, that the bar to award interest on the amounts payable under the contract, would not be sufficient to deny payment of pendente lite interest. In the above view of the matter, we are satisfied, that the clause relied upon by the learned Counsel for the Union of India, to substantiate his contention, that pendente lite interest could not be awarded to the Appellant, was not a valid consideration, for the proposition being canvassed. We are therefore satisfied, that the arbitrator, while passing his award dated 28.6.1999, was fully justified in granting interest pendente lite to the Appellant. Accordingly, while affirming the award passed by the arbitrator on the issue of pendente lite interest, as also, the determination rendered by the learned single Judge in his order dated 6.9.2001, we set aside the impugned order passed by the Division Bench of the High Court, on 17.06.2005, on the question of pendente lite interest. The pendente lite interest determined by the arbitrator, shall be paid to the Appellant, within two months from today.

The instant appeal is allowed in the aforesaid terms.

Advocate List
  • For Appellant/Petitioner/Plaintiff: Raj Kumar Mehta, Adv.
  • For Respondents/Defendant: Ajit Kr. Sinha, Sr. Adv., Kiran Bhardwaj, Uday Prakash, Raj Bahadur, Advs. and Shreekant N. Terdal, AOR
Bench
  • HON'BLE JUSTICE J.S. KHEHAR
  • C.J.I.
  • HON'BLE JUSTICE DR. D.Y. CHANDRACHUD
  • HON'BLE JUSTICE SANJAY KISHAN KAUL
Eq Citations
  • 2018 (1) CDR 153 (SC)
  • AIR 2017 SC 2586
  • 2017 (5) KHC 311
  • (2017) 14 SCC 323
  • 2017 (6) ARBLR 108 (SC)
  • 2017 (4) RLW 3071 (SC)
  • LQ/SC/2017/704
Head Note

Arbitration — Award — Interest — Pendente lite interest — Award of — Effect of contractual bar — Held, bar to award interest on amounts payable under contract, would not be sufficient to deny payment of pendente lite interest — Hence, arbitrator, while passing his award dated 28.6.1999, fully justified in granting interest pendente lite — Order passed by Division Bench of High Court, set aside — Interest Act, 1978, Ss. 34(2)(b) & (c)